Attachment 3_StatementOfWork.pdf
PDF 175 KB Posted
- Solicitation number
- 1240LU26Q0013
- Issued by
-
Department of Agriculture Forest Service
About this file
This Statement of Work (SOW) details the Park Lake Dam Rehabilitation project for the Helena-Lewis and Clark National Forest in Jefferson County, Montana. The project requires comprehensive dam rehabilitation, including clearing and grubbing, dewatering Park Lake, deconstructing the existing dam, constructing a new dam with a seismic foundation, implementing hydraulic seepage control, performing road reconstruction, and site reclamation. The contractor is responsible for all labor, materials, tools, equipment, scheduling, and sequencing necessary to complete the work, with construction expected in the 2026 and 2027 calendar years.
The project is located approximately 13 miles west of Clancy, MT, with precise coordinates of Lat: 46.444272 N, Long: -112.171952. The period of performance begins within 10 days of the Notice to Proceed, with dewatering to start after July 15 in the first year of construction. All work must be completed by October 31, 2027. Prospective bidders are required to visit the site prior to bidding, with a Special Notice posted on SAM.gov on 9/24/2025 regarding the site visit. The full scope of work is detailed in the Forest Service Supplemental Specifications (FSSS) and accompanying Drawings.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Park Lake Dam Rehabilitation Solicitation No. 1240LU26Q0013
STATEMENT OF WORK
PROJECT SCOPE
a. Description:
This project is for the rehabilitation of the Park Lake Dam located on the Helena Ranger District of the Helena-Lewis and Clark National Forest. Work includes but is not limited to; clearing and grubbing, dewatering of Park Lake, deconstruction of the existing dam, construction of a new dam, new seismic foundation, hydraulic seepage control, road reconstruction, reclamation, and all other work associated with dam rehabilitation and construction.
Contractor is responsible for all labor, materials, tools, equipment, scheduling and sequencing, etc. necessary to complete the work.
Full scope of work identified in the Forest Service Supplemental Specifications (FSSS) and Drawings.
NOTE: Park Lake is mountain lake with shorter construction seasons.
b. Location: (See Map in Drawings)
Park Lake Dam Helena Ranger District, Jefferson County, MT Approximately 13 miles west of Clancy, MT.
Lat: 46.444272 N Long: -112.171952
Period of Performance: Work shall begin within 10 days of issuance of the Notice to Proceed.
Dewatering shall start after July 15, the first year of construction.
All work shall be completed by October 31, 2027.
NOTES: Mobilization and construction practices can begin prior to July 15, but dewatering cannot. Construction is expected in the 2026 and 2027 calendar years.
c. Pre-Bid Tour: No Pre-Bid Tour is scheduled for this project. Prospective are responsible to visit the site prior to bidding. A Special Notice was posted on 9/24/2025 in SAM.gov regarding site visit.
PROJECT SCOPE