Attachment - 20 AE Update 1.3 -Attachment 20 V1 549A4-21-700 100 Bid Doc Specs.pdf
PDF 7 MB Posted
- Solicitation number
- 36C77624B0007
About this file
This document provides specifications for developing a critical path method project schedule for the EHRM Infrastructure Upgrades project at the VA North Texas Healthcare facility in Bonham, Texas. The contractor must designate a representative to be responsible for developing, reviewing, and reporting progress on the project schedule. Within 45 days of the notice to proceed, the contractor must submit an interim schedule and final schedule in CPM format, along with computer-generated reports and an electronic file with schedule data. The schedule must show all work activities with durations of 20 days or less, milestones, costs loaded to each activity equal to the total contract price, and responsibility codes for the contractor's work. The contractor must provide monthly schedule updates and computer-generated reports to support payment applications and identify any needed schedule adjustments.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
549A4-21-700 | Bonham EHRM Infrastructure Upgrades Bonham VA Medical Center – Bonham, TX
FINAL BID DOCUMENTS
July 7, 2023
Specifications Sign and Seal:
Texas Architectural Registration No: 22680
Specifications Sign and Seal:
Texas Engineer (Civil) Registration No:
115081
Specifications Sign and Seal: Texas Engineer (Mechanical) Registration No: 136680
Specifications Sign and Seal: Registered Communications Distribution Designer Registration No: BICSIID # 270641
Specifications Sign and Seal: EHS Credential for Hazardous Materials Remediation Registration No: 8594CP
Specifications Sign and Seal: Texas Engineer (Fire Protection) Registration No: 135432
Texas Engineer (Electrical) Registration No: 144295
Texas Engineer (Structurall) Registration No: 98068
A | 4425 East Agave Road Phoenix, AZ 85044 P | 602.584.5010 E | howdy@spur-design.com W | spur-design.com
VA 549A4-21-700 EHRM Infrastructure Upgrades
VA North Texas Healthcare (VHANTX), Bonham, TX
100% Construction Documents
11-28-22
00 01 10-1
TABLE OF CONTENTS
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20
01 33 23 Shop Drawings, Product Data, and Samples 09-22
01 35 26 Safety Requirements 10-22
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 57 19 Temporary Environmental Controls 01-21
01 74 19 Construction Waste Management 04-22
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 01-21
02 41 00 Demolition 08-17
02 82 11 Traditional Asbestos Abatement 01-21
02 82 13.13 Glovebag Asbestos Abatement 01-21
02 82 13.19 Asbestos Floor Tile & Mastic Abatement 01-21
02 82 13.21 Asbestos Roofing Abatement 01-21
02 82 13.31 Asbestos Transite-Type Abatement 01-21
02 83 33 13 Lead Based Paint 01-21
DIVISION 03 – CONCRETE – NOT USED
DIVISION 04 – MASONRY – NOT USED
DIVISION 05 – METALS
05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES - NOT USED
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 27 26 Fluid-Applied Membrane Air Barrier, Vapor Permeable 01-21
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
07 95 13 Expansion Joint Cover Assemblies 01-21
100% Construction Documents
11-28-22
00 01 10-2
TABLE OF CONTENTS
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 14 00 Interior Wood Doors 01-21
08 31 13 Access Doors and Frames 04-22
08 71 00 Door Hardware 05-22
08 80 00 Glazing 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 65 13 Resilient Base and Accessories 01-21
09 65 19 Resilient Tile Flooring 05-18
09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
10 22 13 Wire Mesh Partitions 01-21
10 26 00 Wall and Door Protection 01-21
10 44 13 Fire Extinguisher Cabinets 08-18
DIVISION 11 – EQUIPMENT - NOT USED
DIVISION 12 – FURNISHINGS - NOT USED
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components
01-14
DIVISION 14– CONVEYING EQUIPEMENT - NOT USED
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression Systems 11-16
21 13 13 Wet-Pipe Sprinkler Systems 06-15
21 22 00 Clean Agent Fire Suppression Systems 05-15
DIVISION 22 – PLUMBING - NOT USED
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 10-22
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
10-22
100% Construction Documents
11-28-22
00 01 10-3
TABLE OF CONTENTS
SECTION NO. DIVISION AND SECTION TITLES DATE
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
10-22
23 05 93 Testing, Adjusting, and Balancing for HVAC 10-22
23 08 00 Commissioning of HVAC Systems 10-22
23 09 23 Direct-Digital Control System for HVAC 10-22
23 21 13 Hydronic Piping 10-22 23 21 23 Hydronic Pumps 10-22
23 23 00 Refrigerant Piping 10-22
23 31 00 HVAC Ducts and Casings 10-22
23 36 00 Air Terminal Units 10-22
23 37 00 Air Outlets and Inlets 10-22
23 81 00 Decentralized Unitary HVAC Equipment 10-22
23 81 23 Computer-Room Air-Conditioners 10-22
DIVISION 25 – INTEGRATED AUTOMATION – NOT USED
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 05 73 Overcurrent Protective Device Coordination Study 01-18
26 08 00 Commissioning of Electrical Systems 11-16
26 22 00 Low-Voltage Transformers 01-18
26 24 16 Panelboards 01-18
26 26 00 Power Distribution Units for Static Uninterruptible
Power Systems
01-18
26 27 26 Wiring Devices 01-18
26 29 11 Motor Controllers 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 36 23 Automatic Transfer Switches 01-17
26 41 00 Facility Lightning Protection 01-17
26 51 00 Interior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 06-15
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Conduits and Backboxes for Communications Systems 11-21
27 05 36 Cable Trays for Communications Systems 11-21
27 05 53 Identification for Communications Systems 07-21
27 08 00 Commissioning of Communications Systems 11-16
27 10 00 Structured Cabling 11-21
27 11 00 Telecommunications Room Fittings 06-15
27 11 16 Communications Cabinets, Racks, Frames, and Enclosures 11-21
27 11 19 Communications Termination Blocks and Patch Panels 11-21
27 11 26 Communications Rack Mounted Power Protection and Power
Strips
11-21
27 13 13 Communications Copper Backbone Cabling 11-21
100% Construction Documents
11-28-22
00 01 10-4
TABLE OF CONTENTS
SECTION NO. DIVISION AND SECTION TITLES DATE
27 13 13.13 Communications Copper Cable Splicing and Terminations 11-21
27 13 23 Communications Optical Fiber Backbone Cabling 11-21
27 15 13 Communications Copper Horizontal Cabling 11-21
27 15 13.13 Communications Optical fiber Cable Splicing and
Terminations
11-21
27 16 19 Communications Patch Cords, Station Cords, and Cross
Connect Wire
11-21
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 08 00 Commissioning of Electronic Safety and Security Systems
28 13 00 Physical Access Control Systems 10-11
28 16 00 Intrusion Detection System 10-11
28 23 00 Video Surveillance 09-11
28 31 00 Fire Detection and Alarm Systems 10-11
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 07-16
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 39 Cement and Concrete for Exterior Improvements 08-16
32 12 16 Asphalt Paving 09-15
32 31 13 Chain Link Fences and Gates 05-18
32 90 00 Planting
DIVISION 33 – UTILITIES - NOT USED
DIVISION 34 – TRANSPORTATION - NOT USED
DIVISION 48 – Electrical Power Generation - NOT USED
100% Bid Documents
05-01-20
00 01 15 - 1
LIST OF DRAWINGS
SECTION 00 01 15
LIST OF DRAWINGS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
1 GI000 COVER SHEET
2 GI001 SHEET INDEX
3 GI002 GENERAL INFORMATION
4 GI003 I ICRA CONSTRUCTION DETAILS
HAZARDOUS MATERIALS
5 HA010 BUILDING 1 - BASEMENT - ENVIRONMENTAL HAZARDS
6 HA011 BUILDING 1 - FLOOR 1 - ENVIRONMENTAL HAZARDS
7 HA012 BUILDING 1 - FLOOR 2 - ENVIRONMENTAL HAZARDS
8 HA013 BUILDING 1 - FLOOR 3 - ENVIRONMENTAL HAZARDS
9 HA014 BUILDING 1 - FLOOR 4 - ENVIRONMENTAL HAZARDS
10 HA015 BUILDING 1 - FLOOR 5 - ENVIRONMENTAL HAZARDS
11 HA021 BUILDING 2 - FLOOR 1 - ENVIRONMENTAL HAZARDS
12 HA022 BUILDING 2 - FLOOR 2 - ENVIRONMENTAL HAZARDS
13 HA023 BUILDING 2 - FLOOR 3 - ENVIRONMENTAL HAZARDS
14 HA024 BUILDING 2 - FLOOR 4 - ENVIRONMENTAL HAZARDS
15 HA031 BUILDING 3 - FLOOR 1 - ENVIRONMENTAL HAZARDS
16 HA032 BUILDING 3 - FLOOR 2 - ENVIRONMENTAL HAZARDS
17 HA041 BUILDING 4 - ENVIRONMENTAL HAZARDS
18 HA081 BUILDING 8 - ENVIRONMENTAL HAZARDS
19 HA091 BUILDING 9 - ENVIRONMENTAL HAZARDS
20 HA101 BUILDING 10 - FLOOR 1 - ENVIRONMENTAL HAZARDS
21 HA111 BUILDING 11 - FLOOR 1 - ENVIRONMENTAL HAZARDS
22 HA121 BUILDING 12 - FLOOR 1 - ENVIRONMENTAL HAZARDS
23 HA122 BUILDING 12 - FLOOR 2 - ENVIRONMENTAL HAZARDS
24 HA123 BUILDING 12 - ROOF - ENVIRONMENTAL HAZARDS
25 HA241 BUILDING 24 - ROOF - ENVIRONMENTAL HAZARDS
26 HA291 BUILDING 29 - ENVIRONMENTAL HAZARDS
27 HA340 BUILDING 34 - FLOOR 1 - ENVIRONMENTAL HAZARDS
100% Bid Documents
05-01-20
00 01 15 - 2
LIST OF DRAWINGS
Drawing No. Title
CIVIL
28 GS001 GENERAL LAYOUT PLAN
29 GS002 OVERALL SITE AND DEMOLITION PLAN
30 GS003 SITE AND DEMOLITION PLAN 1
31 GS004 SITE AND DEMOLITION PLAN 2
32 GS005 SITE AND DEMOLITION PLAN 3
33 GS006 SITE AND DEMOLITION PLAN 4
34 GS007 GRADING PLAN 1
35 GS008 GRADING PLAN 2
36 GS009 GRADING PLAN 3
37 GS010 GRADING PLAN 4
38 GS011 UTILITY PLAN 1
39 GS012 UTILITY PLAN 2
40 GS013 UTILITY PLAN 3
41 GS014 UTILITY PLAN 4
42 GS015 EROSION CONTROL PLAN 1
43 GS016 EROSION CONTROL PLAN 2
44 GS017 EROSION CONTROL PLAN 3
45 GS018 EROSION CONTROL PLAN 4
46 GS019 EROSION CONTROL DETAILS
47 GS020 DETAILS
STRUCTURAL
48 S-001 STRUCTURAL GENERAL NOTES
49 S-201 BUILDING 1 ROOF PLAN
50 S-202 BUILDINGS 2 & 3 ROOF PLANS
51 S-203 BUILDINGS 4, 9, 10 & 12 ROOF PLANS
52 S-204 BUILDING 24 ROOF PLAN
100% Bid Documents
05-01-20
00 01 15 - 3
LIST OF DRAWINGS
Drawing No. Title
ARCHITECTURAL
53 A-101 BUILDING 1 - REFERENCE PLANS
54 A-102 BUILDING 1 - REFERENCE PLANS
55 A-103 BUILDING 2 - REFERENCE PLANS
56 A-104 BUILDING 2 - REFERENCE PLANS
57 A-105 BUILDINGS 3, 4, 8, & 9 - REFERENCE PLANS
58 A-106 BUILDINGS 10, 11, & 12 - REFERENCE PLANS
59 A-107 BUILDING 24 - REFERENCE PLAN
60 A-108 BUILDING 24 - REFERENCE PLAN
61 A-109 BUILDING 29 - REFERENCE PLAN
62 AE101 BLDG 1 - BASEMENT - ENLARGED PLANS
63 AE102 BLDG 1 - LEVEL ONE - ENLARGED PLANS
64 AE103 BLDG 1 - LEVEL TWO, LEVEL THREE, & LEVEL FOUR -
ENLARGED PLANS
65 AE104 BLDG 1 - LEVEL FIVE - ENLARGED PLANS
66 AE105 BLDG 2 - LEVEL ONE & LEVEL TWO - ENLARGED PLANS
67 AE106 BLDG 2 - LEVEL TWO, LEVEL THREE, & LEVEL FOUR -
ENLARGED PLANS
68 AE107 BLDG 2 - LEVEL FOUR, BLDG 3 - ENLARGED PLANS
69 AE108 BLDG 4 & 8 - ENLARGED PLANS
70 AE109 BLDG 9 & 10 - ENLARGED PLANS
71 AE110 BLDG 11 & 12 - ENLARGED PLANS
72 AE111 BLDG 24 - LEVEL ONE - ENLARGED PLANS
73 AE112 BLDG 24 - LEVEL TWO - ENLARGED PLANS
74 AE113 BLDG 29 - ENLARGED PLANS
75 AE601 DOOR SCHEDULE & DETAILS
76 AF711 PARTITION, FINISH SCHEDULES & DETAILS
FIRE PROTECTION
77 FA001 FIRE ALARM NOTES MATRIX AND RISER DIAGRAM
78 FA101 BUILDING 1 - REFERENCE PLANS
79 FA102 BUILDING 1 - REFERENCE PLANS
80 FA103 BUILDING 2 - REFERENCE PLANS
81 FA104 BUILDING 2 - REFERENCE PLANS
82 FA105 BUILDINGS 3, 4, 8, & 9 - REFERENCE PLANS
83 FA106 BUILDINGS 10, 11, 12, & 34 - REFERENCE PLANS
100% Bid Documents
05-01-20
00 01 15 - 4
LIST OF DRAWINGS
Drawing No. Title
FIRE PROTECTION CONTINUED
84 FA107 BUILDING 24 - REFERENCE PLAN
85 FA108 BUILDING 24 - REFERENCE PLAN
86 FA109 BUILDING 29 - REFERENCE PLAN
87 FA401 BLDG 1 - BASEMENT - ENLARGED PLANS
88 FA402 BLDG 1 - ENLARGED PLANS
89 FA403 BLDG 2 & 3 - ENLARGED PLANS
90 FA404 BLDG 4 & 8 - ENLARGED PLANS
91 FA405 BLDG 9 & 10 - ENLARGED PLANS
92 FA406 BLDG 24 - ENLARGED PLANS
93 FA407 BLDG 29 - ENLARGED PLANS
94 FA500 FIRE ALARM DETAILS
95 FX001 FIRE SPRINKLER NOTES
96 FX101 BUILDING 1 - REFERENCE PLANS
97 FX102 BUILDING 1 - REFERENCE PLANS
98 FX103 BUILDING 2 - REFERENCE PLANS
99 FX104 BUILDING 2 - REFERENCE PLANS
100 FX105 BUILDINGS 3, 4, 8, & 9 - REFERENCE PLANS
101 FX106 BUILDINGS 10, 11, 12, & 34 - REFERENCE PLANS
102 FX107 BUILDING 24 - REFERENCE PLAN
103 FX108 BUILDING 24 - REFERENCE PLAN
104 FX109 BUILDING 29 - REFERENCE PLAN
105 FX401 BLDG 1 - BASEMENT - ENLARGED PLANS
106 FX402 BLDG 1 - ENLARGED PLANS
107 FX403 BLDG 2 & 3 - ENLARGED PLANS
108 FX404 BLDG 4 & 8 - ENLARGED PLANS
109 FX405 BLDG 9 & 10 - ENLARGED PLANS
110 FX406 BLDG 24 - ENLARGED PLANS
111 FX407 BLDG 29 - ENLARGED PLANS
112 FX500 FIRE SPRINKLER DETAILS
100% Bid Documents
05-01-20
00 01 15 - 5
LIST OF DRAWINGS
Drawing No. Title
MECHANICAL
113 M-000 LEGEND AND ABBREVIATIONS
114 M-101 BUILDING 1 HVAC REFERENCE PLANS
115 M-102 BUILDING 1 HVAC REFERENCE PLANS
116 M-103 BUILDING 2 HVAC REFERENCE PLANS
117 M-104 BUILDING 2 HVAC REFERENCE PLANS
118 M-105 BUILDING 3 HVAC REFERENCE PLANS
119 M-106 BUILDING 4, 8, 9, 10, 11, 12, & 34 HVAC REFERENCE
PLANS
120 M-107 BUILDING 24 HVAC REFERENCE PLANS
121 M-108 BUILDING 24 HVAC REFERENCE PLANS
122 M-109 BUILDING 29 HVAC REFERENCE PLANS
123 M-201 BUILDING 1 HVAC ROOF PLAN
124 M-202 BUILDING 2 & 3 HVAC ROOF PLANS
125 M-203 BUILDING 4, 9, 10, & 12 HVAC ROOF PLANS
126 M-204 BUILDING 24 HVAC ROOF PLAN
127 M-401 BUILDING 1 HVAC ENLARGED PLANS
128 M-402 BUILDING 1 HVAC ENLARGED PLANS CONTINUED
129 M-403 BUILDING 2 HVAC ENLARGED PLANS
130 M-404 BUILDING 2, 3, & 4 HVAC ENLARGED PLANS CONTINUED
131 M-405 BUILDING 8, 9, 10, 11, & 12 HVAC ENLARGED PLANS
132 M-406 BUILDING 24 HVAC ENLARGED PLANS
133 M-407 BUILDING 29 HVAC ENLARGED PLANS
134 M-501 MECHANICAL DETAILS
135 M-502 MECHANICAL DETAILS
136 M-601 MECHANICAL SCHEDULES
137 M-701 MECHANICAL CONTROLS
ELECTRICAL
138 E-001 ELECTRICAL LEGEND AND ABBREVIATIONS
139 E-101 BUILDING 1 - REFERENCE PLANS
140 E-102 BUILDING 1 - REFERENCE PLANS
141 E-103 BUILDING 2 - REFERENCE PLAN
142 E-104 BUILDING 2 - REFERENCE PLAN
143 E-105 BUILDINGS 3, 4, 8, & 9 - REFERENCE PLANS
144 E-106 BUILDINGS 10, 11, 12, & 34 - REFERENCE PLANS
100% Bid Documents
05-01-20
00 01 15 - 6
LIST OF DRAWINGS
Drawing No. Title
ELECTRICAL CONTINUED
145 E-107 BUILDING 24 - REFERENCE PLAN
146 E-108 BUILDING 24 - REFERENCE PLAN
147 E-109 BUILDING 29 - REFERENCE PLAN
148 E-201 BUILDING 1 - ROOF PLANS
149 E-202 BUILDINGS 2 & 3 - ROOF PLANS
150 E-203 BUILDINGS 4, 8, 9, 10, & 12 - ROOF PLANS
151 E-204 BUILDING 24 - ROOF PLANS
152 E-401 BLDG 1 - BASEMENT ELECTRICAL ROOM - ENLARGED PLANS
153 E-402 BLDG 1 - BASEMENT - ENLARGED PLANS
154 E-403 BLDG 1 - LEVEL ONE - ENLARGED PLANS
155 E-404 BLDG 1 - LEVELS TWO, THREE, AND FOUR - ENLARGED PLANS
156 E-405 BLDG 1 - LEVEL FIVE - ENLARGED PLAN
157 E-406 BLDG 2 - LEVELS ONE AND TWO - ENLARGED PLANS
158 E-407 BLDG 2 - LEVELS TWO, THREE, AND FOUR - ENLARGED PLANS
159 E-408 BLDG 3 - LEVEL FOUR - ENLARGED PLANS
160 E-409 BLDG 4 & 8 - ENLARGED PLANS
161 E-410 BLDG 9 & 10 - ENLARGED PLANS
162 E-411 BLDG 11 & 12 - ENLARGED PLANS
163 E-412 BLDG 24 - LEVEL ONE - ENLARGED PLANS
164 E-413 BLDG 24 - LEVEL TWO - ENLARGED PLANS
165 E-414 BLDG 29 - ENLARGED PLANS
166 E-415 BLDG 1, 2, & 3 - ENLARGED MECHANICAL POWER PLANS
167 E-416 BLDG 4, 8, 9, 10, 12, & 24 - ENLARGED MECHANICAL
POWER PLANS
168 E-501 ELECTRICAL DETAILS
169 E-502 ELECTRICAL DETAILS
170 E-503 ELECTRICAL DETAILS
171 E-504 ELECTRICAL DETAILS
172 E-601 BUILDING 1 - ELECTRICAL ONE-LINE DIAGRAM
173 E-602 BUILDING 2 - ELECTRICAL ONE-LINE DIAGRAM
174 E-603 BUILDING 3 & 4 - ELECTRICAL ONE-LINE DIAGRAM
175 E-604 BUILDING 8 - ELECTRICAL ONE-LINE DIAGRAM
176 E-605 BUILDING 9, 10, 11, & 12 - ELECTRICAL ONE-LINE
DIAGRAM
177 E-606 BUILDING 24 - ELECTRICAL ONE-LINE DIAGRAM
100% Bid Documents
05-01-20
00 01 15 - 7
LIST OF DRAWINGS
Drawing No. Title
ELECTRICAL CONTINUED
178 E-607 BUILDING 29 - ELECTRICAL ONE-LINE DIAGRAM
179 E-701 BUILDING 1 & 2 - PANEL SCHEDULES
180 E-702 BUILDING 2, 3 & 4- PANEL SCHEDULES
181 E-703 BUILDING 9, 10, 12, & 24 - PANEL SCHEDULES
182 E-704 BUILDING 29 - PANEL SCHEDULES
183 E-705 ELECTRICAL SCHEDULES
TELECOMMUNICATION
184 T-000 TELECOM SYMBOLS & ABBREVIATIONS
185 T-100 BUILDING 1 - TELECOM PLANS
186 T-101 BUILDING 1 - TELECOM PLANS
187 T-102 BUILDING 2 - TELECOM PLANS
188 T-103 BUILDING 2 - TELECOM PLANS
189 T-104 BUILDING 3, 4, 8 & 9 - TELECOM PLANS
190 T-105 BUILDING 10, 11, 12 & 34 - TELECOM PLANS
191 T-106 BUILDING 24 - TELECOM PLANS
192 T-107 BUILDING 24 - TELECOM PLANS
193 T-108 BUILDING 29 - TELECOM PLANS
194 T-200 TELECOM SITE PLANS
195 T-201 TELECOM BACKBONE PATHWAYS - BLDG 2, 3, 10, 24 & 4
196 T-202 TELECOM BACKBONE PATHWAYS - BLDG 8, 9, 11, 12 & 29
197 T-203 RISER DIAGRAM - BUILDING 1 FIBER OPTIC BACKBONE
198 T-204 RISER DIAGRAM - CAMPUS FIBER BACKBONE 'A' & 'B'
199 T-300 BUILDING 1 - TELECOM ENLARGED PLANS
200 T-301 BUILDING 1 - TELECOM ENLARGED PLANS
201 T-302 BUILDING 1 - TELECOM ENLARGED PLANS
202 T-303 BUILDING 2 - TELECOM ENLARGED PLANS
203 T-304 BUILDING 2, 3, 4 & 8 - TELECOM ENLARGED PLANS
204 T-305 BUILDING 9, 10, 11 & 12 - TELECOM ENLARGED PLANS
205 T-306 BUILDING 24 - TELECOM ENLARGED PLANS
206 T-307 BUILDING 29 - TELECOM ENLARGED PLANS
207 T-400 TELECOM DETAILS
208 T-401 TELECOM TR DETAILS
209 T-402 TELECOM MCR DETAILS
100% Bid Documents
05-01-20
00 01 15 - 8
LIST OF DRAWINGS
Drawing No. Title
SECURITY
210 TY000 ABBREVIATIONS, SYMBOLS, LEGENDS & NOTES
211 TY101 BUILDING 1 - REFERENCE PLANS
212 TY102 BUILDING 1 - REFERENCE PLANS
213 TY103 BUILDING 2 - REFERENCE PLAN
214 TY104 BUILDING 2 - REFERENCE PLAN
215 TY105 BUILDINGS 3, 4, 8, & 9 - REFERENCE PLANS
216 TY106 BUILDINGS 10, 11, & 12 - REFERENCE PLANS
217 TY107 BUILDING 24 - REFERENCE PLAN
218 TY108 BUILDING 24 - REFERENCE PLAN
219 TY109 BUILDING 29 - REFERENCE PLAN
220 TY400 BLDG 1 - SECURITY ENLARGED PLANS
221 TY401 BLDG 1 - SECURITY ENLARGED PLANS
222 TY402 BLDG 1 - SECURITY ENLARGED PLANS
223 TY403 BLDG 2 - SECURITY ENLARGED PLANS
224 TY404 BLDG 3, 4, 8 - SECURITY ENLARGED PLANS
225 TY405 BLDG 9, 10, 11, 12 - SECURITY ENLARGED PLANS
226 TY406 BLDG 24 - SECURITY ENLARGED PLANS
227 TY407 BLDG 29 - SECURITY ENLARGED PLANS
228 TY500 SECURITY DETAILS
229 TY600 SECURITY RISERS AND DIAGRAMS
- - - E N D - - -
100% Bid Documents
11-01-21
01 00 00 -1
GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing items, and furnish labor and materials and perform work for the EHRM upgrades to the VA North
Texas Healthcare Medical Center as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
COR.
C. Offices of Spur Design, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by the Contractor, the Contractor shall notify the
COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, excavation and grading, drainage, necessary removal of existing construction and certain other items.
100% Bid Documents
11-01-21
01 00 00 -2
GENERAL REQUIREMENTS
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
100% Bid Documents
11-01-21
01 00 00 -3
GENERAL REQUIREMENTS
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
100% Bid Documents
11-01-21
01 00 00 -4
GENERAL REQUIREMENTS
2. A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility Manager.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR .
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not
100% Bid Documents
11-01-21
01 00 00 -5
GENERAL REQUIREMENTS
permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved:
H. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR and Contractor, as follows:
Phase I:
100% Bid Documents
11-01-21
01 00 00 -6
GENERAL REQUIREMENTS
Phase II:
I. Building(s) No.(s) 1, 2, 3, 4, 8, 9, 10, 11, 12, 24, 29, and 34 will be occupied during performance of work; but immediate areas of alterations will be vacated.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. Remove the fence when directed by COR.
K. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs
100% Bid Documents
11-01-21
01 00 00 -7
GENERAL REQUIREMENTS
or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR
ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
100% Bid Documents
11-01-21
01 00 00 -8
GENERAL REQUIREMENTS
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
N. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
O. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, 100% Bid Documents
11-01-21
01 00 00 -9
GENERAL REQUIREMENTS
shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.
Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately
100% Bid Documents
11-01-21
01 00 00 -10
GENERAL REQUIREMENTS
protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those
100% Bid Documents
11-01-21
01 00 00 -11
GENERAL REQUIREMENTS
facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES) permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements.
Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the
Contractor's method of operations and operations planning and the
Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair;
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
5. Providing adequately maintained sanitary facilities.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, 100% Bid Documents
11-01-21
01 00 00 -12
GENERAL REQUIREMENTS
do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 PHYSICAL DATA – SOIL CONDITIONS
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by (H2B to provide information).
(FAR 52.236-4)
B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically on drawings.
C. A copy of the soil report will be made available for inspection by bidders upon request to the Engineering Officer at the VA Medical
Center, and shall be considered part of the contract documents.
100% Bid Documents
11-01-21
01 00 00 -13
GENERAL REQUIREMENTS
D. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of
Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.
1.12 PROFESSIONAL SURVEYING SERVICES
A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.
The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.
If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark utility lines, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for utility ductbanks are in accordance with lines and elevations shown on contract drawings.
100% Bid Documents
11-01-21
01 00 00 -14
GENERAL REQUIREMENTS
C. Following completion of general excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as utilities and other major controlling features) is placed.
D. During progress of work, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines and elevations of utility ductbanks and of all outside distribution systems.
2. Lines of elevations of all swales and interment areas.
3. Lines and elevations of roads, streets and parking lots.
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
100% Bid Documents
11-01-21
01 00 00 -15
GENERAL REQUIREMENTS
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction at least 30 days before the planned pre-warranty conference, submit two sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the
Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment.