Attachment 2 Project Requirement Price Schedule.docx
DOCX document 20 KB Posted
- Attached to
- AJJY 25-1074M Repair Saipan Dorm B25007
- Solicitation number
- FA524025R0004
About this file
The file "Attachment 2 Project Requirement Price Schedule.docx" is related to a Design-Build construction project for repairing Saipan Dorm B25007 at Andersen Air Force Base, Guam. The solicitation (FA524025R0004) is a Historically Underutilized Business Zone (HUBZone) Small Business set-aside with a project magnitude between $25-$100 million, targeting commercial and institutional building construction under NAICS code 236220.
The comprehensive renovation encompasses full interior and exterior repairs, including floor, wall, and ceiling updates, complete restroom renovation, HVAC and plumbing system replacements, electrical distribution system overhaul, and fire protection improvements. Key project specifications include replacing central chiller plant, air handlers, ductwork, water heaters, and implementing storm drainage improvements. The project has a 865-calendar day performance period, will be awarded as a Firm Fixed Price contract, and requires electronic proposal submission through the Procurement Integrated Enterprise Environment (PIEE) by the solicitation deadline. A mandatory site visit is scheduled for 24 July 2025, and requests for information are due by 7 August 2025.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| CUI | FA524025R0004 | |
| Attachment 02 |
PROJECT REQUIREMENT PRICE SCHEDULE
Project #: AJJY 25-1074M
Project Name: Repair Saipan Dorm B25007 Andersen Air Force Base, GU
Project Description: The Contractor is tasked with a Design-Build requirement to design and fully repair Saipan Dorm B25007 which includes renovation of interiors including floors, walls, ceiling, finishes, full restroom renovation, updating code for Energy and Life Safety, exterior renovations resulting from recent storm damage. Walkway slabs and spandrel beams will be repaired. Repairs will also include a complete update to the HVAC and Plumbing systems in the Saipan dorm. Saipan is conditioned by a chilled water and a central chiller plant, both will be replaced. A complete replacement of air handlers, ductwork, grilles, variable air volume boxes, and chilled water piping will be replaced. AAFB Justification and Approval (J&A) specifies Dunham Bush as the preferred chiller. Odyne Chillers are also acceptable. The chilled water pump will be replaced. All existing plumbing utilities will be replaced and updated. The existing heat pump water heaters will be replaced with standard electric water heaters with large storage tanks. Electrical updates include an update to the entire electrical distribution system. The system updates will include a complete replacement of electrical distribution from the pad mount transformer secondary conductors to the entire downstream building distribution system. Fire protection updates include sprinkler protection throughout, installation of a mass notification system, and a wet-pipe sprinkler system throughout the dorm. AAFB J&A for the Fire Alarm Panel specifies either Monaco or EST brands. The Saipan dorm must be re-graded to maintain positive drainage away from the building. Existing storm sewer inlets are buried with debris, dirt, and grass- these are to be cleared. Work shall be performed in accordance with the Statement of Work and all associated attachments.
| ITEM |
| DESCRIPTION |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| TOTAL EVALUATED PRICE (TEP) |
| 0001 |
| AJJY 25-1074M Repair Saipan Dorm B25007 AAFB, GU |
| 1 |
| LOT |
| CONTRACTOR/OFFEROR NAME |
| ADDRESS |
Proposal Valid Through (Date): ____________
SIGNATURE DATE SIGNED
CUI
File details come from the government source that posted it. Updated .