Attachment 7_7 Electrical and Telecommunications Design and Construction.docx

DOCX document 39 KB Posted

Attached to
NARA Replace Roof on Bays F&G Federal contract opportunity
Solicitation number
47PL0124R0030
Issued by
General Services Administration Public Buildings Service Region 10

About this file

This document provides detailed electrical and telecommunications design and construction requirements for a GSA Region 10 federal contract opportunity. It lists the applicable publications and standards that must be followed, including requirements for electrical arc flash analysis, telecommunications infrastructure, drawings and diagrams, and designer qualifications. Key details include:

The electrical system must conform to publications such as PBS-P100, NFPA, ANSI, and OSHA standards. An electrical arc flash analysis using the latest SKM Power*Tools software is required, with corresponding arc flash hazard warning labels.

For telecommunications, the design must follow PBS P-100, TDDG, and BICSI standards. The telecommunications drawings must include a cover sheet, plan sheets, elevation diagrams, schematic diagrams, and demolition drawings, all of which must be signed and stamped by a BICSI Registered Communications Distribution Designer (RCDD).

Small-scale projects adding work area outlets from existing telecommunications rooms may not require an RCDD stamp, provided the work is overseen by an RCDD or the government telecommunications manager.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GSA Region 10 Page |

GSA Region 10 Page |

GSA Region 10 Page | 1

GSA Region 10 – Electrical and Telecommunications Design and Construction Requirements (New and Existing Upgrade System)

Applicable Publications:

In addition to this document, provide a system conforming to the requirements of the following latest publications including all amendments to these publications:

1. PBS-P100 – Facilities Standards for the Public Buildings Service

2. PBS-140 – Child Care Center Design Guide (where applicable)

3. USMS Pub 64 – United States Marshall Service (where applicable)

4. NFPA – National Fire Protection Association

5. ANSI A17.1 – Safety Code for Elevators and Escalators

6. ADA & ADAAG – Americans with Disabilities Act and Architectural Barriers Act Accessibility Guidelines

7. Guidelines for Fire Watches During Sprinkler and/or Fire Alarm System Impairment in Federal Buildings (attachment #1)

8. IBC – International Building Code

9. IEEE 1584 - IEEE Guide for Performing Arc-Flash Hazard Calculations

10. IFC – International Fire Code

11. ASME – American Society of Mechanical Engineers

12. Region 10 Policy (Fire Life Safety (FLS), Asbestos, etc.)

13. Occupational Safety and Health Administration

14. ISC Physical Security Standards (Publications will need to be individually requested thru Homeland Security Information network)

Telecommunications Specific:

1. Building Industry Consulting Service International: Telecommunications Distributions Methods Manual (TDMM)

2. US General Services Administration | GSA IT: Telecommunications Distributions Design Guide (TDDG) – Telecommunications and Infrastructure Standards

3. TIA-568.0-E: Generic Telecommunications Cabling for Customer Premises

4. TIA-568.1-E: Commercial Building Telecommunications Infrastructure Standard

5. TIA-568.2-D: Balance Twisted Pair Communications and Components Standard

6. TIA-568.3-D: Optical Fiber Cabling and Components Standard

7. TIA-568.4-D: Broadband Coaxial Cabling and Components Standard

8. TIA-569-E: Telecommunications Pathways and Spaces

9. TIA-606-C: Administration Standard for Telecommunications Infrastructure

10. TIA-607-D: Generic Telecommunications Bonding and Grounding (Earthing) for Customer Premises

11. TIA-758-B: Customer-owned Outside Plant Telecommunications Infrastructure Standard

12. TIA-455-C: Fiber Optic Test Standards

13. TIA-526-7-A: Measurement of Optical Power Loss of Installed Single-Mode Fiber Cable Plant

14. TIA-526-14-C: Optical Power Loss Measurement of Installed Multimode Fiber Cable Plant

15. TIA-942-B: Telecommunications Infrastructure Standard for Data Centers

16. TIA-1179-A: Healthcare Facility Telecommunications Infrastructure Standard

17. TIA-4966: Telecommunications Infrastructure Standard for Educational Facilities

18. TIA-1152-A: Requirements for Field Test Instruments and Measurements for Balanced Twisted-Pair Cabling

19. TSB: Technical Service Bulletins (TSBs related to the above TIA standards)

20. TIA-TSB-162-B: Telecommunications Cabling Guidelines for Wireless Access Points

21. TIA-TSB-184-A: Guidelines for Supporting Power Delivery Over Balanced Twisted-Pair Cabling

22. IEEE 802.11 Wireless Local Area Network Standard, including the IEEE 802.11a, 802.11b, 802.11g, 802.11n, 802.11ac and 802.11ax standards

23. BICSI: Telecommunications Distribution Methods Manual– 14th or latest edition

24. BICSI: Outside Plant Design Reference Manual – 6th or latest edition

25. BICSI: Information Technology Systems Installation Methods Manual – 7th or latest

26. ANSI/BICSI 002-2019, Data Center Design and Implementation Best Practices

27. ANSI/BICSI 004-2018, Information Technology Systems Design and Implementation Best Practices for Healthcare Institutions and Facilities

28. ANSI/BICSI 007-2020, Information Communication Technology Design and Implementation Practices for Intelligent Buildings and Premises

29. ANSI/BICSI 008-2018, Wireless Local Area Network (WLAN) Systems Design and Implementation Best Practices

30. Telecommunications Project Management (TPM) reference, 1st Edition or latest

31. ANSI/BICSI N3-20, Planning and Installation Methods for the Bonding and Grounding of Telecommunication and ICT Systems and Infrastructure

Electrical

General

Design electrical system to meet the needs of the activity and supporting facilities in accordance with this document and PBS P-100.

Electrical Arc Flash Study and Equipment Coordination

1. Electrical Arc Flash analysis and equipment coordination applies to Design Build projects. For Design Bid Build projects, the Arc Flash analysis requirements must be included in the specifications. The analysis must be performed utilizing the latest version of SKM Power*Tools for Windows (PTW) Software.

1.1. Provide a Short Circuit Study and Arc Flash Hazard Analysis for the electrical equipment and devices provided under this project. The study must be provided in pdf copy and consist of a report cover, an executive summary, a summary of all assumed components used in the analysis, a summary of all input data, a Short Circuit Analysis, a Arc Flash Hazard Analysis, a one-line diagram created from the data collected and a printout of the arc flash hazard labels.

1.1.1. The Contractor must collect all required data on-site to perform the analysis and must verify the accuracy of any government provided one-line electrical power drawings.

1.1.2. The study must include the creation of Arc Flash Hazard Warning labels specific to each individually identified piece of equipment. These labels serve as a guide to technicians and others in the selection of proper Personal Protective Equipment (PPE) when working near exposed energized equipment. The Arc Flash Hazard Warning labels must list the “worst case” arc flash hazard condition at each location and must be done in accordance with IEEE 1584-2018, “Guide for Performing Arc Flash Hazard Calculations”, as referenced in NFPA 70E, “Standard for Electrical Safety in the Workplace”. Provide warning labels (Arc Flash labels) that are self-adhesive and capable of adhering to a variety of material. The Arc Flash label color and size must be:

1.1.2.1. WARNING; Orange and White, 4” x 6”, for Hazard Risk Category (HRC) 4 or less

1.1.2.2. DANGER; Red and White, 4” x 6”, for equipment over HRC 4

1.1.3. The study must be performed utilizing the latest version of SKM Power*Tools for Windows (PTW) Software.

1.1.4. Engineering judgment must be used for any equipment data that was unable to be collected or that is not within the software component library. All engineering judgments must be noted on the one-lines and must also be listed in spreadsheet format in the Study Report.

1.2. If an existing Arc Flash study has been conducted and completed for this building. Update the existing Arc Flash study based on the electrical revisions under this project. The study must be provided in pdf copy and consists of a report cover, an executive summary, a summary of all assumed components used in the analysis, a summary of all input data, a Short Circuit Analysis, a Arc Flash Hazard Analysis, a one-line diagram created from the data collected and a printout of the arc flash hazard labels.

1.2.1. Assume that no major electrical alterations have been conducted to the electrical system.

1.2.2. Assume that no major prior electrical alterations have been made that will impact the existing study.

1.2.3. GSA will provide the SKM Power*Tools for Windows (PTW) native files

1.2.4. The study must include the creation and/or recreation of Arc Flash Hazard Warning labels specific to the equipment that are impacted as a result of the electrical revisions of this project. The Arc Flash Hazard Warning labels shall list the “worst case” arc flash hazard condition at each location and shall be done in accordance with IEEE 1584-2018, “Guide for Performing Arc Flash Hazard Calculations”, as referenced in NFPA 70E, “Standard for Electrical Safety in the Workplace”. Provide warning labels (Arc Flash labels) that are self-adhesive and capable of adhering to a variety of material. The Arc Flash label color and size shall be:

1.2.4.1. WARNING; Orange and White, 4” x 6”, for Hazard Risk Category (HRC) 4 or less

1.2.4.2. DANGER; Red and White, 4” x 6”, for equipment over HRC 4

1.2.5. The study must be performed utilizing the latest version of SKM Power*Tools for Windows (PTW) Software

Telecommunications

General

Design interior telecommunications infrastructure to meet the needs of the activity and supporting facilities in accordance with this document, the PBS P-100, TDDG and the BICSI TDMM. A/E contractor generated final drawings and specifications for design-bid-build and design-build projects must be signed and stamped by a BICSI Registered Communications Distribution Designer (RCDD).

Note: Design and construction may be concurrent efforts in Design-Build projects, and multiple phases of construction may be approved. Therefore, the final documents for each construction phase must be signed and stamped.

Small Scale Projects

Small scale projects limited to adding work area outlets from existing telecommunications rooms do not require an RCDD stamp provided the work is being accomplished under the technical authority of an RCDD or the government telecommunications manager.

Designer Qualifications

Refer to the TDDG for designer qualification requirements.

Plans and Diagrams

At a minimum, the telecommunications drawing set shall include the following:

· Cover sheet which must include a sheet list, site map, symbol schedule – see National CAD Standards and BICSI TDMM Glossary and a List of Abbreviations

· Plan Sheets – Telecommunications

· Plan Sheets – Grounding/Bonding (when required)

· Elevation Diagrams – (telecom room walls, telecom/equipment racks, and

· cabinets)

· Schematic Diagrams – (Riser/Backbone Cabling, Grounding/Bonding)

· Demolition (Plans, Elevations, Schematics)

All plan sheets must be scaled, must indicate the scale, and must show a north arrow. All plan sheets must show a key plan when the building floor or site is too big to fit on a single sheet. At a minimum, these drawings must be provided:

· T0.x – Cover sheet

· T1.x - Layout of complete building per floor - Building Area/Serving Zone Boundaries, Backbone Systems, and Horizontal Pathways. Layout of complete building per floor. The drawing indicates location of building areas, serving zones, vertical backbone diagrams, telecommunications rooms, access points, pathways, grounding system, and other systems that need to be viewed from the complete building perspective.

· T2.x - Serving Zones/Building Area Drawings - Drop Locations and Cable Identification (ID’S). Shows a building area or serving zone. These drawings show drop locations, telecommunications rooms, access points and detail call outs for common equipment rooms and other congested areas.

· T3.x – Drawings must be in accordance with TIA-606 that includes telecommunications rooms plan views, pathway layout (cable tray, racks, ladder-racks, etc.), mechanical/electrical layout, and cabinets/racks, backboards and wall elevations. Drawing must show layout of applicable equipment including incoming cable stub or connector blocks, building protector assembly, outgoing cable connector blocks, patch panels and equipment spaces and cabinet/racks. Drawing must include a complete list of equipment and material, equipment rack details, proposed layout and anchorage of equipment and appurtenances, and equipment relationship to other parts of the work including clearance for maintenance and operation. Drawing may also be an enlargement of a congested area of T1.x or T2.x drawings.

· T4.x - Typical detail and riser drawings – fiber optic riser diagram, copper riser diagram, major pathway riser diagram, grounding riser diagram, and firestopping. Detailed drawings of symbols and typicals must also include faceplate labeling, faceplate types, faceplate population installation procedures, detail racking, and raceways.

Revision Date 04/25/2022

Revision Date 04/25/2022

Revision Date 06/15/2022 image2.png image5.png image4.png image6.png image1.png image3.png

File details come from the government source that posted it. Updated .