Attachment 2 - IP_CSP V6_CUI.docx

DOCX document 67 KB Posted

Attached to
RFP for Integration & Production (I&P) Follow-On
Solicitation number
N0042124R0038
Issued by

About this file

This document is a Contract Surveillance Plan (CSP) for a Cost-Plus-Fixed-Fee (CPFF) Indefinite Delivery Indefinite Quantity (IDIQ) contract that provides system integration, production and fabrication, in-service engineering, training, logistics engineering, testing, repair, laboratory and test bed management, quality assurance and quality management, frequency spectrum authorization, and technical management support services for the Combat Integration & Identification Systems (CI&IDS) Division at the Naval Air Warfare Center Aircraft Division (NAWCAD) Webster Outlying Field (WOLF). The CSP outlines the roles and responsibilities of the Contracting Officer (KO), Contracting Officer's Representative (COR), Alternate COR (ACOR), and Government Project Leads (GPLs) in administering and overseeing the contract, including methods of quality assurance surveillance such as Contractor Performance Assessment Reporting System (CPARS) evaluations. The contract has a five-year ordering period with an option to extend six months.

View the file

Other files

File Type Posted
N0042124R0038-0003 CC.docx DOCX document
N0042124R0038-0003.docx DOCX document
Questions and Answers to Amendment 0001.pdf PDF
N0042124R0038-0002 CC.docx DOCX document
N0042124R0038-0002.docx DOCX document
Attachment 4 - OCI List.docx DOCX document
Attachment P1 - Cost Summary Spreadsheet.xlsx XLSX spreadsheet
N0042124R0038-0001.docx DOCX document
N0042124R0038-0001 CC.docx DOCX document
Questions and Answers to RFP N0042124R0038.pdf PDF
Attachment 3 - Locator Form.doc DOC document
Attachment 6 - WD 2015-4279-Rev 25.pdf PDF
N0042124R0038.pdf PDF
Attachment 4 - IP_OCI List.docx DOCX document
Exhibit A - CDRLs.docx DOCX document
Attachment P2 - Annual Fully Burdened Rates.xlsx XLSX spreadsheet
Attachment P3 - SBPCD.docx DOCX document
Attachment 1 -DD FORM 254 JUNE 2025.pdf PDF
Attachment P1 - Cost Summary Spreadsheet.xlsx XLSX spreadsheet
Attachment 5 - Data Transmittal Form.docx DOCX document
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N00421-18-R-0018 Enclosure (3) CUI Enclosure (3)

Contract Surveillance Plan for Combat Integration & Identification Systems Integration and Production Support Services

1. Purpose

This Contract Surveillance Plan (CSP) is a Government developed and applied document used to ensure systematic Quality Assurance (QA) methods are used in the administration and surveillance of tasking under the Contract. The intent is to ensure the Contractor performs In Accordance With (IAW) the Statement of Work (SOW) and the Government receives the quality of services called for in the Single Award (SA) Indefinite Delivery Indefinite Quantity (IDIQ) contract.

The Naval Air Warfare Center Aircraft Division (NAWCAD) Webster Outlying Field (WOLF) Combat Integration & Identification Systems (CI&IDS) Division operating under the organic Lead Systems Integrator® (oLSI®) model, has requirements to provide system integration, production and fabrication, in-service engineering, training, logistics engineering, testing, repair, laboratory and test bed management, quality assurance and quality management, frequency spectrum authorization, and technical management for CI&IDS Division systems and equipment.

This Contract will have Cost-Plus-Fixed-Fee (CPFF) term Contract Line Item Numbers (CLINs) for labor and corresponding cost reimbursable CLINs for Other Direct Costs (ODCs). The Contract will have a five-year ordering period with an option to extend six months in accordance with FAR Clause 52.217-8, Option to Extend Services. A properly executed CSP will assist the Government in achieving the objectives of this procurement.

2. Authority

Authority for issuance of this CSP is provided under Contract Section E – Inspection and Acceptance, which provides for inspections and acceptance of the services, products, and documentation called for in the Contract that will be executed by the Contracting Officer (KO) or a duly authorized representative.

3. Scope

To fully understand the roles and responsibilities of the parties, it is important to first define the distinction in terminology between Quality Control Plan (QCP) and the CSP. The Contractor, and not the Government, is responsible for the QCP, which defines the management and quality control actions necessary to meet the quality standards set forth in the Contract.

The CSP provides Government surveillance oversight of the Contractor’s efforts to assure they are timely, effective, and delivering the results specified in the Contract.

4. Government Resources

The following definitions for Government resources are applicable to this plan:

KO: A person duly appointed with the authority to enter into a contract (Procuring Contracting Officer (PCO)), or a person with the authority to administer contracts (Administrative Contracting Officer (ACO)) and make related determinations and findings on behalf of the Government. The PCO for this Contract is Christopher Kyle Pennini. The ACO will be designated in the resulting Contract. KOs are designated via a written warrant that sets forth limitations of authority.

Contracting Officer’s Representative (COR): An individual appointed in writing by the PCO to act as their authorized representative to assist in administering the Contract. The COR will be appointed in the resulting Contract. The limitations of authority are contained in the letter of appointment.

Alternate Contracting Officer’s Representative (ACOR): An individual appointed in writing by the PCO to act as their authorized representative, in the absence of the COR, to assist in administering the Contract. The ACOR will be appointed in the resulting Contract. The limitations of authority are contained in a written letter of appointment

Government Project Lead (GPL): The COR designates individual GPLs to assist in administering specific efforts under the Contract.

5. Responsibilities

The following Government resources will have responsibility for the implementation of this CSP:

KO: The KO (PCO or ACO) ensures performance of all necessary actions for effective contracting, ensures compliance with the terms of the Contract, and safeguards the interests of the United States in the contractual relationship. The KO assures that the Contractor receives impartial, fair, and equitable treatment under the Contract. The KO is ultimately responsible for the final determination of the adequacy of the Contractor’s performance.

COR: The COR is responsible for technical administration of the Contract and assures proper Government surveillance of the Contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any changes on the Government’s behalf. Any changes that the Contractor deems may affect the Contract price, terms, or conditions shall be referred to the KO for action.

ACOR: The ACOR assists the COR for technical administration of the Contract and assures proper Government surveillance of the Contractor’s performance. The ACOR is not empowered to make any contractual commitments or to authorize any changes on the Government’s behalf. Any changes that the Contractor deems may affect the Contract price, terms, or conditions shall be referred to the KO for action.

GPL: The GPL is responsible for assisting in administering specific efforts under the Contract. A GPL cannot, in any manner, alter the scope of the Contract, make commitments, or authorize any changes on the Government’s behalf.

6.Methods of QA Surveillance
a.Contractor Performance Assessment Reporting System (CPARS): The marketplace for integration and production of CI&IDS is competitive. As such, the successful Offeror has a vested interest in the Government generated CPARS under this Contract. Additionally, an evaluation using the CPARS format will be performed at the end of each ordering year. This evaluation will be one determinant in the award of future contracts/TOs or option exercises. The Government will address the quality of product or service, schedule, cost control, business relations, management, utilization of Small Business (SB), and other important areas for this procurement. Some of the monitoring methods to be used will be Government observation, review of reports, customer feedback, and review of Contract Data Requirements Lists (CDRLs). As this information may affect future source selections throughout the Department of Defense (DoD), as well as the continuation of this tasking, the annual Government assessment will be used appropriately as an additional performance oversight and communication tool within the policies of this CSP.

b. CSP: This document will be used by the COR, ACOR, and GPLs in the technical administration of this Contract. In addition to the below instructions, the form to be used for documentation of QA surveillance is the Surveillance Activity Checklist (SAC).

7. Surveillance

Enclosure (2) sets forth the performance standards, incentives, and surveillance methods for the Contractor, COR, ACOR, and GPLs while Enclosures (1) and (3) provide the checklist and means for the COR to document the results of the surveillance and will be provided to the KO.

8. Documentation

In addition to providing reports to the KO, the COR will maintain a complete QA file. The file will contain copies of all reports, evaluations, recommendations, and any actions related to the Government’s performance of the QA function, including the originals of the QA Checklists. All such records will be maintained for the life of the Contract. The COR shall forward these records to the KO at termination or completion of the Contract.

9. Enclosures

Enclosure (1): Surveillance Activity Checklist (SAC) Enclosure (2): Quarterly Evaluation by Contract Data Requirements List (CDRL) Enclosure (3): Annual Surveillance Summary

CUI

CUI

CUIControlled by: Department of the Navy Controlled by: NAWCAD WOLF CUI Category: SSEL Distribution/Dissemination Control: DL Only (See PMT PID for List) POC: Christopher Kyle Pennini, christopher.k.pennini.civ@us.navy.mil, (240) 298-3470

Source Selection Sensitive Reference FAR 2.101 and 3.104

CUI 3

Source Selection Sensitive Reference FAR 2.101 and 3.104

ENCLOSURE (1): SURVEILLANCE ACTIVITY CHECKLIST (SAC)

Quarterly Surveillance:

The Contracting Officer’s Representative (COR) will perform a quarterly assessment of quality, schedule, cost control, business relations, management, utilization of Small Business (SB), and other areas as applicable utilizing the Contractor Performance Assessment Reporting System (CPARS) evaluation rating definitions listed in Enclosure (3).

QUARTERLY EVALUATION BY SOW PARAGRAPH

Description
Surveillance Method/Measure
Dates
Quality Assessment
Schedule Assessment
Cost Control Assessment
Business Relations Assessment
Management Assessment
Utilization of SB Assessment
Other Areas Assessment
Provide system integration support IAW paragraph 3.3.1
100% Inspection by COR, ACOR, and/or GPLs.
Provide production and fabrication support IAW SOW paragraph 3.3.2
100% Inspection by COR, ACOR, and/or GPLs.
Provide in-service engineering support IAW SOW paragraph 3.3.3
100% Inspection by COR, ACOR, and/or GPLs.
Provide training and training materials IAW SOW paragraph 3.3.4
100% Inspection by COR, ACOR, and/or GPLs.
Provide logistics engineering support IAW SOW paragraph 3.3.5
100% Inspection by COR, ACOR, and/or GPLs.
Provide test planning, management, execution, and reporting support IAW SOW paragraph 3.3.6
100% Inspection by COR, ACOR, and/or GPLs.
Provide repair and validation support IAW SOW paragraph 3.3.7
100% Inspection by COR, ACOR, and/or GPLs.
Provide laboratory and test bed management support IAW SOW paragraph 3.3.8
100% Inspection by COR, ACOR, and/or GPLs.
Provide quality assurance and quality management support IAW SOW paragraph 3.3.9
100% Inspection by COR, ACOR, and/or GPLs.
Provide frequency spectrum authorization support IAW SOW paragraph 3.3.10
100% Inspection by COR, ACOR, and/or GPLs.
Provide technical management support IAW SOW paragraph 3.3.11
100% Inspection by COR, ACOR, and/or GPLs.

Enclosure (1) CUI Enclosure (1)

CUI 8

ENCLOSURE (2): QUARTERLY EVALUATION BY CONTRACT DATA REQUIREMENTS LIST (CDRL)

Description
Surveillance Method/Measure
Dates Due
Dates Completed
No. Submittals
No. of Req’d Rework
Percentage On Time
Comments
A001: Contracting Officer’s Representative (COR) Management Report for Technical Direction Letters (TDLs): Segregation of Cost and Invoice Requirements Reporting for TDLs
100% Inspection by COR, ACOR, and/or GPLs.
A002: Management Plan: Organizational Chart & Labor Mix Report
100% Inspection by COR, ACOR, and/or GPLs.
A003: Certificate of Quality Audit Compliance: International Organization for Standards (ISO) International Standard 9001:2015, Quality Management Systems, September 2015
100% Inspection by COR, ACOR, and/or GPLs.
A004: Trip/Travel Report
100% Inspection by COR, ACOR, and/or GPLs.
A005: Contractor Performance Assessment Report: Technical Assistance Performance Evaluation (TAPE) Report
100% Inspection by COR, ACOR, and/or GPLs.
A006: Government Property (GP) Inventory Report: Contractor Acquired Property (CAP)
100% Inspection by COR, ACOR, and/or GPLs.
A007: Phase-Out Transition Plan: Transition-Out Plan
100% Inspection by COR, ACOR, and/or GPLs.
A008: Certification Data Report: Organizational Conflict of Interest (OCI) Mitigation Plan & Non-Disclosure Agreement (NDA) Status Certification
100% Inspection by COR, ACOR, and/or GPLs.
A009: NAVAIR Operations Security (OPSEC) Plan
100% Inspection by COR, ACOR, and/or GPLs.
A010: Schematic Block Diagrams: Engineering Drawings
100% Inspection by COR, ACOR, and/or GPLs.
A011: Technical Data Package: Wiring and Cabling Drawings
100% Inspection by COR, ACOR, and/or GPLs.
A012: Interface Control Document (ICD)
100% Inspection by COR, ACOR, and/or GPLs.
A013: Installation Control Drawings
100% Inspection by COR, ACOR, and/or GPLs.
A014: General Style and Format Requirements for Technical Manuals: Technical Manual, Maintenance Manual, Operator Manual, Installation Manual
100% Inspection by COR, ACOR, and/or GPLs.
A015: Manuals, Technical, Equipment Operation and/or Maintenance Instructions, Technical Content Requirements (Work Package Concept)
100% Inspection by COR, ACOR, and/or GPLs.
A016: Technical Report - Study/Services: Engineering Analysis
100% Inspection by COR, ACOR, and/or GPLs.
A017: Work Instruction (WI)
100% Inspection by COR, ACOR, and/or GPLs.
A018: Test/Inspection Report: Test Report
100% Inspection by COR, ACOR, and/or GPLs.
A019: System/Subsystem Specification (SSS): Systems Specifications, Requirements Specifications, Interface Specifications
100% Inspection by COR, ACOR, and/or GPLs.
A020: Student Guide: Training Aids
100% Inspection by COR, ACOR, and/or GPLs.
A021: Training Materials: Identification Friend or Foe (IFF) Maintenance Course Training Materials
100% Inspection by COR, ACOR, and/or GPLs.
A022: Report, Record of Meeting/Minutes
100% Inspection by COR, ACOR, and/or GPLs.
A023: Logistics Product Data: Logistics Support Analysis Record
100% Inspection by COR, ACOR, and/or GPLs.
A024: Government Furnished Inspection Equipment Maintenance Report
100% Inspection by COR, ACOR, and/or GPLs.
A025: Commercial Asset Visibility (CAV) Reporting: Commercial Asset Visibility (CAV) Inventory Report
100% Inspection by COR, ACOR, and/or GPLs.
A026: Test Plans/Test Procedures: Test Plans
100% Inspection by COR, ACOR, and/or GPLs.
A027: Test Plans/Test Procedures: Test Procedures
100% Inspection by COR, ACOR, and/or GPLs.
A028: Supplier's Configuration Management Plan: Laboratory Configuration Management Report
100% Inspection by COR, ACOR, and/or GPLs.
A029: Briefing Material
100% Inspection by COR, ACOR, and/or GPLs.
A030: Meeting Agenda
100% Inspection by COR, ACOR, and/or GPLs.

Metric Summary:

Current Period

Cumulative

Total Number of Deliverables Submitted:

Total Number of Deliverables Submitted Late:

Total Number of Deliverables Requiring Revision:

Percentage of Deliverables Submitted Late:

Percentage of Deliverables Requiring Revision:

Enclosure (2) CUI Enclosure (2)

ENCLOSURE (3): ANNUAL SURVEILLANCE SUMMARY

The Contracting Officer’s Representative (COR) will perform an assessment of overall Contract performance utilizing the Contractor Performance Assessment Reporting System (CPARS) evaluation rating definitions listed in Enclosure (3) below. This assessment will be completed annually covering the previous 12 months.

Description
Surveillance Method/Measure
Date Planned
Date Completed
Summary Rating/Results
Quality of Product or Service
Review of Quarterly Ratings
Schedule
Review of Quarterly Ratings
Cost Control
Review of Quarterly Ratings
Business Relations
Review of Quarterly Ratings
Management
Review of Quarterly Ratings
Utilization of Small Business (SB)
Review of Quarterly Ratings
Other Areas
Review of Quarterly Ratings

Annual Surveillance Completed By: _______________________

Date Completed: ________________

All Statement of Work (SOW) and Contract Data Requirements List (CDRL) tasks, including sub-tasks, will be assessed focusing on the following.

Quality of product or service: Assess the Contractor’s effort to transform operational needs and requirements into an integrated solution. Areas of focus may include the planning and management of program tasks, the quality of support provided throughout all phases of contract execution, the integration of program management specialties, management of interfaces and the management of a totally integrated effort of all program management concerns to meet cost, performance and schedule objectives. Assess how successfully the Contractor meets program quality.

Schedule: Assess the Contractor’s adherence to the required delivery schedule by assessing the Contractor’s efforts during the assessment period that contribute to or effect the schedule variance. Also address significance of scheduled events (e.g., design reviews), discuss causes, and assess the effectiveness of Contractor corrective actions.

Cost control: Assess the Contractor’s effectiveness in forecasting, managing, and controlling contract cost. Is the Contractor experiencing cost growth or under-run? If so, discuss the causes and contractor-proposed solutions for the cost overruns. For contracts where task or contract sizing is based upon contractor-provided person hour estimates, the relationship of these estimates to ultimate cost should be assessed. In addition, the extent to which the Contractor demonstrates a sense of cost responsibility through the efficient use of resources in each work effort will be assessed.

Business relations: Assess the timeliness, completeness, and quality of problem identification, corrective action plans, proposal submittals, the Contractor’s reasonable and cooperative behavior, effective business relations, and customer satisfaction.

Management: Assess the Contractor’s success with timely award and management of subcontracts. Discuss the extent to which the Contractor discharges its responsibility for integration and coordination of all activity needed to execute the Contract; identifies and applies resources required to meet schedule requirements; assigns responsibility for tasks/actions required by the Contract; and communicates appropriate information to affected program elements in a timely manner. Assess the Contractor’s risk mitigation plans.

Utilization of Small Business (SB): The Request for Proposal (RFP) and FAR Subpart 19.7 and 15 U.S.C. 637 contains statutory requirements for complying with the SB Subcontracting Program. Assess whether the Contractor provided maximum practicable opportunity for SB (including Alaska Native Corporations (ANCs) and Indian Tribes) (including Small-Disadvantaged Businesses (SDBs) (which also includes ANCs and Indian Tribes), Women-Owned SBs (WOSBs), HUBZone, Veteran-Owned SBs (VOSBs), Service-Disabled Veteran Owned SBs (SDVOSBs), and ANCs and Indian Tribes that are not SDBs or SBs to participate in contract performance consistent with efficient performance of the Contract. Evaluation will focus on the metrics of actual SB utilization as compared to the Contract required targets and the Contractor’s submitted SB plan.

Other areas: Assess additional evaluation areas unique to the Contract or that cannot be captured elsewhere.

The evaluation ratings are as follows:

Exceptional Performance: Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective.

Very Good Performance: Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with some minor problems for which corrective actions taken by the Contractor were effective.

Satisfactory Performance: Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory.

Marginal Performance: Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being evaluated reflects a serious problem for which the Contractor has not yet identified corrective actions. The Contractor’s proposed actions appear only marginally effective or were not fully implemented.

Unsatisfactory Performance: Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective.

CUI 11

File details come from the government source that posted it. Updated .