Attachment 1- Plans.pdf
PDF 18 MB Posted
- Attached to
- FP-2021-15A DA Tank Replacement
- Solicitation number
- S-580100-00002584
- Issued by
- Umatilla County, Oregon
About this file
This document appears to be Attachment 1 - Plans related to the state and local contract opportunity FP-2021-15A DA Tank Replacement in Union County, Oregon. The opportunity involves adding Addendum no. 1 and 5 attachments, including documents related to roofing, HVAC building automation systems, boiler plant mechanical equipment, and addendum drawings. The key details of this opportunity include updating the existing procurement documents with these additional attachments.
The pricing terms, set asides, incumbents, funding requirements, and other salient information are not provided in the given document. The summary is limited to the key details about the added attachments and the agencies, consortiums, and/or jurisdictions involved, which are Union County, Oregon.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NORTH NORTH
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
C O N S U L T A N T
OWNER:
LOCATION:
MARK DATE DESCRIPTION
ONE UNIVERSITY BLVD
LA GRANDE, OREGON
MARCH, 2022
OWNER:
EASTERN OREGON
UNIVERSITY
One University Blvd.
La Grande, OR 97850
o. 541.962.3181
Contact: David Moore
Capital Projects Manager dnmoore@eou.edu
MECHANICAL & ELECTRICAL:
SYSTEMS WEST
ENGINEERS
725 A Street
Springfield, OR 97477
p. 415.323.8934 www.systemswestengineers.com
Contact: Meredith Osborn
S H E E T I N D E X
S I T E M A PV I C I N I T Y M A P
NOT TO SCALE NOT TO SCALE
SITE LOCATION
AREA OF WORK
/1
/2
:0 :5
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
B Y
JS
H
O N
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
03/16/2022
X033.01
G001
MLO
JSH
GNL
EASTERN OREGON UNIVERSITY
PHYSICAL PLANT
Permit Set
STEAM CENTRAL PLANT
SURGE & DEAERATOR
TANK REPLACEMENT
TITLE SHEET
G001 TITLE SHEET
M001 LEGEND, GENERAL NOTES, & SHEET INDEX
M101 DEMOLITION PLAN - LOWER LEVEL
M102 DEMOLITION PLAN - UPPER LEVEL
M110 PLUMBING FOUNDATION PLAN
M121 FLOOR PLAN - LOWER LEVEL
M122 FLOOR PLAN - UPPER LEVEL
M301 SECTIONS
M501 DETAILS
M601 SCHEDULES
M611 DIAGRAMS
M612 DIAGRAMS
E001 LEGEND, GENERAL NOTES, & SHEET INDEX
E101 DEMOLITION PLAN - LOWER LEVEL
E121 FLOOR PLAN - LOWER LEVEL
E611 DIAGRAMS
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
S-1.1 STRUCTURAL TITLE SHEET
S-2.1 FOUNDATION PLAN
P PPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPP
M E C H A N I C A L L E G E N D
PIPING GENERAL
CONTROLS
GENERAL NOTES
ABBREVIATIONS
SYMBOL ABBREV. DESCRIPTION
A
S
SD
SRV
CFR
W
CFS
MAV
AAV
M
RP
DV
BV
BFV
CHV
GV
GBV
PRV
AV
SV
AV
AV
AV
RV
SRV
SSV
TPS
FMS
FCV
ACH AIR CHANGES PER HOUR
AFF ABOVE FINISHED FLOOR
AFS AUTOMATIC FIRE SPRINKLER
AL ALUMINUM
ALT ALTERNATE
APD AIR PRESSURE DROP
BAS BUILDING AUTOMATION SYSTEM
BHP BRAKE HORSEPOWER
BOD BOTTOM OF DUCT
BTUH BRITISH THERMAL UNITS PER HOUR
CFH CUBIC FEET per HOUR CFM CUBIC FEET per MINUTE
CMU CONCRETE MASONRY UNIT
CONC CONCRETE
CONT CONTINUATION
(D) DEMOLITION
DB DRY BULB
dBa DECIBELS ACOUSTIC
DEMO DEMOLITION
DN DOWN
DP DIFFERENTIAL PRESSURE
(E) EXISTING
EAT ENTERING AIR TEMPERATURE
EER ENERGY EFFICIENCY RATIO
EFF EFFICIENCY
EG EXHAUST GRILLE
ESP EXTERNAL STATIC PRESSURE
EWT ENTERING WATER TEMPERATURE
FLA FULL LOAD AMPS
FPM FEET PER MINUTE
FT FEET
FT WC FEET WATER COLUMN
FUT FUTURE
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
GYP BD GYPSUM WALL BOARD
HP HORSEPOWER
HSPF HEATING SEASONAL
PERFORMANCE FACTOR
HVAC HEATING, VENTILATING, &
AIR CONDITIONING
HZ HERTZ (CYCLES PER SECOND)
IAQ INDOOR AIR QUALITY
IN INCHES
IN WC INCHES WATER COLUMN
IPLV INTEGRATED PART LOAD VALUE
IW INDIRECT WASTE
LAT LEAVING AIR TEMPERATURE
LBS POUNDS
LWT LEAVING WATER TEMPERATURE
mA MILLIAMPERE
MAX MAXIMUM
MBH THOUSAND BTUs per HOUR
MCA MINIMUM CIRCUIT AMPS
MFGR MANUFACTURER
MIN MINIMUM
MOP MAX. OVERCURRENT PROTECTION
(N) NEW
NC NOISE CRITERIA
NC NORMALLY CLOSED
NIC NOT IN CONTRACT
NO NORMALLY OPEN
NPLV NON-STANDARD PART LOAD VALUE
NPSH NET POSITIVE SUCTION HEAD
OFCI OWNER FURNISHED/CONTRACTOR
INSTALLED
OSA OUTSIDE AIR
PD PRESSURE DROP
PH PHASE
PPH POUNDS per HOUR PSI POUNDS per SQUARE INCH
REQ'D REQUIRED
RF RETURN FAN
RG RETURN GRILLE
RH RELATIVE HUMIDITY
RPM REVOLUTIONS per MINUTE
SD SUPPLY DIFFUSER
SEER SEASONAL ENERGY EFFICIENCY RATIO
SF SUPPLY FAN
SS STAINLESS STEEL
STL STEEL
TSP TOTAL STATIC PRESSURE
TYP TYPICAL
VFD VARIABLE FREQUENCY DRIVE
WB WET BULB
WC WATER COLUMN
WG WATER GAUGE
PIPING UP
PIPING DOWN
DIRECTION OF SLOPE
CAPPED PIPE
PIPE REDUCING FITTING:
CONCENTRIC, ECCENTRIC
DIRECTION OF FLOW
DRAIN VALVE
UNION
PUMP
BALL VALVE
BUTTERFLY VALVE
CHECK VALVE
GATE VALVE
GLOBE VALVE
BALANCING VALVE /
ECCENTRIC PLUG VALVE
AUTOMATIC CONTROL
VALVE: 2-WAY
AUTOMATIC CONTROL
VALVE: 3-WAY
AUTOMATIC BUTTERFLY VALVE
FLEXIBLE PIPE CONNECTION
PUMP SUCTION DIFFUSER
WYE STRAINER
BASKET STRAINER
PRESSURE REGULATING VALVE
THREE-WAY BYPASS VALVE
SOLENOID VALVE
RELIEF VALVE
SAFETY RELIEF VALVE
(HYDRONIC)
STEAM SAFETY VALVE
TEMPERATURE/PRESSURE
SAFETY VALVE
SELF CONTAINED CONTROL VALVE
CONSOLIDATED FITTING RETURN
CONSOLIDATED FITTING SUPPLY
THERMOMETER
PRESSURE GAUGE
TEST PLUG
SIGHT FLOW INDICATOR
SENSOR WELL
MANUAL AIR VENT
AUTOMATIC AIR VENT
AUTOMATIC FLOW CONTROL VALVE
VENTURI
WATER FLOW METER
STEAM TRAP
VACUUM BREAKER (STEAM)
FLOW MEASURING STATION
REDUCED PRESSURE
BACKFLOW PREVENTER
1. THE FACILITY WILL REMAIN IN OPERATION DURING CONSTRUCTION. COORDINATE ALL
SHUTDOWNS AND CONSTRUCTION ACTIVITY WITH FACILITIES STAFF.
2. SIZE AND LOCATION OF ALL PIPING AND OTHER MECHANICAL EQUIPMENT IS APPROXIMATE.
CONTRACTOR SHALL SITE VERIFY THE LOCATION OF EXISTING PIPING AND EQUIPMENT AND
CONSTRUCT WORK FROM FIELD DIMENSIONS. CONTRACTOR SHALL MAKE ADJUSTMENTS NECESSARY
TO ACCOMMODATE MINOR DEVIATIONS AT NO COST TO OWNER.
3. FINE (LIGHT) LINE WORK INDICATES EXISTING PIPING AND OTHER MECHANICAL EQUIPMENT. BOLD
(HEAVY) LINE WORK INDICATES NEW PIPING AND OTHER MECHANICAL EQUIPMENT.
4. IT IS RESPONSIBILITY OF THE CONTRACTOR TO PROVIDE CUTTING AND PATCHING TO
ALLOW THE INSTALLATION OF MATERIALS AND EQUIPMENT AS SPECIFIED AND SHOWN ON DRAWINGS.
SYMBOL ABBREV. DESCRIPTION SYMBOL DESCRIPTION
SYMBOL DESCRIPTION
(E)
OR diaø
SHEET NUMBER
SECTION LETTER
SHEET NUMBER
EQUIPMENT TYPE
EQUIPMENT NUMBER
EXISTING
DIAMETER
NEW TO EXISTING POINT OF CONNECTION
NOTE REFERENCE MARKER
PLAN OR DETAIL REFERENCE MARKER
SECTION REFERENCE MARKER W/VIEW DIRECTION
EQUIPMENT MARKER
ROOM NUMBER
EXISTING SHOWN LIGHT
NEW WORK SHOWN BOLD
EXISTING TO BE REMOVED
M-301
AHU
PLAN OR DETAIL NUMBER
SYMBOL DESCRIPTION
DEMOLITION NOTES
1. REVIEW DEMOLITION DRAWINGS FOR ITEMS TO REMAIN, TO BE RETAINED FOR RELOCATION, OR TO BE SALVAGED TO THE OWNER. REFER TO ARCHITECTURAL DOCUMENTS FOR ADDITIONAL REQUIREMENTS.
2. DEMOLISH EQUIPMENT, FIXTURES, DEVICES, PIPING, CONDUIT, FITTINGS, AND APPURTENANCES INTERIOR TO THE BUILDING THAT ARE MADE OBSOLETE BY THE NEW WORK AND/OR ARE ABANDONED
AND NO LONGER IN USE.
3. PROTECT AND MAINTAIN OPERABILE EXISTING EQUIPMENT, FIXTURES, OR SYSTEMS THAT ARE
INDICATED TO REMAIN, INCLUDING ELECTRICAL POWER, CONTROLS, AND RELATED SYSTEMS
REQUIRED TO MAINTAIN OPERABILITY.
4. EXISTING CONDITIONS SHOWN ARE BASED ON RECORD DOCUMENTS AND LIMITED FIELD
OBSERVATIONS OF ACCESSIBLE AREAS AND MAY NOT SHOW THE ENTIRE SCOPE OF DEMOLITION
WORK. OMISSION OF EXISTING EQUIPMENT, FIXTURES, DEVICES, PIPING, CONDUIT, FITTINGS, AND APPURTENANCES FROM THE DEMOLITION DRAWINGS DOES NOT RELIEVE THE CONTRACTOR OF THE RESPONSIBILITY TO PROVIDE DEMOLITION OF SYSTEMS THAT ARE MADE OBSOLETE BY THE NEW WORK, ARE ABANDONED, OR AS OTHERWISE REQUIRED TO PERFORM THE WORK DESCRIBED HEREIN.
5. PROTECT AND MAINTAIN SERVICES TO REMAIN OPERATIONAL THAT PASS THROUGH THE AREA OF CONSTRUCTION. WHERE IT IS NOT POSSIBLE TO MAINTAIN THESE SERVICES INTACT, REPLACE, REROUTE, MODIFY, OR PROVIDE NEW AS REQUIRED TO MAINTAIN SERVICES.
6. EQUIPMENT REMOVAL INCLUDES EXISTING PNEUMATIC CONTROLS COMPONENTS AND PERIPHERALS.
PNEUMATIC CONTROLS REMOVAL INCLUDES, BUT IS NOT LIMITED TO: COMPRESSED AIR TUBING, THERMOSTATS, SWITCHES, PNEUMATIC CONTROLLERS, AND DAMPER OPERATORS.
PACKAGE EQUIPMENT BOUNDRY
M-521
M101
A
A
A
FD FLOOR DRAIN
DP
P
T
AHU-1
H
G
CO2
C
PROCESS PIPING SIGNAL
ELECTRICAL SIGNAL
SPACE TEMPERATURE
SPACE HUMIDITY
SPACE CARBON DIOXIDE
SPACE MULTIFUNCTION
PRESSURE MEASUREMENT
TEMPERATURE MEASUREMENT
HUMIDITY MEASUREMENT
FLOW MEASUREMENT
ELECTRICAL CURRENT/POWER
S = SENSOR
T = TRANSMITTER
CO
CO2
NO2
GAS CONCENTRATION
T
FP
RELAY OR SWITCH
C = ELECTRIC CURRENT
FS = FLOW SWITCH
HP = HIGH PRESSURE
LP = LOW PRESSURE
A ACTUATOR - ELECTRIC
A
ES
AI
ALARM
VFD
CWP-2
AUTOMATIC CONTROL
DAMPER
BAS INPUT/OUTPUT POINT
EMERGENCY STOP SWITCH
AI = ANALOG INPUT
AO = ANALOG OUTPUT
DI = DIGITAL INPUT
DO = DIGITAL OUTPUT
FUNCTION DESIGNATION
S/S = START/STOP
EQUIPMENT CONTROL PANEL (W/EQUIP.
INDICATED UNDERLINED)
CP = CONTROL PANEL
BCP = BOILER CONTROL PANEL
CCP = CHILLER CONTROL PANEL
FAP = FIRE ALARM PANEL
MC = MOTOR CONTROLLER
VFD = VARIABLE FREQUENCY DRIVE
T
P
H
F S
G
CO2
SD SMOKE DETECTOR
HP
R
R C
RELAY FREEZE PROTECTION
RELAY
DP = DIFFERENTIAL POWER
T
AHU-1
SPACE THERMOSTAT
FWPD
FWPS
CTPD
CTPS
CPD
R
BD
CBD
BWS
FWS
CF
BFW
BOILER PLANT PIPING:
FEEDWATER PUMP DISCHARGE
FEEDWATER PUMP SUCTION
CONDENSATE TRANSFER PUMP DISCHARGE
CONDENSATE TRANSFER PUMP SUCTION
CONDENSATE PUMP DISCHARGE
PUMP RECIRCULATION
BOILER BLOWDOWN
CONTINUOUS BLOWDOWN
BOILER WATER SAMPLE
FEEDWATER SAMPLE (FROM DEAERATOR)
CHEMICAL FEED
BOILER FEEDWATER
STEAM & CONDENSATE PIPING:
HYDRONIC PIPING:
HS
HR
CDS
CDR
LPS
MPS
HPS
LPR
MPR
HPR
VR
PR
HEATING WATER SUPPLY
HEATING WATER RETURN
CONDENSER WATER SUPPLY
CONDENSER WATER RETURN
LOW PRESSURE STEAM
MEDIUM PRESSURE STEAM
HIGH PRESSURE STEAM
LOW PRESSURE RETURN
MEDIUM PRESSURE RETURN
HIGH PRESSURE RETURN
VACUUM RETURN
PUMPED RETURN
CWS
CWR
CHILLED WATER SUPPLY
CHILLED WATER RETURN
PLUMBING PIPING:
CW POTABLE COLD WATER
HW POTABLE HOT WATER
HWR POTABLE HOT WATER RETURN
NP NON-POTABLE COLD WATER
W SANITARY WASTE
V SANITARY PLUMBING VENT
IRW NON-POTABLE COLD WATER (IRRIGATION)
HTHW POTABLE HOT WATER - HIGH TEMP (140°F OR HIGHER)
PAW PUMPED ACID WASTE
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5 :2
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
LEGEND,
GENERAL
NOTES, &
SHEET INDEX
03/16/2022
X033.01
M001
MLO
JSH
GNL
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
A
M301
(E) BOILER B-2
(E) BOILER B-1
(E) CHILLER CH-2
(E) CHILLER CH-1
(E) CHILLED WATER AND
CONDENSER WATER PUMPS
(E) MCC-2
(E) MCC-1
(E) FEEDWATER HEAT / STORAGE TANK
(E) BAS CONTROL PANEL
(E) CHEMICAL TREATMENT SKID
DEMOLISH STEAM METER
CONTROL CABINET AND
ASSOCIATED POWER AND
CONTROL WIRING
ABANDONED BY WORK.
(E) 8" MPS
(E) 8" CWS (BELOW)
(E) 8" CWR
(E) 8" CDS
(E) 8" CWR
(E
6" C
D S
(E
6" C
D S
(E
8" C
W S
(E) 6" CWS
(E
8" C
W S
(E)
HX
M301
DEMOLISH STEAM CONTROL VALVE AND
ASSOCIATED PNEUMATIC CONTROLS
AND TUBING TO ACTIVE MAIN.
M301
M301
EXISTING WATER SOFTENING
SYSTEM. REMOVE AND
REINSTALL FOR CONNECTION TO
NEW EQUIPMENT.
(E) 4" CPD (BELOW)
(E) 6" CWS
(E) 6" CWR
(E) 6" MPS
(E) CONDENSATE RECEIVER/PUMP UNIT.
(E) CPD FROM FACILITIES SERVICES
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5 :2
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
DEMOLITION
PLAN - LOWER
LEVEL
03/16/2022
X033.01
M101
MLO
JSH
GNL
NORTH
1/4" = 1'-0"1
DEMOLITION PLAN - LOWER LEVEL
R E F E R E N C E N O T E S :
DEMOLISH BOILER FEEDWATER TANK, PUMPS, FRAMEWORK, AND APPURTENANCES.
EQUIPMENT TO REMAIN ON SITE UNTIL COMPLETION OF THE PROJECT FOR
TEMPORARY SERVICE RESULTING FROM ANY UNFORESEEN DELAYS IN DELIVERY.
REMOVE AND RELOCATE EXISTING BOILER FEEDWATER TANK, PUMPS, AND
FRAMEWORK UNDAMAGED TO A SAFE LOCATION WITHIN THE BOILER PLANT FOR
STORAGE DURING CONSTRUCTION. THE EQUIPMENT SHALL BE REMOVED AT
COMPLETION OF WORK AND WHEN THE EQUIPMENT IS NO LONGER OF BENEFIT TO
THE OWNER.
DEMOLISH (E) VENT, DRAIN, AND OTHER RELATED PIPING ASSOCIATED WITH
FEEDWATER HEATER THAT IS NOT INTENDED FOR RECONNECTION TO NEW
EQUIPMENT.
REMOVE EXISTING CHEMICAL TREATMENT SKID WITH SPILL CONTAINMENT BASE
AND STORE UNDAMAGED. REINSTALL AND RECONNECT POWER AND CHEMICAL
INJECTION PIPING TO NEW EQUIPMENT AS SHOWN ON DRAWINGS AND AS
REQUIRED TO PROVIDE INTENDED FUNCTION.
REMOVE EXISTING WATER SOFTNERS, ASSOCIATED EQUIPMENT, AND PIPING AND
STORE UNDAMAGED. REINSTALL AND RECONNECT POWER AND INLET AND SUPPLY
PIPING TO NEW EQUIPMENT AS SHOWN ON DRAWINGS AND AS REQUIRED TO
PROVIDE INTENDED FUNCTION.
S H E E T N O T E S :
1. REFER TO SPECIFICATION SECTION 01 23 00 FOR PROJECT SCOPE ASSOCIATED
WITH ADDITIVE ALTERNATE NO. 2
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
M301
(E) 12" MPS
(E) 8" MPS
(E
M P
S
(E) 10" MPS
(E) 10" MPS
DEMOLISH (E) STEAM FLOW SENSOR,
DIFFERENTIAL PRESSURE TRANSMITTERS,
PIPING, AND CONTROL WIRING.
DEMOLISH 2-1/2" MPS FROM
FEEDWATER HEATER TO
MPS MAIN AND CAP
DEMOLISH FWPD PIPING
M301
M301
(E) 2 1/2" FWPD
(E) 2" FWPD
(E) 1 1/2" CPD
M301
(E) 8" MPS(E) 12" MPS
(E) 4" CPD
DEMOLISH CPD PIPING
DEMOLISH (E) TANK VENT PIPING
UP THRU ROOF AND PATCH ROOFING
(E) FEED WATER HEATER / STORAGE
TANK. 1
DEMOLISH 2" V FOR CONNECTION
TO NEW EQUIPMENT
DEMOLISH NP PIPING
DEMOLISH CPD PIPING
(E) 3" CPD
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5 :2
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
DEMOLITION
PLAN - UPPER
LEVEL
03/16/2022
X033.01
M102
MLO
JSH
GNL
NORTH
1/4" = 1'-0"1
DEMOLITION PLAN - UPPER LEVEL
R E F E R E N C E N O T E S :
DEMOLISH (E) VENT, DRAIN, AND OTHER RELATED PIPING ASSOCIATED WITH
FEEDWATER HEATER THAT IS NOT INTENDED FOR RECONNECTION TO NEW
EQUIPMENT.
S H E E T N O T E S :
1. REFER TO SPECIFICATION SECTION 01 23 00 FOR PROJECT SCOPE ASSOCIATED
WITH ADDITIVE ALTERNATE NO. 2
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
(E) 4" W
(E) 4" W
(E) 3" W
(E
3" W
(E) 3" W UP
TO (E) DRAIN
(E) 3" W UP
TO (E) DRAIN
(E) 3" W UP
TO (E) DRAIN
(E) 3" W UP
TO (E) DRAIN
MANUFACTURER PROVIDED TANK
SUPPORT STAND.3" W UP TO DRAIN RECEIVER S-1.
CUT AND PATCH FLOOR AS NEEDED
TO PROVIDE NEW W PIPING
CONNECTION.
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5 :2
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
PLUMBING
FOUNDATION
PLAN
03/16/2022
X033.01
M110
MLO
JSH
GNL
NORTH
1/4" = 1'-0"1
PLUMBING FOUNDATION PLAN
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
A
(E) BOILER B-2
(E) BOILER B-1
(E) CHILLER CH-2
(E) CHILLER CH-1
(E) CHILLED WATER AND
CONDENSER WATER
PUMPS
(E) CONDENSATE
RECEIVER/PUMP UNIT.
(E) MCC-2
(E) MCC-1
DEAERATORSURGE
M301
(E) BAS CP
STEAM METER
CONTROL CABINET
(E) 6" CWS
(E) 8" CWS
(E) 8" MPS
(E) 8" CDS(E) 6" CDS
(E) 6" CDS
(E) 8" CWR
(E
8" C
W S
(E
8" C
W S
(E)
HX
(E) 6" CWR
M301
M301
TANK SUPPORT STAND.
3" W DN
EXISTING WATER SOFTENING
SYSTEM. RELOCATE AND EXTEND
CONNECTIONS AS NEEDED.
DRAIN COOLER AND SAMPLE
COOLER.
M301
DA CONTROL PANEL.
1-1/2" V UP
SURGE CONTROL PANEL.
EXISTING CHEMICAL CONTAINMENT. RELOCATE
AND EXTEND CONNECTIONS AS NEEDED.
(E) FLASH TANK.
(E) 2" FLASH TANK VENT UP
(E) 3" CPD FLASH UP
(E) 8" MPS UP
(E) 4" CPD UP
3" D
3/4" D
DRAIN
RECEIVER S-1
3" FWPD HEADER
3/4" R UP
(E) CPD FROM FACILITIES SERVICES
3/4" R UP
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5 :2
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
FLOOR PLAN -
LOWER LEVEL
03/16/2022
X033.01
M121
MLO
JSH
GNL
NORTH
1/4" = 1'-0"2
FLOOR PLAN - LOWER LEVEL
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
M301
DEAERATORSURGE
(E) 12" MPS
(E) 2" FWPD
(E) 2 1/2" FWPD
(E) 10" MPS
(E) 10" MPS
(E
M P
S
(E) 8" MPS
CAP MPS STEAM PIPING AT
BRANCH CONNECTION.
M301
M301
REPLACE EXISTING
STEAM FLOW
TRANSMITTER AND
ASSOCATED PIPING.
SEE 2/M501
FT-1
3/4" R
(E) 1 1/2" CPD
(E
1/
2" C
P D
3/4" R
3/ 4"
R
3/4" R DN TO FEED
WATER TRAIN
SEE 1/M611
3/4" R DN TO FEED
WATER TRAIN
SEE 1/M611
M301
(E) 4" CPD
(E) 12" MPS
(E) 3" CPD
1-1/2" V TO ROOF. COORDINATE
ROOF PENETRATION LOCATION
WITH EXISTING COOLING TOWERS.
1-1/2" V DN
(E) 6" MPS
(E) 8" MPS DN
(E) 4" CPD DN
6" V UP
THRU ROOF
(E) 2" V DN
TO FLASH TANK
(E) 2" V
(E) 1-1/2 NON-POTABLE
COLD WATER
1- 1/
2" N
P
(E) 1-1/2" NP
2" F
W P
D
1/
2" F
W P
D
2" V
1-1/2" NP DN
(E) 3" CPD DN
TO CONDENSATE
RECIEVER TANK
FWPD DN
PRV
1SSV
SSV
FT
1-1/4" V UP
THRU ROOF
2" V UP THRU
ROOF
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5 :2
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
FLOOR PLAN -
UPPER LEVEL
03/16/2022
X033.01
M122
MLO
JSH
GNL
NORTH
1/4" = 1'-0"1
FLOOR PLAN - UPPER LEVEL
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
UPPER LEVEL
11' - 0"
LOWER LEVEL
0' - 0"
M301
ROOF
18' - 4"
M301
DA
(E) 3/4" D
DA CONTROL PANELSURGE CONTROL PANELDRAIN COOLER
(E) WATER
SOFTENING
SYSTEM
UPPER LEVEL
11' - 0"
LOWER LEVEL
0' - 0"
M301
M301
ROOF
18' - 4"
DA
(E) 2" CPD
(E)
HX
(E) CHEMICAL CONTAINMENT
DA CONTROL PANEL
UPPER LEVEL
11' - 0"
LOWER LEVEL
0' - 0"
M301
M301
ROOF
18' - 4"
(E)
HX
(E) PANEL A
(E) WATER SOFTENING SYSTEM
UPPER LEVEL
11' - 0"
LOWER LEVEL
0' - 0"
M301
ROOF
18' - 4"
M301
FWP
FWP
FWP
TP
TP
(E) CHEMICAL
CONTAINMENT
(E) WATER
SOFTENING
SYSTEM
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:1 :3
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
SECTIONS
03/16/2022
X033.01
M301
MLO
JSH
GNL
1/4" = 1'-0"
SECTION A
1/4" = 1'-0"
SECTION B
2 1/4" = 1'-0"
SECTION C
3 1/4" = 1'-0"
SECTION D
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
FLOW METERING
DEVICE
TEMPERATURE WELL
FLOW FLOW
STRAIGHT PIPE STRAIGHT PIPE
INLET REDUCER
PROVIDE STRAIGHT SECTION OF REDUCED DIAMTER PIPING AT INLET AND OUTLET OF FLOW MEASURING DEVICE SAME SIZE AS METER.
LENGHT OF PIPING SHALL BE IN ACCORDANCE WITH MANUFACTURERS RECOMMENDATIONS.
INLET AND OUTLET STRAIGHT PIPING SHALL HAVE NO OBSTRUCTIONS SUCH AS THERMOWELLS, FITTINGS, STRAINERS, ETC.
INLET PIPE REDUCER SHALL BE CONCENTRIC FOR HYDRONIC APPLICATIONS AND ECCENTRIC FOR STEAM APPLICATIONS. OUTLET PIPE
REDUCER SHALL BE CONCENTRIC.
LOCATE REQUIRED MEASUREMENT DEVICES INCLUDING TEMPERATURE AND PRESSURE SENSORS DOWNSTREAM OF METERING DEVICES IN
FULL DIAMETER PIPING.
1 2 1 2
T P
REFERENCE NOTES:
DRIP LEG
(TYP)
3/4" DRAIN (ALTERNATE
LOCATIONS) (TYP)
STEAM LINE (TYP)
CAP (TYP)
DRIP LEG PIPE SIZE SAME AS STEAM
MAIN UNLESS OTHERWISE NOTED.
STEAM LINE DRIP LEG
3/4" MINFROM DRIP
CONNECTION
DRIP RETURN
3/8" TEST CONNECTION
1 1
M
IN
T O
M A
IN
R
E Q
U
IP
M E
N T
I
6" M
IN
M
IN
T O
M A
IN
R
E Q
U
IP
M E
N T
I
6" M
IN
FROM STEAM MAIN OR
EQUIPMENT.
FULL SIZE DIRT LEG
WITH CLEAN- OUT
CAP AT END.
M
IN
6" M
IN
M P
S /H
P S
MPS/HPS MPR/HPR
12" FROM BOTTOM OF STEAM MAIN OR EQUIPMENT OUTLET
REFERENCE NOTES:
D
PROVIDE UNION UNLESS
SAFETY VALVE HAS
FLANGED OUTLET
SAFETY VALVE
OPEN DRAIN
(NOTE 3)
CONNECTION TO
PRESSURE
VESSEL OR PIPE
VENT PIPE HORIZONTAL THROUGH
PENTHOUSE WALL MIN. 8' ABOVE
ROOF LEVEL. SUPPORT AS
INDICATED ON DWGS. (NOTES 1, 2)
PIPE THREADED INTO ELBOW
(SAME SIZE AS ELBOW)
DRIP PAN ELBOW
(SECTIONAL VIEW)
3/4" DRAIN TO FLOOR DRAIN OR
OPEN SIGHT DRAIN (NOTE 4)
1" M
IN
24" MAX.
3"
E L E V A T I O N
DETAIL NOTES:
1. UNLESS OTHERWISE SHOWN ON THE DRAWINGS, SIZE THE VENT PIPE SO THAT STEAM IS NOT
BLOWN OUT AT THE VENT PIPE ENTRANCE. UTILIZE THE CALCULATION METHOD CONTAINED IN
ANSI B31.1. POWER PIPING CODE, APPENDIX II.
2. VENT PIPE SHALL TERMINATE 8' MIN. ABOVE FINISHED ROOF.
3. DISCHARGE OF DRAIN MUST BE DIRECTED AWAY FROM PLATFORMS OR OTHER AREAS WHICH
PERSONNEL MAY OCCUPY.
4. DO NOT CONNECT ANY OTHER DRAIN TO THE DRIP PAN ELBOW DRAIN PIPE.
FLEXIBLE CONNECTOR
SAMPLE COOLER
PROVIDE
STRUCTURAL
CHANNEL SUPPORT.
INSTALL ABOVE
DRAIN RECEIVER
S-1.
1/4" SAMPLE
OUTLET
B W
S
N P
D
3/4" NP
ROUTE DRAINS
TO SINK.
3/4" FROM
DA-1
STRAINER
BALL VALVE
WATER TEMPERATURE
REGULATING VALVE
COLD WATER -
SEE PLANS FOR
ROUTING.
CAPILLARY TUBE
A
FROM DEAERATOR OVERFLOW
EXTEND TO WITHIN
4" BOTTOM OF SINK
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5 :3
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
DETAILS
03/16/2022
X033.01
M501
MLO
JSH
GNL
NOT TO SCALE
FLOW METER TRANSMITER
NOT TO SCALE
STEAM DRIP LEG ASSEMBLY W/STEAM TRAP
NOT TO SCALE
STEAM TRAP ASSEMBLY - MED/HI PRESSURE
NOT TO SCALE
STEAM SAFETY VALVE
NOT TO SCALE
WATER SAMPLE COOLER
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
NOT TO SCALE
BOILER BLOWDOWN COOLER
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:1 :3
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
SCHEDULES
03/16/2022
X033.01
M601
MLO
JSH
GNL
(1)MUST BE LESS THAN OR EQUAL TO SAFETY VALVE CAPACITY. STEAM IS DRY AND SATURATED.
S T E A M P R E S S U R E R E D U C I N G V A L V E
TAG QUANTITY
REQUIRED CAPACITY
(LBS/HR)
MAX FLOW WIDE-OPEN
VALVE (LBS/HR) (1)
PRESSURE (PSIG)
REMARKSIN OUT
PRV-1 1 2000 2,800 25.0 7.0
(1)FLOW RATE SHALL EXCEED MAXIMUM FLOW OF PRV OR BYPASS VALVE.
S T E A M S A F E T Y V A L V E
TAG QUANTITY SYSTEM / LOCATION MINIMUM CAPACITY (1) (LB/HR) SET PRESSURE (PSIG) REMARKS
SSV-01 1 DEAERATOR 1200 15 SENTINEL RELIEF VALVE FURNISHED BY UNIT MANUFACTURER
SSV-02 1 DEAERATOR 3000 50
(1)MOTOR CONTROL FURNISHED BY DIV. 23
(2)MS: MOTOR STARTER, VFD: VARIABLE FREQUENCY DRIVE, ECM: ECM MOTOR CONTROLLER, CR: CONTROL RELAY
P U M P
TAG MANUFACTURER MODEL SERVICE TYPE
FLOW
(GPM)
TOTAL HEAD
(FT)
NPSH
(FT)
MOTOR MOTOR
CONTROL (1) (2) REMARKSVOLTS PHASE RPM HP
FWP-01 GRUNDFOS CRE10 BOILER FEEDWATER VERT.MULTI-STAGE 35 250.0 3.0 480 3 3450 5 VFD INTEGRATED VFD
FWP-02 GRUNDFOS CRE10 BOILER FEEDWATER VERT.MULTI-STAGE 35 250.0 3.0 480 3 3450 5 VFD INTEGRATED VFD
FWP-03 GRUNDFOS CRE10 BOILER FEEDWATER VERT.MULTI-STAGE 35 250.0 3.0 480 3 3450 5 VFD INTEGRATED VFD
TP-01 GRUNDFOS CRE15 CONDENSATE VERT.MULTI-STAGE 85 130.0 3.0 480 3 3450 7.5 VFD INTEGRATED VFD
TP-02 GRUNDFOS CRE15 CONDENSATE VERT.MULTI-STAGE 85 130.0 3.0 480 3 3450 7.5 VFD INTEGRATED VFD
F L O W T R A N S M I T T E R
TAG MANUFACTURER MODEL SERVICE TYPE
PIPE SIZE
(IN)
MAX PRESSURE
DROP
(PSI)
FLOW RATE TEMPERATURE
RANGE
(°F)
OPERATING
PRESSURE
(PSIG) REMARKSMIN MAX
FT-1 CADILLAC CV-P STEAM VORTEX 6 3.0 1,010 16,700 250-350 25
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
P PP P P P P P P P P P P P P P P P
P P
P P
P P
P P
P P
P P
P P
P P
P P
P P
P PP P P P P P P P P P P P P P P P
S
PIPI TI TI
PI TI
B
SW
LILT
DEAERATOR
TANK
CPDCAMPUS PUMPED
CONDENSATE RETURN
PUMPED CONDENSATE
RETURN FROM PLANT
CONDENSATE
RECEIVER
PUMPED
CONDENSATE FROM
FACILITES SVCS
CPD
C F
F W
P D
F W
P D
FLUE
GAS
ECONOMIZER
FWPD
FWPD
V
3/4"
BOILER 1
ATMOSPHERE
2"
2"
1"
1 1/2"
2"
3/4"3/4"
BO
2"
2"
3/4"
C B
D
TO BLOWDOWN
VENT
THRU
ROOF
CPD
C P
D
C P
D
V
VENT
THROUGH
ROOF
FROM CW
PRV STATION
CHEMICAL
FEEDWATER
TREATMENT
(E) BOILER 2
2"
2 1/2"
1"
BO
NON-POTABLE
COLD WATER
1 1/2"
1-1/2"
1-1/2"
3/4"
3/4"
C B
D
TO BLOWDOWN COOLER
D
4"
TO SAMPLE COOLER
2"
FROM WATER
COLUMN DRAINS
3/4"3/4"
S
3/4"
E C
D E
C D
ECD
RV
FEEDWATER RECIRCLULATION
FEEDWATER SUPPLY
SURGE TANK
SCOPE BOUNDARY OF
PACKAGED UNIT. REFER
TO SPECIFICATIONS
FOR DETAILED UNIT
DESCRIPTION
ORIFICE PLATE OR
BALANCING VALVE
ORIFICE PLATE OR
BALANCING VALVE
3"
3/ 4"
R
2- 1/
2" F
W P
D
3/ 4"
R
(E
2- 1/
2" F
W P
D
(E
2" F
W P
D
3/4" R
3/4" R
FWP
FWP
FWP
TP
TP
3/ 4"
R
3/ 4"
R
(E
2- 1/
2" F
W P
D
2" FWPD
2-1/2" FWPD
1- 1/
4" V
V E
N T
T O
R O
O F
TO DRAIN
RECEIVER
VENT
TO ROOF
C P
D
NP
1/ 2"
6" 6" 1/ 2" 2"
3"
D 3/
4"
OVERFLOW
FLOAT VALVE
O D
3"
TO DRAIN
RECEIVER
TO DRAIN
RECEIVER
TO DRAIN
RECEIVER
SOFTENED
WATER SUPPLY
1"
LCV
1- 1/
2" 2-
1/ 2"
6"
1- 1/
2"
4" 4"
3"
CF1/2"
FLASH TANK LPS
VENT 2" V V
V
D 3/
4"
3"
2- 1/
2"
2- 1/
2"
2- 1/
2"
TI TI
AI
VFD
TP-1
VFD
TP-2
VFD
FWP-1
VFD
FWP-2
VFD
FWP-3
DO
DI
AO
DI
DO
DI
AO
DI
DO
DI
AO
DI
DO
DI
AO
DI
DO
DI
AO
DI
PT
AI
LLA
LLA
DI DI
LT
D 3/
4"
AI
TO DRAIN
RECEIVER
OVERFLOW
DRAIN
COOLER
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5 :3
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
DIAGRAMS
03/16/2022
X033.01
M611
MLO
JSH
GNL
NOT TO SCALE
BOILER WATER SCHEMATIC DIAGRAM
BAS POINTS LIST - BOILER WATER
POINT TYPE POINT NAME POINT COMM. POINT SOURCE
AI SURGE TANK LEVEL PTP
AI FEEDWATER SUPPLY PRESSURE PTP
AI DA TANK LEVEL PTP
AO TP-1 MOTOR SPEED COMMAND PTP VFD
AO TP-2 MOTOR SPEED COMMAND PTP VFD
AO FWP-1 MOTOR SPEED COMMAND PTP VFD
AO FWP-2 MOTOR SPEED COMMAND PTP VFD
AO FWP-3 MOTOR SPEED COMMAND PTP VFD
DI TP-1 MOTOR STATUS COM VFD
DI TP-1 MOTOR FAULT COM VFD
DI TP-2 MOTOR STATUS COM VFD
DI TP-2 MOTOR FAULT COM VFD
DI FWP-1 MOTOR STATUS COM VFD
DI FWP-1 MOTOR FAULT COM VFD
DI FWP-2 MOTOR STATUS COM VFD
DI FWP-2 MOTOR FAULT COM VFD
DI FWP-3 MOTOR STATUS COM VFD
DI FWP-3 MOTOR FAULT COM VFD
DI SURGE TANK LOW LEVEL ALARM PTP
DI DA TANK LOW LEVEL ALARM PTP
DO TP-1 START/STOP PTP VFD
DO TP-2 START/STOP PTP VFD
DO FWP-1 START/STOP PTP VFD
DO FWP-2 START/STOP PTP VFD
DO FWP-3 START/STOP PTP VFD
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
P PP P P P P P P P P
P P
P
P PP P P P P P P P
P P
P P
P B
2(E)
MPR TO CONDENSATE
STORAGE TANK SEE 1/M611.
LP
S
T O
F A
C
IL
IT
IE
S S
E R
V
IC
E S
M P
S T
O N
O
S O
H
A
LL
M P
S T
O C
A M
P U
S
CHEMICAL FEED
TO FLOOR
DRAIN
MPS
M P
S
BURNER
ROOF
PENETRATION
(TYP)
MPS
B
M P
S
MPR
D
M
S
10"
10" M
P S
3" 10
" 12"
1"
BURNER
12"
3/4"
4"
D D
D V
V
12"
1"
10"
12"
8"
1"
2 1/2"
8"
SSV SSV SSV
(E)
DEAERATOR TANK SURGE TANK
BOUNDARY OF ITEMS
INCLUDED ON UNIT SKID
D V
V
1"
8"
SSV SSV SSV
SSV
4" V
V E
N T
T O
R O
O F
SSV
2" V
V E
N T
T O
R O
O F
CAP EXISTING 2-1/2" MPS TO (E)
WATER TANK
6"
DA
FT
DO AO AO
ALTERNATE 1
DRIP PAN ELBOW.
SEE 1/M501
PT
PT
FT
FT
AI
PRV
SSV
SSV
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5 :3
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
DIAGRAMS
03/16/2022
X033.01
M612
MLO
JSH
GNL
NOT TO SCALE
STEAM SYSTEM SCHEMATIC DIAGRAM
BAS POINTS LIST - STEAM SYSTEM
POINT TYPE POINT NAME POINT COMM. POINT SOURCE
AI DEAERATOR STEAM PRESSURE
AO STEAM FLOWRATE
AO STEAM SUPPLY PRESSURE
DO STEAM TOTALIZED FLOW
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
E L E C T R I C A L L E G E N D
COMBINATION DISCONNECT AND MAGNETIC STARTER
NON-FUSED DISCONNECT WITH CHARACTERISTICS AS NOTED.
MAGNETIC STARTER
MOTOR CONNECTION
CONCEALED RACEWAY AND CONDUCTORS. NUMBER OF SLASHES
INDICATES NUMBER OF CONDUCTORS IF MORE THAN TWO. SIZE
OTHER THAN 12 AWG AS NOTED. (APPLIES TO ALL WIRING SYMBOLS)
UNDERGROUND OR UNDERFLOOR RACEWAY
HOMERUN
OVERHEAD POWER LINE
SPLICE
OHD
GROUND CONNECTION
CONDUIT UP
CONDUIT DOWN
JUNCTION BOX
JUNCTION BOX FLUSH WITH FLOOR OR AT GRADE
CONDUIT STUB
CABLE TRAY
CURRENT TRANSFORMER
ELECTRICAL EQUIPMENT AS NOTED ON DRAWINGS
SURFACE-MOUNTED CABINET, TYPE AS NOTED
ELECTRIC METER, TYPE AS NOTED
MECHANICAL EQUIPMENT DESIGNATOR, SEE SCHEDULES.
REFERENCE NOTE MARKER
PLAN OR DETAIL NUMBER
SHEET NUMBER
EXISTING WORK SHOWN LIGHT
NEW WORK SHOWN BOLD
EXISTING TO BE REMOVED (APPLIES TO DEMOLITION PLANS ONLY)
E-121
E-501
FUSED DISCONNECT WITH CHARACTERISTICS AS NOTED.
AS = SWITCH RATING, AF = FUSE RATING.
J
J
M
M
PB PULL BOX, SIZE AS NOTED OR AS REQUIRED
FB1
SURFACE-MOUNTED PANELBOARD (120/208V)
SURFACE-MOUNTED PANELBOARD (277/480V)
RECESSED PANELBOARD (120/208V)
RECESSED PANELBOARD (277/480V)
CT
AHU
SPD
T DISTRIBUTION TRANSFORMER
GROUNDING BUSBAR
SPECIAL PURPOSE RECEPTACLE WITH NEMA CONFIGURATION AS NOTED.L6-30R
PUSH BUTTON STATION
SIMPLEX RECEPTACLE
DUPLEX RECEPTACLE
QUADPLEX RECEPTACLE
FLUSH FLOOR BOX. REFER TO SPECIFICATIONS AND SCHEDULES FOR
DEVICE QUANTITIES AND TYPES.
FLUSH POKE-THROUGH FLOOR BOX. REFER TO SPECIFICATIONS AND
SCHEDULES FOR DEVICE QUANTITIES AND TYPES.
SPLIT-WIRED RECEPTACLE WITH HALF SWITCHED CONTROL VIA MANUAL
CONTROL, OCCUPANCY SENSING CONTROL, OR TIME BASED CONTROL.
REFER TO SPECIFICATIONS AND DRAWINGS.
RECEPTACLE WITH FULL SWITCHED CONTROL VIA MANUAL CONTROL,
OCCUPANCY SENSING CONTROL, OR TIME BASED CONTROL. REFER TO
SPECIFICATIONS AND DRAWINGS.
FB1 FLUSH FLOOR BOX WITH SWITCHED CONTROL VIA MANUAL CONTROL,
OCCUPANCY SENSING CONTROL, OR TIME BASED CONTROL. REFER TO
SPECIFICATIONS AND DRAWINGS.
PT3 FLUSH POKE-THROUGH FLOOR BOX WITH SWITCHED CONTROL VIA MANUAL
CONTROL, OCCUPANCY SENSING CONTROL, OR TIME BASED CONTROL.
REFER TO SPECIFICATIONS AND DRAWINGS.
LETTER DESIGNATOR(S) INDICATE ADDITIONAL RECEPTACLE
CHARACTERISTICS (APPLIES TO ALL RECEPTACLE AND FLOOR BOX TYPES):
A = INTEGRAL AFCI
B = INTEGRAL WITH USB OUTLET(S)
C = SUPPLIED POWER VIA CRITICAL BRANCH (NEC 517)
E = SUPPLIED POWER VIA LIFE SAFETY BRANCH (NEC 517)
G = INTEGRAL GFCI
IG = SUPPLIED POWER VIA AN ISOLATED GRD SYSTEM
P = INTEGRAL SURGE PROTECTIVE DEVICE
S = SUPPLIED POWER VIA OPTIONAL STANDBY BRANCH (NEC 702)
U = SUPPLIED POWER VIA A UPS
WP = WEATHERPROOF AND INTEGRAL GFCI
A
INDICATES RECEPTACLE ROUGH-IN HEIGHT FROM AFF TO CL OF
RECEPTACLE WHEN NOT AT STANDARD MOUNTING HEIGHT.+48"
INDICATES PANELBOARD AND BRANCH CIRCUIT NUMBER SERVING
RECEPTACLE.
2P1:12
INDICATES BRANCH CIRCUIT NUMBER SERVING RECEPTACLE. REFER TO
SHEET NOTES AND REFERENCE NOTES FOR SOURCE.
SURFACE MOUNTED RACEWAY WITH DUPLEX RECEPTACLES
RACEWAYS, BOXES, AND CONDUCTORS
ELECTRICAL EQUIPMENT - PLANS
WIRING DEVICES
ELECTRICAL EQUIPMENT AS NOTED
AUTOMATIC TRANSFER SWITCH
LV -1
3PH 4W
208V 225A
PANELBOARD WITH CHARACTERISTICS AS NOTED. WHERE NO
CHARACTERISTICS NOTED, SEE PANEL SCHEDULES.
PB PULL BOX, DIMENSIONS AS NOTED OR AS REQUIRED
T
T
T
SERVICE TRANSFORMER, PAD-MOUNTED
SERVICE TRANSFORMER, WITH VAULT
DISTRIBUTION TRANSFORMER
G
GENERATOR
PHOTOVOLTAIC INVERTER
ONE-LINE DIAGRAM
CIRCUIT BREAKER WITH CHARACTERISTICS AS NOTED
200A 3P
CIRCUIT BREAKER WITH INTEGRAL GROUND FAULT PROTECTIONG
200A 3P
SWITCH WITH CHARACTERISTICS AS NOTED200A
3P
200AS
200AF
3P
FUSED SWITCH WITH CHARACTERISTICS AS NOTED.
AS = SWITCH RATING, AF = FUSE RATING.
200A
200AS
200AF
SURGE PROTECTIVE DEVICE
EQUIPMENT CONNECTION
3000B FEEDER TAG. SEE FEEDER SCHEDULE.
E
FEEDER CONTINUATION CALLOUT. SEE CALLOUT ON DRAWING IDENTIFIED
WITH THE SAME LETTER TAG.
GENERAL
ABBREVIATIONS
(#) DESIGNATES QUANTITY
A AMPERE (AMP)
AC ALTERNATING CURRENT
AFC AVAILABLE FAULT CURRENT
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
AL ALUMINUM
ARCH ARCHITECT/ARCHITECTURAL
ATS AUTOMATIC TRANSFER SWITCH
AWG AMERICAN WIRE GAUGE
BLDG BUILDING
BOCT BOTTOM OF CABLE TRAY
BSC BIOLOGICAL SAFETY CABINET
C. CONDUIT
CENT CENTRIFUGE
CKT CIRCUIT
CL CENTERLINE
CLG CEILING
CRI COLOR RENDERING INDEX
CU COPPER
DC DIRECT CURRENT
DF DRINKING FOUNTAIN
DW DISHWASHER
(E) EXISTING
ECR ENVIRONMENTAL CONTROL ROOM
ELEC ELECTRICAL
EMERG EMERGENCY
EMT ELECTRICAL METALLIC TUBING
FA FIRE ALARM
FH FUME HOOD
FLA FULL LOAD AMPS
FTL FEED-THROUGH LUGS
GFCI GROUND FAULT CIRCUIT INTERRUPTER
GFP GROUND FAULT PROTECTION
GND GROUND
HP HORSEPOWER
IDF INTERMEDIATE DISTRIBUTION FRAME
INC INCUBATOR
K KELVIN
KW KILOWATT
KWH KILOWATT-HOUR
KV KILOVOLT
KVA KILOVOLT-AMPERE
KVAR KILOVOLT-AMPERE REACTIVE
LED LIGHT EMITTING DIODE
LM LUMENS
LV LOW VOLTAGE
LSI LSI ELECTRONIC TRIP UNIT
LSI/G LSI/G ELECTRONIC TRIP UNIT
LTG LIGHTING
MCA MINIMUM CIRCUIT AMPACITY
MCB MAIN CIRCUIT BREAKER
MCC MOTOR CONTROL CENTER
MDF MAIN DISTRIBUTION FRAME
MDS MAIN DISTRIBUTION SWITCHBOARD
MDP MAIN DISTRIBUTION PANELBOARD
MECH MECHANICAL
MLO MAIN LUG ONLY
MTS MAIN TRANSFER SWITCH
MVA MEGAVOLT-AMPERE
MW MEGAWATT
(N) NEW
(NL) NEW LOCATION
NA NOT APPLICABLE
NIC NOT IN CONTRACT
PA PUBLIC ADDRESS
PE PHOTOELECTRIC CELL
PF POWER FACTOR
PNL PANELBOARD
PV PHOTOVOLTAIC
PVC POLYVINYL CHLORIDE
PWR POWER
(R) REMOVE
(RL) RELOCATE
REFL REFLECTOR
SCCR SHORT CIRCUIT CURRENT RATING
SDP SUB-DISTRIBUTION PANELBOARD
SWBD SWITCHBOARD
TR TAMPER RESISTANT
TTB TELEPHONE TERMINAL BOARD
TV TELEVISION
TYP TYPICAL
UC UNDER CABINET
UG UNDERGROUND
UON UNLESS OTHERWISE NOTED
UPS UNINTERRUPTIBLE POWER SUPPLY
V VOLTAGE
VA VOLT-AMPERE
VP VAPOR PROOF
W WATT
WP WEATHERPROOF
XFMR TRANSFORMER
PT1
E1A-1 LAB EQUIPMENT DESIGNATOR, SEE SCHEDULES.
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5 :0
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
C
K
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
LEGEND,
GENERAL
NOTES, &
SHEET INDEX
03/16/2022
X033.01
E001
CKO
CKO
MBR
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
(E) MSB-CH
(E) PANEL A
(E) PANEL P
(E) MCC-1 (E) MCC-2
M M
2 2
(E) DA TANK
4 4
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5 :0
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
DEMOLITION
PLAN - LOWER
LEVEL
03/16/2022
X033.01
E101
CKO
CKO
MBR
NORTH
1/4" = 1'-0"1
ELECTRICAL DEMOLITION PLAN - LOWER LEVEL
R E F E R E N C E N O T E S :
1 PANEL P, TRANSFORMER, AND PANEL A ARE INTEGRATED INTO MCC-1
SWITCHGEAR. SEE SHEET E611 FOR DETAILS.
REMOVE CONNECTION TO EXISTING FWP-1 AND FWP-2. DEMOLISH WIRE AND
RACEWAY BACK TO MCC-1. REFER TO MECHANICAL DRAWINGS FOR ADDITIONAL
INFORMATION AND COORDINATE WITH MECHANICAL PRIOR TO COMMENCING
WORK.
RELOCATE AND EXTEND CONNECTION TO EXISTING CHEMICAL CONTAINMENT AND
WATER SOFTENING SYSTEM AS NEEDED. COORDINATE REQUIREMENTS WITH
MECHANICAL.
ADD ALTERNATE #2: EXTEND AND RECONNECT EXISTING CONDUIT AND FEEDER FOR
REUSE OF EXISTING PUMPS IN TEMPORARY LOCATION. SEE MECHANICAL
DRAWINGS FOR ADDITIONAL INFORMATION.
S H E E T N O T E S :
1. REVIEW DEMOLITION DRAWINGS FOR ITEMS TO REMAIN, TO BE RETAINED FOR
RELOCATION, OR TO BE SALVAGED TO THE OWNER. REFER TO ARCHITECTURAL
DOCUMENTS FOR ADDITIONAL REQUIREMENTS.
2. DEMOLISH EQUIPMENT, FIXTURES, DEVICES, PIPING, CONDUIT, FITTINGS, AND
APPURTENANCES INTERIOR TO THE BUILDING THAT ARE MADE OBSOLETE BY THE
NEW WORK AND/OR ARE ABANDONED AND NO LONGER IN USE.
3. PROTECT AND MAINTAIN OPERABLE EXISTING EQUIPMENT, FIXTURES, OR SYSTEMS
THAT ARE INDICATED TO REMAIN, INCLUDING ELECTRICAL POWER, CONTROLS,
AND RELATED SYSTEMS REQUIRED TO MAINTAIN OPERABILITY.
4. EXISTING CONDITIONS SHOWN ARE BASED ON RECORD DOCUMENTS AND LIMITED
FIELD OBSERVATIONS OF ACCESSIBLE AREAS AND MAY NOT SHOW THE ENTIRE
SCOPE OF DEMOLITION WORK. OMISSION OF EXISTING EQUIPMENT, FIXTURES,
DEVICES, PIPING, CONDUIT, FITTINGS, AND APPURTENANCES FROM THE
DEMOLITION DRAWINGS DOES NOT RELIEVE THE CONTRACTOR OF THE
RESPONSIBILITY TO PROVIDE DEMOLITION OF SYSTEMS THAT ARE MADE
OBSOLETE BY THE NEW WORK, ARE ABANDONED, OR AS OTHERWISE REQUIRED
TO PERFORM THE WORK DESCRIBED HEREIN.
5. PROTECT AND MAINTAIN SERVICES TO REMAIN OPERATIONAL THAT PASS
THROUGH THE AREA OF CONSTRUCTION. WHERE IT IS NOT POSSIBLE TO MAINTAIN
THESE SERVICES INTACT, REPLACE REROUTE, MODIFY, OR PROVIDE NEW AS
REQUIRED TO MAINTAIN SERVICES.
6. REFER TO SPECIFICATION SECTION 01 23 00 FOR PROJECT SCOPE ASSOCIATED
WITH ADDITIVE ALTERNATE NO. 2.
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
(E) MSB-CH (E) MCC-2
(E) PANEL A
(E) PANEL P
(E) MCC-1
J J
2 1
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5 :0
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
FLOOR PLAN -
LOWER LEVEL
03/16/2022
X033.01
E121
CKO
CKO
MBR
NORTH
1/4" = 1'-0"1
ELECTRICAL FLOOR PLAN - LEVEL
PROVIDE NEW CONNECTION TO DA-1. SEE MECHANICAL CONNECTION SCHEDULE
ON SHEET E611 FOR DETAILS. COORDINATE WITH MECHANICAL.
PROVIDE NEW CONNECTION TO SR-1. SEE MECHANICAL CONNECTION SCHEDULE
ON SHEET E611 FOR DETAILS. COORDINATE WITH MECHANICAL.
RELOCATE AND EXTEND CONNECTION TO EXISTING CHEMICAL CONTAINMENT AND
WATER SOFTENING SYSTEM AS NEEDED. COORDINATE REQUIREMENTS WITH
MECHANICAL.
1. PROTECT EXISTING LIGHT FIXTURES, EQUIPMENT, AND CIRCUITS TO REMAIN
DURING CONSTRUCTION
R E F E R E N C E N O T E S :
S H E E T N O T E S :
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
SPACE3P 3P
20A 3P
3P 20A 3P
3P
(E) PANEL P
3P/4W
480V/277Y 300A
T
(E) XFMR
4160V:480V/277Y
300KVA
TO EXISTING MAIN MSB
3P T
(E) XFMR
480V:120V/208Y
75KVA
(E) PANEL A
3P/4W
208Y/120V 225A
(E) MCC-1
400A BUS, 480V, 3-PHASE, 4-WIRE
(E) FUSED DISCONNECT
800AS/400AF
SECTION A SECTION B SECTION C SECTION D SECTION E
3P 3P
M M
FWP-1 FWP-2
300A 3P
90A 3P
SPARE SPARE SPARE SPARE SPARE SPARE
OIL
TRANSFER
PUMP
SPACE
40A 3P
3P 20A 3P
3P 20A 3P
3P
(E) PANEL P
3P/4W
480V/277Y 300A
T
(E) XFMR
4160V:480V/277Y
300KVA
TO EXISTING MAIN MSB
40A 3P T
(E) XFMR
480V:120V/208Y
75KVA
(E) PANEL A
3P/4W
208Y/120V 225A
(E) MCC-1
400A BUS, 480V, 3-PHASE, 4-WIRE
(E) FUSED DISCONNECT
800AS/400AF
SECTION A SECTION B SECTION C SECTION D SECTION E
3P 3P
J J
DA-1 SR-1
300A 3P
90A 3P
SPARE SPARE SPARE SPARE SPARE SPARE
OIL
TRANSFER
PUMP
1 1
DATE:
DRAWN:
CHECKED:
PROJECT:
DESIGNED:
725 A Street
Springfield, OR 97477
541.342.7210 systemswestengineers.com
SYSTEMS WEST ENGINEERS
OWNER:
LOCATION:
MARK DATE DESCRIPTION
/1
/2
:5 :0
P
M
STEAM CENTRAL
PLANT SURGE &
DEAERATOR TANK
REPLACEMENT
P
LO
T T E D
PHYSICAL
PLANT
ONE UNIVERSITY
BLVD, LA GRAND, OR
97850
EASTERN OREGON
UNIVERSITY
DIAGRAMS
03/16/2022
X033.01
E611
CKO
CKO
MBR
NOT TO SCALE
PARTIAL ONE-LINE DIAGRAM - DEMO
NOT TO SCALE
PARTIAL ONE-LINE DIAGRAM - NEW
PROVIDE NEW BREAKER AND CONNECTION TO NEW MECHANICAL EQUIPMENT IN
EXISTING MCC-1 BUCKET AND BYPASS EXISTING MOTOR STARTER. SEE
MECHANICAL EQUIPMENT SCHEDULE FOR CONDUCTOR SIZING AND ADDITIONAL
DETAILS.
R E F E R E N C E N O T E S :
1. MECHANICAL EQUIPMENT AND ASSOCIATED FEEDERS SHOWN ARE EXISTING TO
REMAIN, UON.
G E N E R A L N O T E S :
3. EQUIPMENT CONSISTS OF (2) PUMPS AT HORSEPOWER INDICATED FED FROM A SINGLE CONTROL PANEL. PROVIDE SINGLE POINT OF CONNECTION TO CONTROL PANEL. COORDINATE REQUIREMENTS WITH MECHANICAL.
2. EQUIPMENT CONSISTS OF (3) PUMPS AT HORSEPOWER INDICATED FED FROM A SINGLE CONTROL PANEL. PROVIDE SINGLE POINT OF CONNECTION TO CONTROL PANEL. COORDINATE REQUIREMENTS WITH MECHANICAL.
1. PROVIDE NEW BREAKER IN EXISTING MCC BUCKET AS INDICATED IN ONE-LINE DIAGRAM. BYPASS ANY EXISTING MOTOR CONTROLLER LOCATED WITHIN MCC.
NOTES:
2. WHERE INDICATED IN SCHEDULE ABOVE, DISCONNECTS SHALL BE FURNISHED AND INSTALLED BY DIVISION 26. COORDINATE DISCONNECT REQUIREMENTS WITH MECHANICAL.
1. PROVIDE CONDUCTORS WITH TYPE XHHW INSULATION FOR FEEDERS AND BRANCH CIRCUITS BETWEEN VFDS AND THEIR ASSOCIATED MOTORS.
GENERAL NOTES:
SURGE TANK - PUMP #2 480 3 7.5 11.0 NA DIV 23 DIV 23
SR-1
SURGE TANK - PUMP #1 480 3 7.5 11.0
(3) 10 AWG CU, (1) 10 AWG GND. IN 3/4" C. 40/3 MCC-1
NA DIV 23 DIV 23
1, 3
DEAREATER TANK - PUMP #3 480 3 5.00 7.6 NA DIV 23 DIV 23
DEAREATER TANK - PUMP #2 480 3 5.00 7.6 NA DIV 23 DIV 23DA-1
DEAREATER TANK - PUMP #1 480 3 5.00 7.6
(3) 6 AWG CU, (1) 10 AWG GND. IN 1" C. 50/3 MCC-1
NA DIV 23 DIV 23
1, 2
TAG DESCRIPTION VOLTAGE PHASE HP KW FLA FEEDER DESCRIPTION
CIRCUIT
BREAKER
(AMPS/POLES)
PANEL
IDENTIFICATION
STARTER
DIVISION
DISCONNECT
DIVISION
VFD
DIVISION
NOTES
MECHANICAL EQUIPMENT CONNECTION SCHEDULE
© Systems West Engineers, Inc. 2022. The signature in this document is encrypted. Editing this document is prohibited. (OAR 820)
CONCRETE WALLS & COLUMNS WALLS & COLUMNS
F`c = 2500 psi F`c = 3000 psi F`c = 4000 psi
Bar Size
Length of Lap Hook Embed
Ldh
Length of Lap Hook Embed
Ldh
Length of Lap Hook Embed
Ldh Ld & Ld & Ld &
Class A Class B Class A Class B Class A Class B #3 15 '' 19 '' 6 '' 13 '' 17 '' 6 '' 12 '' 16 '' 6 '' #4 19 '' 25 '' 7 '' 18 '' 23 '' 7 '' 15 '' 20 '' 6 '' #5 24 '' 31 '' 9 '' 22 '' 28 '' 8 '' 19 '' 25 '' 7 '' #6 29 '' 37 '' 11 '' 26 '' 34 '' 10 '' 23 '' 29 '' 8 '' #7 41 '' 54 '' 12 '' 38 '' 49 '' 11 '' 33 '' 43 '' 10 '' #8 47 '' 61 '' 14 '' 43 '' 56 '' 13 '' 37 '' 49 '' 11 ''
PODIUM DECK PODIUM DECK
F`c = 5000 psi F`c = 6000 psi
Bar Size
Length of Lap Hook Embed
Ldh
Length of Lap Hook Embed
Ldh Ld & Ld &
Class A Class B Class A Class B #3 12 '' 16 '' 6 '' 12 '' 16 '' 6 '' #4 14 '' 18 '' 6 '' 13 '' 16 '' 6 '' #5 17 '' 22 '' 6 '' 16 '' 20 '' 6 '' #6 20 '' 26 '' 8 '' 19 '' 24 '' 7 '' #7 29 '' 38 '' 9 '' 27 '' 35 '' 8 '' #8 34 '' 44 '' 10 '' 31 '' 40 '' 9 ''
MASONRY
F`m = 1500 psi
Bar Size
Length of Lap, Ld
Hook Embed
Ldh #3 12 '' 5 '' #4 20 '' 7 '' #5 31 '' 8 '' #6 59 '' 10 '' #7 80 '' 11 '' #8 121 '' 13 ''
STD. DEVELOPMENT LENGTHS & LAP SPLICES
Ld
2d C lr.
M in
2d C lr.
M in .d
Stagger Adj. Class A Splices 2Ld Min., or Use Class B* Splices
*Concrete ONLY
PROJECT INFORMATION
Systems West Engineers 725 A Street Springfield, OR 97477 541 342 7210
CLIENT:
DESIGN PARAMETERS
SEISMIC DESIGN BASIS**
Seismic Design Category C
Seismic Factors
Importance Factor, Ie 1.00
Design Base Shear
SS / S1
SDS / SD1
V = 0.17*W
Risk Category II
Site Class D
Resisting System: Elevated Tank on Symmetric
Unbraced Legs
Analysis Procedure: Eqv. Lateral Force
(ASCE 7-16, T. 15.4-2)
0.331 / 0.121
0.339 / 0.190
Response Mod.
Coefficient, R
**Preliminary Analysis Performed to Determine Seismic Anchorage Forces.
All reactions from Elevated Tank & Support Structure to be Provided by Supplier & Verified by EOR.
WIND DESIGN BASIS
Ultimate Wind Speed, VULT 101 mph
Exposure B Importance Factor, Iw 1.00
Risk Category II
GENERAL PARAMETERS
2018 OSSC *Building Code
SOILS VALUES
Bearing Pressure 2000 psf
(per Record Drawings)
SHEET INDEX
S-1.1 Structural Title Sheet
S-2.1 Foundation Plan
ABBREVIATIONS
AB Anchor Bolt A&B Above and Below Abv. Above Adn. Addition (al) Adj. Adjacent,Adjustable Alt. Alternate (ive) Appd. Approved Arch. Architect(ural) Avg. Average Bdry. Boundary Bldg. Building Blk(g). Block (ing) Bm. Beam BN Boundary Nailing B-O Bottom of BO By Others Bot. Bottom Brg. Bearing Btwn. Between BW Both Ways Cant. Cantilever(ed) CIP Cast in Place CJ Ceiling Joist CJP Complete Joint
Penetration CL Center Line Clg. Ceiling CMU Conc. Masonry Unit Col. Column Com. Common Comp. Component Conc. Concrete Conn. Connection Const. Construction Cont. Continue (ous) Ctr. Center d Penny Dbl. Double Defl. Deflection Deg. Degree Demo. Demolish(tion) Dep. Depress(ed) DF Douglas Fir Dia. Diameter Diaph. Diaphragm Dif. Different Dim. Dimension Dist. Distance DJ Deck Joist DL Dead Load Dwg. Drawing
(E) Existing Ea. Each EF Each Face EFP Equivalent Fluid
Pressure Elev. Elevator, Elevation Embed. Embed(ed), (ment) Engr. Engineer EOR Engineer of Record Eq. Equal, Equivalent ES Each Side EW Each Way Exp. Expand, Expansion Ext. Exterior Fdn. Foundation FF Finished Floor FJ Floor Joist Flr(g). Floor (ing) FOC Face of Concrete FOM Face of Masonry FOS Face of Studs FOW Face of Wall Frmg. Framing Ft. Foot, Feet Ftg. Footing Ga. Gage, Gauge Galv. Galvanized GB Grade Beam GC General Contractor Gyp. Gypsum HD Holdown Hdr. Header Hdw. Hardware Hgr. Hanger Hor(iz). Horizontal Ht. Height ID Inside Diameter In. Inch(es) Insp. Inspect(ion) Int. Interior Inv. Invert, Inverted Jst. Joist K Kips (1,000 pounds) KLF Kips per Linear Ft.
King King Stud KP King Post KSF Kips per Square Ft.
KSI Kips per Square In.
Lb(s). Pound(s) LL Live Load Loc. Location LW Light Weight
Mas. Masonry Max. Maximum MB Machine Bolt MF Moment Frame Mfr. Manufacture(r) Min. Minimum, Minute Mod. Modif(y), (ication) Mtl. Metal
(N) New N/A Not Applicable Nat. Natural NTS Not to Scale o/ Over oc On Center OD Outside Diameter Opng. Opening Opp. Opposite Opt. Optional Para. Parallel PCF Lbs per Cubic Ft.
Pen. Penetrate, (tion) Perf. Perforated Perim. Perimeter Perp. Perpendicular PI Panel Index PJP Partial Joint Pen.
PL Plate PLF Lbs per Linear Ft.
Pl. Plate Ply. Plywood Prep. Prepare, (ation) Press. Pressure Proj. Project Prop. Property PSF Lbs per Square Ft.
PSI Lbs per Square In.
PT Pressure-Treated PV Photovoltaic (Solar
Panels) R Radius Rec(s). Recommendation(s) Rect. Rectangular Ref. Reference Reinf. Reinforce(d), (ment),(ing) Req(d). Require(d) Reqs. Requirements Ret. Retain(ing) RJ Roof Joist RR Roof Rafter RW Redwood SAD See Arch Dwg's Sched. Schedule Sgl. Single Shtg. Sheathing Sim. Similar SIP Str. Insulated Panel SM Sheet Metal SMS Sheet Metal Screw SOG Slab on Grade Spec. Specifi(ed),(cations) Sq. Square SS Structural Steel Std. Standard Stgr. Stagger(ed) Stl. Steel Struc. Structure, (al) SW Shear Wall Sym. Symmet(ry), (rical) T&B Top and Bottom T&G Tongue and Groove Temp. Temporary Thk. Thick(ness) Thru Through TN Toe-Nail TP Top Plate T-O Top of TOB Top of Beam TOC Top of Concrete TOG Top of Grade TOM Top of Masonry TOS Top of Steel TOW Top of Wall TRU To Remain
Unchanged Trmr. Trimmer Stud Typ. Typical UNO Unless Noted
Otherwise Vert. Vertical VIF Verify in Field VWA Verify with Arch w/ With w/n Within w/o Without WS Wood Screw Wndw. Window Wt. Weight WWF Welded Wire Fabric Yd. Yard
@ At º Degrees Ø Diameter > Greater Than < Less Than # Number, Pound(s) / Per % Percent(age) ± Plus or Minus
STANDARD DETAILS
TYPICAL REINFORCING BAR BENDS
STANDARD TIES & STIRRUPS STANDARD END HOOKS
Bar Size D
#3 1-1/2" 2"#4
4-1/2"
H (Approx.)
3" 3"
2-1/2"#5 3-3/4"
5-1/4"#7 6"#8
4-1/2" 5-1/4"
6"
Bar Size D
2-1/4" 3"
4-1/2"
J
3" 4"
3-3/4" 5"
5-1/4" #8 6"
6" 7" 8"
D
D
D d d d D
12d for #6 & Larger 6d for #5 & Smaller
6d3" Min.
d
J
4d 2-1/2" Min.
Dimension per Details
Dimension per Details
Note:
All Bar Bend Diameters & End Lengths Must Conform to the CRSI Manual of Standard Practice
#6
#3 #4 #5
#7 #6
H
The 2019 Oregon Structural Specialty Code (OSSC), based on the 2018 International Building Code (IBC), is the governing code in the State of Oregon.
SPECIFICATIONS
CONCRETE
1. All concrete shall have:
(a) an ultimate compressive strength (f'c) of 3,000 psi at 28 days (UNO).
(b) a maximum slump of 5" at point of placement.
(c) a W/C ratio of 0.55 or less for all slabs, walls, and columns, and 0.60 or less for all foundations.
(d) a normal dry-weight density (UNO).
2. Special inspection is NOT required as the foundations have been designed with f'c = 2,500 psi in accordance with the Governing Building Code, section 1705.3, exceptions 1, 2.1, and 2.3, unless explicitly specified herein, on the structural plans, or by the Building Department.
As a minimum, special inspection is always required on:
(a) structural slabs, flat plates
(b) walls, columns, beams
(c) piles, caissons
(d) welding of reinforcement, installation of mechanical bar splice devices, epoxy application When required or specified, special inspection services shall conform to the Governing Building Code, Chapter 17 and shall be provided by an ICC certified inspector or Building Department approved engineer. The Building Department reserves the right to waive or require the special inspection requirements [Section 1704.1 and 1704.4] . Nothing in these plans waives the Building Department's right to require special inspection at any point and on any material.
3. Testing of materials used in concrete construction must be performed as noted on structural plans or at the request of the Building Department to determine if materials are quality specified. Tests of materials and of concrete shall be made by an approved agency and at the expense of the contractor; such tests shall be made in accordance with the standards listed in the Governing Building Code, Table 1705.3. When testing of concrete is required, four (4) test cylinders shall be taken from each 150 yards, or fraction thereof, poured in any one day. One (1) cylinder shall be tested at seven (7) days; two (2) at 28 days; one (1) shall be held in reserve. Where 4x8 cylinders are used, (5) test cylinders shall be taken, with (3) cylinders tested at 28 days. If Contractor elects to have additional tests performed for "early-break" results, additional test cylinders must be taken. At no time shall the Contractor instruct the testing agency to perform tests on a schedule different than above without the prior authorization of the Engineer. Contractor is responsible for complying with applicable testing requirements of theBuilding Department. Copies of all test reports shall be provided to Engineer and Building Department for review in a timely manner.
4. The Contractor shall remove and replace any concrete which fails to attain specified 28 day compressive strength if so directed by the Engineer. Any defects in the hardened concrete shall be repaired to the satisfaction of the Engineer and/or Architect or the hardened concrete shall be replaced at the Contractor's expense.
5. All concrete work shall conform with the Governing Building Code, Chapter 19.
6. All cement shall be Portland Cement Type I or II and shall conform to ASTM C 150.
7. All aggregates shall conform to ASTM C33. Maximum aggregate sizes:
(a) Footings: 1-1/2"
(b) All other work: 3/4"
8. Where not specifically detailed, the minimum concrete cover on reinforcing steel shall be:
(a) Permanently exposed to earth or weather
i. Cast against earth: 3"
ii. Cast against forms: 2"
(b) Not exposed to earth or weather
i. Slabs, walls, joists: 3/4"
ii. Beams, girders, columns: 1-1/2"
9. The minimum lap splice length for all reinforcing steel shall be as noted in the typical details on sheet S-1.1. All lap splices to be staggered.
10. All reinforcing steel, anchor bolts, dowels, inserts, and any other hardware to be cast in concrete shall be well secured in position prior to foundation inspection. All hardware to be installed in accordance with respective manufacturer's specifications. Refer to architectural and structural plans for locations of embedded items.
11. Locations of all construction joints, other than specified on the structural plans, shall be approved by the Architect and Engineer prior to forming. Construction joints shall be thoroughly air and water cleaned and heavily roughened so as to expose coarse aggregates.
All surfaces to receive fresh concrete shall be maintained continuously wet at least three (3) hours in advance of concrete placement.
This is the start of the file's text. The full file is on GovTribe.