Attachment 6 - Pricing Schedule.pdf
PDF 209 KB Posted
- Attached to
- Sacramento River East Levee (SREL) Contract 3
- Solicitation number
- W9123822B0002
About this file
This document contains a pricing schedule and related solicitation for the Sacramento River East Levee Contract 3 federal construction project. The scope of work includes constructing approximately 2 miles of various types of seepage cutoff walls along the levee and relocating multiple encroachments. The pricing schedule provides estimated quantities and unit pricing for line items such as mobilization, clearing, excavation, cutoff wall construction using soil-bentonite, slag cement-cement-bentonite, and deep mix methods, as well as embankment fill, paving, and seeding. It also includes optional line items for cultural preservation, replacing a pumping plant pipe, and additional cutoff wall construction. The related solicitation provides details such as the $25-50 million estimated value, 237990 NAICS code, construction completion by December 2022, and prequalification requirements.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pricing Schedule - American River Common Features 2016 - Sacramento River East Levee, Contract 3
CLIN 0001 – CUTOFF Wall to (-105' to -45') Stations: 1426+00 – 1530+60 (10,460')
Contract Line
Item No.
Item Description Estimated
Quantity Unit Unit Price Total Price
1.1 Mobilization and Demobilization 1 JOB $ $
1.2 Clearing and Grubbing 1 JOB $ $
1.3 Traffic Control 1 JOB $ $
1.4 Storm Water Pollution Control 1 JOB $ $
1.5 Vibration Monitoring 1 JOB $ $
1.6 Restore Ellsworth C. Zacharias Park 1 JOB $ $
1.7 Maintenance of Zacharias Park to April 15, 2023 1 JOB $ $
1.8 Not Used - - $ $
1.9 Not Used - - $ $
1.10 Remove and Dispose Encroachment – Stairway* 36 EA $ $
1.11 Remove and Dispose Encroachment – Elevated
Structure* 2 EA $ $
1.12 Remove, Store, and Reinstall Encroachment –
Elevated Structure* 1 EA $ $
1.13 Topsoil Stripping* 7,739 CY $ $
1.14 Remove and Dispose - Asphalt Concrete* 30 TN $ $
1.15 Remove and Dispose - Aggregate Base* 229 TN $ $
1.16 Remove Aggregate Surfacing* 22,303 SY $ $
1.17 Abandon Existing Piezometer* 2 EA $ $
1.18 Utility Inspect and Restore* 1 EA $ $
1.19 Utility Pole Remove and Dispose* 5 EA $ $
1.20 Abandon Utility* 1 EA $ $
1.21 Not Used - - $ $
1.22 Remove and Dispose Utility - Up to 4' Depth* 9 EA $ $
1.23 Remove and Dispose Utility - Greater than 4'
Depth* 3 EA $ $
1.24 Remove, Store, and Reinstall CLF Gate* 2 EA $ $
1.25 Remove, Store, and Reinstall Gate* 2 EA $ $
1.26 Not Used - - $ $
1.27 Levee Excavation (Levee Degrade and Cutoff
Trench) * 101,996 CY $ $
1.28 SB Cutoff Wall* 559,015 SF $ $
1.29 DMM Cutoff Wall* 282,304 SF $ $
1.30 SCCB Cutoff Wall* 84,700 SF $ $
1.31 Levee Embankment Fill * 103,571 CY $ $
1.32 Aggregate Base* 229 TN $ $
1.33 Aggregate Surface Course* 4,667 CY $ $
1.34 Asphalt Concrete Paving* 34 TN $ $
1.35 Erosion Control Seeding* 8.73 AC $ $
1.36 Archaeological Testing* 4 EA $ $
1.37 Cultural Recovery Trench* 400 LF $ $
TOTAL
NOTE: AC is acre, CY is cubic yard, TN is ton, SF is square Foot, and SY is square yard.
*Indicates quantity is estimated and subject to Federal Acquisition Regulation clause 52.211-18 Variation in Estimated Quantity.
Bold Italic font signifies revised or newly added information
OPTIONAL CLIN 1001 – Cultural Resources Preservation Cap
Item No.
1001.1 Cultural Resources Preservation Cap 1 JOB $ $
OPTIONAL CLIN 1002 – Sump 70 Pumping Plant Pipe Replacement
Item No.
1002.1 Sump 70 Pumping Plant Pipe Replacement 1 JOB $ $
OPTIONAL CLIN 1003 – CUTOFF: DMM Wall to (98’) Stations: 1424+20 – 1426+00 (180')
Contract Line
Item No.
1007.1 Mobilization and Demobilization 1 JOB $ $
1007.2 Clearing and Grubbing 1 JOB $ $
1007.3 Traffic Control 1 JOB $ $
1007.4 Storm Water Pollution Control 1 JOB $ $
1007.5 Vibration Monitoring 1 JOB $ $
1007.6 Demolition at Sump 70 (STA 1425+50) 1 JOB $ $
1007.7 Sump 70 (STA 1425+50) 1 JOB $ $
1007.8 Remove and Dispose Encroachment – Stairway* 2 EA $ $
1007.9 Topsoil Stripping* 158 CY $ $
1007.10 Remove and Dispose - Aggregate Base* TN $ $
1007.11 Remove Aggregate Surfacing* 451 SY $ $
1007.12 Abandon Existing Piezometer* 2 EA $ $
1007.13 Levee Excavation (Levee Degrade and Cutoff
Trench)* 1,533 CY $ $
1007.14 DMM Cutoff Wall* 18,540 SF $ $
1007.15 Levee Embankment Fill* 1,651 CY $ $
1007.16 Aggregate Surface Course* 80 CY $ $
1007.17 Erosion Control Seeding* .2 AC $ $
TOTAL $
NOTE: AC is acre, CY is cubic yard, TN is ton, SF is square Foot, and SY is square yard.
*Indicates quantity is estimated and subject to Federal Acquisition Regulation clause 52.211-18 Variation in Estimated Quantity.
Bold Italic font signifies revised or newly added information
Price Schedule Roll-up
Contract Line
Item No.
0001 CUTOFF Wall to (-105' to -45')
1 JOB $ $
1001 Cultural Resource Preservation Cap 1 JOB $ $
1002 Sump 70 Pumping Plant Pipe Replacement 1 JOB $ $
1003 CUTOFF: DMM Wall to (98’) 1 JOB $ $
TOTAL $
Evaluation of Line Items: In order to be considered the low bid for this project, the Government will add the total price for all the options to the total price for the base line item 0001.
| CLIN 0001 – CUTOFF Wall to (-105' to -45') |
| OPTIONAL CLIN 1001 – Cultural Resources Preservation Cap |
| OPTIONAL CLIN 1002 – Sump 70 Pumping Plant Pipe Replacement |
| OPTIONAL CLIN 1003 – CUTOFF: DMM Wall to (98’) |
| CUTOFF Wall to (-105' to -45') |