This is an SF30 amendment (A0002) to solicitation 1282B125R0003 for Region 2 Road Maintenance and Forest Maintenance/Support Services, issued by the USDA Forest Service. The amendment posts late questions and answers while maintaining the original due date of January 13, 2025 at 1500 MT.
The Q&A clarifies that pricing must be submitted using Attachment 2 Schedule of Items (SOI), with contractors required to provide pricing for at least one unit (forest) but may price multiple units if willing to work in multiple locations for projects under $100,000. Units include Big Horn NF, Blackhills NF, GMUG, MBRTB, Nebraska NFs NGs, Rio Grande NF, ARP, PSICC, San Juan NF, Shoshone NF, and White River NF. Services include flagging, passenger vehicle road maintenance, high clearance vehicle road maintenance, paved surface cleaning, vegetation maintenance, and curve brushing, with detailed specifications provided in Attachment 3 R2RM_Service_Specs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30 1282B125R0003 A0004.pdf | ||
| SF30 1282B125R0003 A0003.pdf | ||
| 1282B125R0003.pdf | ||
| 1282B125R0003 QA 1.docx | DOCX document | |
| SF 30 A00001.pdf | ||
| Solicitation_Update_20241218.docx | DOCX document | |
| ATTACHMENT 5 R2RM_SOI_for_TOPRs_Under 100k_20241127.xlsx | XLSX spreadsheet | |
| ATTACHMENT 3 R2RM_Service Specs_20241203.docx | DOCX document | |
| ATTACHMENT 4 R2RM_AdminUnitsTable_20241127.xlsx | XLSX spreadsheet | |
| ATTACHMENT 2 R2RM_SOI_MATOC_Proposal_20241127.xlsx | XLSX spreadsheet | |
| 1282B125R0003.pdf | ||
| ATTACHMENT 7 FORM Equipment Cleaning Inspection Form_20241203.pdf | ||
| ATTACHMENT 1 WAGE DETERMINATION ARAPAHOE CO.pdf | ||
| ATTACHMENT 8 PAST PERFORMANCE QUESTIONNAIRE.docx | DOCX document | |
| ATTACHMENT 6 R2RM_SOI_for_TOPRs_Over 100k_20241127.xlsx | XLSX spreadsheet |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1282B125R0003 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
82B1
WASHINGTON DC 20250-0001
1400 INDEPENDENCE AVE SW MS-1138
SPOC INTERMOUNTAIN
USDA FOREST SERVICE
12/11/20240002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
12/11/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
JESSICA LYN H. RASMUSSEN
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Region 2 Road Maintenance and other Forest Maintenance and Support Services
This amendment is to post questions and answers that came in late via Email. All other information remains the same and the due date remains 1/13/2025 at 1500 MT.
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
QUESTIONS:
1. What pricing information should be entered on the SF 1442 for the required CLIN’s (0001, 1001, 2001, 3001)?
A: This is to show the years. Please add pricing to the attached Schedule of items (SOI).
ATTACHMENT 2 R2RM_SOI_MATOC_Proposal. Also, see the solicitation file “1282B125R0003.pdf,” Section E – Solicitation Provisions, FAR 52.212-1 Instructions of O erors, Evaluation Factors and Methodology, 1.4 Factor 4: Price for submission requirements.
2. Please confirm “Pricing for all items” (ITEMS DEFINED AS… Single Flagger, Dual Flagger, Maintain Passenger Vehicle Roads (x2), Maintain High Clearance Vehicle Roads (x2), Paved Surface Cleaning Single and Double Lane, Vegetation Maintenance, Curve Brushing) are required, but (per Sol. Page 31 “1.4.1 Price”) only one unit (UNIT DEFINED AS… Big Horn NF, Blackhills NF, GMUG, MBRTB, Nebraska NFs NGs, Rio Grande NF, ARP, PSICC, San Juan NF, Shoshone NF, White River NF) is required to be filled out on Attachment 2 in order to be deemed responsive. In other words, can you confirm we are only required to submit pricing on one of the locations in order to meet the solicitation requirements?
A: Attachment 2 R2RM_SOI_MATOC_Proposal pricing is required for a minimum of one unit.
If there is only one location you are willing to work for projects estimated less than $100,000, then only one unit SOI for MATOC Proposal (the unit you are willing to work), is required. However, if you are willing to work in more than one unit for projects estimated value less than $100,000, then you will need to provide prices for all applicable units.
Provide pricing for each unit you are willing to work for estimated value less than $100,000 on the ATTACHMENT 2 R2RM_SOI_MATOC_Proposal file. There is a separate tab for each unit. Note, you must also fill out the “Attachment 4 R2RM_AdminUnitsTable identify each unit you are willing to work for projects estimated value under $100,000. For each unit identified in this table, a SOI with pricing must be provided.
3. Is there further detail on what should be included or excluded from the Description of work items listed on the schedule of items (attachment 2), or is it up to the contractor to apply all necessary costs to the vague description? The purpose of this question would be that we may not be able to accurately price these descriptions / be held to their costs on every project if we do not have more information on what is to be included in each line item (i.e.
what specific costs / scopes should “curve brushing” include?).
A: ATTACHMENT 3 R2RM_Service_Specs includes the specifications for what work is expected and covered by the line items. For example, CLIN 842(3) Curve Brushing falls under Specification Section 842 – Vegetation Maintenance.