Attachment_6_-_Orovada_WFC_Room_Requirements_FSB_2025-01-16.pdf

PDF 104 KB Posted

Attached to
Orovada Fire Engine Cover & Crew Quarters, NV Federal contract opportunity
Solicitation number
140L0625R0006
Issued by
Department of the Interior Bureau of Land Management National Office

About this file

This document is a Room Requirements specification for the Orovada Wildland Fire Complex Fire Station Building, dated 1/10/2025. The detailed room-by-room breakdown provides specifications for seven distinct rooms and a mezzanine, totaling 5,876 gross square feet, with each space having specific construction and finishing requirements. Key rooms include an Engine Bay (3,925 sq ft) with 20 wall-mounted fire gear lockers, a Shop (322 sq ft), Laundry (92 sq ft) with washer, dryer, and sink, Mechanical/Electrical room (76 sq ft), ADA-compliant Toilet (85 sq ft), Tools room (103 sq ft), and a Mezzanine (876 sq ft) with OSHA-approved safety gate for forklift material loading. Consistent design elements across rooms include sealed concrete floors, rubber cove base, light gray semi-gloss paint, and specific wall treatments such as 5/8" plywood paneling to 8 feet above finished floor in certain areas.

View the file

Other files for this federal contract opportunity

Other files attached to Orovada Fire Engine Cover & Crew Quarters, NV, newest first.
File Type Posted
Attachment_17_-_SV_Sign-In-Sheet_Orovada_0002.pdf PDF
Attachment_16_-_Sol_Q_A_140L0625R0006_0002.pdf PDF
Sol_140L0625R0006_Amd_0002.pdf PDF
Attachment_15_-_Past_Performance_Questionnaire_-_Revised_0002.docx DOCX document
Attachment_14_-_BLM_Orovada_Fire_Station_Design_BP2_-_Reference_Planset_0001.pdf PDF
Attachment_13_-_BLM_Orovada_Fire_Station_Design_BP1_-_Reference_Planset_0001.pdf PDF
Attachment_3_-_SOW__REVISED_Orovada_General-Site_0001.pdf PDF
Sol_140L0625R0006_Amd_0001.pdf PDF
Attachment_10_-_Orovada_Letters.pdf PDF
Attachment_7_-_Prototypical_Crew_Quarters_Building_2025-01-22.pdf PDF
Attachment_8_-_Orovada_Fire_Station_Reports_and_Feasibility_Study.pdf PDF
Attachment_9_-_Orovada_WFC_Sustainable_Doc_2025-03-13.pdf PDF
Attachment_11_-_Past_Performance_Questionnaire.docx DOCX document
Attachment_12_-_SF1442_Instructions_P1.pdf PDF
Attachment_1_-_SOW_Orovada_Fire_Station_Building_2025-03-11.pdf PDF
Attachment_2_-_SOW_Orovada_Crew_Quarters_2025-03-11.pdf PDF
Attachment_3_-_SOW_Orovada_General-Site_2025-03-11.pdf PDF
Attachment_5_-_OWFS_Performance_Specs_2025-03-14.pdf PDF
Sol_140L0625R0006.pdf PDF
Attachment_4_-_Orovada_Plans_2025-03-10.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Orovada Wildland Fire Complex

Fire Station Building

Room Requirements

1/10/2025

Number Name Area

(rough) Notes

101 Engine Bay 3925

Sealed concrete floor; rubber cove base; light gray semi‐gloss paint on solid walls; 5/8" plywood to 8' AFF all walls; HM personnel doors with small reinforced vison lites to the exterior; insulated overhead doors with insulated vision lites; (20) wall mounted fire gear lockers; metal stairway to mezzanine painted medium gray with solid fire resistant under panel

102 Corridor 103

Sealed/stained concrete floor; rubber cove base; light gray semi‐gloss paint on walls and ceiling; gypsum ceiling; HM personnel doors with small reinforced vison lites to the exterior;

personal lockers; eye wash station; water cooler with bottle filler

103 Shop 322

Sealed concrete floor; rubber cove base; light gray semi‐gloss paint on walls and ceiling;

gypsum ceiling; 5/8" plywood to 8' AFF all walls; pair of solid doors with office latch set

104 Laundry 92

Sealed concrete floor with floor drain; rubber cove base; light gray semi‐gloss paint on walls and ceiling; gypsum ceiling; acoustic batt and sealant treated walls/ceiling; solid door with passage latch set; mop sink with FRP surround; wall mounted broom and mop holder; 48" of floor cabinets with solid surface countertop; 48" of upper wall cabinets; washer; dryer;

larger free standing laundry sink

105 Mechanical/Electrical 76

Sealed concrete floor with floor drain; rubber cove base; light gray semi‐gloss paint on walls and ceiling; gypsum ceiling; acoustic batt and sealant treated walls/ceiling; solid door with office latch set

106 Toilet 85

ABA/ADA compliant; sealed concrete floor with floor drain; rubber cove base; light gray semi‐gloss paint on walls and ceiling; gypsum ceiling; acoustic batt and sealant treated walls/ceiling; solid door with privacy latch set

107 Tools 103

Sealed concrete floor; rubber cove base; light gray semi‐gloss paint on walls and ceiling;

gypsum ceiling; solid door with office latch set

201 Mezzanine 876

Epoxy coated wood floor; rubber cove base; light gray semi‐gloss paint on solid walls; 5/8" plywood to 8' AFF all walls; safety railing on open side; OSHA approved safety gate for loading of materials via forklift

5.0% 294 Support space, structure, etc.

5876 Gross Building Area with Mezzanine

5000 Gross Footprint