This is a Request for Proposal (RFP) for a design-build construction project to develop a fire engine cover and crew quarters facility in Orovada, Nevada. The Bureau of Land Management is seeking a small business contractor to design and construct fire station and crew quarters buildings through a two-phase competitive source selection process. The total project budget is $8.3 million, with a firm fixed-price contract awarded under NAICS code 236220 and a small business size standard of $45.0 million.

Key proposal submission dates include a site visit on April 17, 2025, questions due by April 25, 2025, and phase one proposals due by May 9, 2025. The project requires a 710-calendar day completion timeline, with the contractor beginning work within 7 calendar days of contract award. Proposals will be evaluated in two phases, with up to five offerors selected after phase one to submit detailed phase two proposals. Evaluation criteria will assess the design-build team, key personnel qualifications, past performance, project approach, schedule, and pricing, with a focus on best value to the government.

View the file

Other files for this federal contract opportunity

Other files attached to Orovada Fire Engine Cover & Crew Quarters, NV, newest first.
File Type Posted
Sol_140L0625R0006_Amd_0002.pdf PDF
Attachment_15_-_Past_Performance_Questionnaire_-_Revised_0002.docx DOCX document
Attachment_16_-_Sol_Q_A_140L0625R0006_0002.pdf PDF
Attachment_17_-_SV_Sign-In-Sheet_Orovada_0002.pdf PDF
Attachment_3_-_SOW__REVISED_Orovada_General-Site_0001.pdf PDF
Sol_140L0625R0006_Amd_0001.pdf PDF
Attachment_14_-_BLM_Orovada_Fire_Station_Design_BP2_-_Reference_Planset_0001.pdf PDF
Attachment_13_-_BLM_Orovada_Fire_Station_Design_BP1_-_Reference_Planset_0001.pdf PDF
Attachment_7_-_Prototypical_Crew_Quarters_Building_2025-01-22.pdf PDF
Attachment_8_-_Orovada_Fire_Station_Reports_and_Feasibility_Study.pdf PDF
Attachment_9_-_Orovada_WFC_Sustainable_Doc_2025-03-13.pdf PDF
Attachment_11_-_Past_Performance_Questionnaire.docx DOCX document
Attachment_12_-_SF1442_Instructions_P1.pdf PDF
Attachment_4_-_Orovada_Plans_2025-03-10.pdf PDF
Attachment_1_-_SOW_Orovada_Fire_Station_Building_2025-03-11.pdf PDF
Attachment_2_-_SOW_Orovada_Crew_Quarters_2025-03-11.pdf PDF
Attachment_3_-_SOW_Orovada_General-Site_2025-03-11.pdf PDF
Attachment_5_-_OWFS_Performance_Specs_2025-03-14.pdf PDF
Attachment_6_-_Orovada_WFC_Room_Requirements_FSB_2025-01-16.pdf PDF
Attachment_10_-_Orovada_Letters.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION CALL

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0044008956

BLM CONSTRUCTION and A&E - NOC

DENVER FEDERAL CENTER

BUILDING 85

PO BOX 25047

LNC

DENVER CO 80225-0047

Jonathan Peterson 3147080329

1x 04/08/2025

140L0625R0006

INVITATION FOR BID

REQUEST FOR PROPOSAL

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Phase One Attachments

Attachment 1 - Statement of Work - Fire Station Building

Attachment 2 - Statement of Work - Crew Quarters

Attachment 3 - Statement of Work - General

Attachment 4 - Plans

Attachment 5 - Performance Specifications

Attachment 6 - Room Requirements

Attachment 7 - Prototypical Crew Quarters Building

Attachment 8 - Fire Station Reports and Feasibility Study

Attachment 9 - Sustainability Implementation

Attachment 10 - Orovada Letters

Attachment 11 - Past Performance Questionnaire

Attachment 12 - Phase 1-SF1442 Completion Instructions

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

7 710 calendar days and complete it within ________________ ________________ calendar days after receiving

FAR 52.211-10

05/09/2025

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 12/2022)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

BLM CONSTRUCTION and A&E - NOC

DENVER FEDERAL CENTER

BUILDING 85

PO BOX 25047

LNC

DENVER CO 80225-0047

Nathan Roush

28. NEGOTIATED AGREEMENT 29. AWARD

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

10 U.S.C. 3204(a) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 12/2022) BACK

Continued...

and return

(Contractor is not required to sign this document.) Your offer on this

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 46

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140L0625R0006

GAOA - Orovada Fire Engine Cover & Crew Quarters, NV

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

140L0625R0006 GAOA – Orovada Fire Engine Cover & Crew Quarters, NV

Type of Contract: Design/Build Construction, Firm Fixed Priced (FFP), Single Award Contract County: Humboldt County, NV Type of Construction: Building

FAR Magnitude: $5M - $10M NAICS: 236220 SIZE STD: $45.0M SET-ASIDE: Total Small Business

Bureau of Land Management Contacts

Contracting Officer (CO) Contract Specialist (CS) (Primary Contact)

Name: Nathan Roush Jonathan Peterson

Email: nroush@blm.gov jrpeterson@blm.gov

Proposal Submittal Information: Key deadlines for each phase are shown as follows. Please note that only those offerors who are determined to be the most highly qualified after phase one reviews will be requested to participate in phase two.

Phase One Deadlines (All Offerors)

Site Visit: April 17, 2025 / 12PM Local Time (See clause instructions / FAR 52.236-27)

Questions Due Date: April 25, 2025 / 2PM Mountain Time

Proposal Due Date: May 09, 2025 / 2PM Mountain Time

Phase Two Deadlines (Invited Offerors Only)

Proposal Due Date: TBD after review of phase one proposals

Question Due Date: TBD after review of phase one proposals

SOLICITATION NO: 140L0625R0006

PROJECT DESCRIPTION: GAOA – Orovada Fire Engine Cover & Crew Quarters, NV

Table of Contents

SECTION A: SOLICITATION / CONTRACT FORM

SECTION B: BID SCHEDULE

SECTION C: SPECIFICATIONS/DRAWINGS

SECTION D: PACKAGING AND MARKETING

SECTION E: INSPECTION AND ACCEPTANCE

SECTION F: DELIVERIES OR PERFORMANCE

SECTION G: CONTRACT ADMINISTRATION DATA

SECTION H: SPECIAL CONTRACT REQUIREMENTS

SECTION I: CONTRACT CLAUSES

SECTION J: LIST OF ATTACHMENTS

SECTION K: REPRESENTATIONS, CERTIFCATIONS, AND OTHER STATEMENTS OF OFFERORS

SECTION L: INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

SECTION M: EVALUATION FACTORS FOR AWARD

PART I – THE SCHEDULE

SECTION A: SOLICITATION / CONTRACT FORM

Refer to pages 1-3 of this solicitation package (SF1442 - Solicitation, Offer, and Award).

(END OF SECTION)

SECTION B: BID SCHEDULE

CONTRACT PRICE SCHEDULE

The competition for this project will be conducted in two separate phases.

PHASE ONE: Schedule and pricing shall not be submitted during phase one.

PHASE TWO: Offerors selected by the government from Phase One shall complete and submit the pricing worksheet attached for Phase Two, including all options and Limitations on Subcontracting Breakout (See Attachments).

SECTION C: SPECIFICATIONS/DRAWINGS

The statement of work and all attachments are included in section J and incorporated herein by reference.

SECTION D: PACKAGING AND MARKETING

Not Applicable.

SECTION E: INSPECTION AND ACCEPTANCE

CLAUSES INCORPORATED BY REFERENCE

Clause Title Date

52.246-12 Inspection of Construction August 1996

SECTION F: DELIVERIES OR PERFORMANCE

CLAUSES INCORPORATED BY REFERENCE

Clause Title Date

52.242-14 Suspension of Work April 1984

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (April 1984)

The Contractor shall be required to

(a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 710 calendar days after receipt of the notice to proceed. The time stated for completion shall include final cleanup of the premises.

SECTION G: CONTRACT ADMINISTRATION DATA

CLAUSES INCORPORATED BY FULL TEXT

DIARS 1452.201-70 AUTHORITIES AND DELEGATIONS (September 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

(End of clause)

G-1 CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM

1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.

3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.

4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.

5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.

a) Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.

b) Your comments should focus on objective facts in the AO's narrative and should a)provide your views on the causes and ramifications of the assessed performance.

c) All information provided should be reviewed for accuracy prior to submission.

d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.

e) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.

f) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."

6) The following guidelines apply concerning your use of the past performance evaluation:

a) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.

b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.

7) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

G-2 ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System

(IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

1. Invoice date and Government Contract Number

2. Billing period specified with beginning and ending dates. The beginning date must not be later than the completion date or within any previous billing dates.

3. The accounting must follow the approved schedule of values as described in the specification attachment.

4. Total amount due for the billing period

5. Certification of Progress Payment

6. Payrolls (Mail weekly)

7. Substantiation of Subcontractor Payment

8. 52.223-9 Certification with final payment request.

9. A Release of Claims (See 1452.204-70) with a request for final payment.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

https://www.ipp.gov/

G-3 LOCAL INTERNET PAYMENT PLATFORM (IPP) HOTLINE

To check payment status, contact the Payment Hotline at 877-480-9724 or 303-236-2850. You will need to leave a message with the following information:

1. Company Name

2. Contract Number

3. Invoice Number

4. Invoice Amount

5. A brief description of why you are calling

6. Your contact information

If you do not receive a callback from the Payment Hotline within 72 hours, please contact the Contract Officer with the day and time you contacted the Payment Hotline.

G-4 GOVERNMENT POINTS OF CONTACT

Contract Specialist (Primary POC) Jonathan Peterson jrpeterson@blm.gov Bureau of Land Management, OC-664 Building 85, Denver Federal Center P.O. Box 25047 Denver, CO 80225-0047

Contracting Officer Nathan Roush nroush@blm.gov Bureau of Land Management, OC-664 Building 85, Denver Federal Center P.O. Box 25047 Denver, CO 80225-0047

G-5 CONSTRUCTION CONTRACT ADMINISTRATION

FAR 36.211(b) requires that agencies provide descriptions of policies and procedures that apply to the definitization of equitable adjustments for change orders under construction contracts. Data on the time required to definitize equitable adjustments for change orders can be found at: https://www.doi.gov/pam/acquisition/policy/constructioncontract.

SECTION H: SPECIAL CONTRACT REQUIREMENTS

H-1 WORK HOURS

The performance period established for this contract is based upon all work being conducted during regular working hours between 7:00am and 5:30pm, Monday through Friday, excluding government holidays. If the contractor desires to carry on work outside regular hours (Saturdays, Sundays, government holidays), a written request must be submitted to the contracting officer in sufficient time allow satisfactory arrangements to be made by the government for access to the work site and inspection.

H-2 FIRE DANGER SEASON

If the Government allows the contractor to continue work during periods of declared fire danger or season, the contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the Government.

H-3 DRAWINGS

(a) Reference scope of work.

(b) Typical Drawings. Any drawings titled typical are general only and dimensions of each structure will be fixed by the contracting officer to adapt the design to existing conditions at the structure location.

(c) Reduced Size Drawings. Any drawings identified as "REDUCED SIZE DRAWINGS" appearing in the solicitation are photographically reduced in size. Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. Prospective offerors desiring to review a copy of the full-size drawings may contact the primary contracting office point-of-contact contracting identified in the solicitation.

H-4 PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA

(a) The Historic and Archeological Data Preservation Act of 1974 provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.

(b) If, in connection with operations under this contract, the contractor, subcontractors, or the employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the contractor shall immediately suspend all operations in the vicinity of the cultural value and shall notify the contracting officer in writing, giving the location and nature of the findings. No objects of cultural resource value may be removed.

(c) Where appropriate by reason of discovery, the contracting officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the Changes clause.

(d) The contractor will be responsible for protecting the cultural resources within the affected area from damage. In addition, the contractor will be liable for all damage to the identified cultural resources caused by their actions or the actions of their agents or representatives. The contractor shall immediately notify the contracting officer or his representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.

H-5 SAFETY AND QUALITY CONTROL PLAN

Within 10-days following contract award, the contractor must provide effective quality control and safety plans for acceptance by the government.

H-6 FEDERAL HOLIDAYS

The following federal holidays are observed, to include those proclaimed by executive order:

New Year’s Day Martin Luther King Jr. Day President’s Day Memorial Day

Juneteenth Day Independence Day Labor Day Columbus Day

Veterans’ Day Thanksgiving Day Christmas Day

H-7 LIMITATIONS ON SUBCONTRACTING REPORTING

In accordance with 52.219-14 Limitations on Subcontracting, the prime contractor must perform at least 15% of the cost of the contract, excluding the cost of materials with its own employees and employees of a similarly situated subcontractor. A similarly situated subcontractor is a small business concern subcontractor that is a participant of the same SBA program that qualified the prime contractor as an eligible offeror and awardee of the contract. The contractor is responsible for ensuring compliance with the Limitations on Subcontracting clause.

At the conclusion of the period of performance and prior to final payment, the contractor shall submit a Limitations on Subcontracting Report directly to the Contracting Officer. The following information is required as part of the report:

1) The total amount paid to the prime during the performance period broken out by labor and materials

2) List of similarly situated subcontractors and the amounts paid to each during the performance period broken out by labor and materials

3) List of any other subcontractors and the amounts paid to each during the performance period broken out by labor and materials

If the contracting officer review of the report finds that the contractor is not in compliance for the period of performance, the contractor will be notified in writing. Penalties for failure to comply are described in 13 CFR 125.6(h) which states:

Whoever violates the requirements set forth in paragraph (a) of this section shall be subject to the penalties prescribed in 15 U.S.C.

645(d), except that the fine shall be treated as the greater of $500,000 or the dollar amount spent, in excess of permitted levels, by the entity on subcontractors. A party's failure to comply with the spirit and intent of a subcontract with a similarly situated entity may be considered a basis for debarment on the grounds, including but not limited to, that the parties have violated the terms of a government contract or subcontract pursuant to FAR 9.406-2(b)(1)(i) (48 CFR 9.406-2(b)(1)(i)).

H-8 KEY PERSONNEL, SUBCONTRACTORS, AND OUTSIDE ASSOCIATES OR CONSULTANTS

The firms, key personnel, subcontractors, and outside associates or consultants proposed and/or awarded under the contract must remain fixed for the duration of the contract unless a change request to permanently substitute the aforementioned is submitted in writing and approved by the Contracting Officer. The contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes and qualifications for the proposed substitutes, and any additional information requested by the Contracting Officer. Should there be a specialized service unavailable within the contractor team, the contractor shall provide a detailed explanation of the circumstances necessitating the proposed addition, complete resumes and qualifications for the proposed addition, and any additional information requested by the Contracting Officer. Addition of firms, key personnel, subcontractors, and outside associates or consultants is at the sole discretion of the Contracting Officer. The Contracting Officer will notify the Contractor within 30 calendar days after receipt of all required information of the decision for requested substitutions or additions.

(END OF SECTION & PART I)

PART II – CONTRACT CLAUSES

SECTION I: CONTRACT CLAUSES

CLAUSES INCORPORATED BY REFERENCE

Clause Title Date

52.202-1 Definitions June 2020 52.203-3 Gratuities April 1984 52.203-5 Covenant Against Contingent Fees May 2014 52.203-6 Restrictions on Subcontractor Sales to the Government June 2020 52.203-7 Anti-Kickback Procedures June 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity May 2014 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity May 2014 52.203-12 Limitation on Payments to Influence Certain Federal Transactions June 2020 52.203-13 Contractor Code of Business Ethics and Conduct November 2021 52.203-14 Display of Hotline Poster(s) November 2021 52.203-17 Contractor Employee Whistleblower Rights Nov 2023 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements January 2017 52.204-9 Personal Identify Verification of Contractor Personnel January 2011 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards June 2020 52.204-13 System for Award Management Maintenance October 2018 52.204-14 Service Contract Reporting Requirements October 2016 52.204-19 Incorporation by Reference of Representations and Certifications January 2025 52.204-21 Basic Safeguarding of Covered Contractor Information Systems November 2021 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or

Provided by Kaspersky Lab and Other Covered Entities December 2023

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment

November 2021

52.204-27 Prohibition on a ByteDance Covered Application June 2023 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded January 2025

52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters October 2018 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations November 2015 52.210-1 Market Research November 2015

52.215-2 Audit and Records – Negotiation June 2020 52.215-8 Order of Precedence – Uniform Contract Format October 1997 52.215-21, Alt III Requirements for Certified Cost or Pricing Data and Data Other than Certified Cost or Pricing Data – Modifications November 2021 October 1997

52.219-8 Utilization of Small Business Concerns January 2025 52.219-28 Post-Award Small Business Program Representation January 2025 52.222-3 Convict Labor June 2003 52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation March 2018 52.222-6 Construction Wage Requirements August 2018 52.222-7 Withholding of Funds May 2014 52.222-8 Payrolls and Basic Records July 2021 52.222-10 Compliance with Copeland Act Requirements February 1988 52.222-11 Subcontracts (Labor Standards) May 2014 52.222-12 Contract Termination-Debarment May 2014

52.222-13 Compliance with Construction Wage Rate Requirements and Related Act Regulations May 2014 52.222-14 Disputes Concerning Labor Standards February 1988 52.222-15 Certification of Eligibility May 2014 52.222-35 Equal Opportunity for Veterans June 2020 52.222-36 Equal Opportunity for Workers with Disabilities June 2020 52.222-37 Employment Reports Veterans June 2020 52.222-40 Notification of Employee Rights Under the National Labor Relations Act December 2010 52.222-50 Combating Trafficking in Persons November 2021 52.222-54 Employment Eligibility Verification January 2025 52.222-55 Minimum Wages Under Executive Order 13658 January 2022 52.222-62 Paid Sick Leave Under Executive Order 13706 January 2022 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts May 2024 52.223-3 Hazardous Material Identification and Material Safety Data, Alternate I February 2021

July 1995 52.223-5 Pollution Prevention and Right-to-Know Information May 2024

52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons May 2024

52.223-19 Aerosols May 2024 52.223-21 Foams May 2024 52.223-23 Sustainable Products and Services May 2024 52.225-13 Restrictions on Certain Foreign Purchases February 2021 52.226-7 Drug-Free Workplace May 2024 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving May 2024 52.227-1 Authorization and Consent June 2020 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement June 2020 52.227-4 Patent Indemnity – Construction Contracts December 2007 52.228-2 Additional Bond Security October 1997 52.228-5 Insurance – Work on a Government Installation January 1997 52.228-11 Pledges of Assets February 2021 52.228-12 Prospective Subcontractor Requests for Bonds December 2022 52.228-14 Irrevocable Letter of Credit November 2014 52.228-15 Performance and Payment Bond – Construction June 2020 52.229-3 Federal, State and Local Taxes February 2013 52.232-5 Payments under Fixed-Price Construction Contracts May 2014 52.232-17 Interest May 2014 52.232-23 Assignment of Claims May 2014 52.232-27 Prompt Payment for Construction Contracts January 2017 52.232-33 Payment by Electronic Funds Transfer-- System for Award Management October 2018 52.232-39 Unenforceability of Unauthorized Obligations June 2013 52.232-40 Providing Accelerated Payments to Small Business Subcontractors March 2023 52.233-1, Alt 1 Disputes May 2014

December 1991 52.233-3 Protest After Award August 1996 52.233-4 Applicable Law for Breach of Contract Claim October 2004 52.236-2 Differing Site Conditions April 1984 52.236-3 Site Investigation and Conditions Affecting the Work April 1984 52.236-5 Material and Workmanship April 1984

52.236-6 Superintendence by the Contractor April 1984 52.236-7 Permits and Responsibilities November 1991 52.236-8 Other Contracts April 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements April 1984 52.236-10 Operations and Storage Areas April 1984 52.236-11 Use and Possession Prior to Completion April 1984 52.236-12 Cleaning up April 1984 52.236-13 Accident Prevention November 1991 52.236-14 Availability and Use of Utility Services April 1984 52.236-17 Layout of Work April 1984 52.236-21, Alt I Specifications and Drawings for Construction February 1997

April 1984 52.236-26 Preconstruction Conference February 1995 52.242-13 Bankruptcy July 1995 52.242-14 Suspension of Work April 1984 52.243-4 Changes June 2007 52.244-6 Subcontracts for Commercial Products and Commercial Services February 2024 52.245-1 Government Property September 2021 52.245-9 Use and Charges April 2012

52.246-21 Warranty of Construction March 1994 52.248-3 Value Engineering – Construction October 2020 52.249-2, Alt I Termination for Convenience of the Government (Fixed-Price) April 2012

September 1996 52.249-10, Alt I Default (Fixed-Price Construction) April 1984 52.253-1 Computer Generated Forms January 1991 DIAR 1452.203-70 Restrictions on Endorsements – Department of the Interior July 1996

CLAUSES INCORPORATED BY FULL TEXT

52.217-7 OPTION FOR INCREASED QUANTITY – SEPARATELY PRICED LINE ITEM (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor 15 days prior to exercise of the option.

Delivery of added option shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

52.219-14 LIMITATIONS ON SUBCONTRACTING (October 2022) (DEVIATION OCT 2022)

(a) This clause does not apply to the unrestricted portion of a partial set-aside.

(b) Definition. Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that—

(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and

(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.

(c) Applicability. This clause applies only to—

(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);

(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);

(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;

(4) Orders expected to exceed the simplified acquisition threshold and that are—

(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or

(ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);

(5) Orders, regardless of dollar value, that are—

(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or

(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and

(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.

(d) Independent contractors. An independent contractor shall be considered a subcontractor.

(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees to the following requirements in the performance of a contract assigned a North American Industry Classification System (NAICS) code applicable to this contract:

(1) Services (except construction). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding certain other direct costs and certain work performed outside the United States (see paragraph (e)(1)(i)), to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract.

(i) The following services may be excluded from the 50 percent limitation:

(A) Other direct costs, to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service. Examples include airline travel, work performed by a transportation or disposal entity under a contract assigned the environmental remediation NAICS code (562910), cloud computing services, or mass media purchases.

(B) Work performed outside the United States on awards made pursuant to the Foreign Assistance Act of 1961, or work performed outside the United States required to be performed by a local contractor.

(2) Supplies (other than procurement from a nonmanufacturer of such supplies). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract.

(3) General construction. It will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 85 percent subcontract amount that cannot be exceeded.

(4) Construction by special trade contractors. It will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 75 percent subcontract amount that cannot be exceeded.

(f) The Contractor shall comply with the limitations on subcontracting as follows:

(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause –

☒ By the end of the base term of the contract and then by the end of each subsequent option period; or ☐ By the end of the performance period for each order issued under the contract.

(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.

(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (e) of this clause will be performed by the aggregate of the joint venture participants.

52.223-2 REPORTING OF BIOBASED PRODUCTS UNDER SEVICE AND CONSTRUCTION CONTRACTS (MAY 2024)

(DEVIATION FEBRUARY 2025)

(a)Definitions. As used in this clause—

Biobased product means a product determined by the U.S. Department of Agriculture (USDA) to be a commercial product or industrial product (other than food or feed) that is composed, in whole or in significant part, of biological products, including renewable domestic agricultural materials and forestry materials, or that is an intermediate ingredient or feedstock. The term includes, with respect to forestry materials, forest products that meet biobased content requirements, notwithstanding the market share the product holds, the age of the product, or whether the market for the product is new or emerging. ( 7 U.S.C.

8101) (7 CFR 4270.2)

USDA-designated product category means a generic grouping of products that are or can be made with biobased materials—

(1)That are listed by USDA in a procurement guideline available at ttps://www.biopreferred.gov/resources/categories.html;and (2)For which USDA has provided purchasing recommendations (available at https://www.biopreferred.gov or 7 CFR part 4270).

(b)The Contractor shall report to https://www.sam.gov, with a copy to the Contracting Officer, on the product types and dollar value of any biobased products in USDA-designated product categories purchased by the Contractor during the previous Government fiscal year, between October 1 and September 30; and

(c)Submit this report no later than—

(1)October 31 of each year during contract performance; and (2)At the end of contract performance.

52.223-23 SUSTAINABLE PRODUCTS AND SERVICES (MAY 2024) (DEVIATION FEB 2025)

(a)Definitions. As used in this clause—

Biobased product means a product determined by the U.S. Department of Agriculture (USDA) to be a commercial product or industrial product (other than food or feed) that is composed, in whole or in significant part, of biological products, including renewable domestic agricultural materials and forestry materials, or that is an intermediate ingredient or feedstock. The term includes, with respect to forestry materials, forest products that meet biobased content requirements, notwithstanding the market share the product holds, the age of the product, or whether the market for the product is new or emerging. ( 7 U.S.C.

8101) ( 7 CFR 3201.2).

Recovered material means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process. ( 42 U.S.C. 6903).

Sustainable products and services means

(i)Products containing recovered material designated by the U.S. Environmental Protection Agency (EPA) under the Comprehensive Procurement Guidelines ( 42 U.S.C. 6962) ( 40 CFR part 247) ( https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program#products).

(ii)Energy- and water-efficient products that are ENERGY STAR® certified or Federal Energy Management Program (FEMP)-designated products ( 42 U.S.C. 8259b) ( 10 CFR part 436, subpart C) ( https://www.energy.gov/eere/femp/search-energy-efficient-products and https://www.energystar.gov/products?s=mega).

(iii)Biobased products meeting the content requirement of the USDA under the BioPreferred® program ( 7 U.S.C.

8102) ( 7 CFR Part 4270) ( https://www.biopreferred.gov).

(iv)Acceptable chemicals, products, and manufacturing processes listed under EPA's Significant New Alternatives Policy (SNAP) program, which ensures a safe and smooth transition away from substances that contribute to the depletion of stratospheric ozone ( 42 U.S.C. 7671l) ( 40 CFR part 82, subpart G) ( https://www.epa.gov/snap).

(b)Requirements.

(1)The sustainable products and services, including the purchasing program and type of product or service, that are applicable to this contract, and any products or services that are not subject to this clause, will be set forth in the statement of work or elsewhere in the contract.

(2)The Contractor shall ensure that the sustainable products and services required by this contract are— (i)Delivered to the Government;

(ii)Furnished for use by the Government;

(iii)Incorporated into the construction of a public building or public work; and (iv)Furnished for use in performing services under this contract, where the cost of the products is a direct cost to this contract (versus costs which are normally applied to the Contractor's general and administrative expenses or indirect costs). This includes services performed by contractors performing management and operation of Government-owned facilities to the same extent that, at the time of award, an agency would be required to comply if an agency operated or supported the facility.

(c)Resource. The Green Procurement Compilation (GPC) available at https://sftool.gov/greenprocurement provides a comprehensive list of sustainable products and services and sustainable acquisition guidance. The Contractor should review the GPC when determining which [statutory] purchasing programs apply to a specific product or service.

52.225-11 BUY AMERICAN - CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (November 2023)

(a) Definitions. As used in this clause— Caribbean Basin country construction material means a construction material that—

(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or https://www.epa.gov/snap

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation

(FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C.40102(4), such as agricultural products and petroleum products.

Component means an article, material, or supply incorporated directly into a construction material.

Construction material means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S.

supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency.

The list of critical items is at FAR 25.105.

Designated country means any of the following countries:

(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, North Macedonia, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);

(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);

(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea- Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or

(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).

Designated country construction material means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if—

(A) The cost of its components…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .