Attachment 2 - AF 66 - 29 JAN 24.xlsx
XLSX spreadsheet 29 KB Posted
- Attached to
- Cathodic Protection, Wells
- Solicitation number
- FA468624R0013
About this file
This document is an attachment to a federal contract opportunity related to the repair of a cathodic protection system at well fields for the United States Air Force. The attachment is a submittal schedule that lists various design, demolition, civil, architectural, structural, mechanical, plumbing, electrical, and closeout submittals required for the project, including their required submission dates and approval process.
The related federal contract opportunity is for a Cathodic Protection Wells project at Beale AFB, with an estimated magnitude between $300K and $500K. The NAICS code is 238190 for Cathodic Protection Installation. Key dates include a site visit on April 11, 2024, RFIs due by April 16, 2024, and proposals due by April 22, 2024.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal 1
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT NAME | SOLICITATION /CONTRACT NUMBER | |||||||||||||||||||
| 1135097 | Repair Cathodic Protection System at Well Fields | FA468624R0013 | ||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||||
| LINE NUMBER | Note: 3 copies required per submittal. Government will retain all submittals. Provide an electronic copy for each submittal. | CERTIF. OF COMPLIANCE | SHOP DRAWINGS | COLOR SELECTION | MANUFATURUR'S RECOMMENDATION | CATALOG DATA | O&M RECOMMENDATIONS | CALCULATIONS | WARRANTY | DRAWINGS | REPORT | TEST RESULTS | REQUIRED SUBMISSION DATE | DATE TO CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | APPROVED | DISAPPROVED | CONTRACTOR SUBMITTAL | FINAL APPROVAL | |
| GENERAL | ||||||||||||||||||||||
| Project Specific Form 66 | X | NTP + 15 | ||||||||||||||||||||
| Construction Schedule | X | NTP + 7 | ||||||||||||||||||||
| TCN Schedule (electronic required, hard copy optional) | X | NTP + 7 | ||||||||||||||||||||
| Contractor's Health, Safety, and Environment Plan | X | X | NTP + 7 | |||||||||||||||||||
| Contractor's QA/QC Plan | X | X | X | |||||||||||||||||||
| Copy of Engineering License(s) of person or consultancy responsible for design | X | Design | ||||||||||||||||||||
| DESIGN | ||||||||||||||||||||||
| All submissions to be provided electronically unless noted. | X | x | X | X | X | X | x | X | x | NTP + 15 | PE STAMP REQ'D, NO HARD COPY | |||||||||||
| Roof Drain Storm Sewer Tie In | ||||||||||||||||||||||
| Wind Loading Diagrams for Roof | ||||||||||||||||||||||
| Structural Connection Details for Shear Walls | ||||||||||||||||||||||
| Structural Connection Details for Framing | ||||||||||||||||||||||
| Structural Connection Details for Blast Resistant Doors & Windows | ||||||||||||||||||||||
| HVAC Calculations | ||||||||||||||||||||||
| Sprinkler Layout | ||||||||||||||||||||||
| Fire Alarm Layout | ||||||||||||||||||||||
| Communications Layout | ||||||||||||||||||||||
| Technical Specifications | X | X | X | X | NTP+45 | PE STAMP REQ'D, NO HARD COPY | ||||||||||||||||
| DEMOLITION/ASBESTOS | ||||||||||||||||||||||
| Demolition Plan | ||||||||||||||||||||||
| Asbestoes Plan (IF NEEDED) | X | X | ||||||||||||||||||||
| CIVIL | ||||||||||||||||||||||
| Soil Gradations for each type of soil used | ||||||||||||||||||||||
| Moisture-Density curve for each type of soil used | ||||||||||||||||||||||
| Nuclear Densometer Calibration | ||||||||||||||||||||||
| Soil Compaction Test Results for Utilities, Facilities & Pavement | X | X | X | Install+15 | ||||||||||||||||||
| Storm Pipe | ||||||||||||||||||||||
| ARCHITECTURAL | ||||||||||||||||||||||
| Blast Resistant Doors and Frames | ||||||||||||||||||||||
| Door Hardware | ||||||||||||||||||||||
| Gypsum Board-Type X | ||||||||||||||||||||||
| Gypsum Board-Type X-Mold Resistant | ||||||||||||||||||||||
| Wood Paneling | ||||||||||||||||||||||
| Wood Chair Rails | ||||||||||||||||||||||
| Wood Ceiling Cloud | ||||||||||||||||||||||
| Sheet Vinyl Flooring | ||||||||||||||||||||||
| Rubber Base | ||||||||||||||||||||||
| Ceiling Tiles | ||||||||||||||||||||||
| Blast Resistant Window | ||||||||||||||||||||||
| Glazing | ||||||||||||||||||||||
| Solid Surface Countertops | ||||||||||||||||||||||
| Kitchen Cabinets | ||||||||||||||||||||||
| Garbage Disposal | ||||||||||||||||||||||
| Interior Paint | ||||||||||||||||||||||
| Exterior Paint | NTP+45 | |||||||||||||||||||||
| Roofing System | ||||||||||||||||||||||
| Roofing Insulation | ||||||||||||||||||||||
| Roof Drains | ||||||||||||||||||||||
| Scuppers | ||||||||||||||||||||||
| Coping | ||||||||||||||||||||||
| Flashing | ||||||||||||||||||||||
| STRUCTURAL | ||||||||||||||||||||||
| Reinforcing Steel Drawings | ||||||||||||||||||||||
| Concrete Mix Design | ||||||||||||||||||||||
| Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion Joints | ||||||||||||||||||||||
| Concrete Field Test Results | ||||||||||||||||||||||
| Reinforcing Steel Mill Certifications | ||||||||||||||||||||||
| Slump Test results & Concrete Truck Tickets (per truck) | ||||||||||||||||||||||
| 7-Day Concrete Compressive Strength Test | ||||||||||||||||||||||
| 28-Day Concrete Compressive Strength Test | ||||||||||||||||||||||
| Blast Resistant Window Attachment | ||||||||||||||||||||||
| MECHANICAL |
PLUMBING
| INTERIOR ELECTRICAL | |||||||||
| Cables(electrical,comm,fire alarm) | X | X | X | NTP+7 | |||||
| Switches | X | X | NTP+7 | ||||||
| Receptacles | X | X | X | NTP+7 | |||||
| Panels | X | X | NTP+7 | ||||||
| Breakers | X | X | NTP+7 | ||||||
| Conduits | X | X | X | ||||||
| Lighting Fixtures | |||||||||
| Lighting UPS units (if req'd) | |||||||||
| Communication System Outlets(incl jacks) | |||||||||
| Communications patch panels | |||||||||
| PA Speakers | |||||||||
| Fire Alarm Devices (All) | |||||||||
| Occupancy Sensors | |||||||||
| Power Packs | |||||||||
| EXTERIOR ELECTRICAL | |||||||||
| Conduits (IF NEEDED) | X | X | X | ||||||
| Transformer | |||||||||
| Meter | |||||||||
| Cables(med & low voltage) | x | X | X | X | X | X | NTP+14 | ||
| Switches | x | x | NTP+14 | ||||||
| Contactors | x | NTP+14 | |||||||
| Panels | NTP+14 | ||||||||
| Breakers | x | X | x | NTP+14 | |||||
| Controller | x | X | NTP+14 | ||||||
| Junction Cabinet | X | x | X | NTP+14 | |||||
| Heating Mat | NTP+14 | ||||||||
| CLOSEOUT | |||||||||
| O&M maint data and maint manuals & Manufacturer's Warranty for Communications Equipment | X | x | X | X | Install + 4 | ||||
| Factory and Field Test Certificates, Logs and Test Results | x | X | X | Before Acceptance | |||||
| Inspection Logbook | x | X | x | Before Acceptance | |||||
| As Builts (electronic in AutoCAD and hard copies on Mylar) | X | X | Final + 7 |