Attachment 4 - Submittal Requirements.pdf

PDF 255 KB Posted

Attached to
Crane Lake Dam Rehabilitation
Solicitation number
12445526Q0047
Issued by

About this file

This document is a submittal requirements table for a federal construction contract that outlines specific deliverables contractors must provide, the regulatory references governing each requirement, submission deadlines, submission frequency, and applicable pay items.

The submittal requirements span multiple construction phases and disciplines. Pre-construction submittals due 7-14 days before work starts include the overall quality control plan, construction schedule, soil erosion and sediment control plan, spill prevention plan, and surveying documentation. During construction, contractors must submit daily operations reports, weekly soil erosion reports and soil test results, and routine quality certifications. Material-specific submittals include aggregate testing prior to delivery, geosynthetics production certifications with each shipment, concrete mix designs 30 days before production, and shop drawings for water control gates prior to ordering. Structural work requires excavation and backfill testing submissions both prior to and during work on major structures, baffle risers, impact basins, culverts, and mechanically stabilized earth walls, with testing frequency specified in referenced tables. As-built drawings must be submitted prior to final inspection. All requirements reference specific sections of FP-14 specifications, supplemental specifications, or applicable technical tables that dictate the precise scope and testing parameters for each submittal category.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBMITTALS REQUIREMENTS DUE OCCURRENCE PAY ITEM

AS-BUILT DRAWINGS FP-14: 104.03 (b) PRIOR TO FINAL

INSPECTION

ONCE CONTRACTOR QUALITY

CONTROL

AGGREGATE TESTING SUPPLEMENTAL

SPECS 105.07

PRIOR TO ANY

MATERIAL BEING

DELIVERED

QUANTITY BASED CONTRACTOR QUALITY

CONTROL

ACCEPTANCE OF WORK FP-14: 106.03 BEFORE

INCORPORATION OF

MATERIAL INTO THE

WORK

AS PER SPECIFIC

SECTIONS

AS PER SPECIFIC

SECTIONS

SPILL PREVENTION,

CONTROL, AND COUNTER

MEASURE PLAN

FP-14: 107.10(b) 2-DAYS BEFORE START

OF WORK

ONCE CONTRACTOR QUALITY

CONTROL

SURVEYING TECHNOLOGY

STATEMENT

FP-14: 152.03 (a) PRECONSTRUCTION

CONFERENCE

ONCE CONSTRUCTION

SURVEYING & STAKING

SURVEYING PERSONNEL

QUALIFICATIONS

FP-14: 152.03 (b) PRECONSTRUCTION

CONFERENCE

ONCE CONSTRUCTION

SURVEYING & STAKING

OVERALL QC PLAN FP-14: 153.03 14-DAYS BEFORE

START OF WORK

EVERY TIME IT IS

UPDATED

CONTRACTOR QUALITY

CONTROL

CONSTRUCTION

OPERATIONS REPORTS

FP-14: 153.07 (a) DAILY DAILY CONTRACTOR QUALITY

CONTROL

CONSTRUCTION SCHEDULE FP-14: 155 7-DAYS BEFORE THE

PRECONSTRUCTION

CONFERENCE

UPDATED EVERY

MONTH

SCHEDULES FOR

CONSTRUCTION

CONTRACTS

SOIL EROSION AND

SEDIMENT CONTROL &

DEWATERING PLAN

SUPPLEMENTAL

SPECS 157.03

14-DAYS BEFORE

START OF WORK

EVERY TIME IT IS

UPDATED

SOIL EROSION AND

SEDIMENT CONTROL

AND LAKE DRAWDOWN

SOIL EROSION AND

SEDIMENT CONTROL &

DEWATERING REPORTS

FP-14: 157.14 WEEKLY AFTER LAND

DISTURBANCE STARTS

WEEKLY SOIL EROSION AND

SEDIMENT CONTROL

AND LAKE DRAWDOWN

SOIL TEST RESULTS SUPPLEMENTAL

SPECS 204

PRIOR TO WORK AND

WEEKLY

WEEKLY EXCAVATION &

EMBANKMENT

SAMPLING & TESTING

PRODUCTION

CERTIFICATION -

GEOSYNTHETICS

FP-14 207.08 WITH EACH

SHIPMENT

AT SHIPMENT EARTHWORK

GEOSYNTHETICS

COFFER DAM DRAWINGS

& BACKFILL TESTING

FP-14 208.05,

208.11 & TABLE

208-01

PRIOR TO AND

DURING WORK

AS REQUIRED

PER TABLE 208-01 STRUCTURE EXCAVATION

& BACKFILL (MAJOR

STRUCTURES)

BAFFLE RISER, IMPACT

BASIN AND CULVERT

EXCAVATION & BACKFILL

TESTING

FP-14 209 & TABLE

209-01

PRIOR TO AND

DURING WORK

AS REQUIRED

PER TABLE 209-01 STRUCTURE EXCAVATION

& BACKFILL

MSE WALLS FP-14 255.06 PRIOR TO AND

DURING WORK

AS REQUIRED

PER TABLE 255-2 MSE WALLS

ATTACHMENT 4 - SUBMITTAL REQUIREMENTS

CERTIFICATES OF

COMPLIANCE,

INSPECTION, EXPERIENCE,

TESTING, WARRANTY, AS-

BUILTS

SUPPLEMENTAL

SPECIFICATIONS

261.03 - 261.07

PER SPECIFICATION PER

SPECIFICATION

ENGINEERED TURF

CONCRETE MIX DESIGN

PER FP-14 601.03 30-DAYS PRIOR TO

PRODUCTION

PRIOR TO

PRODUCTION

MINOR CONCRETE

STRUCTURES

FINE AND COARSE DRAIN

FILTER MATERIAL

GRADATIONS

SUPPLEMENTAL

SPECIFICATION

610.02

PRECONSTRUCTION ONCE HORIZONTAL DRAINS

SHOP DRAWINGS SUPPLEMENTAL

SPECIFICATION

630.02

PRIOR TO

ORDERING/PURCHASE

ONCE WATER CONTROL GATES