The document is a Past Performance Questionnaire (PPQ) for a design-build construction project at Andersen Air Force Base, Guam, involving comprehensive renovation of the Saipan Dorm B25007. The project, valued between $25-$100 million, requires full repair and modernization including interior and exterior renovations, complete HVAC and plumbing system replacements, electrical distribution updates, fire protection enhancements, and site grading. Specific systems to be replaced include chillers (Dunham Bush or Odyne preferred), air handlers, ductwork, electrical components, water heaters, and fire alarm panels (Monaco or EST brands).

The solicitation is a HUBZone small business set-aside with a Firm Fixed Price contract type, targeting commercial and institutional building construction (NAICS 236220). The project has a 865-calendar day performance period, with proposal submissions required through the Procurement Integrated Enterprise Environment (PIEE). Key submission dates include a site visit on 24 July 2025, request for information deadline of 7 August 2025, and a past performance questionnaire response deadline of 18 August 2025. The contracting activity is the 36th Contracting Squadron of the Department of Air Force Pacific Air Forces, with points of contact including 2d Lt Shelby Benko, Mr. Darrell Chargualaf, Mr. Eddie Pelkey, and Ms. Katrina Pangelinan.

View the file

Other files

File Type Posted
Attachment 9a Roofing As-BUILTs B25007.pdf PDF
Solicitation Amendment FA524025R00040002 SF 30.pdf PDF
Attachment 1a Updated Statement of Work AJJY 25-1074M Repair Saipan Dorm B25007 08AUG25.pdf PDF
Attachment 9 As-BUILTs B25007.zip ZIP file
Solicitation Amendment FA524025R00040001 SF 30.pdf PDF
RFI Responses - FA524025R0004 Part 2 _Expanded Cell Blocks.pdf PDF
08 Aug 25_RFI Responses - FA524025R0004 Part 2.pdf PDF
07 Aug 25_RFI Responses - FA524025R0004 Part 1.pdf PDF
Attachment 1D AJJY 25-1074M Repair Saipan Dorm B25007 35 pct Dwgs.pdf PDF
Attachment 2 Project Requirement Price Schedule.docx DOCX document
Attachment 8 PIEE Proposal Manager Reference Guide.pdf PDF
Solicitation - FA524025R0004.pdf PDF
Attachment 1G 201307 B25007 Report B Asbestos and Lead Empsco Apec.docx DOCX document
Attachment 1H 201307 B25007 Report A Asbestos and Lead Empsco Apec.pdf PDF
Attachment 6 Wage Determination (GU20250001).pdf PDF
Attachment 1 Statement of Work AJJY 25-1074M Repair Saipan Dorm B25007.pdf PDF
Attachment 1J Cat Management 4 HVAC Standardization Policy Guidance Memorandums.pdf PDF
Attachment 3 Past Performance Fact Sheet (PPFS).docx DOCX document
Attachment 5 AAFB IFS_27FEB24.pdf PDF
Attachment 7 Common Construction Prevailing Wage Rates_Guam.pdf PDF
Attachment 1A AAFB Contractor Antiterrorism Awareness.pdf PDF
Attachment 1B 36 CES Contractors Builder Inventory Sheet Template.xlsx XLSX spreadsheet
Attachment 1C AJJY 25-1074M Repair Saipan Dorm B25007 Map.pdf PDF
Attachment 1E AJJY 25-1074M Repair Saipan Dorm B25007 35 pct Concept Design.pdf PDF
Attachment 1F 19960111 B25007 Jacobs Asbestos.pdf PDF
Attachment 1I USAF Fire Alarm Panel Approval Memorandum.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Controlled Unclassified Information When completed, this document is Source Selection Information IAW FAR 2.101 and 3.104.

Section L Attachment: Past Performance Questionnaire (PPQ) The 36th Contracting Squadron is in the process of competitively selecting a source for a project to design and fully repair Saipan Dorm B25007 AAFB, GU. The contractor shall include renovation of interiors including floors, walls, ceiling, finishes, full restroom renovation, updating code for Energy and Life Safety, exterior renovations resulting from recent storm damage. Walkway slabs and spandrel beams will be repaired. Repairs will also include a complete update to the HVAC and Plumbing systems in the Saipan dorm. Saipan is conditioned by a chilled water and a central chiller plant - both will be replaced. A complete replacement of air handlers, ductwork, grilles, variable air volume boxes, and chilled water piping will be replaced. AAFB Justification and Approval (J&A) specifies Dunham Bush as the preferred chiller. Odyne Chillers are also acceptable. The chilled water pump will be replaced. All existing plumbing utilities will be replaced and updated. The existing heat pump water heaters will be replaced with standard electric water heaters with large storage tanks. Electrical updates include an update to the entire electrical distribution system. The system updates will include a complete replacement of electrical distribution from the pad mount transformer secondary conductors to the entire downstream building distribution system. Fire protection updates include sprinkler protection throughout, installation of a mass notification system, and a wet-pipe sprinkler system throughout the dorm. AAFB J&A for the Fire Alarm Panel specifies either Monaco or EST brands. The Saipan dorm must be re-graded to maintain positive drainage away from the building. Existing storm sewer inlets are buried with debris, dirt, and grass- these are to be cleared. The design-build contractor will design and construct the above repairs in accordance with the requirements of this contract.

In accordance with FAR 36.204(h) and DFARS 236.204(ii) the magnitude of this project is between $25,000,000.00 and $100,000,000.00.

One of the considerations in the proposal evaluation is the verification of the offerors' past performance on contracts or other work efforts which reflect the offeror's ability to perform on the proposed effort. We depend on information received from organizations such as yours, which have had first-hand experience with the offeror, for the evaluation of the offeror's performance on those contracts or work efforts.

Our areas of interest regarding the offeror are summarized in the enclosed questionnaire. To meet the acquisition milestones, we request your written response no later than Monday, 18 August 2025 by 1400 hours (ChST).

To assist you in preparing your response and expediting your reply, the questionnaire may be filled out electronically and e-mailed to all of the following: shelby.benko.1@us.af.mil, eddie.pelkey@us.af.mil, and katrina.pangelinan@us.af.mil. Your completed questionnaire will become a part of the official Source Selection records. Please title the email: PPQ – FA524025R0004 – Contractor Name Your assistance is greatly appreciated, and your prompt response will be one of the keys to the successful and timely completion of this Source Selection.

Katrina J. Pangelinan Contracting Officer

Attachments:

1. Past Performance Questionnaire (PPQ)

Section 1: Contract Identification

A. Contractor (Company/Division):

B. Contractor Cage Code:

C. Contract Number and/or Task Order Number:

D. Contract Type (e.g., FFP, FPIF, CPIF, CPFF, etc.):

E. Program Title:

F. Brief Program Description:

G. Program Phase (e.g., Engineering & Manufacturing Development (EMD)):

H. Period of Performance

1. Original Schedule (assuming all options exercised):

Beginning Date __________ through __________

2. Current Schedule (assuming all options exercised):

Beginning Date _________ through ____________

3. Reason for difference (if applicable):

I. Contract Dollar Value

1. Original maximum contract dollar value (assuming all options exercised): $

2. Current maximum contract dollar value (assuming all options exercised): $

3. Reasons for difference between original and current contract dollar value (if applicable):

J. Description of work performed. *Please describe design requirements and any facets of construction associated with the project, if possible:

K. Was this a competitively awarded contract? ☐ Yes ☐ No

L. Contractor’s Role: ☐ Prime Contractor ☐ Subcontractor ☐ Key Personnel

Section 2: Customer or Agency Identification

A. Customer or agency name:

B. Customer or agency description (if applicable):

C. Geographic description of services under this contract (i.e., local, nationwide, worldwide, other Commands):

Section 3: Respondent Identification

A. Respondent’s name:

B. Respondent’s title:

C. Respondent’s phone number / fax number / e-mail address:

D. Respondent’s position (e.g., Program Manager, PCO/ACO, etc.):

E. Length of time (number of years/months) respondent worked on subject contract and description of responsibility/position/role:

F. Other suggested points of contact:

Section 4: Performance Information

In the tables below, indicate your rating for the contractor’s performance by placing an “X” in the appropriate block to the right of each question. Provide supporting information for each response in the space provided. Attach additional pages if more space is needed. The performance rating scale is defined as follows:

Code Performance Rating

E EXCEPTIONAL – Performance meets contractual requirements and exceeds many requirements to the Government’s benefit. The contractual performance being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

V VERY GOOD – Performance meets contractual requirements and exceeds some requirements to the Government’s benefit. The contractual performance being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

S SATISFACTORY – Performance meets contractual requirements. The contractual performance being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

M MARGINAL – Performance does not meet some contractual requirements. The contractual performance being assessed reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.

U UNSATISFACTORY – Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance being assessed contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

N/A NOT APPLICABLE – Unable to provide a rating. Contract did not include performance for this aspect, performance was not observed, or information was not available. Do not know.

Technical Performance
E
V
S
M
U
N/A

How well did the contractor meet the technical requirements of the project?

COMMENTS:

Schedule/Timeliness
E
V
S
M
U
N/A

How well did the contractor adhere to the schedule?

Management
E
V
S
M
U
N/A

How well did the contractor integrate and coordinate activities to execute the project?

Government Contracts Only: Was this contract partially or completely terminated for default or convenience, or are there any pending terminations?

☐ Yes ☐ Default ☐ Convenience ☐ Pending Terminations ☐ No

If yes, please explain (e.g., inability to meet cost, performance, or delivery schedules).

SECTION 5: GENERAL COMMENT

Given what I know today about the contractor’s ability to execute what they promised in their proposal, I [ click and select an item ] award to them today given that I had a choice.

REMARKS:

[click and pick the date]

Respondent’s Signature Date

Thank you for your prompt response and assistance!

Please return to: shelby.benko.1@us.af.mil, eddie.pelkey@us.af.mil, katrina.pangelinan@us.af.mil