Attachment 5- Scoring Criteria.pdf
PDF 149 KB Posted
- Attached to
- FP-2021-15A DA Tank Replacement
- Solicitation number
- S-580100-00002584
- Issued by
- Umatilla County, Oregon
About this file
The document provided is the Scoring Criteria for the FP-2021-15A EOU DA Tank Replacement bid. This bid is for a project located in Union County, Oregon. The scoring criteria outlines the maximum points available for each evaluation factor, including Price (60 points), Company Qualifications (20 points), Schedule (10 points), and References (10 points). The lowest bid will receive the maximum 60 points for the Price factor, while other bidders will receive a proportional score based on their bid price. The Company Qualifications factor requires bidders to describe their experience in Central Utility Plants and provide resumes for key team members. The Schedule factor evaluates the bidder's ability to perform the work within the required timeframe, including providing a Gantt chart and identifying long lead time items. The References factor requires bidders to provide three references for similar projects at universities or facilities comparable to EOU's Central Utility Plant.
The related state and local contract opportunity is for the FP-2021-15A DA Tank Replacement project, which includes the addition of Addendum No. 1 and five attachments related to roofing, Building Automation System (BAS) sequence of operations, boiler plant mechanical equipment, and other related documents.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FP-2021-15A
EOU DA TANK REPLACEMENT
BID SCORING CRITERIA
Description Max Points Available
Bidder 1 Score
Bidder 2 Score
Bidder 3 Score
Bidder 4Score
Price: Lowest bid will receive the maximum points available. Other bidders will receive a score that is calculated by dividing their price by lowest qualified price and multiplying the result by their score.
Company Qualifications: Describe your company’s experience working in Central Utility Plants. Please provide a list of similar projects successfully completed in the last 5 years. Provide resumes and qualifications for key team members ie, Project Manager, Superintendent, who will be assigned to this project.
Schedule: Ability to perform the work in the required time frame, start and finish date, completeness of Gantt Chart. Provide long lead time items and durations.
References: Provide three references at Universities or facilities similar to EOU’s Central Utility Plant
Total 100