About this file
This is a Past and Present Performance Questionnaire template used by a federal agency to evaluate contractor performance on design/build projects including new construction, renovation, alteration, and repair work with multiple disciplines.
The questionnaire is submitted to Athena.jackson@va.gov and collects general information including the contractor's name, project title, contract number, dollar amount, and performance period. Section B identifies the work scope as design/build projects with multiple disciplines. Respondents indicate their role (Prime Contractor, Sub-Contractor, Key Personnel, Teaming/Joint Venture, or Architect/Engineer) and provide contact information. The evaluation uses a five-point rating scale (1=Unsatisfactory, 2=Marginal, N=Neutral, 3=Satisfactory, 4=Very Good, 5=Exceptional) with "Not Applicable" as an option. Narrative explanations are required for any ratings of 1 or 2. The questionnaire contains 23 performance factors addressing management and staffing, delegation of authority, risk identification, responsiveness to changes, cooperation, quality control, subcontractor claims, site investigation, design quality, cost management, scheduling, environmental considerations, innovation, small business subcontracting implementation, deficiency correction, workforce quality, briefings, quality emphasis, cure notices, and likelihood of future contract award. Item 24 requests an overall rating on the 1-5 scale. The form includes a remarks section for additional narrative detail and notes that separate evaluation forms should be completed for other contracts held with the agency within the preceding five years.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 2
PAST AND PRESENT PERFORMANCE QUESTIONNAIRE
A. GENERAL INFORMATION: Please correct any information below known to be inaccurate:
Contractor’s Name: ___________________________
Project Title and Brief Description of Work:
Contract Number Provided by Offeror: Dollar Amount $_________________
Contract Period of Performance: _______________________
*Note: If offeror holds or has held other contracts with your agency/organization in the last 5 years, please complete separate evaluation forms for those contracts as well.
B. AGENCY INFORMATION: Work to be performed design/build projects, such as new construction, renovation, alteration and repair, with multiple disciplines.
Offeror submitted as:
Prime Contractor Sub-Contractor Key Personnel Teaming/Joint Venture Architect/Engineer
C. RESPONDENT INFORMATION (Person who is completing information):
Name of Respondent: _________ _ _ _ _ Title: __________ __________________
Address: __________ _ _ _ _ _ _ Telephone Number: __________ _ _ __
__________ _ _ _ _ _ _ Fax Number: _________ _ _ _ _ __
__________ _ _ _ _ _ _ Email Address: ________ _ _ _ _ _
D. EMAIL COMPLETED SURVEY FORM TO: Athena.jackson@va.gov
E. PERFORMANCE INFORMATION: Choose the number on the scale of 1 to 5 that most accurately describes the contractor’s performance or situation. If there was no performance in this project that can be rated use “Not
Applicable (N/A)”. PLEASE PROVIDE A NARRATIVE EXPLANATION FOR ANY RATINGS OF 1 OR 2.
1 2 N 3 4 5 N/A
Unsatisfactory Marginal Neutral Satisfactory Very Good Exceptional
Performance did Performance The record is Performance Performance Performance The contractor not meet most did not meet inconclusive or met contract met all contract met all contract did not contractual some without requirements. requirements requirements perform this requirements. contractual comment. There were and exceeded and exceeded effort.
There were requirements. some minor some to the many to the serious problems There were problems and government’s government’s and the problems, some corrective benefit. There benefit.
contractor’s of a serious actions taken were a few Problems, if corrective nature, for by the minor any, were actions were which contractor were problems, negligible and ineffective corrective satisfactory. which, the were resolved action was only contractor in a timely, marginally resolved in a highly effective effective. timely, manner effective manner.
mailto:Athena.jackson@va.gov
It e m
FACTORS TO BE RATED
E x ce p ti o n al
V er y G o o d
S at is fa ct o ry
M ar g in al
U n sa ti sf ac to ry
(1
N /A
N eu tr al
1 Firm provided experienced managers and disciplines with the administrative and technical abilities needed to meet contract requirements.
2 Firm delegated authority to project managers commensurate with contract requirements. Project manager’s role was clear.
3 Identified risks/problems as they occurred and offered constructive and/or viable solution/alternatives.
4 Was the firm responsive and reasonable to contract changes from the standpoint of timeliness, suggested solutions, and price.
5 Firm displayed a cooperative attitude with company/government personnel before and after award.
6 Firm’s Quality Control procedures and execution were concernment to the project.
7 Were there any claims by subcontractors/suppliers for none payment. If yes, please explain outcome in “Remarks”.
8 How would you rate the firm’s knowledge and thoroughness of site investigation/field analysis?
9 Firm’s team/partner consistently produced quality designs with minimal errors
10 Firm’s team/partner consistently provided plans and specs that were accurate and coordinated ready for construction.
11 Firm’s responsiveness to contract modifications (other than differing site conditions, user changes) during construction for design errors and omissions.
12 Did the firm provide plans that were clear and detailed sufficiently?
13 How would you rate the firm’s ability to achieve cost limitations?
14 Developed, managed, and adhered to realistic schedules and met established project milestones.
15 How would you rate the firm’s solution environmentally suitable for the project?
16 Did the firm use any innovative approaches/technologies on the project? Please provide example under “Remarks”.
17 How well did the firm implement small business subcontracting plan? Applicable to Large Businesses Only
18 Firm corrected deficiencies in a timely manner and pursuant to their quality control procedures.
19 Firm maintained a quality workforce and subcontractors through project completion.
20 How would you rate the firm’s quality of briefings and presentations?
21 Firm’s emphasis on delivering a quality product was apparent in day-to-day operations.
22 Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain outcome in
"Remarks."
23 Would you award another contract to this contractor? If not, explain in "Remarks."
OVERALL ASSESSMENT
24 Overall, on the scale of 1 – 5, how would you rate the contractor being surveyed