Attachment 3 A-E MATOC Past Performance Questionnaire (PPQ).docx

DOCX document 37 KB Posted

Attached to
NIH Multiple Award Task Ordering Contract (MATOC) for Architect-Engineering Services, Construction Quality Management, and Commissioning
Solicitation number
NIH_FY2026_AE_MATOC
Issued by

About this file

This document is a Past Performance Questionnaire (PPQ) for the National Institutes of Health (NIH) Architect and Engineering (A/E) Multiple Award Task Order Contract (MATOC). The PPQ is designed to evaluate contractor performance across five key areas: quality of work, schedule performance, cost control effectiveness, management effectiveness, and overall performance. Contractors are rated using a scale from Exceptional to Unsatisfactory, with references asked to provide ratings and comments for each performance category.

The questionnaire is part of a pre-solicitation process for NIH's FY2026 A/E MATOC, which aims to establish multiple indefinite-delivery, indefinite-quantity (IDIQ) contracts for professional architectural and engineering services. The solicitation will also include Commissioning Support Services (Cx) and Construction Quality Management (CQM) services. Firms are required to submit SF 330 forms for evaluation, and selection will be based on demonstrated competence and qualifications. Completed questionnaires must be emailed to three NIH contacts: Thuy Le, Ana Marie Pagulayan, and Magan Miller.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR OFFICIAL USE ONLY

Source Selection Sensitive Information – See FAR 2.101 and 3.104

Architect and Engineer (A/E) Multiple Award Task Order Contract (MATOC)

FOR OFFICIAL USE ONLY

Source Selection Sensitive Information – See FAR 2.101 and 3.104

Architect and Engineer (A/E) Multiple Award Task Order Contract (MATOC)

ATTACHMENT 3

PAST PERFORMANCE QUESTIONNAIRE (PPQ)

Your organization has been identified for participation in past performance evaluation on a current solicitation at the National Institutes of Health (NIH) at Bethesda, Maryland. This information contained in this questionnaire will be used to evaluate the past performance for the contractor and contracting action identified below.

NIH’s Architect and Engineering (A/E) Multiple Award Task Order Contract (MATOC)

Your candid response to the questions is important to our evaluation effort and may affect the award outcome. Please indicate "Unknown" in any area that was not applicable to work performed on your contracting action.

THE COMPLETED FORM MUST BE SUBMITTED BY E-MAIL TO THE FOLLOWING INDIVIDUALS:

Thuy Le, thuy.le@nih.gov Ana Marie Pagulayan, anamarie.pagulayan@nih.gov Magan Miller, magan.miller@nih.gov

If you have any questions/concerns pertaining to this survey and/or the requested information, please contact Thuy Le, Ana Marie Pagulayan, and Magan Miller using the above contact information.

Thank you for your time and effort in completing this survey.

PAST PERFORMANCE QUESTIONNAIRE for offering A/E

PART I - TO BE COMPLETED BY A/E

Item
Requested Information
Information Provided by Contractor
A
A/E Information

A/E Company Name

A/E Representative Name

Title

Address

Telephone

Fax

E-mail Address

Contract Number

Task Order Number

Title of Contract

B
Project Owner Information

Owner/ Company/ Organization/ Agency Name

Owner Representative Name

Title

Address

Telephone

Fax

E-mail Address

PAST PERFORMANCE QUESTIONNAIRE

PART II - TO BE COMPLETED BY A/E’s REFERENCE

DEFINITIONS

Please use the following definitions when completing the Past Performance Questionnaire:

Rating
Description

Exceptional

Performance meets and exceeds many contractual requirements to the Client’s benefit. The contractual performance of the element was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

Very Good

Performance meets and exceeds some contractual requirements to the Client’s benefit. The contractual performance of the element was accomplished with some minor problems for which corrective actions taken by the contractor was effective.

Satisfactory

Performance meets contractual requirements. The contractual performance of the element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

Marginal

Performance does not meet some contractual requirements. The contractual performance of the element being evaluated reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.

Unsatisfactory

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

N/A

Performance was not observed. This indicates neither a favorable nor unfavorable rating.

PAST PERFORMANCE QUESTIONNAIRE

PART II - TO BE COMPLETED BY A/E’s REFERENCE

INSTRUCTIONS

Place a ‘rating’ in the appropriate column box using the definitions above.

Item

How do you rate the A/E’s ...?

Comments Please provide any comments, at the bottom of this form, to explain the rationale for you Rating to facilitate the Technical Evaluators in their review of the survey results. Please indicate if an item is not applicable to the representative project.

1 - Quality of Work

Ability to maintain quality control of design deliverables.

Responsiveness to design drawing review comments.

Review of submittals and shop drawings.

Item 1. Quality Rating here >

2 - Schedule Performance

Ability to provide and maintain design schedule.

Ability to adhere to administrative deadlines.

Processes in place to address any slippage of the design schedule.

Item 2.
Schedule Rating here >

PAST PERFORMANCE QUESTIONNAIRE

PART II - TO BE COMPLETED BY CONTRACTOR’S REFERENCE

3 - Effectiveness of Cost Control

Effectiveness in forecasting, managing, and controlling contract/modifications.

Any innovations in controlling costs.

Suitable process in place to make adjustments if the cost estimate exceeded available funds.

Item 3.
Cost Control Rating here >

4 - Effectiveness of Management

Ability onsite and at home office to adequately respond to approved changes in design.

Effectiveness in communicating concerns with the Contracting Officer/Owner concerning design construction.

Effectiveness of key A/E personnel in resolving identified issues in design and during construction.

Item 4.
Management Rating here >

Item 5. Overall Rating here >

Would you recommend this A/E firm for similar requirements in the future? Yes / No __________

Any other comments:

Attachment 3 - Past Performance Questionnaire - Offeror, Page 2 of 2 (Rev 04/19)