Attachment 2A_ 512A5-16-303 Construction Specifications Package - Perry Point.pdf

PDF 3 MB Posted

Attached to
Y1DA--VISN 5 - MULTIPLE AWARD TASK ORDER CONTRACT CONSTRUCTION 2022 Federal contract opportunity
Solicitation number
36C24522R0056
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 5

About this file

This is a solicitation for a multiple award task order contract for construction services within Veterans Integrated Service Network 5. The contract will have indefinite-delivery, indefinite-quantity terms and will be for one base year with four option years. Task orders will cover general construction categories including maintenance, repair, alteration, mechanical, electrical, HVAC, demolition, painting, paving, earthwork, carpentry, concrete, roofing, site work, excavation, interior and exterior renovation, and installation of ceilings, fixtures, electrical systems, plumbing, and flooring. Work may involve some or all elements and will be further defined in individual task orders. The contractor must have all required insurance and bonding and will work in and around an occupied hospital. Submittals will be required for staging equipment and supplies. Task orders will identify the applicable Davis-Bacon wage rates. Each awardee will be provided fair opportunity for task orders unless a statutory exception applies. The resulting contract will not provide for economic price adjustments and overhead and profit percentages will apply to the contract duration.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--VISN 5 - MULTIPLE AWARD TASK ORDER CONTRACT CONSTRUCTION 2022, newest first.
File Type Posted
Resized_20221013_065215.jpg JPG image
Resized_20221013_063747.jpg JPG image
Resized_20221013_065407.jpg JPG image
Resized_20221013_063737.jpg JPG image
Resized_20221013_063621.jpg JPG image
Resized_20221013_065235.jpg JPG image
Resized_20221013_065343.jpg JPG image
Resized_20221013_063752.jpg JPG image
36C24522R0056 0003.pdf PDF
Resized_20221013_065220.jpg JPG image
Resized_20221013_063633.jpg JPG image
Resized_20221013_063615.jpg JPG image
Resized_20221013_063628.jpg JPG image
Drawing 32-01-A12 Main Building Elevations C _ D - Copy.pdf PDF
Building 1 first floor-Layout1 - Copy.pdf PDF
Building 1 Second Floor-Layout1 - Copy.pdf PDF
Lab Waiting Sign In - Copy.pdf PDF
MATOC Site Visit Attendance_8-30-2022 - Copy.pdf PDF
15246 Perry Point ACM Summary Report_Medgas - Copy.pdf PDF
Perry Point Lead Survey Summary Report_Medgas - Copy.pdf PDF
36C24522R0056 0002.pdf PDF
MATOC Site Visit Attendance_9-22-2022 - Copy.pdf PDF
Building 1 Basement-Layout1 - Copy.pdf PDF
Expansion Joint Spec - Copy.pdf PDF
36C24522R0056 0001.pdf PDF
Attachment 7_ RFI SHEET.pdf PDF
Attachment 6C_ Security_SelfCertificationContinuousService.pdf PDF
Attachment 6A_ Security_ServicesRequestForm.pdf PDF
Attachment 6_Security Requirements Cover Page.pdf PDF
Attachment 5_ Surety Information.pdf PDF
Attachment 2D_ WAGE DETERMINATIONS PERRY POINT.pdf PDF
Attachment 8_ GEOGRAPHIC AREA SELECTION FORM.pdf PDF
Attachment 2B_ 512A5-16-303 SOW Upgrade Medical Gas Systems -Perry Point .docx DOCX document
Attachment 1D_ WAGE DETERMINATIONS BECKLEY VAMC - Copy.pdf PDF
36C24522R0056_1.docx DOCX document
Attachment 6F_ Security_PIVSponsorshipForm.pdf PDF
Attachment 3_ Past Performance Evaluation.docx DOCX document
Attachment 2C_ 512A5-16-303 Construction Drawings Package- Perry Point.pdf PDF
Attachment 1B_ Combined Specs Renovate Lab Waiting Area - Beckley.pdf PDF
Attachment 1A_ SOW - 517-17-123 Lab Waiting Area Beckley.docx DOCX document
Attachment 6E_ VA0710.pdf PDF
Attachment 6D_ OF306.pdf PDF
Attachment 6B_ Security_ServicesRequestForm_Supplemental.pdf PDF
Attachment_4 Construction Price Breakdown(R).xls XLS spreadsheet
Attachment 1C_ Combined Final Drawings Renovate Lab Waiting Area -Beckley.pdf PDF
Show all 45

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION BID DOCUMENTS

SPECIFICATIONS

UPGRADE MEDICAL GAS SYSTEMS

Project No. 512-A5-16-303

VA Maryland Healthcare System Perry Point VA Medical Center

Perry Point, MD

Miller-Remick LLC 1010 Kings Highway South

Building Two – 2nd Floor Cherry Hill, New Jersey 08034

(856) 429-4000

January 18, 2019

Department of Veterans Affairs VA Project No. 512-A5-16-303 Perry Point VA Medical Center Upgrade Medical Gas Systems Perry Point, MD Construction Bid Documents: 01/18/19

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

DIVISION 00 - SPECIAL SECTIONS DATE

00 01 15 List of Drawing Sheets 07-15

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 03-22 01 25 00 Substitution Procedures 05-19 01 26 00 Contract Modification Procedures 05-19 01 31 00 Project Management and Coordination 05-19 01 32 00 Construction Progress Documentation 05-19 01 32 16.15 Project Schedules 05-19 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 02-17 01 42 19 Reference Standards 05-16 01 45 29 Testing Laboratory Services 05-19 01 58 16 Temporary Interior Signage 07-15 01 73 00 Execution 05-19 01 74 19 Construction Waste Management 09-13 01 77 00 Closeout Procedures 05-19 01 78 39 Project Record Documents 05-19 01 79 00 Demonstration and Training 05-19

DIVISION 02 – EXISTING CONDITIONS

02 82 11 Traditional Asbestos Abatement 09-15 02 82 13.13 Glovebag Asbestos Abatement 09-15 02 82 13.19 Asbestos Floor Tile and Mastic Abatement 09-15 02 83 33.13 Lead-Based Paint Removal and Disposal 08-16

DIVISION 03 – CONCRETE

03 30 53 Cast-in-Place Concrete 02-16

DIVISION 05 – METALS

05 50 00 Metal Fabrications 05-19

DIVISION 06 – WOOD,PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-15

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping 02-16

00 01 10-2

07 92 00 Joint Sealants 10-15

DIVISION 09 – FINISHES

09 22 16 Non-Structural Metal Framing 05-16 09 29 00 Gypsum Board 11-14 09 51 00 Acoustical Ceilings 12-16 09 91 00 Painting 01-16

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural

Components 01-14

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16 22 05 12 General Motor Requirements for Plumbing Equipment 09-15 22 05 23 General-Duty Valves for Plumbing Piping 09-15 22 11 00 Facility Water Distribution 09-15 22 13 00 Facility Sanitary and Vent Piping 09-15 22 61 13.74 Dental Compressed-Air Piping 09-15 22 61 19.74 Dental Compressed-Air Equipment 09-15 22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15 22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 08-17 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 08-17

23 07 11 HVAC and Boiler Plant Insulation 02-15 23 23 00 Refrigerant Piping 02-15 23 81 00 Decentralized Unitary HVAC Equipment 02-11

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 05-14 26 27 26 Wiring Devices 01-16 26 29 11 Motor Controllers 08-14 26 29 21 Enclosed Switches and Circuit Breakers 01-17

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 06-15 27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Raceways and Boxes for Communications Systems 06-15

00 01 10-3

27 10 00 Control, Communication and Signal Wiring 06-15 27 15 00 Communications Structured Cabling 01-16

DIVISION 31 – EARTHWORK

31 20 11 Earthwork (Short Form) 10-12

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWINGS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

GI001 COVER SHEET AND DRAWING INDEX

HAZARDOUS MATERIALS

HA101 BUILDING 14 - BASEMENT LEVEL

HA102 BUILDING 14 - FIRST AND SECOND FLOORS

HA103 BUILDING 19 - BASEMENT

HA104 BUILDING 23 - BASEMENT

HA105 BUILDING 23 - FIRST AND SECOND FLOORS

HA106 GENERIC TENTED GLOVE BAG WORK AREA CONTAINMENT

HA107 GENERIC TRADITIONAL ABATEMENT WORK AREA CONTAINMENT

ARCHITECTURAL

AS001 ARCHITECTURAL GENERAL NOTES, ABBREVIATIONS, SYMBOLS, AND

GENERAL DETAILS

AS002 ICRA NOTES AND REGULATIONS

GR001 ARCHITECTURAL PHOTOGRAPHS EXISTING CONDITIONS

GR002 ARCHITECTURAL PHOTOGRAPHS EXISTING CONDITIONS

AS101.T1-4 ARCHITECTURAL PLAN TUNNELS

AS101.T5 ARCHITECTURAL PLAN TUNNELS

AS101.13 ARCHITECTURAL PLAN BASEMENT

AS101.14 ARCHITECTURAL PLAN BASEMENT

AS101.19 ARCHITECTURAL PLAN BASEMENT

AS101.23 ARCHITECTURAL PLAN BASEMENT

AS101.24 ARCHITECTURAL PLAN BASEMENT

AS101.25 ARCHITECTURAL PLAN BASEMENT

AS101.365 ARCHITECTURAL PLAN BASEMENT

AS111.14 ARCHITECTURAL PLAN FIRST FLOOR

AS121.14 ARCHITECTURAL PLAN SECOND FLOOR

PLUMBING

00 01 15 - 2

P-001 ABBREVIATIONS, GENERAL NOTES & SYMBOLS

PS101 MEDICAL GAS SITE PLAN EAST SIDE

PS102 MEDICAL VACUUM SITE PLAN WEST SIDE

PS103 MEDICAL AIR SITE PLAN WEST SIDE

PS104 MEDICAL OXYGEN SITE PLAN WEST SIDE

P-100.13 PLAN BASEMENT LEVEL

P-100.14 PLAN BASEMENT LEVEL

P-101.14 PLANS 1ST & 2ND FLOOR

P-100.19 PLANS BASEMENT & 1ST FLOOR

P-100.23 PLAN BASEMENT LEVEL

P-101.23 PLANS 1ST & 2ND FLOOR

P-10B.24 PLAN SUB-BASEMENT LEVEL

P-100.24 PLAN BASEMENT LEVEL

P-100.25 PLAN BASEMENT LEVEL

P-100.364 PLAN BASEMENT LEVEL

P-400.23 ENLARGED PLANS BASEMENT LEVEL

P-501 DETAILS

P-601 MEDICAL GAS RISER DIAGRAM BUILDINGS 14H, 24H & 25H

P-602 MEDICAL GAS RISER DIAGRAM BUILDINGS 19H, 23H & 361

P-701 SCHEDULES

ELECTRICAL

E-001 ABBREVIATIONS, NOTES, & SYMBOLS

ES101 MEDICAL GAS SITE PLAN

E-100.14 PLAN - BASEMENT, 1ST, & 2ND FLOOR

E-100.19 PLAN - BASEMENT & 1ST FLOOR

E-100.23 PLAN - BASEMENT & 2ND FLOOR

E-100.24 PLAN - SUB-BASMENT & BASEMENT LEVEL

E-100.25 PLAN - BASEMENT LEVEL

E-100.361 PLAN - GROUND LEVEL

E-100.364 PLAN - BESEMENT LEVEL

E-601 MEDICAL GAS RISER DIAGRAM

E-701 SCHEDULES AND DETAILS

- - - E N D - - -i

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 SAFETY REQUIREMENTS

1.2 GENERAL INTENTION

1.3 STATEMENT OF BID ITEMS

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.5 CONSTRUCTION SECURITY REQUIREMENTS

1.6 OPERATIONS AND STORAGE AREAS

1.7 ALTERATIONS

1.8 DISPOSAL AND RETENTION

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

1.10 RESTORATION

1.11 AS-BUILT DRAWINGS

1.12 USE OF ROADWAYS

ii

1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.14 TEMPORARY USE OF EXISTING ELEVATORS

1.15 TEMPORARY TOILETS

1.16 AVAILIBILITY AND USE OF UTILITY SERVICES

1.17 TESTS

1.18 INSTRUCTIONS

1.19 HISTORIC PRESERVATION

iii

PAGE INTENTIONALLY LEFT BLANK

01 00 00 - 1

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the Upgrade Medical Gas

Systems project at the Perry point VA Medical Center in Perry point, MD as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the

Medical Center Contracting Officer’s Representative (COR).

C. Offices of Miller-Remick LLC, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer.

D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: All work as required by drawings and specifications, including general construction, demolition and alteration of existing construction, structural, mechanical, electrical, plumbing, fire protection, hazardous material removal, relocation of hospital equipment, utility systems, necessary alteration of existing structure, and certain other items.

01 00 00 - 2

The project will be completed in phases and provide equipment and distribution upgrades to the medical gas systems (Medical Air, Medical

Vacuum, and O2) within Buildings 14H, 19H, 23H, 24H, and 25H, as well as alarm and monitoring upgrades for Buildings 361 and 364.

The existing source equipment/systems are either in poor physical and operating condition, are not energy efficient, do not maintain proper system pressures/quality, are not properly monitored/alarmed, are not properly piped for distribution/inlet/outlet/isolation piping and, in many instances, do not comply with the latest requirements and recommendations outlined within the VA Design Guides for Medical Gas

System design, operation, monitoring and alarming.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

Badges must always be carried and displayed by contract employees while on Medical Center property.

2. Contractor and all sub-contractors shall, upon notice of contract award, immediately begin the process of obtaining or verifying existing security badging. Badging process includes submitting paperwork for background checks and obtaining fingerprinting though the VA personnel security office for every employee assigned to the project. All security paperwork for personnel must be submitted

01 00 00 - 3 within 15 calendar days of contract award. Contractor and subcontractors shall account for time and cost requirements for multiple in-person trips to the VA facility by each employee to secure badging and fingerprinting, independent of contract work.

Contractor shall not delay security badging efforts until they have arrived on site.

3. No photography of VA premises is allowed without written permission of the Contracting Officer.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including tool boxes, trailers, parked machines, and to take any emergency action within the work area.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

01 00 00 - 4

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2 to 5) permits shall be issued for General

Contractor and its employees for parking in designated areas only.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The

01 00 00 - 5 temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workmen are subject to rules of Medical Center applicable to their conduct.

F. Contractor may not use Medical Center restroom facilities. Contractor shall provide and maintain adequate portable restrooms and handwashing stations for all contract personnel.

G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of

01 00 00 - 6

Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment may be permitted subject to fire and safety requirements, and as allowed by the project COR.

H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved: 1.

Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

I. Phasing:

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to insure accomplishment of this work in successive phases mutually agreeable to

COR and Contractor.

01 00 00 - 7

J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

K. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and 27 05 11 REQUIREMENTS

FOR COMMUNICATIONS INSTALLATIONS for additional requirements.

2. Contractor shall submit a request to interrupt any such services to

COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least

01 00 00 - 8 inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

M. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

N. Coordinate the work for this contract with other construction operations as directed by the COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF

ROADWAYS.

01 00 00 - 9

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a signed report to the

Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and the COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by

Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE

CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR

852.236-88).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

01 00 00 - 10

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of

Contractor to restore damage caused by Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by the COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center grounds and disposed on in accordance with all local, state, and federal environmental regulations.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by

01 00 00 - 11 the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the

Contractor fails or refuses to repair the damage promptly, the

Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

(FAR 52.236-9)

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall

01 00 00 - 12 conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. Contractor is required to thoroughly survey and record by means of photography the pre-construction condition of the existing structure and adjacent area to construction to establish a pre-construction condition. Any existing issues shall be brought to the attention of the

Contracting Officer prior to commencing construction operations.

D. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

E. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR

52.236-2).

F. Contractor to investigate all existing drains that will require connections in the contract drawings. Any existing sanitary or storm water drains that new piping will connect to shall be investigated with a sewer camera and conditions documented by videotaping the inspection.

New piping shall be thoroughly cleaned and jetted to the nearest manhole location following installation, and debris dislodged during cleaning shall be removed from manhole or piping. Documentation of the final cleaned condition of all new drain piping installed on the project shall be submitted with close-out documentation. In the event pre-construction documentation of drain piping is not completed prior to work commencing, the contractor shall assume responsibility for the condition of the existing drain piping.

01 00 00 - 13

1.11 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR to review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.12 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.

C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.

1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

01 00 00 - 14

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the

COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.

Installation of temporary electrical equipment or devices shall be in accordance with the current edition of NFPA 70, National

Electrical Code. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned.

Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

01 00 00 - 15

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.

1.14 TEMPORARY USE OF EXISTING ELEVATORS

A. Use of existing elevators for handling building materials and

Contractor's personnel will be permitted subject to following provisions:

1. Contractor makes all arrangements with the COR for use of elevators.

The COR will ascertain that elevators are in proper condition.

Contractor may use elevators for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of Veterans Affairs.

2. Contractor covers and provides maximum protection of following elevator components:

a. Entrance jambs, heads soffits and threshold plates.

b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.

c. Finish flooring.

3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractors expense.

4. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining at the contractors expense.

5. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the contractors expense, if recommended by elevator inspector after elevator is released by Contractor.

01 00 00 - 16

6. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.

1.15 TEMPORARY TOILETS

A. Contractor may have for use of Contractor's workmen, such toilet accommodations as may be assigned to Contractor by Medical Center.

Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.

1.16 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

C. Contractor shall install meters at Contractor's expense and furnish the

Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.

D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:

01 00 00 - 17

1. Obtain heat by connecting to Medical Center heating distribution system.

E. Electricity (for Construction and Testing).

1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.

F. Water (for Construction and Testing).

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the

Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR’s discretion) of use of water from Medical Center's system.

1.17 TESTS

A. The contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.

B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.

C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.

Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

01 00 00 - 18

D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.

E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonable period of time, during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.

F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.

1.18 INSTRUCTIONS

A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.

B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and

01 00 00 - 19 instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.

C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned

Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.

This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.

1.19 HISTORIC PRESERVATION

Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the COR verbally, and then with a written follow up.

01 00 00 - 20

1.20 ELECTRONIC SUBMITTAL PROCEDURES

A. Summary:

1. A/E Design Submissions, Shop drawing and product data submittals shall be transmitted to the Government (PDF) format using a web- based submittal exchange website service designed specifically for transmitting submittals between all construction team members, including designated VA team members for this project.

2. The intent of electronic submittals is to expedite the construction process by reducing paperwork, improving information flow, and decreasing turnaround time.

3. The electronic submittal process is not intended for color samples, color charts, or physical material samples.

B. Procedures:

1. Create submittal log in the submittal by inserting required submittals listed in individual design submission requirements and specification sections.

2. Submittal Preparation - Contractor may use any or all of the following options:

a. Subcontractors and Suppliers provide electronic (PDF) submittals to Contractor via the submittal exchange website.

b. Subcontractors and Suppliers provide electronic (PDF) submittals to Contractor via email.

c. Subcontractors and Suppliers provide paper submittals to a scanning service/program which electronically scans and converts to PDF format.

3. Printed Submittals: Provide two printed sets of submittals for shop drawings for structural framing in addition to electronic submittals.

4. Contractor shall review and apply electronic stamp certifying that the submittal complies with the requirements of the Contract Documents including verification of manufacturer / product, dimensions and coordination of information with other parts of the work.

5. Contractor shall transmit each submittal to Architect using the submittal exchange website.

6. The Government as well as design Architect/Engineer review comments will be made available on the submittal exchange website for downloading. Contractor will receive email notice of completed review.

7. Distribution of reviewed submittals to subcontractors and suppliers is the responsibility

01 00 00 - 21 of the Contractor.

8. Submit paper copies of any reviewed submittals not submitted electronically at project closeout for record purposes.

C. Costs:

1. Contractor shall include the full cost of the submittal exchange project subscription for the duration of the project in their proposal. This cost is included in the base Contract Amount.

2. The intent is for the submittal exchange service cost to be in lieu of postage or shipping costs typically paid for paper submittals. Service cost is a net cost savings to Contractor because submittals sent electronically do not need to be shipped physically.

3. After award of contract, training shall be provided by the submittal exchange service regarding use of their website and PDF submittals. The costs of the training shall be included in the base contract amount.

4. Internet Service and Equipment Requirements:

a. Email address and Internet access at Contractor’s main office.

b. Adobe Acrobat (www.adobe.com), Bluebeam PDF Revu

(www.bluebeam.com), or other similar PDF review software for applying electronic stamps and comments.

5. A particular service may be considered if submitted prior to bid date for pre-approval. Product requirements:

a. Independently hosted, web-based system for automated tracking, storage, and distribution of contract submittals, Requests For Information, and other contract related documents. FTP sites, e-mail exchanges, and server-based systems hosted from inside a contractor’s office will not be considered are not acceptable.

b. Utilize 256-bit SSL encryption and hosted at SAS70 Type II compliant data centers.

c. Minimum five years documented experience of use on comparable commercial construction projects.

“Comparable commercial construction projects” shall be defined as documented use on a minimum of five hundred governmental, public-entity, or private sector projects each of $1 million construction value or greater.

d. Minimum five years documented 99.5% website uptime.

e. Unlimited individual user accounts and system access for all project subcontractors, general

01 00 00 - 22 contractor, owner staff, architect, design consultants, and sub-consultants, with no additional fees for those parties to access the system.

f. Separate locations for owner, architect, design consultant, and sub-consultant review comments with contractors restricted from viewing comments until final review or release by owner or primary design consultant.

g. Full version histories and dates of exchanges automatically tracked and available for viewing, searching, and reporting in a linear log format compatible with AIA G712.

h. Functionality to group submittals as required packages and apply forms and review comments to…