Attachment 3__01 52 13-Field Offices and Sheds.pdf

PDF 74 KB Posted

Attached to
Y1DA--630-12-106 Renovate Sterile Processing Dept. - Building 200
Solicitation number
36C24225B0039
Issued by

About this file

This document is a technical specification section for Field Offices and Sheds for the Northport VA Medical Center's Sterile Processing Department Renovation project. The specification details a temporary Sterile Processing Services Trailer with specific equipment requirements, including two Getinge GSS 6713 Integrated Steam Sterilizers, two 86-Series Washer/Disinfectors, an Ultrasonic Cleaner, workstations, and a water treatment system. The trailer must meet precise water quality standards for utility and critical water, with specific parameters for hardness, conductivity, pH, chlorides, bacteria, and endotoxins. The trailer will have a pass-through window, cold-weather package, and must be approved by the Northport VA Medical Center prior to ordering. Construction requirements include portable or mobile buildings with raised floors, weather-resistant exterior, fire extinguishers, and environmental controls for heating, cooling, and ventilation.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

632-12-106 Renovate Sterile Processing Dept., B200 Northport, VAMC Field Offices and Sheds

01 52 13 - 1

SECTION 01 52 13

FIELD OFFICES AND SHEDS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Temporary Sterile Processing Services Trailer

1.2 RELATED REQUIREMENTS

A. Section 01 10 00 - Summary: use of premises and responsibility for providing field offices.

B. Section 01 50 00 - Temporary Facilities and Controls:

PART 2 PRODUCTS

2.1 MATERIALS, EQUIPMENT, FURNISHINGS

A. Materials, Equipment, Furnishings: Serviceable, new or reconditioned to be like new in a fully sanitized condition, adequate for required purpose.

B. Basis of Design: mmic Mobile Sterile Processing System (MSPS) equipped with two (2) Geting GSS 6713 Integrated Steam Sterilizers (12 tray capacity each). Each sterilizer must be equipped with one load car and one transfer carriage. Also include two (2) Getinge 86-Series (either model 8666 or 8668, depending on equipment availability) Washer/Disinfectors, one (1) Getinge 2460 or 1150 Ultrasonic Cleaner and one (1) stainless steel workstation with integral 3-bay sinks. Each washer/disinfector shall be accompanied by (1) 3 or 4 level heavy duty wash cart and two (2) smart transport trolleys. Contractor shall provide three (3) 30" x 48" prep & pack workstations. An air compressor shall be installed with a connection for an air-gun, at the 3-bay sink. The unit shall be equipped with a pass-through window from the decontamination side to the sterile side. The trailers shall also be equipped with a cold-weather package.

1. Operational flow between SPS trailer, connecting corridor, and temporary supply trailer shall meet the intent as outlined on the contract drawings.

2. Trailer layouts and functional flow shall be approved by the Northport VA Medical

Center prior to ordering from vendor.

3. General Contractor to refer to mechanical, eletrical, plumbing, telecom, and structural drawings for trailer deployment and auxiliary equipment requirements.

4. A water treatment system shall be provided with the temporary building consisting of softening and a reverse osmosis filtration system. Basis of design is MMIC Mobile Water Solutions Unit.

C. Water Treatement: The water treatment syste shall provide utility water and critical water based on the requirements of AAMI TIR34 and the requirements of the temporary equipment provided. The water quality requirements are cited in the following chart:

1.

Water Quality Measurement Units Utility Water Critical Water

Hardness mg/L < 150 < 1 Conductivity (mg/L = ppm) μS/cm < 500 < 10 pH 6-9 5-7 Chlorides mg/L < 250 < 1 Bacteria cfu/mL n/a < 10

Endotoxins EU/mL n/a < 10

632-12-106 Renovate Sterile Processing Dept., B200 Northport, VAMC Field Offices and Sheds

01 52 13 - 2

2.2 CONSTRUCTION

A. Portable or mobile buildings, or buildings constructed with floors raised above ground, securely fixed to foundations, with steps and landings at entrance doors.

B. Construction: Structurally sound, secure, weather tight enclosures for office. Maintain during progress of Work; remove when no longer needed.

C. Temperature Transmission Resistance of Floors, Walls, and Ceilings: Compatible with occupancy requirements.

D. Exterior Materials: Weather resistant, finished in one color.

E. Interior Materials in Offices: Sheet type materials for walls and ceilings, prefinished or painted;

resilient floors and bases.

F. Fire Extinguishers: Appropriate type fire extinguisher at each office.

2.3 ENVIRONMENTAL CONTROL

A. Heating, Cooling, and Ventilating: Automatic equipment to maintain comfort conditions.

2.4 OWNER AND ARCHITECT/ENGINEER OFFICE

PART 3 EXECUTION

3.1 PREPARATION

A. Fill and grade sites for temporary structures to provide drainage away from buildings.

3.2 INSTALLATION

3.3 REMOVAL

A. At completion of Work remove buildings, foundations, utility services, and debris. Restore areas.

END OF SECTION