attachment-8-rfb-dmavs-2025-03.pdf

PDF 140 KB Posted

Attached to
NHARNG Strafford Water Disinfection
Solicitation number
RFB DMAVS 2025-03
Issued by
Strafford County, New Hampshire

About this file

This document is a Submittal Procedures attachment for Request for Bid (RFB) DMAVS 2025-03 issued by the New Hampshire Department of Military Affairs and Veterans Services for the NHARNG Strafford Water Disinfection project at the NH Army National Guard Training Site in Center Strafford, NH. The project involves installing a permanent water disinfection system including a 45-gallon polyethylene sodium hypochlorite tank with containment pallet, peristaltic chemical metering pumps, inline static mixer, new analyzers, control panels, and associated piping and electrical infrastructure. The bid closing date is June 9, 2025 at 12:00 PM EST, with mandatory bidder site visits scheduled for May 5 and May 14, 2025 at 9:00 AM. The contract term commences upon Governor and Council approval and extends through November 28, 2025. Contractors must submit detailed documentation including project record drawings in AutoCAD/Revit and PDF formats, operation and maintenance manuals, and warranty documentation for one year from substantial completion.

The submittal procedures establish requirements for all contractors to submit materials for review and acceptance prior to installation, including shop drawings, samples, test reports, certificates, and manufacturer's instructions. All submittals must be transmitted electronically with a cover sheet simultaneously to the Department and the Department's Consultant, with 14 days allowed for review excluding delivery time. Work cannot commence until submittal items are approved and returned by the Department. Contractors must maintain a binder on site of all approved submittals for departmental review during construction and provide monthly construction photographs documenting site conditions and project progress. The project requires general liability insurance of $1,000,000 per occurrence and $2,000,000 aggregate, along with workers' compensation insurance, and includes a $10,000 allowance for unforeseen conditions and owner-initiated changes.

View the file

Other files

Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rev: 9/6/2018

SUBMITTAL PROCEDURES

1. SUBMITTAL PROCEDURES

A. Submittals shall be made for all materials to be used in construction of the project for review and acceptance of the Department PRIOR to installation of said materials.

B. The word “Submittals” shall include all products and materials that will become part of the finished product whether or not they are specified in the construction documents. This shall also include any shop drawings that need to be approved for any kind of layout of installation. (i.e.: Rebar, steel fabrication, etc...)

C. Shop drawings will be reviewed for the limited purpose of checking for conformance with information given and design concept expressed in the contract documents.

D. Contractor to indicate any special utility and/or electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances on shop drawings as applicable.

E. Transmit each submittal electronically via e-mail with a cover sheet and all pertinent information for review to the Department and the Department’s Consultant simultaneously. Schedule submittals to expedite the Project.

F. Sequentially number transmittal forms and separate items logically. Mark revised submittals with original number and sequential alphabetic suffix.

G. Identify Project, Contractor, subcontractor and supplier; pertinent drawing and detail number, and specification section number, appropriate to submittal.

H. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with requirements of the Work and Contract Documents. Incomplete items or items submitted without the Contractor's signed stamp of approval thereon will be returned rejected.

I. For each submittal for review, allow 14 days excluding delivery time to and from Architect, Engineer and the Department and Contractor.

J. The Department and the Department’s Consultant will review submittals and coordinate return of same to the Contractor.

K. Identify variations from Contract Documents and product or system limitations that may be detrimental to successful performance of completed Work.

L. Allow space on submittals for Contractor and Architect or Engineer review stamps.

M. When revised for resubmission, identify changes made since previous submission.

N. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report inability to comply with requirements.

O. Work shall not begin until submittal items have been approved and returned to

General Contractor by the Department.

P. Contractor shall keep a binder on site of all approved submittals for review by the

Department and their consultants at any time during construction.

2. CONSTRUCTION PROGRESS SCHEDULES

A. Submit initial schedule at Preconstruction Meeting.

B. Submit revised Progress Schedules with each Application for Payment.

C. Distribute copies of revised schedules to Project site file, subcontractors, suppliers, and other concerned parties.

D. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in schedules.

E. Submit horizontal bar chart with separate line for each section of Work, identifying first work day of each week.

3. SAMPLES

A. Submit for review for limited purpose of checking for conformance with information given and design concept expressed in Contract Documents.

B. Samples For Selection as specified in individual specification sections or as noted on plans:

i. Submit to the Department for aesthetic, color, or finish selection.

ii. Submit samples of finishes from full range of manufacturers' standard colors, textures, and patterns for the Department and Architect/Engineer selection.

C. Submit samples to illustrate functional and aesthetic characteristics of Products, with integral parts and attachment devices, Coordinate sample submittals for interfacing work.

D. Include identification on each sample with full Project information.

E. Submit number of samples specified in individual specification sections; the

Department will retain one sample and Architect or Engineer will retain one sample.

F. Reviewed samples which may be used in the Work are indicated in individual specification sections.

4. TEST REPORTS

A. Submit for Department and Architect and Engineer's knowledge as required per plans or individual specification sections.

B. Submit test reports for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents.

5. CERTIFICATES

A. When specified in individual specification sections, submit certification by manufacturer, installation/application subcontractor, or Contractor, to the Department in quantities specified for Product Data.

B. Indicate material or product conforms to or exceeds specified requirements.

Submit supporting reference data, affidavits, and certifications as appropriate.

C. Certificates may be recent or previous test results on material or Product, but must be acceptable to the Department.

6. MANUFACTURER'S INSTRUCTIONS

A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, to the Department in quantities specified for Product Data.

B. Indicate special procedures, perimeter conditions requiring special attention and special environmental criteria required for application or installation.

7. CONSTRUCTION PHOTOGRAPHS

A. Provide photographs of site and construction throughout progress of Work.

B. Contractor will NOT take any photographs of military personnel or equipment.

C. Contractor will NOT use any project photographs for any reason other than stated in this section without prior written consent of the Department.

D. Each month submit photographs with Application for Payment.

E. Photographs: Submit digital images via email.

F. In addition to progress photos, contractor is to take four site photographs from differing directions and four interior photographs of each building area indicating relative progress of the work, five days maximum, prior to submitting.

G. Take photographs as evidence of existing project conditions.

H. Identify each image, identify name of Project, orientation of view, date and time of view.

END OF SECTION