This document is a storm water pollution prevention plan (SWPPP) for a construction site that will disturb between 1 to 5 acres. The SWPPP outlines erosion and sediment controls, waste management procedures, potential pollutants, inspection requirements, and other best practices to prevent stormwater pollution during construction activities. It includes appendices with a site map, inspection records template, hazardous materials SDSs, and a project completion report form. The SWPPP provides guidance on developing and implementing controls for temporary and permanent stabilization, structural practices, good housekeeping, and spill prevention. Inspections must occur every 14 days and within 24 hours of 0.5 inches of rain. Records must be kept on site for three years after final stabilization.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STORM WATER POLLUTION PREVENTION PLAN
For Sites that disturb 1 to 5 Acres Version: Feb. 2016
Project Name:
Plan Accessibility: A copy of this plan will be kept at the following on site location:
I. Posting of Notice
A notice will be posted at the main entrance of the construction site with the following information:
A. LPDES
Permit No.
B. Effective
Permit Date
C. Local POC D. Brief
Project
Description
E. Location of this SWPPP
LAR200000 March 1, 2013 Name:
Telephone No:
II. Note: A complete copy of LAR20000 is available at Louisiana's DEQ website.
Select Division, Water Permits, LPDES Permits, Water Discharge General Permits, LAR200000.
III. Project Description. Briefly describe the project's function and all soil disturbing construction activities that will take place.
IV. Site Information
A. Site map: Must be filed in Appendix A; depicts the following:
Drainage pattern
Approximate slope after major grading
Areas of soil disturbance
Location of major structural (e.g. basins, swales, outfalls) and nonstructural controls (e.g. minimize soil disturbance/compaction, revegetation)
Expected areas of stabilization
Locations of off-site material, waste, borrow, or storage
Surface waters and/or wetlands
Location of storm water discharge to surface water
B. Area of site (in acres):
C. Area of soil disturbance (in acres):
FA460822R0001
Attachment 5
V. Sequence of Major Activities
The order of activities will be as follows: (grubbing, excavation, grading, etc.)
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Attach a separate page if additional items are needed.
VI. Runoff Coefficient
Industrial/Residential= .75 Steep Grassy Area= .20 Flat Grassy Area= .15
Pre construction:
Post construction:
VII. Additional Site Information
A. Name of Receiving Waters:
B. Do storm water discharges from the site have an effect on endangered/threatened species and/or critical habitat? _________ (Yes/No)
C. If so, explain the proximity of endangered/threatened species and/or critical habitat to the site and whether such species may be affected by the site’s storm water discharges.
D. Describe wetlands that will be disturbed or receive discharges from disturbed area of project:
E. Do storm water discharge-related activities have an effect on a property that is listed or eligible for listing on the National Register of Historic Places? _______ (Yes/No)
F. If so, fully describe the places, agreements with the State Historic Preservation
Officer, measures to minimize adverse impacts, and all other items in LAR200000-AI
92973 Part III D.1.j.
Neatness does not count.
FA460822R0001
VIII. Controls
A. Erosion and Sediment Controls: Short and Long term goals and criteria.
The controls that follow are designed to retain sediment on site to the maximum extent practical and have been selected and will be installed and maintained in accordance with good engineering practices. If periodic inspections or other information indicates a control has been used inappropriately or incorrectly, it will be replaced or modified and noted in Appendix B, the records of inspections. A stabilized construction entrance will be provided. Sediment on the paved street adjacent to this entrance will be removed at a frequency sufficient to minimize off-site impact. Dust shall be minimized.
Stabilization Practices-Existing vegetation will be preserved where practical. Use of impervious surfaces for stabilization will be avoided. Disturbed site areas will establish temporary or permanent vegetation.
B. Temporary Stabilization- Measures will be initiated at the site or portion there of after construction activity has ceased for 14 days unless activity will resume within 21 days. If weather (snow or drought) makes this impractical, then stabilization will begin as soon a practical.
The site specific temporary stabilization measures are as follows:
C. Permanent Stabilization- Measures will be initiated at the site or portion there of after construction activity has ceased for 14 days unless activity will resume within 21 days. If weather (snow or drought) makes this impractical, then stabilization will begin as soon a practical.
The site specific permanent stabilization measures are as follows:
D. Structural Practices-These will be used to divert flows from exposed soils, store flows, or otherwise limit runoff and the discharge of pollutants from exposed areas of the site to the degree attainable. Placement of these structural practices in floodplains will be avoided if possible. Installation of these devices may be subject to Section 404 of the
Clean Water Act.
E. Site Specific structural practices are:
Revisions should occur.
FA460822R0001
IX. Log of major soil disturbing and stabilization activities. Any time soil disturbance activities begin or stop and/or stabilization practices are implemented, fill in the date, description of activity, and whether stabilization measures are temporary or permanent.
Date Begin activity/cease activity/stabilization If stabilization occurred:
temporary or permanent Ex: 18 Feb 2016 Broadcast grass seed. Permanent
X. Storm Water Management
A. Good Housekeeping-
As possible, only enough product to complete job will be stored on site
Containers will be stored neatly in their original container with lids closed when not in use.
Substances will not be mixed unless recommended by manufacturer
Materials will be kept under roof when possible
Materials will be disposed of according to manufacturer’s recommendation
Site will be cleaned up each day
B. Hazardous Materials-
Prior to the start of construction, a list of all Hazardous Materials and a copy of each SDS will be put in Appendix C
Products will be kept in their original container and stored in a designated location in a manner that will prevent spills and contamination of run-off
Hazardous materials will be handled and disposed of in accordance with all applicable federal, state, and local laws and regulations
C. Waste Disposal-Regular, Hazardous, Sanitary
All solid waste will be disposed of at a state approved, off-base landfill
Recycling will take place whenever feasible
Prior to the beginning of any process that will generate hazardous waste, 2 CES/CEIE will be notified at 456-4629 and provided with information about the proposed action, duration, and the amount of waste to be generated
All hazardous waste will be managed in strict compliance with federal, state, and local regulations
All hazardous waste generated on the base must be processed through the Central
Accumulation Point (456-8580) for disposal
FA460822R0001
XI. Potential Pollutant Inventory
A. These products are expected to be on site during the project.
XII. Product Specific Practices
Petroleum-Vehicles will be checked for leaks and repaired if leaks are noted.
Products will be stored in tightly sealed containers.
Asphalt- Products will be applied per manufacturer’s recommendations.
Paints-All containers will be tightly sealed and stored when not in use. No paint may be poured out
Equipment with latex paint must be washed in a sink that discharges to sanitary sewer
XIII. Spill Control Practices
In addition to the Good Housekeeping and Product Specific Practices discussed in the previous sections, the following practices for spill prevention and clean up will be in effect:
A spill kit will be kept at the staging area
The spill kit contents will be sufficient to cleanup a spill from the largest single container on site that does not have secondary containment
Spill debris will be properly containerized and disposed of
Call 911 if there is a spill that causes an emergency
Call 456-5256, 3522, & 2770 to report spills and receive info if needed.
Fines for not complying with this SWPPP can be as much as $15,000/day/violation.
FA460822R0001
XIV. Maintenance/Inspection Procedures
A. The following are the inspection and maintenance practices that will be used to maintain erosion and sediment controls. If a repair is required, it will be initiated within
24 hours
Disturbed areas, structural control measures, and locations where vehicles enter/exit the site will be inspected at least every 14 days, before anticipated storm events, and within 24 hours of a storm event (≥ 0.5 in) will be inspected
Built up sediment will be removed from silt fences when it reaches one-third the height of the silt fence.
Silt fences will remain properly secured and be inspected for tears
Diversion dikes will be inspected for breaches
Temporary and permanent seeding and planting will be inspected for bare spots, washouts, and healthy growth
An inspection report will be made after each inspection. A form is provided in
Appendix B. The completed report will be filed in this appendix.
B. If there is an inspection by the LDEQ of this plan and site, record
Date of inspection:
Are changes to plan or controls required? _______ (yes/no) If yes, these must be implemented within 7 calendar days.
XV. Non-Storm Water Discharges
A. It is expected that the following non-storm water discharges will occur from the site during the construction period (e.g. fire hydrant flushing, water from dust control):
XVI. Record Retention
A. A copy of this storm water pollution Prevention Plan and all records and reports required by LAR 20000 will be kept by the permittee for a period of three years from the date of final stabilization for the site unless that date is extended by the State
Administrative Authority.
Date of final stabilization: __________________________________.
XVII. Report Submittal
A. Once construction is complete and the site has been stabilized, a Small Construction
Activity Completion Report (SCACR) must be submitted within SIXTY (60) DAYS after
COMPLETION of covered activities.
The Small Construction Activity Completion Report is available in the Addendum B of
LAR200000 General Permit which may be downloaded at
(http://www.deq.louisiana.gov/portal/Default.aspx?tabid=245) (LAR200000 from the bottom of the Water Discharge General Permits list)
A copy is also provided in Appendix D.
I certify under penalty of law that this document and any attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information contained herein.
Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for attesting to false information, including the possibility of fine and imprisonment for knowing violations.
Print Name Signature
Title Date http://www.deq.louisiana.gov/portal/Default.aspx?tabid=245
APPENDIX A
Site Map
This page left blank intentionally.
APPENDIX B
RECORD OF INSPECTIONS
Date of
Inspection
Inspector Has a copy of the Inspection Checklist been placed in this Appendix?
Construction Site Inspection Checklist
Project Name:
Inspector’s Name: Date:
Inspector’s Telephone Number:
Inspector’s Qualifications:
Date of last rainfall: Amount of last rainfall: inches
Area of Inspection
Attach Additional Pages if needed for Soil Disturbed Areas
Soil Disturbed Area 1. Describe:
Date of last disturbance:
Date of next disturbance:
Stabilized (yes/no):
Stabilized with:
Condition:
Note: Stabilization, if required, must be initiated by ______________ (no longer than 14 days from date of last disturbance) (date)
Soil Disturbed Area 2. Describe:
Date of last disturbance:
Date of next disturbance:
Stabilized (yes/no):
Stabilized with:
Condition:
Note: Stabilization, if required, must be initiated by ______________ (no longer than 14 days from date of last disturbance) (date)
Exposed Materials Storage Area 1. Describe:
Are there signs of pollutants in the storm water discharge? _____ (yes/no)
_____________________________(date)
Structural Control Measure 1. Describe: Main Construction Entrance
Is sediment tracked onto road? _____ (yes/no) If so, is it cleaned up as required in the SWPPP?
Note: If changes to this control are required, they must be initiated by _________
(no longer than 7 days from inspection date) (date)
Checklist Continued
Structural Control Measure 2. Describe:
Is maintenance required? _____ (yes/no)
Note: If changes to this control are required, they must be implemented by
(no longer than 7days from inspection date) (date)
Based on this inspection, are changes to the SWPPP needed? _______ (yes/no)
I certify under penalty of law that this document and any attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information contained herein.
Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information is to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for attesting to false information, including the possibility of fine and imprisonment for knowing violations.
Print Name Signature
APPENDIX C
HAZARDOUS MATERIALS SDSs
Hazardous Material Expected to be on site
Has an SDS been filed in this Appendix?
APPENDIX D
Completion report
STATE OF LOUISIANA
DEPARTMENT OF ENVIRONMENTAL QUALITY
Office of Environmental Services, Permits Division
Post Office Box 4313
Baton Rouge, Louisiana 70821-4313
PHONE#: (225) 219-3181
FAX#: (225) 219-3309
SMALL CONSTRUCTION ACTIVITY
COMPLETION REPORT LAR200000
To be submitted within SIXTY (60) DAYS after COMPLETION of covered activities.
Section I – Operator Information
Name:
Mailing Address:
City: State: Zip:
Phone Number: DEQ AI# (if known):
Section II – Facility/Site Information
Name of Project:
Location of Project:
City: State: Zip:
Parish: Name of Receiving Water:
Total Area of Land Disturbance (in acres)
Construction Start Date:
Construction Completion/Site Stabilization Date:
List existing or prior water discharge permits for the location:
Section III - Certification I certify under penalty of law that project activities were completed in accordance with the requirements of the Clean Water Act and the Louisiana Environmental Quality Act, and specifically in accordance with the LPDES Small Construction General Permit, LAR200000, under which the storm water discharges related to the construction were authorized. I understand that submittal of this Report does not release an
Operator from liability for any violation of the permit or the Act. I further certify that the information submitted is, to the best of my knowledge and belief, true, accurate, and complete, and that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations.
Printed Name:
Signature:
Date:
APPENDIX E
Extra pages for notes
Notes: