This is a Closeout and Operation & Maintenance (O&M) Requirements Template issued by the National Park Service Denver Service Center dated January 27, 2021.

The template is a checklist document designed to track and ensure completion of closeout and O&M submittals for NPS construction projects. It is organized by topic categories including Project Record Drawings, System Demonstration and Training, Tools/Spare Parts/Equipment, Extra Stock, Reports, Keys & Keying Schedule, and O&M Data/Warranties/Guarantees. The document specifies submittal requirements across multiple specification sections (referenced by CSI division numbers) and includes columns to document submittal dates, completion status, and park receipt confirmation. Key requirements include submission of project record drawings per sections 01770 and 87100; maintenance materials and tools inventory; extra stock quantities ranging from 2% to 12% of amounts installed depending on material type and specification section; various reports including inventory lists of salvaged items, research reports for post-installed anchors, material and compliance certificates, and qualification data; keying schedules; warranties with specified durations (ranging from 18 months for panelboards to 10 years for vapor retarder barrier materials); and comprehensive O&M manuals and maintenance data for mechanical, electrical, and plumbing systems including domestic water piping, HVAC equipment, furnaces, condensing units, split system AC, VRF systems, luminaires, and flushometer valves. The template serves as an administrative tool to ensure contractors provide all necessary documentation and materials required for project completion and long-term facility operations and maintenance.

View the file

Other files for this federal contract opportunity

Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Closeout and Operation & Maintenance (O&M) Requirements Template National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21

Topic Specification

Section Requirement

Submittal

Date Completed

Received by Park

01770 Project Record Drawings

Project Record 87100 Project Record Drawings

Drawings

System

Demonstration and Training

87100 Maintenance Materials & Tools

Tools

Spare Parts

Equipment

93013 3% Tile, Trim and Grout Attic Stock

Extra Stock 95113 2% Ceiling Panels, Suspension System & Hold-Down Clips

96513 Minimum 10 Linear Feet of each Product

96519 One box for every 50 boxes installed.

96813 5% of amount installed

96813 5% of amount installed

99113 5% of amount installed

99123 5% of amount installed

99300 5% of amount installed

101423 12 Replacement Inserts

102113 Extra Hardware Parts, One Each

102600 2% of amount installed

122413 5% of amount installed

24119 Inventory: Submit a list of items that have been removed and salvaged.

Reports 55000 Research Reports: For post-installed anchors.

61000 Material Certificates

62013 Compliance Certificates

64116 Qualification Data: For manufacturer and Installer. Field quality-control reports.

17000 Keying Schedule

Keys & Keying 87100 Keying Schedule

Schedule

16700 Sustainable Design Close-Out Documents

17000 Closeout Submittals

17000 Warranties Submittal

17823 O & M Manuals Submittal

19114 Commissioning Closeout Documents

Closeout and Operation Maintenance (O) Requirements Template | National Park Service (NPS) - Denver Service Center (DSC) page 1 of 2

Topic Specification

Section Requirement

Submittal

Date Completed

Received by Park

24119 Demolition Closeout Submittals

33000 Sheet vapor retarder barrier material and accessories for sheet vapor retarder barrier and accessories: 10 years

62013 Engineered Wood Manufacturer's Warranty

76200 Maintenance Data

76200 Special Warranties

79200 Warranties Submittal

79219 Warranties Submittal

79219 Warranties Submittal

81416 Warranties Submittal

84113 Warranties Submittal

84113 O & M Manuals Submittal

85113 Warranties Submittal

87100 Warranties Submittal

87100 Maintenance Data

88000 Warranties Submittal

95113 O & M Manual Submittal

96519 Maintenance Data

96813 Maintenance Data

96813 Maintenance Data

96813 Warranties Submittal

101423 Maintenance Data

101423 Maintenance Data

102113 Maintenance Data

102600 Maintenance Data

102800 Maintenance Data

102800 Warranties Submittal

104413 Maintenance Data

104416 Warranties Submittal

104416 Maintenance Data

122413 Maintenance Data

123661 Maintenance Data

221119 Operation and Maintenance Data: For domestic water piping specialties

224213 Operation and Maintenance Data: For flushometer valves and electronic sensors

224216 Maintenance Data for Sinks

224713 Miantenance Data for Drinking Fountains

233300 Maintenance Data for Air Duct Accessories

232423 Operation and Maintenance Data for HVAC power ventilators

235416 Operation and Maintenance Data for Furnaces

236200 Operation and Maintenance Data for Condensing Units

238126 Operation and Maintenance Data for Split System AC

O&M Data 238129 Opeartion and Maintenance Data for VRF

Warranties 265119 Materials and Workmanship for luminaires: Five years

Guarantees 262416 Panelboards: 18 months

262416 SPD: Five Years