This Schedule of Items details the Park Lake Dam Rehabilitation project for the Helena-Lewis and Clark National Forest, with contract number 1240LU26Q0013. The project encompasses comprehensive dam reconstruction activities including preconstruction tasks, clearing and grubbing, deconstruction, reconstruction, seismic foundation improvements, hydraulic seepage control, road reconstruction, and reclamation. Key quantities include 22,200 cubic yards of dam excavation, 24,000 cubic yards of embankment fill, 20,300 square yards of clearing and grubbing, and multiple specialized activities such as compaction grouting, drain pipe installation, riprap placement, and instrumentation. The scope involves detailed engineering work with specific requirements for materials like filter layers, concrete sand, and aggregate, along with infrastructure elements such as fencing, gates, and road improvements.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1240LU26Q0013
SCHEDULE OF ITEMS
PARK LAKE DAM REHABILITATION
HELENA-LEWIS AND CLARK NATIONSL FOREST
Park Lake-Complete Dam Rehabilitation No. Description Quantity Unit Unit Price Cost Notes
Preconstruction
15101 Mobilization and Demobilization 1 LS
15102 Access Road Improvements 1 LS
15201 Construction Staking and Survey 1 LS
63501 Temporary Traffic Control 1 LS
Clearing and Grubbing
20101 Clearing and Grubbing downstream of dam and along access
20,300 SY
Deconstruction
20401 Dam Excavation 22,200 CY Quantity is in-situ.
20402 Temporary Stock Piling of Material 24,000 CY Assumes 440 CY waste of existing drain material and 10% swell.
20403 Borrow for Grout Mix 3,750 CY Quantity is in-situ.
Assume 750 CY will be wasted.
63001 Dewatering 1 LS
Reconstruction
20404 Embankment Fill 24,000 CY Quantity is compacted in-place. Placement is incidental.
20405 Soil Mixing and Disking 30,260 CY
25101 Class 2 Riprap - Dam Embankment 770 CY Placement cost only.
Quantity is placed volume.
25102 Class 2 Riprap - Saddle Dike 5,860 CY Placement cost only.
Quantity is placed volume.
25103 Class 2 Riprap - Ripping/Excavating 4,296 CY Quantity is in-situ bedrock volume, assumes 40% swell to placed volume and 80% of dam riprap is salvage.
70401 M1 Filter (ASTM C33 Washed Concrete Sand) 1,740 CY Placement is incidental.
70402 M2 Filter/Bedding Layer (AASHTO #89) 120 CY Placement is incidental.
70403 M3 Filter/Bedding Layer (AASHTO #357) 385 CY Placement is incidental.
60401 24" Standard Riser Inlet 1 UNITS Weir and customization incidental.
64001 6-inch Diameter Dual-Wall HDPE Perforated Drain
Pipe 270 LNFT Fittings and installation are incidental.
64002 6-inch Diameter Dual-Wall HDPE Solid Drain Pipe 240 LNFT Includes cleanouts.
Fittings and installations are incidental.
Seismic Foundation Improvement
26201 Primary Borings and Compaction Grouting 132 UNITS
26202 Secondary Borings and Compaction Grouting 30 UNITS
26203 Performance Testing 400 FEET
Hydraulic Seepage Control Barrier
26204 Shallow Borings and Compaction Grouting 179 UNITS
26205 Mid-Level Borings and Compaction Grouting 62 UNITS
26206 Deep Borings and Compaction Grouting 33 UNITS
26207 Secondary Borings and Grouting 15 UNITS
26208 Performance Testing 1 LS
Road Reconstruction
15202 Grade Survey 1 LS
30102 Road Surface Aggregate 425 CY Includes 25 cy of 6" thick aggregate for area of turnaround (1333 sf)
20406 Soil Borrow for Turnaround 7 CY
20404 Fill for Turnaround 5 CY
61901 Fencing 2,000 LNFT
61902 16' Gate 1 EA 61903 25' Gate 2 EA
Reclamation
62601 Transplanting Existing Vegetation 1 LS
21101 Temporary Haul Road Obliteration and Borrow Site Reclamation
1 LS
Misc Costs
64003 Add Instrumentation (Piezometers) 12 EA
Saddle Dike
20406 Soil Borrow 6,260 CY Quantity is in-situ and assumes 10% shrink from in-situ to compacted in-place condition.
70402 M2 Filter/Bedding Layer (AASHTO #89) 2,459 CY
70403 M3 Filter/Bedding Layer (AASHTO #357) 1,511 CY
20404 Embankment Fill 5,641 CY Quantity is compacted in-place. Placement is incidental.
Total
Method of Measures: CY= Cubic Yard, LS=Lump Sum, SY= Square Yard, LNFT= Linear Feet
Vender Name:
Representative:
SAM UEI #:
Phone#:
E-Mail:
HELENA-LEWIS AND CLARK NATIONSL FOREST