Attachment 1 - Schedule of IItems.pdf
PDF 275 KB Posted
- Attached to
- Crane Lake Dam Rehabilitation
- Solicitation number
- 12445526Q0047
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Schedule of Items document for the Crane Lake Dam Rehabilitation project located in the Potosi-Fredericktown Springs Ranger District of Mark Twain National Forest in Missouri. The document establishes the base estimate pricing structure for the construction contract using the FP-14 specification format.
The schedule comprises 22 line items covering comprehensive dam rehabilitation work, including mobilization and demobilization, construction surveying and staking, contractor quality control, and sampling and testing activities. Major construction components include clearing and grubbing, removal of existing concrete structures, excavation and embankment work (5,200 cubic yards), installation of modular retaining walls (380 square feet), engineered turf application (4,540 square yards), reinforced subgrade work (548 square yards), and various drainage systems including toe drains (390 linear feet) and horizontal drains (155 linear feet of 30-inch reinforced concrete pressure pipe). Additional items address concrete structures such as NRCS baffle risers, impact basins, and anchor trenches, as well as turf establishment (1 acre). All line items are priced on a lump sum (LS) basis with blank price fields for contractor bid submission. The document concludes with a total base bid estimate line requiring the contractor's overall project cost.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Crane Lake Dam Rehabilitation Section B
Pg. 1
SECTION B SCHEDULE OF ITEMS
CRANE LAKE DAM REHABILITATION
POTOSI-FREDERICKTOWN SPRINGS RANGER DISTRICT
MARK TWAIN NATIONAL FOREST
STATE OF MISSOURI
BASE ESTIMATE
FP-14
Section
Pay Item Description Estimated
Qty Unit Total Price
151 Mobilization and Demobilization 1 LS $_______________________________
152 Construction Surveying & Staking 1 LS $_______________________________
153 Contractor Quality Control 1 LS $_______________________________
Sampling & Testing - Including but not limited to: Supplemental Specifications 204.15, FP-14 Table 208-1, FP-14 Table 209-1, FP-14 Table 302-1 & FP-14 Table 552-9)
1 LS
155 Schedules for Construction Contracts 1 LS
157 Soil Erosion and Sediment Control and Lake Drawdown 1 LS $_______________________________
201 Clearing and Grubbing 1 LS $_______________________________
203 Removal of Structures & Obstructions (Removal/Recycling of Existing Concrete Structures)
1 LS
204 Excavation & Embankment 5,200 CY LS $_______________________________
255 Modular Retaining (MSE) Walls 380 SF LS $_______________________________
261 Engineered Turf 4,540 SY LS $_______________________________
302 Reinforced Subgrade at Dam Crest
548 SY LS
601 Minor Concrete Structures (NRCS Baffle Riser)
1 LS
601 Minor Concrete Structures (NRCS Impact Basin)
1 LS
601 Minor Concrete Structures (Anchor Trench)
693 LF LS
603 Structural Plate
(Batten Bar Anchor)
400 LF LS
605 Under Drains (Toe Drains) 390 LF LS $_______________________________
605 Under Drains (Drainage Layer) 811 SY LS $_______________________________
Crane Lake Dam Rehabilitation Section B
Pg. 2
FP-14
Section
Pay Item Description Estimated
Qty Unit Total Price
610 Horizontal Drains (30” Reinforced Conc Pressure Pipe with filter drain and concrete cradle)
155 LF LS
625 Turf Establishment 1 ACRE LS $_______________________________
TOTAL BASE BID ESTIMATE $_______________________________