This document outlines requirements for the overhaul of a rudder assembly for the United States Coast Guard. Key details include:
-
The contractor shall overhaul a rudder assembly to serviceable Condition A in accordance with provided Coast Guard drawings, which involves dimensional inspection, paint removal, ultrasonic testing, air pressure testing, preservation, and painting of the rudder blade. Specific processes such as abrasive grit blasting, flow coating of internal cavities, and application of corrosion preventative compound are outlined.
-
The rudder assembly consists of various components that must be inspected, repaired, or replaced as needed. Upon completion, the overhauled rudder assembly shall be preserved, packed, marked, barcoded, and shipped according to military standards to the Surface Forces Logistics Center in Baltimore, Maryland. Requirements for reusable wood shipping containers, wood packing material, and specific markings and labels are provided.
-
Quality assurance inspections will be conducted by a Coast Guard representative to ensure dimensional tolerances, surface preparation, non-destructive testing, paint thickness, preservation, and other specifications are properly met before acceptance.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SRT_0520
WORK ITEM 1: 2040-01-685-0063, Rudder Assembly, Overhaul
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to overhaul to a serviceable “A” condition of rudder assembly(s) in accordance with the referenced drawing(s) and data provided within.
NOTE
Serviceable “A” condition is defined as a reconditioned rudder meeting all required design specifications and design dimensions in accordance with
Coast Guard drawing: 627-WMEC-562-004 and being capable of functioning and performing in the same manner as an identical new rudder although it may not have the appearance of a new rudder.
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN
P/N
CAGE
QTY
(EA.)
ESTIMATED COST
($/UNIT)
Y ***Rudder Assembly, 210A WMEC Combined
Rudder and Stock
NSN: 2040-01-685-0063
618-WMEC-562-003 NO
210B562R
Y ***Rudder Blade, A&B
Class
NSN: 2040-01-336-6545 1
N ***Rudder Stock, B-
CLASS
NSN: 2040-01-344-8471 1
*Government-loaned property, which shall be returned to the Coast Guard upon completion of the contract.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by the Coast Guard.
2. REFERENCES
COAST GUARD DRAWINGS
627-WMEC-562-004, Rudder Assembly
627-WMEC-562-003, Rev A, Rudder Blade Construction
627-WMEC-562-001 Rev H, Arrg’t & Details Rudder Stocks, Bearings and Stuffing Box
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
USCG-SFLC Specification D-000-0100 Rev G, 02/2006, Bar Coding for USCG Surface Forces
Logistics Center procured material.
OTHER REFERENCES
ASTM-E797/E797M Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse –
Echo Contact Method
DOD 4140.01-M-1, 7 Sep 2007; Compliance for Defense Packaging: Phytosanitary Requirements for Wood Packaging Material (WPM)
ISO/IEC 16388:2007(E), 15 May 2007 Information Technology - Automatic identification and data capture techniques - Code 39 bar code symbology specification
MIL-PRF-16173E w/ Int. Amendment 1, Sep 2006, Corrosion Preventive Compound, Solvent
Cutback, Cold- Application
MIL-STD-129R (w/CHANGE 1), 24 May 2018 Department of Defense Standard Practice
Military Marking for Shipment and Storage
MIL-STD-2073-1E w/Change 3, 20 Nov 2018 Department of Defense Standard Practice for
Military Packaging
SSPC-SP 10/NACE No. 2, 1 Jan 2007 Joint Surface Preparation Standard, Near-White Blast
Cleaning
3. REQUIREMENTS
3.1 General. The complete Rudder Stock Assembly consists of the following items:
• Rudder Blade, 1 each
• Rudder Nut, 1 each
• Rudder Nut Keeper, 1 each
• Rudder Nut Wrench, 1 each
• Rudder Blade Key, 1 each
• Rudder Stock, Finished, 1 each
• Rudder Stock Nut, 1 each
• Rudder Stock Sleeve, 1 each
• Retaining Ring, 1 each
• Packing Ring, 1 each
• Packing Plate Ring, 1 each
• Upper Plate Ring, 1 each
• Retaining Rings, Lower packing, Upper Packing, Outer Race, Inner Race, 1 of each
• Bearing Plate, 1 each
• Spacer Ring, 1 each
• Rudder Stock Wrench, 1 each
• Tiller Keys, 1 ½” x 2” x 4 ½”, 2 each
• Pin, Retaining, ½” x 10”, 1 each
• Keeper, Retaining Pin, ½” sq stock 4 ½” lg, 2 each
• Eye Bolt, Shoulder, 1 ¼” x 1 ¼ 7NC, 1 each
3.1.1 Tech rep. None.
3.2 Inspection. The Contractor shall receive the rudder assembly and preform a Receiving Inspection to ensure the correct items have been received and complete. The contractor shall provide the Contracting
Officer (KO) a Receiving Inspection Report within two working days of receiving the rudderstock assembly. The contractor shall remove the rudder assembly from the GFP crates and conduct a thorough inspection to determine all conditions included in section 3.2.1. A Condition Found Report (CFR) shall be submitted to the Coast Guard KO within ten (10) business days of receipt of GFP. The CFR shall include all inspection findings, test results as specified below, including any recommended work required to return the rudder assembly to serviceable “A” condition. The CFR shall also include a breakdown of estimated cost of labor and materials for any repair work that is beyond the scope of work in this specification. No further work shall proceed until authorized by the KO.
3.2.1 Dimensional inspection. Dimensionally inspect the rudder assembly for the following:
• Excessive wear on the taper surfaces
• Straightness of blade
• Keyways excessive wear
• Any worn or damaged threads
• Corrosion and other mechanical defects
3.2.2 Paint removal. Abrasive grit blast all coated rudder surfaces to SSPC-SP 10/NACE No. 2 using grit conforming to MIL-A-22262 with a 3.0-4.0 mil profile. All pipe plugs shall be installed prior to grit blasting in accordance with Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec
6310), 2014, Requirements for Preservation of Ship Structures.
3.2.3 Ultrasonic test. Perform ultrasonic testing to the rudder to measure blade plate thickness. Ultrasonic testing shall be in accordance with ASTM-E797/797M. Take 20-30 UT shots on each side and log readings and location on CFR. Degradation in excess of 25% will render the rudder non-repairable.
3.3 Air pressure test. The Contractor shall conduct an air pressure test on the blade section after all the paint and primer are removed as per 3.2.2. Using a calibrated pressure gauge, test shall be performed at 5
PSI for a period of 10 minutes. If any pressure loss is noted, check porosity areas, plug threads, and all welds using a soapy water solution to expose leaky areas. The active formation of air bubbles on the blade surface indicates the presence of cavitation erosion damage. This condition needs to be repaired prior to acceptance. A second air test will need to be performed in order to ensure the void does not leak. All traces of soapy water solution shall be removed.
3.3.1 Indicated leakage through welds. Rudders shall be serviceable if leakage is only found coming through welds but not through the skin surface. If air leaks are found through welds only, then the
Contractor shall include the extent of weld leakage to the Contracting Officer in the CFR with recommended repairs and cost. The Coast Guard shall determine if double skinned rudders having leaking welds should be repaired in accordance with Surface Forces Logistics Center Standard Specification 0740
(SFLC Std Spec 0740), 2014, Welding and Allied Processes or scrapped based on the extent of leaks and total cost to repair.
3.3.1.1 The air pressure test shall be repeated on rudders that undergo weld leakage repair work (see 3.5).
The cost of additional air test if required shall be covered under the repair.
3.4 Beyond economical repair. Any rudder the Contracting Officer deems “Beyond Economical Repair” shall be returned to the Coast Guard at the address listed in 5.6.1 and shall be marked in “H” condition as described in 5.5.
3.5 Preservation. The interior and exterior surfaces of the rudder blade shall be preserved as follows:
3.5.1 Flow coating (Interior). The rudder internal cavities shall be cleaned as appropriate to facilitate preservation. Once cleaned, fill and drain (flow coat) with corrosion preventative compound that confirms to MIL-PRF-16173 Grade 3. Replace pipe plugs with new stainless-steel plugs.
3.5.2 Rudder coating system (blade). The Painting of the blade shall be accomplished after all other repair work is complete. Reference: Surface Forces Logistics Center Standard Specification 6310 (SFLC Std
Spec 6310), 2012, Requirements for Preservation of Ship, Appendix A.
3.6 Paint data sheet. Paint data sheets per Surface Forces Logistics Center Standard Specification 6310
(SFLC Std Spec 6310), Appendix E shall be prepared to certify the paint type and mil thickness used on the rudder blade. The paint data sheets shall verify all manufacturers’ instructions were followed throughout the entire coating process. The paint data sheet shall be packed with each reconditioned rudder.
3.7 Blade bore taper. Each rudder blade taper bore shall be thoroughly coated with Grade 3 preservative
IAW MIL-PRF-16173E INT AMD 1, ref., 2.2.2.b. Cover taper bore ends using wooden blanks with a minimum thickness of 1-1/2” installed over thin rubber sheeting. Use 5/8” minimum diameter all-thread, with nylock style nuts, fender washers and commercial grade sealant between the nuts, washers and wooden blanks to secure the wooden blanks in place.
4. QUALITY ASSURANCE
4.1 Inspections and tests (completed units). The contractor shall be responsible for notifying the
Contracting Officer within ten (10) business days prior to Quality Assurance inspections. The inspections
& tests required herein are the minimum necessary and are not intended to replace any controls, examinations, or tests normally employed by the Contractor to assure the quality of the product.
4.1.1 Validation. Contractor shall have the latest versions of the drawings, specifications, tolerances, approved test procedures and test equipment calibration certificates available traceable to NIST for inspection, as necessary.
4.1.1 Quality assurance inspections. The contractor is responsible for providing all facilities, materials and personnel for conducting inspections. These actions are required and will be monitored by a Coast
Guard SFLC Quality Assurance Representative.
• Overall dimensional tolerances are in accordance with the drawing
• Surface texture (stock section)
• Weld inspection
• Air pressure test
• Paint thickness check
• Paint data sheets
• Float coat application
• Blade straightness in reference to the centerline on the drawing
• Slade packing kit secured and marked in crate
• Preservation, packing, marking and bar-coding of rudder prior to shipping
5. PRESERVATION, PACKING, MARKING, AND SHIPPING
5.1 Preservation. Each rudder manufactured under this contract shall be preserved in accordance with
MIL-STD-2073-1E, Method 10. The rudder stock shall be supported in the box by use of cradles and blocking that will not allow shifting of the rudder within the box. The entire rudder stock shall be protected with PVC pipe or a heavy plastic mesh.
5.2 Packing. Each rudder shall be individually packaged in its own reusable wood box, or a new reusable shipping container.
NOTE
All GFP must be stored indoors in a locked, environmentally controlled location at the contractor’s facility. Any new crates fabricated per this statement of work shall be safe guarded and stored in the same place as other
GFP.
5.2.1 New reusable shipping container. When a change request is authorized by the KO, the Contractor shall construct a new reusable shipping container as follows:
5.2.1.1 The wooden box shall be constructed using 2” x 8” framing and ¾” plywood top and bottom.
Particle board, flake board, OSB etc. will not be acceptable. The box shall be skid mounted and constructed with a removable lid secured with corrosion resistant wood screws to allow easy access and removal of the rudder without damage to the box.
5.2.2 Wood packing material (WPM) requirements. The new shipping container shall meet the
Phytosanitary Requirements for WPM in accordance with DOD 4140.01-M-1, Compliance for Defense
Packaging Ref. 2 paragraph C2.1.1. WPM is defined as wood pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frames and cleats. Packaging material exempt from the requirements are materials that have undergone a manufacturing process such as corrugated fiberboard, plywood, particleboard, veneer and oriented strand board (OSB). All new purchases of WPM shall be constructed from heat treated (treated to 56° C. core temperature for 30 Minutes) lumber and certified by an accredited agency recognized by the American Lumber Standard Committee (ALSC).
5.2.3 WPM markings. All new shipping containers shall have the appropriate markings in accordance with DOD 4140.01-M-1, Compliance for Defense Packaging Ref. 2 paragraph C2.5.
5.2.4 Newly manufactured shipping containers shall be secured and stored per 5.2 note.
5.3 Marking. Shipping container shall be stenciled with the information laid out below. Markings shall be placed on each side of the two longest sides of the container so it will be visible to a forklift driver during storage and shipment. Stencil shall be applied directly on the container and a minimum of 1inch height black characters on a highly contrasting painted background, using permanent waterproof ink or enamel paint. Marking is in accordance with MIL-STD-129R.
5.3.1 Marking layout (ready for issue) “A” condition rudder blades.
NATIONAL STOCK
NUMBER
2040-01-685-0063
ITEM NAME
RUDDER, MARINE
DRAWING NUMBER
627-WMEC-562-004, 210B562R
SHIPPING WEIGHT
(LBS)
As Determined by Contractor
CONTRACT
NUMBER
(See Contract)
DELIVERY ORDER
NUMBER
(See Contract)
QUANTITY & UNIT
OF ISSUE
1 - EA
CONDITION
CONDITION H
OTHER DATA AS
DIRECTED
U.S. COAST GUARD SFLC
MATERIAL, CRATE 1 OF 2 AND 2 OF
5.3.2 Marking layout (scrap) “H” condition rudder blades.
NATIONAL STOCK
2040-01-685-0063
ITEM NAME
RUDDER, MARINE
DRAWING NUMBER
627-WMEC-562-004, 210B562R
SHIPPING WEIGHT
(LBS)
As Determined by Contractor
CONTRACT
(See Contract)
DELIVERY ORDER
(See Contract)
QUANTITY & UNIT
OF ISSUE
1 - EA
CONDITION
CONDITION H
OTHER DATA AS
DIRECTED
U.S. COAST GUARD SFLC
MATERIAL, CRATE 1 OF 2 AND 2 OF
5.4 Bar coding. U.S. Coast Guard requires bar coding of the NSN, IAW ISO/IEC 16388-2007 Code 39
Symbology.
5.4.1 Bar code label. Can be applied separately or as part of the marking required in 5.3.
5.5 Shipping. The Contractor shall ship and deliver the repaired rudder to the government address specified in paragraph. 5.5.1 Notice the Contracting Officer representative (COR) and KO about the shipment 7 days in advance. Provide timely shipping information to COR including the name of the shipping company, date of shipment leaving Contractor’s facility, and expecting arrival date and time at the government facility. No shipment shall arrive outside of government normal business hours as determined by the KO.
5.5.1 Unless otherwise specified, the Contractor shall ship, and deliver the rudder(s) to the following government address:
U.S. Coast Guard
Surface Forces Logistics Center
2401 Hawkins Point Rd, Bldg. 88
Baltimore, MD 21226
NOTE
Normal deliver hours at the warehouse are Monday through Friday 0730-
1300. If delivery is needed to be made outside that delivery window the
Contractor shall notify the Contracting Officer.
6 NOTES
6.1 Document sources.
6.1.1 Government document sources.
• Department of Defense Single Stock Point (DODSSP)
Building 4, Section D
700 Robbins Avenue
Philadelphia, PA 19111-5094
215-697-2667/2179
FAX 215-697-1462
• DOD & Navy Publications & Forms (Other Than DODSSP)
Naval Publication and Forms Center
5801 Tabor Ave.
Philadelphia, PA 19120
215-697-2000
• USCG Surface Forces Logistics Center
2401 Hawkins Point Road
Baltimore, MD. 21226-5000
Phone: 410-762-6649
ATTN: Contracting Branch, CPD1
6.1.2 Commercial document sources.
• ASTM International
1916 Race Street
Philadelphia, PA 19103-1187
Phone: 215-299-5585
Fax: 215-977-9679
• International Standard Organization (ISO)
1, ch. De la Voie-Creuse
CP 56 - CH-1211 Geneva 20
Switzerland
Phone: +41 22 749 01 11
Fax: +41 22 733 34 30
• The Society for Protective Coatings (SSPC)
800 Trumbull Drive
Pittsburg, PA 15205
Phone: 1-877-281-7772