Attachment 2 - USCGC KENNEBEC DD FY26 - SPECIFICATION.doc

DOC document 2 MB Posted

Attached to
USCGC KENNEBEC DRYDOCK FY 26
Solicitation number
70Z08525QIBCT0024
Issued by

About this file

This document is a detailed specification for drydocking and repairing the USCGC KENNEBEC (WLIC 802), a 160' Inland Construction Tender, in fiscal year 2026. The comprehensive specification outlines 68 distinct work items covering extensive vessel maintenance and preservation tasks, including underwater hull inspections, coating renewal, piping replacements, tank cleaning, mechanical system overhauls, and structural repairs. Key work includes renewing propulsion shaft seals, preserving underwater and freeboard hull surfaces, inspecting and repairing tanks, testing mechanical systems, and performing ultrasonic thickness measurements on various vessel components.

The specification is associated with Solicitation Number 70Z08525QIBCT0024 issued by the US Coast Guard, with a planned award as a Fixed Firm Price Definitive Contract. Contractors must be certified by the Joint Certification Program to access certain restricted documents, and must request drawings no later than 8 AM PST on 10 November 2025. Site visit coordination is required through specific Coast Guard personnel, and the vessel is homeported in Coast Guard District 5 in Virginia. The drydocking work is intended to comprehensively assess and restore the vessel's structural integrity, mechanical systems, and protective coatings to ensure continued operational readiness.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC KENNEBEC (WLIC 802)

SPECIFICATION FOR DRYDOCK REPAIRS

FY2026

Developed By: William A Baker2 (REV-0, 23 June 2025)

TABLE OF CONTENTS

iv

Revisions Record v

Consolidated List of References xi

Consolidated List of Government-furnished Property xii

Consolidated List of Critical Inspection Items xiv

Principal Characteristics

General Requirements

WORK ITEM 1: Fire Prevention Requirements Dry Dock

WORK ITEM 2: Hull Plating, Side Scan, Ultrasonic Testing

WORK ITEM 3: Hull Plating, U/W Body, Inspect

WORK ITEM 4: Hull Plating, U/W Body, Ultrasonic Testing

WORK ITEM 5: Hull Plating, Freeboard, Ultrasonic Testing

WORK ITEM 6: U/W Body, Preserve, 100 percent

WORK ITEM 7: Hull Plating Freeboard, Preserve, 100 Percent

WORK ITEM 8: Appendages, U/W, Leak Test

WORK ITEM 9: Propulsion Shaft Rope Guards, Inspect

WORK ITEM 10: Appendages, U/W, Internal, Preserve

WORK ITEM 11: Tanks, MP Fuel Stowage and Overflow, Clean and Inspect

WORK ITEM 12: Voids, Non-Accessible, Leak Test

WORK ITEM 13: Voids, Non-Accessible, Internal Surfaces, Preserve

WORK ITEM 14: Tanks, MP Fuel Service, Clean and Inspect

WORK ITEM 15: Tanks, Potable Water, Clean and Inspect

WORK ITEM 16: Tanks, Ballast, Clean and Inspect

WORK ITEM 17: Propulsion Shaft Seals (Inflatable), Overhaul and Inflatable Renewal

WORK ITEM 18: Propulsion Shafting; Remove, Inspect, and Reinstall

WORK ITEM 19: Propulsion Shaft Coating, Renew

WORK ITEM 20: Propulsion Shafting, Straighten

WORK ITEM 21: Mechanical Shaft Seal Assemblies, Renew

WORK ITEM 22: Propulsion Shafting, Optical or Laser Alignment Check

WORK ITEM 23: Propulsion Shaft Bearings, External, Check Clearances

WORK ITEM 24: Propulsion Shaft Bearings, External, Renew

WORK ITEM 25: Propulsion Stern Tube Bearings, Renew

WORK ITEM 26: Stern Tube Interior Surfaces, Preserve, 100 Percent

WORK ITEM 27: Propeller s, Clean And Inspect

WORK ITEM 28: Propeller s, Remove, Inspect, and Reinstall

WORK ITEM 29: Propeller, Minor Repairs and Reconditioning, Perform

WORK ITEM 30: Keel Coolers, Clean, Inspect and Hydro

WORK ITEM 31: Fathometer Transducer, Renew

WORK ITEM 32: Sea Strainers, Duplex, All Sizes, Overhaul

WORK ITEM 33: Rudder Assembly, Remove, Inspect And Reinstall

WORK ITEM 34: Rudders, Preserve, 100 Percent

WORK ITEM 35: Rudder Stock Bearings Clearances, Check

WORK ITEM 36: Rudder Stock Housing, Lower, Renew

WORK ITEM 37: Rudder Stock Housing, Upper, Renew

WORK ITEM 38: Rudder Stock, Rebuild

WORK ITEM 39: Hull Fittings (Mooring and Towing), Inspect and Test

WORK ITEM 40: Spuds, Overhaul

WORK ITEM 41: Spud Wells, Preserve

WORK ITEM 42: Spud Wells, Inspect

WORK ITEM 43: Sewage Holding Tanks, Clean and Inspect

WORK ITEM 44: Tanks (Sewage Holding), Preserve, Partial

WORK ITEM 45: Tanks, Ballast, Preserve, Partial

WORK ITEM 46: Tanks, Dirty Oil and Waste, Preserve, Partial, WORK ITEM 47: Accessible Void(s), Preserve, Partial, WORK ITEM 48: Tanks, MP Fuel Service, Preserve, Partial

WORK ITEM 49: Tanks, MP Fuel Storage and Overflow, Preserve, Partial

WORK ITEM 50: Tanks, Potable Water, Preserve, Partial, WORK ITEM 51: Decks - Exterior, Preserve, Non-Skid Broadcast Grit System

WORK ITEM 52: Decks – Exterior (Buoy or Construction Deck), Preserve 100%

WORK ITEM 53: Cathodic Protection, Zinc Anodes, Renew, WORK ITEM 54: Drydock

WORK ITEM 55: Temporary Services, Provide - Tender

WORK ITEM 56: Temporary Messing and Berthing, Provide

WORK ITEM 57: Sea Trial Performance, Support, Provide

WORK ITEM 58: Bilges, Inspect

WORK ITEM 59: Bilges, Preserve

WORK ITEM 60: Boat Davit Winch, Shrink Wrap

WORK ITEM 61: Buoy and Cargo Handling Crane, Shrink Wrap

WORK ITEM 62: Compartment Insulation, General, Renew

WORK ITEM 63: Piping Insulation, Renew

WORK ITEM 64: System Piping, Renew

WORK ITEM 65: Forward PW Tank Repair

WORK ITEM 66: Deck Covering (Interior Wet/Dry), Renew

WORK ITEM 67: Gooseneck Ventilation, Renew

WORK ITEM 68: Deck Drain, Repair

WORK ITEM 69: Stern Bulwark Repair

Revisions Record This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE
REV#
WORK ITEM#
CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

Consolidated List of References The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Bill of Material 160B WLIC 58, Rev -. Pollution Abatement and Drainage System Coast Guard Drawing 160-WLIC 0101-7-1 Rev A DIAGRAMMATIC ARRGT PIPING SYSTEM Coast Guard Drawing 160 WLIC 0103-2, Rev A, Booklet of General Plans Coast Guard Drawing 160 WLIC 0103-2, Rev A, Sheet 1, Booklet of General Plans Coast Guard Drawing 160 WLIC 1101-001, Rev C, Shell Pltg Expansion & Framing Coast Guard Drawing 160 WLIC 1101-1, Rev C, Shell Pltg Expansion & Framing Coast Guard Drawing 160 WLIC 1201-001, Rev D, Hull Fittings and Chain Stoppers Coast Guard Drawing 160 WLIC 1205-001, Rev F, Spudwells and Spuds Coast Guard Drawing 160 WLIC 244-003, Rev B, GA OF 6" TYPE FSE MANEGUARD SEAL Coast Guard Drawing 160 WLIC 4105-007, Rev -, Arrangement Of Engine Cooling Piping (KENNEBEC)

COAST GUARD DRAWING 160-WLIC-101-9 DIAG FRESH WATER SYS

COAST GUARD DRAWING 160B-WLIC-4801-1 POLLUTION ABATEMENT AND DRAINAGE SYSTEM

Coast Guard Drawing 160-WLIC-3800-5 ARRG Heating and Chilling sys

Coast Guard Drawing 160-WLIC-4804-1 diagram fresh water system

Coast Guard Drawing 160 WLIC 4301-001, Rev G, Shafting & Prop Arrgt & Dets (Applicable for both A and B class) Coast Guard Drawing 160 WLIC 4301-003, Rev A, Shafting Arrangement and Details Coast Guard Drawing 160 WLIC 4301-003, Rev C, Shafting Arrangement and Details Coast Guard Drawing 160B WLIC 0500-001, Rev -, Lines Corrected Coast Guard Drawing 160B WLIC 0700-001, Rev B, Docking Plan (KENNEBEC) Coast Guard Drawing 160B WLIC 0700-003, Rev B, Docking Plan (KENNEBEC) Coast Guard Drawing 160B WLIC 103-003, Rev-, Booklet of General Plans Coast Guard Drawing 160B WLIC 103-003, Rev-, Booklet of General Plans Coast Guard Drawing 160B WLIC 103-3, Rev-, Booklet of General Plans Coast Guard Drawing 160B WLIC 1101-001, Rev C, Shell Plating Expansion and Longitudinal Framing Coast Guard Drawing 160B WLIC 1101-002, Rev D, Forepeak & Afterpeak Framing Coast Guard Drawing 160B WLIC 1103-002, Rev A, Vertical Keel, Skeg, and Bottom Girders Coast Guard Drawing 160B WLIC 1105-001, Rev B, Transverse Watertight and Oil Tight Bulkheads Coast Guard Drawing 160B WLIC 1105-002, Rev C, Longitudinal Watertight and Oil Tight Bulkheads and Bottom Tanks Coast Guard Drawing 160B WLIC 1108-002, Rev B, Shaft Struts and Stern Tubes Coast Guard Drawing 160B WLIC 1108-002, Rev B, Shaft, Struts, And Stern Tubes Coast Guard Drawing 160B WLIC 1205-1, Rev F, Spudwells and Spuds Coast Guard Drawing 160B WLIC 1205-3, Rev B, Zinc Hull Protectors Coast Guard Drawing 160B WLIC 160B 0103-3, Rev- Booklet of General Plans Coast Guard Drawing 160B WLIC 2200-001 (Including BM-32), Rev A, Steering Machinery Arrangement Rudder Stock & Fitting Coast Guard Drawing 160B WLIC 2200-001, Rev A, Steering Machinery Arrangement Rudder Stock & Fitting Coast Guard Drawing 160B WLIC 2200-001, Rev A, Steering Machinery Arrangement, Rudder Stock and Fittings Coast Guard Drawing 160B WLIC 2901-004, Rev -, Curves of Form Coast Guard Drawing 160B WLIC 4105-006, Rev -, Engine Cooling System (KENNEBEC) (802) Coast Guard Drawing 160B WLIC 4808-001, Rev F, Pollution Abatement and Drainage System Coast Guard Drawing 160B WLIC 700-001, Rev B, Docking Plan (KENNEBEC) Coast Guard Drawing 160B-WLIC 103-003, Rev -, Booklet of General Plans Coast Guard Drawing 160B-WLIC 103-02, Rev A, Booklet of General Plans Coast Guard Drawing 160B-WLIC 1101-1, Rev E, Shell Plating Expansion & Framing Coast Guard Drawing 160B-WLIC 1105-1, Rev B, Transverse WT & OT Bhds Coast Guard Drawing 160B-WLIC 1106-01, Rev D, Main Deck Plating Coast Guard Drawing 160-WLIC 244-3, Rev B, GA OF 6" Type FSE Maneguard Seal Coast Guard Drawing 160-WLIC 4400-3, Rev A, Propeller (Supersedes 160-WLIC-4400-001, 4400-002, & 160B-WLIC-4400-001) Coast Guard Drawing 160-WLIC 6700-3, Rev D, Booklet of General Elex Arrg, Wrg & Details Coast Guard Fleet Drawing FL 2602-10, Rev R, Spud Arrangements and Details Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters

TBD

COAST GUARD PUBLICATIONS

«REF_A»

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual Coast Guard Technical Publication (TP) 3494, Aug 2013, Technical Manual for Type F.S.E. Seal Coast Guard Technical Publication (TP) 4914, 12-NOV-18, FSE Shaft Seal - 2nd Generation Fire Prevention and Response Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Preserve Ship Structures Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2022, Install New Deck Covering Systems Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2020, Temporary Services Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2020, Temporary Hull Accesses Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary Hull Accesses Surface Forces Logistics Center Technical Specification 245-2 (SFLC TS 245-2), 2014, CPP Propellers and Blades

OTHER REFERENCES

AAA/CAA - http://newsroom.aaa.com/diamond-ratings/diamond-rating-definitions/ American Bureau of Shipping (ABS) 2, Rule Requirements for Survey After Construction, 2014, Part 7, Appendix Section 10, Guide for Bronze and Stainless Steel Propeller Castings American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2019, Disinfection of Water-Storage Facilities American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System Components - Health Effects American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System Components - Health Effects American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2020, Recommended Practice for Personal Qualification and Certification in Nondestructive Testing ANSI/AWWA reference if work does not deal with potable water piping.

ASTM F683, if piping insulation renewal is not applicable.

ASTM F992, if valve label is not applicable.

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D1709, 2008, Standard Test Methods for Impact Resistance of Plastic Film by the Free-Falling Dart Method ASTM International (ASTM) D1922, 2008, Standard Test Method for Propagation Tear Resistance of Plastic Film and Thin Sheeting by the Pendulum Method ASTM International (ASTM) D3951, Reapproved 2010, Standard Practice for Commercial Packaging ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An) ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component Adhesives (AN) ASTM International (ASTM) D882, 2009, Standard Test Method for Tensile Properties of Thin Plastic Sheeting ASTM International (ASTM) F683, 2014, Standard Practice for Selection and Application of Thermal Insulation for Piping and Machinery ASTM International (ASTM) F992, 2017, Standard Specification for Valve Label Plates Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Anti-seize, Zinc Dust-Petrolatum Developer: Delete the following references:

Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections Fernstrum Gridcooler Installation and Maintenance Manual, 2013, Form 175 For Caterpillar applications, use CAT Extended Life Pre-Mix coolant.)

FORBES (formerly MOBIL) Travel Guide - http://www.forbestravelguide.com/ Hotel-Motel National Master List, http://www.usfa.fema.gov/applications/hotel/ International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing Tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50 m, Inclusive International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2018, Pipe Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation MIL PRF-16173, Sep 2006, Corrosion Preventive Compound, Solvent Cutback, Cold-Application MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418) MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning MIL-PRF-16173, 2006, Corrosive Preventive Compound, Solvent Cutback, Cold Application MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application MIL-PRF-16173, Sep 2006, Corrosion Preventive Compound, Solvent Cutback, Cold-Application MIL-PRF-24647, Jan 2018, Paint System, Anticorrosive and Antifouling, Ship Hull MIL-S-45180, 1998, Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant MIL-STD-167-1, Nov 2005, Mechanical Vibrations of Shipboard Equipment (Type I - Environmental and Type II - Internally Excited) MIL-STD-2191, Nov 1992, Nov 1992, Repair Welding, Weld Cladding, Straightening, and Cold Rolling of Main Propulsion Shafting MIL-STD-2191, Nov 1992, Repair Welding, Weld Cladding, Straightening, and Cold Rolling of Main Propulsion Shafting MIL-STD-2199A (SH), Jan 2020, Covering for Waterborne Main Propulsion Shafting on U.S. Naval Surface Ships and Submarines Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA-PRO-160, Nov 2011, Chapter 16, Cofferdams NAVSEA Drawing 804-5773931, Rev-A, Insulation for Compartments, Acoustic and Thermal – Installation Details NAVSEA Drawing 804-5959214, Rev-, Piping Insulation - Installation Details NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure Public Law 101-391, 1990, Hotel and Motel Fire Safety Act Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C-6183B, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183B, 2019, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2020 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power-Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2013, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2013, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2013, Power Tool Cleaning The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 1 No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by Waterjetting Prior to Recoating The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2007, Surface Preparation and Cleaning of Steel & Other Hard Materials by High and Ultrahigh Pressure Water Jetting The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning The Society for Protective Coatings (SSPC)/NACE International (NACE), 2007, Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, Near-White Blast Cleaning The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2004, Near-White Blast Cleaning The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning Consolidated List of Government-furnished Property The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK ITEM
MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST

($/Unit)

17
N
160’WLIC Major Overhaul Kit
H78011-01-9
2 ea.
8,000.00
18
Y
**Propeller shaft
NSN:
1 ea.
21
Y
Wartsila Type FSE Seal (6� Fully Split). Shaft Seal Assembly PN: H78011-01
NSN: 2995-01-604-5903
2 ea.
14,595.86
24
N
Aft Strut Bearing
NSN: 3120-01-051-2510
1 ea.
683.00
25
N
Stern Tube Bearing
NSN: 3120-01-046-8511
1 ea.
$1865
27
Y
Propeller (right hand)
NSN: 2010-01-037-7295
1 ea.
$
27
Y
Propeller (left hand)
NSN: 2010-01-037-7597
1 ea.
$
27
N
Propeller nut wrench
NSN:
1 ea.
$
28
Y
Propeller (right hand)
NSN: 2010-01-037-7295
1 ea.
$
28
Y
Propeller (left hand)
NSN: 2010-01-037-7597
1 ea.
$
28
N
Propeller nut wrench
NSN:
1 ea.
$
30
N
Coolant (QTY in gallons)
NSN: PN:
31
N
***Fathometer Transducer, Shallow Water, 50-200 kHz (Airmar Technology SS505)
NSN: 5845-01-470-2500
1 ea.
343.63
33
Y
**Rudder Blade
NSN: 3120-01-560-3314
1 ea.
36,531
33
N
Bearing Sleeve
NSN: 3120-01-560-3316
1 ea.
2,693.45
54
Y
*Transducer Cover Plate
N/A
2 ea.
50.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter

Consolidated List of Critical Inspection Items The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item
Title
2
Hull Plating, Side Scan, Ultrasonic Testing
4
Hull Plating, U/W Body, Ultrasonic Testing
6
U/W Body, Preserve, 100 percent
8
Appendages, U/W, Leak Test
11
Tanks, MP Fuel Stowage and Overflow, Clean and Inspect
12
Voids, Non-Accessible, Leak Test
14
Tanks, MP Fuel Service, Clean and Inspect
16
Tanks, Ballast, Clean and Inspect
17
Propulsion Shaft Seals (Inflatable), Overhaul and Inflatable Renewal
18
Propulsion Shafting; Remove, Inspect, and Reinstall
23
Propulsion Shaft Bearings, External, Check Clearances
24
Propulsion Shaft Bearings, External, Renew
27
Propeller s, Clean And Inspect
32
Sea Strainers, Duplex, All Sizes, Overhaul
33
Rudder Assembly, Remove, Inspect And Reinstall
47
Accessible Void(s), Preserve, Partial,
54
Drydock
59
Bilges, Preserve
62
Compartment Insulation, General, Renew
64
System Piping, Renew
66
Deck Covering (Interior Wet/Dry), Renew
67
Gooseneck Ventilation, Renew

Principal Characteristics 160' WLIC (B-CLASS), Inland Construction Tender

Physical

Length overall
160' 10"
Depth (main deck at side to baseline)
10' 0"
Maximum beam
30' 0"
Height of highest fixed projection
40’ 0” (above keel)
Height of highest projection with antenna mast extended
59’ 0” (above keel)
Frame spacing
1' 0"
Full load draft
4' 7-1/2” LCF Draft
Full load displacement
474.73 Long Tons (Fresh water)
Shore tie voltage requirements
N/A

HULL

Hull material
Steel

Machinery

Number of propellers
2
Number of blades per propeller
4
Diameter of propeller
48"
Pitch
44" fixed
RPM
475
Shaft diameter
N/A

Tank Capacities

Fuel tanks

Fresh water tanks

Lube oil

00000_0824_FLT

REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121) General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

Coast Guard Drawings None Coast Guard Publications Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures Other References Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.

3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.

3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan as requested in the Fire Protection and Response work item, with the Contractor’s bid.

note NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents. Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:

· Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.

· Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken. Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

· ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.

· ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm. For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet; for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:

· SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

· SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B-Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY-130.

3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.

3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B-Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.

NOTE

NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding Weldox 900 are considered the same as those for welding HY-130.

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

· Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

· National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

· Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).

3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.

3.7.1 SFLC Standard Specification 5550: Replace paragraph 3.11.3 to state, “Material supporting imminent work shall be brought on the cutter and stored where the work is being performed. Material that appreciably contributes to fire load shall be removed at the end of each work shift when personnel are not present. Trash, debris, and packaging materials shall be promptly removed from the vessel at the end of each work shift and not allowed to accumulate.” Advance the paragraph numbering of the Fire Prevention and Safety Inspection form to 3.11.4.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Name of QP-1/AMPP Inspector
Signature
Cert. #
Date / Time
NAME of CG Representative
Signature
Unit
DATE/TIME

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Vessel Name
Hull #
Work Item #
Work Item Title

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE & TIME
ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION (Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL. HUMID-ITY
DEW PT.
SURFACE
AMBIENT
ΔT

| DP - Surface |

Name of QP-1/AMPP Inspector
Signature
Cert. #
Date / Time
NAME of CG Representative
Signature
Unit
DATE/TIME

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (Frame References)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean
SSPC-SP-10/AMPP No. 2
(
SSPC-SP WJ-2/AMPP WJ-2
(
SSPC-SP-3
(
SSPC-SP-11
(
SSPC-SP-11 (inaccessible area)
(
Brush-blasting (non-metallic substrate)
(

Abrasive Manufacturer:

Abrasive Sieve Size:

Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings:

Name of QP-1/AMPP Inspector
Signature
Cert. #
Date / Time
NAME of CG Representative
Signature
Unit
DATE/TIME

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean
SSPC-SP-10/AMPP No. 2
(
SSPC-SP WJ-2/AMPP WJ-2
(
SSPC-SP-3
(
SSPC-SP-11
(
SSPC-SP-11 (inaccessible area)
(
Brush-blasting (non-metallic substrate)
(

Abrasive Manufacturer:

Abrasive Sieve Size:

Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):

Mean Reading (mils)

Name of QP-1/AMPP Inspector
Signature
Cert. #
Date / Time
NAME of CG Representative
Signature
Unit
DATE/TIME

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15.

Date
Test Locations
Conductivity (Microsiemens/CM)
Name of QP-1/AMPP Inspector
Signature
Cert. #
Date / Time
NAME of CG Representative
Signature
Unit
DATE/TIME

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

Vessel Name
Hull #
Work Item #
Work Item Title
Coating Mfg
Product Name
Batch #
Induction Time
Coating System Sequence (Primer/Touchup/3rd Coat, etc.)

Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2.

SPOT
1
2
3
4
5
AVERAGE VALUE

*BASE METAL READING (BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Application Method (Airless, Conventional Spray, Rolled)
Average DFT
Name of QP-1/AMPP Inspector
Signature
Cert. #
Date / Time
NAME of CG Representative
Signature
Unit
DATE/TIME

4.2 Tank and Void Assessment form.

55500_ACC_0323_IBCT

WORK ITEM 1: Fire Prevention Requirements Dry Dock

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to minimize shipboard fire risk and to clarify the Contractors’ role in fire prevention and response.

Note

This work item is not separately priced. Factor fire prevention and response costs into bid of affected work items.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings None

Coast Guard Publications Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response Other References None

3. REQUIREMENTS

3.1 Fire Plan. The Contractor must develop and implement a written fire plan in accordance SFLC Std Spec 5550. The Contractors Fire Plan must address Fire Protection and Response specifics as required in this Work Item.

3.1.1 The availability’s specific Fire Plan must always address the following:

· material condition and fire protection boundary obstruction mitigations

· inoperable fittings log

· fire alarms

· firefighting equipment disposition

3.1.2 The Fire Plan must also address the following:

· fire protection system status

· communication links

· temporary services

· power disconnects

· fire prevention and safety inspections

3.2 Fire Prevention Responsible Party. The Contractor must appoint a Fire Prevention Responsible Party (FPRP) who acts as the Contractor’s Responsible Person for fire prevention concerns during the entire availability.

3.3 Fire Prevention and Response Conference. The Contractor must participate in the Fire Prevention and Response Conference as required in Std Spec 5550, paragraph 3.12. The participants must address the contents of SFLC Std Spec 5550, paragraph 3.12.1, as applicable.

3.4 Fire Responsibility Familiarization Tour and Initial Inspection. The Contractor must participate in the Fire Responsibility Familiarization Tour and Initial Inspection as required in Std Spec 5550, paragraphs 3.12.2 through 3.12.4.

3.5 Material Condition and Fire Protection Boundary Obstruction Mitigation Requirements. The Contractor must conform to all material condition and fire protection boundary obstruction mitigation requirements detailed in SFLC Std Spec 5550, paragraph 3.2.

3.6 Inoperable Fittings Log Requirements. The Contractor must conform to all inoperable fittings log requirements detailed in SFLC Std Spec 5550, paragraph 3.3.

3.6.1 The Contractor must maintain an Inoperable Fittings log. The logs must contain the same information as a Damage Control Closure Log found in Appendix A of SFLC Std Spec 5550. The log must remain at the access point of the vessel available for inspection or use by authorized personnel, i.e., casualty response. Deliver all logs to the CG when requested and at the end of the availability.

3.7 Fire Prevention Service Particulars. The Contractor must conform to the below listed fire prevention service requirements, in accordance with SFLC…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .