Attachment 2 BLA Water Tower Rehab Specs.pdf

PDF 402 KB Posted

Attached to
Blackwell Water Tower Rehab
Solicitation number
12441926Q0001
Issued by

About this file

This document is a comprehensive specification for a water tower rehabilitation project at the Blackwell Job Corps Civilian Conservation Center in Laona, Wisconsin. The project consists of two primary components: Base Item No. 1 involves a complete water tower rehabilitation, including replacing the SCADA transducer valve, cleaning and recoating the exterior insulated sphere and stem, abrasive blasting and recoating the tank interior and platforms, installing new pipe insulation, adding sampling and chemical injection taps, and reconfiguring the overflow/tank drain outlet. Optional Item No. 2 involves replacing an existing submersible water well pump with a new 5 HP, 3-phase, 208V pump with specific performance requirements, including a capacity of 50 gpm at 250' total dynamic head and a set depth of 80'-100'.

The specification provides detailed technical requirements for surface preparation, coating systems, valves, piping, and installation procedures. The coatings must comply with AWWA D102 standards and be NSF certified, with specific layers and thickness requirements for both exterior and interior surfaces. The project includes provisions for temporary water tower bypass, pressure monitoring, and strict discharge sampling and reporting requirements. Contractors must follow precise surface preparation standards, use specified coating materials (primarily Tnemec products), and adhere to Wisconsin state and federal regulations for potable water systems. The work must be completed with minimal disruption to the Job Corps Center's operations, with work hours restricted to 8:00 AM-4:30 PM Monday through Friday.

View the file

Other files

File Type Posted
Questions - Answers 3.pdf PDF
Questions - Answers 2.pdf PDF
Questions - Answers.pdf PDF
Attachment 4 12441926Q0001 SOI.xlsx XLSX spreadsheet
12441926Q0001.pdf PDF
Attachment 5 Wage Rate Determinations.pdf PDF
Attachment 1 BLA Water Tower Rehab Dwgs.pdf PDF
Attachment 3 BLA WT Sustainable Prods.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WATER TOWER REHAB 010150 – 1

BLACKWELL JOB CORPS CCC GENERAL REQUIREMENTS

SECTION 010150

GENERAL REQUIREMENTS

PART 1 – SUMMARY OF WORK

1.1 DESCRIPTION

A. Work for this project requires the contractor to be responsible for supplying all labor, materials, equipment, utilities, miscellaneous items, freight and delivery and all necessary valid licenses for the work summarized as follows:

1. Base Item No. 1 –Water Tower Rehabilitation

2. Optional Item No. 2 – Pump Replacement

1.2 LOCATION

A. This project is located at the Blackwell Job Corps Civilian Conservation Center located five miles from Laona, Wisconsin in Forest County. The address is 4155 County Highway H, Laona, WI 54541. Driving instructions can be obtained from the Center by calling 800-733-5627.

1.3 WORK HOURS

A. Work hours for this project are between 8:00 AM-4:30 PM Monday through Friday.

1.4 USE OF PREMISES

A. Confine constructions operations to immediate area of work. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Government will occupy site and buildings during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the work so as not to interfere with Government's day-to-day operations.

C. Keep driveways, parking areas, loading areas and entrances to buildings clear and available to Government, Government's employees, and emergency vehicles at all times.

Do not use these areas for parking or storage of materials. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government.

1.5 DEFINITIONS

A. The following terms in any combination relating to the installation of products/materials:

install, furnish, provide, or similar statements; mean that the contractor is responsible for

WATER TOWER REHAB 010150 – 2

the procurement and installation of the products unless it is specifically designated as either a government furnished item, supply only product, or spare.

1.6 STANDARDS AND CODES

A. All contract work shall adhere to the most recent version of:

1. All the International Code Council Family of codes (ICC) e.g. International

Building Code (IBC), International Fire Code (IFC), and International Mechanical Code (IMC).

2. All National Fire Protection Association (NFPA) codes and Standards e.g., NFPA 70: National Electrical Code (NEC), NFPA 1: Fire Code, and NFPA 101- Life Safety Code.

3. Architectural Barriers Act Standards (ABA or ABAAS).

4. Product Manufacturer’s installation instructions.

5. State of Wisconsin standards for community water systems.

1.7 QUALIFICATIONS

A. When applicable to specific contract work items:

1. Electrical work shall be performed by journey level electricians licensed in the

State of contract performance or trainees/apprentices working under the direct supervision of State-licensed electrical supervisors (or State equivalent).

2. Plumbing work shall be performed by journey level plumbers licensed in the State of contract performance or trainees/apprentices working under the direct supervision of State-licensed plumbing supervisors (or State equivalent).

1.8 ELECTRICAL INSPECTIONS

A. This Federal contract is exempt from State permitting requirements. However, electrical work must be inspected by a third-party Inspector who is either State-licensed or ICC-certified. The Contractor will arrange for the inspection and pay any fees required for the inspection and associated report; arrangement may include completion and submission of load calculations, permit applications, and any other required coordination. The Inspector does not have any jurisdictional authority on Federal projects. The USFS is the jurisdiction having authority. The inspection will be based on the most recent version of the NFPA 70 National Electric Code (NEC) and currently adopted State codes. A list of deficiencies with corresponding code reference is to be provided in a report signed by the inspector. The addressee in the report is to be the Job Corps Center. The Inspector will provide a copy of their current inspection credentials with the inspection report. The Contractor will submit the report to the COR. The CO will determine which deficiency/violations will be enforced for the Contractor to fix.

1.9 WORK RESTRICTIONS

WATER TOWER REHAB 010150 – 3

A. Smoking is permitted on campus only in the designated smoking area.

1.10 SCHEDULE OF ITEMS

A. Schedule of Items:

1. Provide pricing for all items listed in the Schedule of Items.

2. Contract award will be made for all Base Items.

3. Optional Items may or may not be awarded, depending on funding availability.

B. Base Items (BI):

1. Base Item No. 1 –Water Tower Rehabilitation

a. Measurement: This item is measured as a Lump Sum quantity.

b. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor, and incidentals to:

i. Replace valve serving water tower SCADA transducer.

ii. Clean and recoat exterior insulated sphere including appurtenances such as hatches, rail system, vents; protect vent screens or operable parts from overspray which would interfere with their function/operation. Utilize cleaning and preparation techniques that won’t damage the insulation where present.

iii. Clean, spot repair, and recoat entire exterior stem and bottom bell.

iv. Abrasive blast and recoat entire tank interior (wet) including built-in appurtenances including but not limited to ladders, platforms, overflow inlets, etc.

v. Abrasive blast and recoat top and bottom of platforms and adjoining surfaces exhibiting corrosion.

vi. Clean and dispose of trash, dirt, debris, and abandoned parts on platforms, floor, and sump.

vii. Remove any loose pipe insulation jacket and install new vapor barrier/insulation jacket on all fill/supply and bubbler/recirculation piping over existing pipe insulation. Provide joints in vapor barrier at expansion joint for future inspection purposes.

viii. Furnish and install valved sampling tap and auxiliary chemical injection tap.

ix. Furnish and install removable insulation and jackets at expansion joint and at the proposed taps.

x. Reconfigure overflow/tank drain outlet:

1. Replace flap valve with duckbill check valve with downturned elbow.

2. Locate utilities.

3. Regrade outlet area.

4. Replace or reset concrete splash pad on prepared subgrade and insulation board.

5. Finish grade, seed, mulch disturbed area.

WATER TOWER REHAB 010150 – 4

xi. Provide pressure monitoring and modulation, bypass piping/valving, and outlet erosion protection for any excess water resulting from bypass system.

Bypass shall discharge to groundwater in accordance with WI General Permit WI-B057681-05-0 requirements. Pressure shall be modulated at 60 psi +/-, immediately report any instances of water pressure dropping below 20 psi to the Contracting Officer and Center’s water system operator.

1. Provide flowmeter or other approved means of water discharge volume measurement (daily) during construction and provide weekly report of daily discharge to the Center Point of Contact and COR of volumes. Note: Center POC will enter flow data into WI DNR Switchboard utilizing Contractor provided volumetric monitoring.

xii. Provide disinfection and bacteriological testing in accordance with State of Wisconsin requirements prior to returning the tank to service.

xiii. Complete and submit any closeout documentation required by the State’s permitting requirements.

c. Deficiencies: #151189.

C. Optional Items (OI):

1. Optional Item No. 2 –Pump Replacement

d. Measurement: This item is measured as a Lump Sum quantity.

e. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor, and incidentals to:

i. Remove and replace existing submersible water well pump in one of the existing wells and replace with a new pump, motor, foot valve, control box and start/run capacitors per new pump requirements, connect to existing pump control panel, verify correct pump operation, dispose of existing pump, disinfect the well and distribution piping according to the requirements of the State of Wisconsin Community Well Code:

1. Motor Capacities. 3 Phase, 208V, 5 HP.

2. Pump, Motor exterior, and Shaft Material: Stainless steel.

3. Pump Capacity: 50 gpm @ 250’ TDH, nominal.

4. Approximate set depth of 80’-100’.

5. Well Static Water Level: 78’ +/-

6. System Pressure: Transducer Setpoints: 116.5’ pump on, 121.8’ pump off.

7. Basis of Design Manufacturers:

a. Franklin Pump.

b. Pentek.

c. Goulds.

d. Sta-Rite.

ii. ***Note, this Optional Bid Item may be awarded at any time during the period of performance at the discretion of the Contracting Officer. If

WATER TOWER REHAB 010150 – 5

awarded, the contractor shall be responsible for completion of the work within 72 hours of written notice from the Contracting Officer. If awarded provide pump/motor submittals after field verification of existing pump/motor/and system electrical requirements.

PART 2 – PROJECT SCHEDULE

2.1 PROJECT SCHEDULE

ITEM* REQUIRED DUE DATE (calendar days)

Pre-Construction Conference

Within 10 days of Award (virtually)

Notice To Proceed (NTP)

Issued first weekday after Pre-Construction Conference

Bonds 10 days after Award

Action and Informational Submittals

12 days after NTP (CORs have 12 days to return)

Closeout Submittals

Prior to CO acceptance of project

Contract Release form and final pay request

10 days after CO acceptance of project

* All items above must be included in Contractor’s construction schedule

PART 3 – SUBMITTAL PROCEDURES

3.1 DEFINITIONS

A. Action Submittals: Written and graphic information that requires Government approval.

WATER TOWER REHAB 010150 – 6

B. Informational Submittals: Written information that does not require Government approval. Submittals may be rejected for not complying with requirements.

3.2 PROCEDURES

A. Contractor Responsibilities

1. Review each submittal and check for compliance with the Contract Documents.

2. Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

3. Include the following information on label or cover sheet for processing and recording action taken:

a. Project name.

b. Date.

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. Date of Contractor’s approval.

i. Statement certifying that submittal has been reviewed, checked, and approved by the Contractor for compliance with the Contract Documents.

4. The Government will not review submittals that do not bear Contractor's approval and will return them without action.

5. Unless additional copies are required for final submittal, and unless the

Contracting Officer (CO) observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

6. Submittals must be submitted in electronic PDF format. Submit to CO via email or electronic file transfer site.

7. Only final submittals with mark indicating action taken by Government are to be used for construction.

8. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

B. Processing Time: Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Government will review initial submittal within 12 calendar days.

Additional time may be needed if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. Resubmittals: If resubmittal is necessary, it will be resubmitted within 3 calendar days, and reviewed by the Government within 3 calendar days.

3.3 ACTION SUBMITTALS

A. Prepare and submit Action Submittals required in the Technical Specifications in this contract, if applicable, and as indicated at the end of this subsection.

WATER TOWER REHAB 010150 – 7

B. Collect information into a single submittal for each element of construction and type of product or equipment.

1. Mark up each submittal to show which products and options are applicable.

2. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

C. Required Action Submittals

1. Product Data: See Technical Specification Sections and

a. Pipe Jacket Material.

b. Pump/motor in the event

3.4 INFORMATIONAL SUBMITTALS

A. Prepare and submit Informational Submittals required in the Technical Specifications in this contract, if applicable, and as indicated below:

B. Required Informational Submittals:

1. Accident Prevention Plan.

2. Construction Schedule.

3. Current licensure and/or certifications for individuals indicated in

QUALIFICATIONS paragraph above or as required in individual technical sections.

3.5 CLOSEOUT SUBMITTALS

A. Prepare and submit Closeout Submittals, as follows:

1. See Technical Specification Sections.

2. One-Year Warranty on Entire Project as required by FAR 52.246–21

3. Project Record Documents.

PART 4 – TEMPORARY FACILITIES AND CONTROLS

4.1 USE OF UTILITIES

A. Utilities: Use of Government existing facilities will be permitted without metering and without payment of use charges, as long as facilities are cleaned and maintained in an acceptable condition. At Substantial Completion, restore these facilities to condition

WATER TOWER REHAB 010150 – 8

existing before initial use. The following are available for use by the contractor: water, and electrical power services. The following are not available: telephone service. The contractor is expected to provide whatever phone service he deems necessary for the duration of the project.

4.2 SANITARY FACILITIES

A. Sanitary facilities are not available for use by the Contractor. Facilities must be cleaned and maintained daily.

4.3 STAGING AND STORAGE

A. Coordinate on-site staging and storage requirements with the Center Point of Contact or the Contracting Officer Representative (COR).

4.4 CONSTRUCTION WASTE DISPOSAL FACILITIES

A. Provide waste-collection containers in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste. Use of Government waste containers will not be permitted.

4.5 SAFETY AND ENVIRONMENTAL PROTECTION

A. Environmental Protection: Contractor shall provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

B. Barricades, Warning Signs, and Lights: Comply with the national or state Manual on Uniform Traffic Control Devices (MUTCD) for erecting structurally adequate barricades, paint with appropriate colors, graphics, and warning signs/lights to inform personnel, students, and the public of possible hazards.

C. Fire Protection.

1. Store combustible materials in containers in fire-safe locations.

2. Maintain unobstructed access to fire extinguishers, fire hydrants, fire-protection facilities, stairways, and other access routes for firefighting. Prohibit smoking in hazardous fire-exposure areas.

3. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition.

PART 5 – EXECUTION REQUIREMENTS

5.1 EXAMINATION

WATER TOWER REHAB 010150 – 9

A. Before beginning work, examine areas and document existing conditions. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.

B. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

C. Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to CO. Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.

5.2 INSTALLATION

A. Locate the Work and components of the Work accurately, in correct alignment and elevation to fit with existing construction.

B. Make vertical work plumb and make horizontal work level.

C. Install per manufacturer's written instructions and recommendations.

5.3 PROGRESS CLEANING

A. Clean Project site and work areas daily, including common areas. Dispose of materials lawfully.

1. Comply with NFPA 241 requirements for removal of combustible waste materials and debris.

2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).

B. Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted.

5.4 PROTECTION OF INSTALLED CONSTRUCTION

A. Provide protection and maintain conditions that ensure installed Work does not get damaged or deteriorated prior to Substantial Completion.

5.5 CORRECTION OF THE WORK

A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

PART 6 – CLOSEOUT PROCEDURES

WATER TOWER REHAB 010150 – 10

6.1 SUBSTANTIAL COMPLETION

A. Definition of Substantial Completion: The Date certified by the CO when construction is sufficiently complete, in accordance with the Contract Documents, so the Government can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.

B. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.

1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.

2. Advise the CO of pending insurance changeover requirements.

3. Submit specific warranties, workmanship bonds, final certifications, and similar documents.

4. Obtain and submit releases permitting Government unrestricted use of the Work and access to services and utilities.

5. Deliver tools, spare parts, extra materials, and similar items to location designated by Government. Label with manufacturer's name and model number where applicable.

6. Complete startup testing of systems.

7. Submit changeover information related to Government occupancy, use, operation, and maintenance.

8. Complete final cleaning requirements, including touchup painting.

9. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.

C. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by CO, that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for Final

Completion.

6.2 FINAL COMPLETION

A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:

1. Submit certified copy of CO’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by CO. The certified copy

WATER TOWER REHAB 010150 – 11

of the list shall state that each item has been completed or otherwise resolved for acceptance.

2. Submit evidence of final, continuing insurance coverage complying with insurance requirements.

3. Instruct Government personnel in operation, adjustment, and maintenance of products, equipment, and systems.

B. Inspections: Submit a written request for final inspection for acceptance. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

6.3 LIST OF INCOMPLETE ITEMS (PUNCH LIST)

A. Preparation: Submit two copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

6.4 PROJECT RECORD DOCUMENTS

A. General: Do not use Project Record Documents for construction purposes. Protect Project Record Documents from deterioration and loss. Provide access to Project Record Documents for CO's reference during normal working hours.

B. Provide Draft of Project Record Drawings at Substantial Completion. CO will return reviewed copy. Provide Final Project Record Drawings at Final Completion.

C. Record Drawings: Maintain and submit one set of blue- or black-line white prints of Contract Drawings and Shop Drawings.

1. Mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints.

a. Give particular attention to information on concealed elements that cannot be readily identified and recorded later.

b. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.

2. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at the same location.

WATER TOWER REHAB 010150 – 12

3. Note Construction Change Directive numbers, Change Order numbers, alternate numbers, and similar identification where applicable.

4. Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location. Organize into manageable sets;

bind each set with durable paper cover sheets. Include identification on cover sheets.

6.5 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

C. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:

1. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

2. Remove tools, construction equipment, machinery, and surplus material from Project site.

3. Touch up and otherwise repair and restore marred, exposed finishes and surfaces.

Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.

D. Remove waste materials from Project site and dispose of lawfully.

END OF SECTION 010150

WATER TOWER REHAB

BLACKWELL JOB CORPS CCC

220719 - 1

PLUMBING PIPING JACKET

SECTION 220719 - PLUMBING PIPING INSULATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes jacket replacements on the following plumbing piping services:

1. Potable Water Distribution Piping and Accessories.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Samples: For each type of insulation and jacket indicated.

1.3 INFORMATIONAL SUBMITTALS

A. Qualification Data: For qualified Installer.

B. Material test reports.

C. Field quality-control reports.

1.4 QUALITY ASSURANCE

A. Installer Qualifications: Skilled mechanics who have successfully completed an apprenticeship program or another craft training program certified by the Department of Labor, Bureau of Apprenticeship and Training.

1.5 SCHEDULING

A. Schedule insulation application after pressure testing systems and, where required, after installing and testing heat tracing. Insulation application may begin on segments that have satisfactory test results.

PART 2 - PRODUCTS

2.1 ADHESIVES

A. Materials shall be compatible with insulation materials, jackets, and substrates and for bonding insulation to itself and to surfaces to be insulated unless otherwise indicated.

220719 - 2

PLUMBING PIPING JACKET

B. FSK Jacket Adhesive: Comply with MIL-A-3316C, Class 2, Grade A, for bonding insulation jacket lap seams and joints.

C. PVC Jacket Adhesive: Compatible with PVC jacket.

2.2 SEALANTS

A. Materials shall be as recommended by the insulation manufacturer and shall be compatible with insulation materials, jackets, and substrates.

B. Joint Sealants:

1. Permanently flexible, elastomeric sealant.

2. Service Temperature Range: Minus 58 to plus 176 deg F.

3. Color: White or gray.

C. FSK and Metal Jacket Flashing Sealants:

1. Fire- and water-resistant, flexible, elastomeric sealant.

2. Service Temperature Range: Minus 40 to plus 250 deg F.

3. Color: Aluminum.

2.3 FIELD-APPLIED JACKETS

A. Field-applied jackets shall comply with ASTM C1136, Type I, unless otherwise indicated.

B. FSK Jacket: Aluminum-foil-face, fiberglass-reinforced scrim with kraft-paper backing.

C. PVC Jacket: High-impact-resistant, UV-resistant PVC complying with ASTM D1784, Class 16354-C; thickness as scheduled; roll stock ready for shop or field cutting and forming.

Thickness is indicated in field-applied jacket schedules.

1. Adhesive: As recommended by jacket material manufacturer.

2. Color: White.

3. Factory-fabricated fitting covers to match jacket if available; otherwise, field fabricate.

a. Shapes: 45- and 90-degree, short- and long-radius elbows, tees, valves, flanges, unions, reducers, end caps, soil-pipe hubs, traps, mechanical joints, and P-trap and supply covers for lavatories.

D. Metal Jacket:

1. Aluminum Jacket: Comply with ASTM B209, Alloy 3003, 3005, 3105, or 5005, Temper H-14.

a. Finish and thickness are indicated in field-applied jacket schedules.

b. Moisture Barrier for Indoor Applications: 3-mil-thick, heat-bonded polyethylene and kraft paper.

c. Factory-Fabricated Fitting Covers:

1) Same material, finish, and thickness as jacket.

2) Preformed two-piece or gore, 45- and 90-degree, short- and long-radius elbows.

3) Tee covers.

220719 - 3

PLUMBING PIPING JACKET

4) Flange and union covers.

5) End caps.

6) Beveled collars.

7) Valve covers.

8) Field fabricate fitting covers only if factory-fabricated fitting covers are not available.

E. Self-Adhesive Indoor/Outdoor Jacket (Non-Asphaltic): Vapor barrier and waterproofing jacket for installation over insulation located aboveground outdoors or indoors. Specialized jacket has five layers of laminated aluminum and polyester film with low-temperature acrylic pressure-sensitive adhesive. Outer aluminum surface is coated with UV-resistant coating for protection from environmental contaminants.

1. Permeance: 0.00 perm as tested in accordance with ASTM F1249.

2. Flamespread/Smoke Developed: 25/50 as tested in accordance with ASTM E84.

3. Aluminum Finish: Embossed or Smooth.

2.4 TAPES

A. ASJ Tape: White vapor-retarder tape matching factory-applied jacket with acrylic adhesive, complying with ASTM C1136.

1. Width: 3 inches.

2. Thickness: 11.5 mils.

3. Adhesion: 90 ounces force/inch in width.

4. Elongation: 2 percent.

5. Tensile Strength: 40 lbf/inch in width.

6. ASJ Tape Disks and Squares: Precut disks or squares of ASJ tape.

B. FSK Tape: Foil-face, vapor-retarder tape matching factory-applied jacket with acrylic adhesive;

complying with ASTM C1136.

1. Width: 3 inches.

2. Thickness: 6.5 mils.

3. Adhesion: 90 ounces force/inch in width.

4. Elongation: 2 percent.

5. Tensile Strength: 40 lbf/inch in width.

6. FSK Tape Disks and Squares: Precut disks or squares of FSK tape.

C. PVC Tape: White vapor-retarder tape matching field-applied PVC jacket with acrylic adhesive;

suitable for indoor and outdoor applications.

1. Width: 2 inches.

2. Thickness: 6 mils.

3. Adhesion: 64 ounces force/inch in width.

4. Elongation: 500 percent.

5. Tensile Strength: 18 lbf/inch in width.

D. Aluminum-Foil Tape: Vapor-retarder tape with acrylic adhesive.

1. Width: 2 inches.

2. Thickness: 3.7 mils.

3. Adhesion: 100 ounces force/inch in width.

4. Elongation: 5 percent.

5. Tensile Strength: 34 lbf/inch in width.

220719 - 4

PLUMBING PIPING JACKET

2.5 SECUREMENTS

A. Bands:

1. Stainless Steel: ASTM A240/A240M, Type 304 or Type 316; 0.015 inch thick, 1/2 inch wide with wing seal or closed seal.

2. Aluminum: ASTM B209, Alloy 3003, 3005, 3105, or 5005; Temper H-14, 0.020 inch thick, 1/2 inch wide with wing seal or closed seal.

B. Staples: Outward-clinching insulation staples, nominal 3/4-inch-wide, stainless steel or Monel.

C. Wire: 0.062-inch soft-annealed, stainless steel.

2.6 CUSTOM REMOVABLE JACKETS

1. Basis of Design Product: Thermaxx Antifreeze Custom Water Piping Jackets.

2. Materials:

a. Jacket: Interior and Exterior: PTFE/Silicone-coated Fiberglass.

b. Insulation: 20 mm Aerogel.

3. Securements: Hook and Loops, compression straps, or shock cords.

PART 3 - EXECUTION

3.1 PREPARATION

A. Clean and dry surfaces to receive insulation. Remove materials that will adversely affect insulation application.

B. Clean and prepare surfaces to be insulated. Before insulating, apply a corrosion coating to insulated surfaces as follows:

1. Stainless Steel: Coat 300 series stainless steel with an epoxy primer 5 mils thick and an epoxy finish 5 mils thick if operating in a temperature range of between 140 and 300 deg F. Consult coating manufacturer for appropriate coating materials and application methods for operating temperature range.

2. Carbon Steel: Coat carbon steel operating at a service temperature of between 32 and 300 deg F with an epoxy coating. Consult coating manufacturer for appropriate coating materials and application methods for operating temperature range.

C. Coordinate insulation installation with the tradesman installing heat tracing. Comply with requirements for heat tracing that apply to insulation.

D. Mix insulating cements with clean potable water; if insulating cements are to be in contact with stainless steel surfaces, use demineralized water.

3.2 GENERAL INSTALLATION REQUIREMENTS

A. Install insulation materials, forms, vapor barriers or retarders, jackets, and of thicknesses required for each item of pipe system, as specified in insulation system schedules.

220719 - 5

PLUMBING PIPING JACKET

B. Install accessories compatible with insulation materials and suitable for the service. Install accessories that do not corrode, compress, or otherwise damage insulation or jacket.

C. Apply adhesives, mastics, and sealants at manufacturer's recommended coverage rate and wet and dry film thicknesses.

D. Install insulation with factory-applied jackets as follows:

1. Draw jacket tight and smooth, but not to the extent of creating wrinkles or areas of compression in the insulation.

2. Cover circumferential joints with 3-inch-wide strips, of same material as insulation jacket. Secure strips with adhesive and outward-clinching staples along both edges of strip, spaced 4 inches o.c.

3. Overlap jacket longitudinal seams at least 1-1/2 inches. Install insulation with longitudinal seams at bottom of pipe. Clean and dry surface to receive self-sealing lap.

Staple laps with outward-clinching staples along edge at 4 inches o.c.

a. For below-ambient services, apply vapor-barrier mastic over staples.

4. Cover joints and seams with tape, in accordance with insulation material manufacturer's written instructions, to maintain vapor seal.

5. Where vapor barriers are indicated, apply vapor-barrier mastic on seams and joints and at ends adjacent to pipe flanges and fittings.

E. Cut insulation in a manner to avoid compressing insulation.

F. Finish installation with systems at operating conditions. Repair joint separations and cracking due to thermal movement.

G. Repair damaged insulation facings by applying same facing material over damaged areas.

Extend patches at least 4 inches beyond damaged areas. Adhere, staple, and seal patches in similar fashion to butt joints.

3.3 PENETRATIONS

A. Insulation Installation at penetrations: Install insulation jacket continuously through open penetrations.

3.4 GENERAL PIPE INSULATION INSTALLATION

A. Requirements in this article generally apply to all insulation materials, except where more specific requirements are specified in various pipe insulation material installation articles below.

B. Install removable insulation covers at locations indicated. Installation shall conform to the following:

1. Make removable insulation covers at riser pipe expansion joint, extend insulation from at least 2 times the insulation thickness over adjacent pipe insulation on each side of flange or union. Secure flange cover in place with stainless steel or aluminum bands. Select band material compatible with insulation and jacket.

220719 - 6

PLUMBING PIPING JACKET

3.5 INSTALLATION OF FIELD-APPLIED JACKETS

A. Where FSK jackets are indicated, install as follows:

1. Draw jacket material smooth and tight.

2. Install lap or joint strips with same material as jacket.

3. Secure jacket to insulation with manufacturer's recommended adhesive.

4. Install jacket with 1-1/2-inch laps at longitudinal seams and 3-inch-wide joint strips at end joints.

5. Seal openings, punctures, and breaks in vapor-retarder jackets and exposed insulation with vapor-barrier mastic.

B. Where PVC jackets are indicated, install with 1-inch overlap at longitudinal seams and end joints. Seal with manufacturer's recommended adhesive.

1. Apply two continuous beads of adhesive to seams and joints, one bead under lap and the finish bead along seam and joint edge.

C. Where metal jackets are indicated, install with 2-inch overlap at longitudinal seams and end joints. Overlap longitudinal seams arranged to shed water. Seal end joints with weatherproof sealant recommended by insulation manufacturer. Secure jacket with stainless steel bands 12 inches o.c. and at end joints.

3.6 INDOOR, FIELD-APPLIED JACKET SCHEDULE

A. Install jacket over insulation material. For insulation with factory-applied jacket, install the field-applied jacket over the factory-applied jacket.

B. If more than one material is listed, selection from materials listed is Contractor's option.

C. Piping, Concealed or Exposed:

1. PVC: 20 mils thick.

2. Aluminum, Smooth or textured: 0.024 inch thick.

3. Painted Aluminum, Smooth: 0.024 inch thick.

4. FSK.

5. Self-Adhesive Indoor/Outdoor Jacket.

END OF SECTION 220719

221216 - 1

FACILITY ELEVATED, POTABLE-WATER STORAGE TANKS

SECTION 221216 - FACILITY ELEVATED, POTABLE-WATER STORAGE TANKS

PART 1 - GENERAL

1.1 SUMMARY

A. Interior and exterior rehabilitation of an existing steel spheroid potable water tank.

1. Interior/Exterior Re-Coating as scheduled.

2. Temporary Water Tower Bypass System

3. Valves.

4. Pipe and Fittings.

5. Splash Pad.

6. Discharge Water Sampling, Testing, and Reporting

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include manufacturer’s:

a. Installation requirements and recommendations.

b. System application guide for coatings that adhere to specified AWWA D102 coating standards.

c. Minimum/Maximum layer and total coating thicknesses in accordance with manufacturer specification and the products NSF certification to achieve AWWA coating standard.

B. Water bypass and erosion control plan.

1.3 INFORMATIONAL SUBMITTALS

A. Field quality-control plan.

B. Field quality-control reports.

C. Sampling and Testing Reports

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Comply with NSF 61, NSF 600, and NSF 372.

B. Pipes, fittings, valves, and accessories for potable water use shall be lead free.

C. Comply with 29 CFR 1910.

221216 - 2

FACILITY ELEVATED, POTABLE-WATER STORAGE TANKS

D. Utilize UL classified materials.

E. Society for Steel Painting Structures (SSPC). Surface preparation standards as scheduled.

F. AWWA D102 Coating Systems.

G. Wisconsin Administrative Code NR 810 and other standards referenced within.

H. Use only products manufacturer recommended for the intended purpose, exposure, and conditions.

2.2 VALVES

A. Brass Ball Valves, Two Piece with Full Port and Stainless Steel Trim:

1. Standard: MSS SP-110; MSS SP-145; IAPMO/ANSI Z1157.

2. CWP Rating: Minimum 200 psig.

3. Body Design: Two piece.

4. Body Material: Forged brass.

5. Ends: Threaded.

6. Press-End Connections Rating: Minimum 200 psig.

7. Seats: PTFE or RPTFE.

8. Stem: Stainless steel.

9. Ball: Stainless steel, vented.

10. Port: Full.

11. O-Ring Seal: Buna-N or EPDM

B. Duckbill Valve:

1. Basis of Design: Proco Style 710.

2. Standard: NSF 61.

3. Flanged duckbill style check valve for connection to existing fittings.

4. Body and Tube Material: Neoprene.

C. Smooth Nose Sample Tap:

1. Basis of Design: Aye McDonald 7200NT.

2. Rough Cast Brass Body.

3. Lead Free.

4. 125 psi WOG.

2.3 Pipe and Fittings:

A. Galvanized Steel Pipe.

1. Standard: ASTM A53/A53M.

B. Galvanized Steel Pipe Nipples.

1. Standard: ASTM A733 made of ASTM A53/A53M or ASTM A106/A106M, Standard

Weight, seamless steel pipe with threaded ends.

C. Galvanized, Gray-Iron Threaded Fittings:

1. Standard: ASME B16.4, Class 125, standard pattern.

221216 - 3

FACILITY ELEVATED, POTABLE-WATER STORAGE TANKS

D. Brass Pipe Nipples:

1. Standard: ASTM B687-97.

E. Brass Plugs and Fittings:

1. Standard: ASTM B62.

F. Concrete Splash Pad and Accessories:

1. Re-set existing pad or replace with 3,000 psi air entrained cast-in-place or precast concrete pad (3’x6’x6”) with trowel finish and tooled center flume to direct water ½”-1” nominal depth at center.

2. Provide with centered lift ring and steel reinforcement centered vertically in the slab consisting of #4 rebar at 18” on center both directions or 6”x6” W1.4 Wire Mesh.

3. Sub-Slab Insulation:

a. 4’x8’x2” Extruded Polystyrene Board Insulation.

b. ASTM C578.

c. Compressive Strength: 25 psi.

2.4 PAINT MATERIALS AND METHODS

A. Paint: Comply with AWWA D102 standards referenced.

B. Comply with manufacturer’s recommendations for surface preparation and product installation instructions. In the event of a conflict between the manufacturer’s instructions and the specifications; follow the more stringent requirement.

C. Volatile Organic Compounds (VOC): Comply with State and Federal VOC limitations for the intended application.

D. Acceptable Manufacturer’s:

1. Tnemec

a. Represented by Coating Resources, Inc.;

1) Brittany Zehner; (920) 840-2887; brittany@coatingresourcesinc.com

2. Carboline

3. Sherwin Williams

E. Basis of Design Product Requirements:

1. Urethane Primer, Zinc Rich:

a. Tnemec Series 91-H2O

1) VOC content: 318 grams/liter

2) Volume solids: 63%

3) Zinc Type: ASTM D 520 Type III

4) ASTM D 4541: 2,083 psi

5) ASTM B 117: 50,000 hours

6) ASTM G 85: 15,000 hours

7) Special qualifications: Certified in accordance with ANSI/NSF Std. 61 for tanks 8,000 gallons and greater. Meets AWWA D102-11 Inside Systems Nos. 3 & 5 and Outside Systems Nos. 3, 4 and 6.

b. Series 94-H2O Hydro-Zinc:

1) VOC content: 89 grams/liter

2) Volume solids: 62% mailto:brittany@coatingresourcesinc.com

221216 - 4

FACILITY ELEVATED, POTABLE-WATER STORAGE TANKS

3) Zinc Type: ASTM D 520 Type III

4) ASTM G8, Method A: 30 days – no blistering, cracking, rusting or undercutting at holiday

5) ASTM D 4541: 1,713 psi

6) ASTM B 117: 10,000 hours

7) ASTM G 85: 10,000 hours

8) Special qualifications: Certified in accordance with ANSI/NSF Std. 61 for tanks 500 gallons and greater. Meets AWWA D102-11 Inside Systems Nos.

3 & 5 and Outside Systems Nos. 3, 4 and 6.

2. Exterior Overcoat Primer:

a. Tnemec Series 118 Uni-Bond:

1) VOC Content: 31 grams/liter

2) Volume Solids: 55%

3) ASTM D4541: No less than 1,000 psi bond strength to exterior aged aliphatic polyurethane.

4) ASTM D5894: No blistering, cracking, rusting or delamination of film or creepage at the scribe after 5,376 hours

5) ASTM D522 Conical Mandrel: No cracking

6) ASTM D2247: No blistering or rusting after 5,000 hours

7) D412, Method C: No less than 436 psi tensile strength and 237% elongation at break

8) ASTM D1653, Method B Wet Cup: No more than 15.71 g/m2 per 24 hours water vapor transmission and no more than 1.23 perms water vapor permeance

3. Exterior Topcoat, Aliphatic Acrylic Polyurethane:

a. Tnemec Series 1095 Endura Shield

1) VOC content: 232 grams/liter

2) Volume solids: 66%

3) Finish: semi-gloss

b. Tnemec Series1094 Endura Shield

1) VOC content: 259 grams/liter

2) Volume Solids: 60%

3) Finish: gloss

4. Interior Wet, Polyamidoamine Epoxy

a. Tnemec Series L140 Pota-Pox Plus

1) Special Qualifications: Certified by NSF International in accordance with NSF/ANSI/CAN Std. 61 and the extraction requirements of

NSF/ANSI/CAN

2) Volume Solids: 65%

3) VOC Content: 123 grams/liter

5. Interior Dry, Modified Polyamidoamine Epoxy

a. Tnemec Series 135 Chembuild

1) Volume Solids: 84%

2) VOC: 86 grams/liter

3) HAPS: 1.29 lbs/gallon solids

4) ASTM D4541: No less than 883 psi.

5) ASTM D 4585: No blistering, cracking, rusting or delamination of the film after 2,000 hours exposure.

F. Exterior Coating Schedules:

221216 - 5

FACILITY ELEVATED, POTABLE-WATER STORAGE TANKS

1. Stem and lower bell (steel, not insulated):

a. System Type: Exterior Overcoat: Mastic Waterborne Acrylic/ Aliphatic Acrylic

Polyurethane

b. Surface Preparation: All surfaces shall be thoroughly clean to levels defined by

SSPC-SP WJ-4/NACE WJ-4 Light Cleaning by use of Low-Pressure Water Cleaning (LP WC) and dry prior to overcoating. Thoroughly power wash surfaces using hot water and detergent at sufficient pressure and flow rate to remove all chalk and surface contaminants. This can usually be accomplished using a rotating nozzle with 140F biodegradable detergent/water solution (1-2 oz. detergent per gallon of water) at 1,000-2,000 psi with 3-5 gallons per minute flow rater. If may be necessary to use some means of additional mechanical agitation during power-washing to help facilitate the removal of chalk or non-water-soluble contaminants.

Rinse surfaces with clean water. If mildew is present, allow the surface to dry and wet mildewed surfaces with bleach solution consisting of 3 parts warm water and 1 part household bleach. Allow the bleach solution to remain on the surface until dry then rinse with clean tap water. If present, clear coats must be thoroughly and uniformly abraded to degloss. De-gloss any areas where coating remains gloss by feasible means. Prepare bare metal and rusty areas according to SSPC-SP11 Power Tool Cleaning to Bare Metal and feather edges for smooth transition into tightly adhered coating. Prepare areas of exposed epoxy according to SSPC-SP3 Power Tool Cleaning and feather edges for smooth transition into tightly adhered coating.

c. Basis of Design Products:

1) Spot Primer: Tnemec Series 118 Uni-Bond Mastic @ 6.0-8.0 mils DFT.

2) Full Primer: Tnemec Series 118 Uni-Bond Mastic @ 6.0-8.0 mils DFT.

Vary color from topcoat to facilitate visual inspection of coverage.

3) Topcoat: Tnemec Series 1095 Endura Shield (semi-gloss), or 1094 (gloss)

Endura Shield @ 2.0-3.0 mils DFT. Color – XX Blue.

2. Sphere (insulated steel):

a. System Type: Exterior Overcoat: Mastic Waterborne Acrylic/ Aliphatic Acrylic Polyurethane

b. Surface Preparation: Carefully clean coated insulation using methods that do not damage tank insulation. Any loose coatings need to be removed. Make sure surface is clean, dry, and free of contaminants.

c. Basis of Design Products:

1) Intermediate Overcoat: Tnemec Series 118 Uni-Bond Mastic @ 6.0-8.0 mils

DFT. Vary color from topcoat to facilitate visual inspection of coverage.

2) Topcoat: Tnemec Series 1095 Endura Shield (semi-gloss), or 1094 Endura

Shield (gloss) @ 2.0-3.0 mils DFT. Color – XX Blue.

3) Optional Logo: Tnemec Series 700 HydroFlon @ 2.0-3.0 mils DFT

G. Interior Coating Schedules:

1. Tank Interior wet:

a. System Type: AWWA D102, ICS-5 (Zinc Rich Urethane Primer/Epoxy/Epoxy)

1) Certifications: NSF 61 & NSF 600

b. Surface Preparation: Remove all visible oil, grease, soil, dirt, and other soluable contaminants in accordance with SSPC-SP1 Solvent Cleaning. Weld slag, weld spatter, rough and sharp edges of weld seams shall be ground smooth. All areas shall be abrasive blast cleaned to a Near White finish in accordance with to SSPC- SP10/NACE 2. A minimum angular surface profile of 2.0 mils is required. All surfaces must be clean, dry, and free of oil, grease, and other contaminants.

221216 - 6

FACILITY ELEVATED, POTABLE-WATER STORAGE TANKS

c. Basis-of-Design Products:

1) Zinc Rich Urethane Primer: Tnemec Series 91-H2O or Series 94-H2O

Hydro-Zinc @ 2.5-3.5 mils DFT .

2) Stripe Coat: Tnemec L140 Pota-Pox Plus, Beige or White,

3) Intermediate Coat: Tnemec L140 Pota-Pox Plus Beige @ 4.0-6.0 mils DFT.

4) Topcoat: Tnemec L140 Pota-Pox Plus White @ 4.0-6.0 mils DFT.

2. Tank Interior dry (tower platforms and adjoining surface exhibiting corrosion):

a. System Type: Epoxy/Epoxy

b. Surface Preparation: Remove all visible oil, grease, soil, dirt and other soluable contaminants in accordance with SSPC-SP1 Solvent Cleaning. Weld slag, weld spatter, rough and sharp edges of weld seams shall be ground smooth. Areas to be coated shall be abrasive blast cleaned to a Commercial Blast Finish (SSPC- SP6/NACE 3) or Bare Metal Power Tool Clean (SSPC-SP11). Feather edges of the surrounding intact coatings making sure they are tight. A minimum angular surface profile of 1.5 mils is required. All surfaces must be clean, dry, and free of oil, grease, and other contaminants.

c. Basis-of Design Products (Epoxy/Epoxy)

1) Prime Coat: Tnemec Series 135 Chembuild @ 4.0-6.0 mils DFT.

2) Finish Coat: Tnemec Series 135 Chembuild @ 4.0-6.0 mils DFT

PART 3 - EXECUTION

3.1 FIELD PREPARATION AND PAINTING

A. Provide temporary protective measures according to approved safety plan, specifications, and according to the requirements of the State of Wisconsin.

B. Prepare Surfaces to be re-coated in accordance with manufacturer’s instructions and prescriptive surface preparation standards.

C. Capture and properly dispose of blast media, removed coating debris, and residual materials in accordance with any EPA or State required requirements.

D. Apply prime coat in accordance with manufacturer's directions.

E. Strip Coat welds and exposed edges and corners of steel plates, angles, and similar profiles when indicated in coating schedules.

F. Apply intermediate and topcoat according to approved finish schedules.

G. All products shall be applied in strict accordance with the manufacturer’s requirements for application methods, dry film thickness, cure times, and environmental conditions and as required to adhere to NSF approvals. Adhere to any/all manufacturer technical bulletins for required application conditions.

H. Overflow Pipe: Paint pipe exterior that is outside tank and structure as indicated for tank exterior.

221216 - 7

FACILITY ELEVATED, POTABLE-WATER STORAGE TANKS

I. Balcony and Exterior Ladders: Paint as indicated for tank exterior.

J. Complete daily painting to allow time for paint to dry before condensation is expected.

3.2 TOWER BYPASS AND PRESSURE MONITORING

A. Provide temporary tower bypass piping, pumps, pressure controls, and outlet erosion control for any excess water, adjust/repair erosion control measures throughout construction as required to prevent erosion or other damage to approved water discharge area. Temporary tower bypass shall adhere to the requirements of NR810.17 except fire hoses shall not be utilized for any potable water purposes.

B. Maintain water treatment (chlorine injection) and contact times in accordance with water system’s mandated treatment requirements throughout course of construction.

C. Set water pressure relief piping for 60 psi nominal, provide secondary maximum water pressure relief valve/piping at 70 psi for redundant pressure control.

D. Provide pressure monitoring to ensure water pressure in the distribution system is maintained above 20 psi at all times.

E. Upon returning the tower to service remove all temporary systems and erosion control measures.

3.3 TRANSDUCER ISOLATION VALVE:

A. Replace valve serving water level transducer piping with new valve of same nominal pipe size as existing.

3.4 OVERFLOW PIPE OUTLET, SPLASH PAD, AND EARTHWORK:

3.5 See plans for required installation and incidental requirements not listed in specifications.

3.6 DISCHARGE SAMPLING, TESTING, AND REPORTING:

A. The Contractor shall be responsible for the following:

1. Recording discharge volume for tower draining and flushing water and bypass water discharged to land during the course of construction.

a. Volume recording: Daily.

2. The daily recordings shall be reported to the Contracting Officer’s Representative with a cc to the water system operator on a weekly basis until all contract related discharges are completed including final flushing.

3. The bypass discharge shall be run through a water flow meter.

4. Water tower flushing and draining shall be calculated based upon water tower storage changes and flow meter readings.

221216 - 8

FACILITY ELEVATED, POTABLE-WATER STORAGE TANKS

3.7 FIELD QUALITY CONTROL

A. Perform the following tests and inspections:

1. Test coating thicknesses applied at random locations for all coats that are applied.

B. Provide documentation of remedy any coatings that do not meet the manufacturer's installation requirements. Retest and report all corrected areas.

C. Prepare test and inspection reports and submit to the Contracting Officer.

3.8 CLEANING

A. Clean interior and exterior of elevated, potable-water storage tanks.

B. Disinfect elevated,…