Attachment 7- Appendix E - Utility Outage.pdf
PDF 210 KB Posted
- Attached to
- REPAIR TRUEMPER ROAD JBSA-LACKLAND TX
- Solicitation number
- MPLS239369
About this file
This document is the 502d Civil Engineer Squadron Utility Outage Request Standard Operating Procedure for Joint Base San Antonio. It outlines the planning and notification process for planned, urgent unplanned, and emergency unplanned utility outages across the base.
The key details are:
- The Outage Manager is responsible for coordinating and notifying impacted facility managers and mission partners of utility outages.
- Planned outages require 45-60 days advance notification, urgent unplanned outages require 2-15 days notification, and emergency outages require immediate notification.
- The 502 CES Director or Deputy Director has final approval authority for all utility outages and is responsible for notifying 502 ABW, 502 CEG, and Executive Agent personnel of emergency outages.
- The document includes a Utility Outage Coordination Form that must be completed and signed by impacted facility managers and various 502 CES shop supervisors.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
502 Civil Engineer Squadron Joint Base San Antonio
502d CES UTILITY OUTAGE
REQUEST
STANDARD OPERATING
PROCEDURES
KEITH KELLNER, GS-15, DAF
Director, 502d Civil Engineer Squadron 502d CES UTILITY OUTAGE REQUEST AND NOTIFICATION STANDARD OPERATING PROCEDURES
502d CIVIL ENGINEER SQUADRON UTILITY OUTAGE REQUEST STANDARD OPERATING PROCEDURE
1. PURPOSE:
This Standard Operating Procedure (SOP) is intended to direct the 502 Civil Engineer Squadron (CES) planning and notification process for planned, urgent unplanned and emergency unplanned utility outages across JBSA. This SOP applies to 502 CES Site Leads, Work-Center Superintendents, Supervisors and subordinate personnel planning and requesting outages across the JBSA enterprise.
2. DEFINITIONS:
Outage Manager: The Outage Manager for any planned outage will be the 502 CES Site Lead, Work- Center Superintendent or his/her designated representative. The Project Manager is responsible for all coordination and notifications related to an outage
Planned Outage: An outage required by 502 CES to support maintenance, repair or projects that need a utility to be turned off to effect required actions.
Urgent Unplanned Utility Outage: An outage required for urgent maintenance and repair planned by the 502 CES. This type outage must be executed as soon as possible to avoid disruption to utility services to facilities which could cause disruption to Mission Partner activities.
Emergency Unplanned Utility Outage: This type of outage is a result of utility loss or requires immediate utility outage due to life/safety/health or severe damage to utility or facility.
3. PLANNED AND URGENT UNPLANNED OUTAGE REQUEST NOTIFICATION:
a. The 502 CES Work-Center Supervisor or designated representative determines need for utility outage (NOTE: 802 CES Project Manager will manage requests coming from the 802 CES).
b. The 502 CES Work-Center Supervisor requesting the outage will be responsible for completing the 502 CES Outage Coordination form (Figure 1) and submitting to 502 CES Operations Site Lead within the timeline required dependent on the type of outage.
c. 502 CES Work-center supervisor or designated representative will speak directly with impacted Facility Manager(s) (FM) to inform them of the need for utility outage and proposed dates for the outage. They will obtain contact information for the impacted FM(s)/Mission Partner(s) (name/phone number/email) and signature(s) of the FM(s) on the 502 CES Outage Coordination form. The form must be completed within the timeframe listed below and once all notifications/contacts are completed, submit to the 502 CES Operations Site Lead.
Figure 1:
Type of Outage Notification Planned 45-60 Days prior
Urgent Planned 2 - 15 Days prior Emergency Immediate Notification to 502 CES
Director and Deputies
d. Site Lead is responsible for reviewing and signing the Outage Request form and submitting to 502 CES Director and/or Deputies.
e. 502 CES Director and/or Deputy Director who will review and provide final approval for any utility outage. Their signature on the outage request form will annotate approval.
f. 502 CES Director and/or Deputies will provide notification of outage to 502 CEG and 502 ABW Leadership as appropriate.
Figure 2:
5. EMERGENCY UNPLANNED OUTAGE NOTIFICATION:
a. 502 CES personnel or Privatized Utility operator must notify the 502 CES Director and Deputy Director’s as soon as an outage occurs or outage need is identified with no less than a one (1) hour delay between outage need and outage execution.
b. The 502 CES Director or Deputies will be responsible for notifying 502 ABW, 502 CEG and Executive Agent personnel of the outage via text message and keep them updated on a regular basis until the outage is resolved.
Outage Required
• 502 CES Lead determines outage is required
Notification
• 502 CES Lead completes Outage Request Form and Informs all affected Facility Managers and Mission Partners and submits to Site Lead
Approval
• 502 CES Director or Deputy Director is final approval authority for all utility outages
Figure 1. Utility Outage Coordination Form
502d CIVIL ENGINEER SQUADRON
(FSH/RND/LAK)
PLANNED/URGENT UNPLANNED UTILITY OUTAGE
COODINATION
(Modified and Approved Dec 2020) Date: ………..
Work Task or Project #:
Type of Utility Outage:………..…… Proposed Date:…………………..Alternate Date:……….……….
Building Number:………. Mission Partner (s) Impacted:………………………………………………..
Duration of Outage:…………………Start Time:…………. End Time: ………………
Requester (Must Be Supervisor):……………………….…………………..
Phone: ……………………………
Work Description:
Area/Room/Floor/Other Facilities Affected:
COORDINATION: (Please PRINT name and Sign to acknowledge outage if your area of responsibility is affected)
Printed Facility Manager(s) Name (Must be legible) and Signature:______________________________
Shop Coordination (Name Must Be Legible)
Interior Electric Shop Supervisor/Alt: __________________________________
Exterior Shop Supervisor/Alt:________________________________________
Plumbing Shop Supervisor/Alt: (Water/Gas/Backflow /Fire Systems) ______________________________
Alarm Shop Supervisor/Alt: ___________________________________________________________________
EMCS (Controls) Supervisor/Alt: _______________________________________________________________
HVAC Supervisor/Alt: _________________________________________________________________________
Power Production Supervisor/Alt: ________________________________________________________
Water/Wastewater Ops Supervisor/Alt: ________________________________________________________
CE Customer Service Supervisor:__________________________________________________________
902 CES Fire Emergency Services Lead: _____________________________________________________
502d Communications Squadron:_________________________________________________________
Chief, Operations Flight (Site Lead):_______________________________________________________
Service Contracts(Portables, handwashing stations, etc) ______________________________________
502 CES DIRECTOR/DEPUTY
(Approve/Disapprove)_____________________________________________________________
| 502 Civil Engineer Squadron |
| Joint Base San Antonio |
| 502d CES UTILITY OUTAGE REQUEST |
| STANDARD OPERATING PROCEDURES |
| ROGER N. WILKSON, GS-15, DAF |
| Director, 502d Civil Engineer Squadron |
| PLANNED/URGENT UNPLANNED UTILITY OUTAGE |
| (Modified and Approved Dec 2020) |