This is a Schedule of Items (SOI) template spreadsheet for Task Order Project Requests (TOPRs) under $100,000 for Region 2 Road Maintenance and Forest Maintenance/Support Services. The template lists 76 line items across various maintenance categories including snow removal, furnished equipment (excavators, loaders, dozers, etc.), flagging operations, road maintenance, surface treatments, drainage work, vegetation management, barrier/gate maintenance, and signage work.
The document indicates that some line items will use pre-established MATOC procurement prices while others will have pricing determined "PER TASK ORDER." The template is designed to be filled in by the Contracting Officer after award based on Administrative Units and MATOC Proposal SOIs. The document relates to solicitation 1282B125R0003 from the USDA Forest Service, which includes an upcoming information session scheduled for December 19, 2024 from 1300-1500 Mountain time.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30 1282B125R0003 A0004.pdf | ||
| SF30 1282B125R0003 A0003.pdf | ||
| SF30 1282B125R0003 A0002.pdf | ||
| 1282B125R0003.pdf | ||
| 1282B125R0003 QA 1.docx | DOCX document | |
| SF 30 A00001.pdf | ||
| Solicitation_Update_20241218.docx | DOCX document | |
| ATTACHMENT 3 R2RM_Service Specs_20241203.docx | DOCX document | |
| ATTACHMENT 4 R2RM_AdminUnitsTable_20241127.xlsx | XLSX spreadsheet | |
| ATTACHMENT 2 R2RM_SOI_MATOC_Proposal_20241127.xlsx | XLSX spreadsheet | |
| 1282B125R0003.pdf | ||
| ATTACHMENT 7 FORM Equipment Cleaning Inspection Form_20241203.pdf | ||
| ATTACHMENT 1 WAGE DETERMINATION ARAPAHOE CO.pdf | ||
| ATTACHMENT 8 PAST PERFORMANCE QUESTIONNAIRE.docx | DOCX document | |
| ATTACHMENT 6 R2RM_SOI_for_TOPRs_Over 100k_20241127.xlsx | XLSX spreadsheet |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Road Mx SOI
| R2 Road Maintenance and Other Forest Maintenance/Support Services |
| Schedule of Items for Task Order Project Requests (TOPRs) |
Estimated Value UNDER $100,000
| Prices apply to work within Administrative Unit: | [(Will be filled in by CO after award based on the Administrative Units and the MATOC Proposal SOI(s)] | ||||
| Description of Offered Item | Quantity | Unit | Unit Price | Amount | |
| 803(1) | Snow Removal - Single Lane | 0 | MI | PER TASK ORDER | PER TASK ORDER |
| 803(2) | Snow Removal - Double Lane | 0 | MI | PER TASK ORDER | PER TASK ORDER |
| 803(3) | Snow Removal | 0 | LS | PER TASK ORDER | PER TASK ORDER |
| 803(4) | Snow Removal | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 807(1) | Furnished Equipment, Large Excavator | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(2) | Furnished Equipment, Medium Excavator | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(3) | Furnished Equipment, Small Excavator | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(4) | Furnished Equipment, Mini Excavator | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(5) | Furnished Equipment, Backhoe | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(6) | Furnished Equipment, Wheel Loader | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(7) | Furnished Equipment, Grader | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(8) | Furnished Equipment, Dump Truck | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(9) | Furnished Equipment, Belly Dump | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(10) | Furnished Equipment, Brush Cutter | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(11) | Furnished Equipment, Roller | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(12) | Furnished Equipment, Small Dozer | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(13) | Furnished Equipment, Medium Dozer | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(14) | Furnished Equipment, Skid Steer | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(15) | Furnished Equipment, Water Truck (2000 Gallons) | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(16) | Furnished Equipment, Water Truck (4000 Gallons) | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(17) | Furnish Equipment, Mobile Welder | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 807(18) | Furnish Equipment, Non-Standard Attachment | 0 | Hour | PER TASK ORDER | PER TASK ORDER |
| 808(1) | Single Flagger Operation | 0 | Hour | PER MATOC PROCUREMENT PRICE | PER MATOC PROCUREMENT PRICE |
| 808(2) | Dual Flagger Operation | 0 | Hour | PER MATOC PROCUREMENT PRICE | PER MATOC PROCUREMENT PRICE |
| 808(3) | Variable Message Board(s) | 0 | Day | PER TASK ORDER | PER TASK ORDER |
| 811(1) | Maintain Passenger Vehicle Road - Drainage and Roadway | 0 | MI | PER MATOC PROCUREMENT PRICE | PER MATOC PROCUREMENT PRICE |
| 811(2) | Maintain Passenger Vehicle Road - Roadway, No Drainage | 0 | MI | PER MATOC PROCUREMENT PRICE | PER MATOC PROCUREMENT PRICE |
| 811(3) | Maintain High Clearance Vehicle Roads - Drainage and Roadway | 0 | MI | PER MATOC PROCUREMENT PRICE | PER MATOC PROCUREMENT PRICE |
| 811(4) | Maintain High Clearance Vehicle Roads - Drainage Maintenance Only | 0 | MI | PER MATOC PROCUREMENT PRICE | PER MATOC PROCUREMENT PRICE |
| 811(5) | Road Surface Compaction, Method (FILL IN "A" or "B") | 0 | MI | PER TASK ORDER | PER TASK ORDER |
| 812(1) | Surface Stabilization Single Lane, Application Rate (FILL IN) | 0 | MI | PER TASK ORDER | PER TASK ORDER |
| 812(2) | Surface Stabilization Double Lane, Application Rate (FILL IN) | 0 | MI | PER TASK ORDER | PER TASK ORDER |
| 813(1) | Spot Surfacing, Gradation (FILL IN), Compaction Method (FILL IN “A” or “B”) | 0 | CY | PER TASK ORDER | PER TASK ORDER |
| 813(2) | Spot Surfacing, Gradation (FILL IN), Compaction Method (FILL IN “A” or “B”) | 0 | Ton | PER TASK ORDER | PER TASK ORDER |
| 813(3) | Riprap, Size (FILL IN) | 0 | CY | PER TASK ORDER | PER TASK ORDER |
| 813(4) | Boulders, Size (FILL IN) | 0 | CY | PER TASK ORDER | PER TASK ORDER |
| 814(1) | Pothole Patching | 0 | Ton | PER TASK ORDER | PER TASK ORDER |
| 814(2) | Skin Patching | 0 | Ton | PER TASK ORDER | PER TASK ORDER |
| 814(3) | Crack Sealing | 0 | LF | PER TASK ORDER | PER TASK ORDER |
| 814(4) | Paved Surface Cleaning Single Lane | 0 | MI | PER MATOC PROCUREMENT PRICE | PER MATOC PROCUREMENT PRICE |
| 814(5) | Paved Surface Cleaning Double Lane | 0 | MI | PER MATOC PROCUREMENT PRICE | PER MATOC PROCUREMENT PRICE |
| 814(6) | Paved Surface Cleaning Per Task Order | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 832(1) | Load, Haul, and Place Material - (FILL IN material type or gradation) | 0 | CY | PER TASK ORDER | PER TASK ORDER |
| 832(2) | Load, Haul, and Place Material - (FILL IN material type or gradation) | 0 | LS | PER TASK ORDER | PER TASK ORDER |
| 833(1) | 18" 16 Gauge CMP Remove and Replace | 0 | LF | PER TASK ORDER | PER TASK ORDER |
| 833(2) | 24" 16 Gauge CMP Remove and Replace | 0 | LF | PER TASK ORDER | PER TASK ORDER |
| 833(3) | 18" HDPE Remove and Replace | 0 | LF | PER TASK ORDER | PER TASK ORDER |
| 833(4) | 24" HDPE Remove and Replace | 0 | LF | PER TASK ORDER | PER TASK ORDER |
| 833(5) | Install New Drain Dip | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 833(6) | Install New Drivable Waterbar | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 833(7) | Clean Culverts 24" Diameter and Under | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 833(8) | Clean Culverts 24" Diameter through 48" | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 833(9) | Clean Culverts over 48" | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 833(10) | Jetting Culverts | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 841(1) | Disturbed Area Treatment | 0 | Acre | PER TASK ORDER | PER TASK ORDER |
| 841(2) | Disturbed Area Treatment | 0 | MI | PER TASK ORDER | PER TASK ORDER |
| 842(1) | Vegetation Maintenance | 0 | MI | PER MATOC PROCUREMENT PRICE | PER MATOC PROCUREMENT PRICE |
| 842(2) | Danger Tree Removal | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 842(3) | Curve Brushing | 0 | Acre | PER MATOC PROCUREMENT PRICE | PER MATOC PROCUREMENT PRICE |
| 861(1) | Maintain Cattleguard | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 861(2) | Replace Cattleguard | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 861(3) | Maintain Traffic Gate | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 861(4) | Maintain Guardrail | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 861(5) | Maintain Guardrail Barrier | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 861(6) | Maintain Rock/Earth Barrier | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 861(7) | Maintain Retaining Wall | 0 | LF | PER TASK ORDER | PER TASK ORDER |
| 861(8) | Replace Traffic Gate | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 861(9) | Remove Ttraffic Gate | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 861(10) | Remove Guardrail Barrier | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 861(11) | Remove Jersey Barrier | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 861(12) | Remove Rock/Earth Barrier | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 872(1) | Clean Sign Face | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 872(2) | Recondition Sign Face | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 872(3) | Remove and Replace Single Post and Sign | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 872(4) | Remove and Replace Double Post and Sign | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 872(5) | Remove and Replace Sign | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 872(6) | Remove Sign | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 872(7) | Remount Sign | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 872(8) | Apply New Sign Face | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 872(9) | Maintain Marker | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 872(10) | Replace Marker | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 872(11) | Sign, Marker Maintenance | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 881(1) | Mobilization & Equipment Moving | 0 | LS | PER TASK ORDER | PER TASK ORDER |
| 891(1) | Water Supply and Watering (FILL IN – Government Source or Contractor Provided) | 0 | mgal | PER TASK ORDER | PER TASK ORDER |
| 893(1) | Aggregate Supply and Stockpiling (FILL IN gradation or class) | 0 | Ton | PER TASK ORDER | PER TASK ORDER |
| 893(2) | Aggregate Supply and Stockpiling (FILL IN gradation or class) | 0 | CY | PER TASK ORDER | PER TASK ORDER |
| 894(1) | Roadway Obliteration, Method 1 | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 894(2) | Roadway Obliteration, Method 1 | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 894(3) | Roadway Obliteration, Method 3 | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| 894(4) | Entrance Way Obliteration | 0 | EA | PER TASK ORDER | PER TASK ORDER |
| Total | $ - 0 |