Attachment 4 Contract Discrepancy Report.pdf
PDF 111 KB Posted
- Solicitation number
- 36C78626B0008
About this file
This is a Contract Discrepancy Report (CDR) template used in federal contracting to document and resolve performance or compliance issues between the government and contractors.
The CDR form serves as a formal communication tool for identifying and addressing contract discrepancies. The initiating party (Contracting Officer or Contracting Officer's Representative) completes the upper section by documenting the contract number, report number, discrepancy details with reference to the Performance Work Statement (PWS) directive, and three key dates: report preparation, contractor response deadline, and action completion. The contractor then responds in section 9 with a detailed explanation of the cause, corrective actions taken, and preventive measures to avoid recurrence. The government evaluates the contractor's response in section 11, indicating acceptance, partial acceptance, or rejection, and specifies government actions in section 12, which may include reduced payment, cure notices, show cause orders, or other remedies. The form concludes with a closeout section requiring signatures and dates from the contractor, Contracting Officer's Representative (COR), and Contracting Officer (CO) to document completion and notification of all parties. This template is designed to provide a structured process for managing contractor performance issues while maintaining documented evidence of the discrepancy resolution process.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 4 CONTRACT DISCREPANCY REPORT (CDR)
CONTRACT DISCREPANCY REPORT
Contract Number: Report No. for this Discrepancy:
To: (Contractor/Manager’s Name) From: (Name of COR)
5. Dates 5a. Prepared: 5b. Returned by Contractor: 5c. Action Complete:
Discrepancy or Problem: (Describe in detail. Include reference to PWS Directive; attach additional sheet if necessary.)
Signature of Contracting Officer or COR:
8a. To: (Contracting Officer and/or COR) 8b. From: (Contractor)
9. Contractor Response as to Cause, Corrective Action and Actions to Prevent Recurrence: (attach additional sheet if necessary.)
10a. Signature of Contractor Representative: 10b. Date:
11. Government Evaluation: (Acceptance, partial acceptance, reflection; attach additional sheet if necessary.)
12. Government Actions: (Reduced payment, cure notice, show cause, other)
13. Close Out Name Title Signature Date
Contractor Notified
b. COR
c. CO
File details come from the government source that posted it. Updated .