Attachment 2_ScheduleOfItems.pdf

PDF 203 KB Posted

Attached to
Helena National Forest - Park Lake Dam Rehabilitation
Solicitation number
1240LU26Q0013
Issued by

About this file

This Schedule of Items details the Park Lake Dam Rehabilitation project for the Helena-Lewis and Clark National Forest, with contract number 1240LU26Q0013. The project encompasses comprehensive dam reconstruction activities including preconstruction tasks, clearing and grubbing, deconstruction, reconstruction, seismic foundation improvements, hydraulic seepage control, road reconstruction, and reclamation. Key quantities include 22,200 cubic yards of dam excavation, 24,000 cubic yards of embankment fill, 20,300 square yards of clearing and grubbing, and multiple specialized activities such as compaction grouting, drain pipe installation, riprap placement, and instrumentation. The scope involves detailed engineering work with specific requirements for materials like filter layers, concrete sand, and aggregate, along with infrastructure elements such as fencing, gates, and road improvements.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1240LU26Q0013

SCHEDULE OF ITEMS

PARK LAKE DAM REHABILITATION

HELENA-LEWIS AND CLARK NATIONSL FOREST

Park Lake-Complete Dam Rehabilitation No. Description Quantity Unit Unit Price Cost Notes

Preconstruction

15101 Mobilization and Demobilization 1 LS

15102 Access Road Improvements 1 LS

15201 Construction Staking and Survey 1 LS

63501 Temporary Traffic Control 1 LS

Clearing and Grubbing

20101 Clearing and Grubbing downstream of dam and along access

20,300 SY

Deconstruction

20401 Dam Excavation 22,200 CY Quantity is in-situ.

20402 Temporary Stock Piling of Material 24,000 CY Assumes 440 CY waste of existing drain material and 10% swell.

20403 Borrow for Grout Mix 3,750 CY Quantity is in-situ.

Assume 750 CY will be wasted.

63001 Dewatering 1 LS

Reconstruction

20404 Embankment Fill 24,000 CY Quantity is compacted in-place. Placement is incidental.

20405 Soil Mixing and Disking 30,260 CY

25101 Class 2 Riprap - Dam Embankment 770 CY Placement cost only.

Quantity is placed volume.

25102 Class 2 Riprap - Saddle Dike 5,860 CY Placement cost only.

Quantity is placed volume.

25103 Class 2 Riprap - Ripping/Excavating 4,296 CY Quantity is in-situ bedrock volume, assumes 40% swell to placed volume and 80% of dam riprap is salvage.

70401 M1 Filter (ASTM C33 Washed Concrete Sand) 1,740 CY Placement is incidental.

70402 M2 Filter/Bedding Layer (AASHTO #89) 120 CY Placement is incidental.

70403 M3 Filter/Bedding Layer (AASHTO #357) 385 CY Placement is incidental.

60401 24" Standard Riser Inlet 1 UNITS Weir and customization incidental.

64001 6-inch Diameter Dual-Wall HDPE Perforated Drain

Pipe 270 LNFT Fittings and installation are incidental.

64002 6-inch Diameter Dual-Wall HDPE Solid Drain Pipe 240 LNFT Includes cleanouts.

Fittings and installations are incidental.

Seismic Foundation Improvement

26201 Primary Borings and Compaction Grouting 132 UNITS

26202 Secondary Borings and Compaction Grouting 30 UNITS

26203 Performance Testing 400 FEET

Hydraulic Seepage Control Barrier

26204 Shallow Borings and Compaction Grouting 179 UNITS

26205 Mid-Level Borings and Compaction Grouting 62 UNITS

26206 Deep Borings and Compaction Grouting 33 UNITS

26207 Secondary Borings and Grouting 15 UNITS

26208 Performance Testing 1 LS

Road Reconstruction

15202 Grade Survey 1 LS

30102 Road Surface Aggregate 425 CY Includes 25 cy of 6" thick aggregate for area of turnaround (1333 sf)

20406 Soil Borrow for Turnaround 7 CY

20404 Fill for Turnaround 5 CY

61901 Fencing 2,000 LNFT

61902 16' Gate 1 EA 61903 25' Gate 2 EA

Reclamation

62601 Transplanting Existing Vegetation 1 LS

21101 Temporary Haul Road Obliteration and Borrow Site Reclamation

1 LS

Misc Costs

64003 Add Instrumentation (Piezometers) 12 EA

Saddle Dike

20406 Soil Borrow 6,260 CY Quantity is in-situ and assumes 10% shrink from in-situ to compacted in-place condition.

70402 M2 Filter/Bedding Layer (AASHTO #89) 2,459 CY

70403 M3 Filter/Bedding Layer (AASHTO #357) 1,511 CY

20404 Embankment Fill 5,641 CY Quantity is compacted in-place. Placement is incidental.

Total

Method of Measures: CY= Cubic Yard, LS=Lump Sum, SY= Square Yard, LNFT= Linear Feet

Vender Name:

Representative:

SAM UEI #:

Phone#:

E-Mail:

HELENA-LEWIS AND CLARK NATIONSL FOREST

File details come from the government source that posted it. Updated .