Attachment 18 - PWS Enclosure 4-Community Involvement Plan.pdf

PDF 215 KB Posted

Attached to
MISSISSIPPI GROUP OPTIMIZED REMEDIATION CONTRACT AT COLUMBUS AIR FORCE BASE, MISSISSIPPI KEESLER AIR FORCE BASE, MISSISSIPPI
Solicitation number
FA890326R0001
Issued by

About this file

This document is Enclosure 4 of a federal contract opportunity outlining requirements for preparing or updating a Community Involvement Plan (CIP), also known as a Community Relations Plan (CRP), for Department of the Air Force (DAF) environmental restoration activities at military installations.

The contractor must prepare a new CIP or update an existing CIP using the provided DAF template to enable meaningful community involvement in Installation Restoration Program (IRP) and Military Munitions Response Program (MMRP) cleanup activities under CERCLA compliance. The CIP must be prepared early in the CERCLA process prior to the Remedial Investigation (RI) phase, with updates required after the Decision Document/Record of Decision (DD/ROD) is signed, every five years thereafter, and for removal actions with planning periods exceeding six months or activities lasting more than four months. Key requirements include: (1) describing the site including contamination type, extent, human health risks, and environmental concerns; (2) providing a comprehensive community demographic profile and local government structure; (3) conducting a community interest assessment reaching at least one percent of the surrounding population with minimum 100 completed assessments using multiple outreach methods (public notices, social media, websites, press releases, civic leader engagement); (4) identifying key community needs, questions, and concerns; (5) evaluating technical assistance needs such as TAPP grants; (6) developing an action plan with specific outreach activities, strategies, community involvement mechanisms, and project milestones; (7) addressing emerging contaminants like PFAS and off-base contamination impacts; (8) allowing for public comment on draft documents; and (9) consulting with regulatory agencies throughout development. The contractor must deliver one community interest assessment, 100 completed community assessments, one summary table of outreach efforts, minimum one flyer template, one each of public notices, social media announcements, website postings, public service announcements, and press releases, minimum one civic leader engagement, one summary table of community comments, one draft CIP, and one final CIP.

View the file

Other files

File Type Posted
Attachment 22 - FY26 MS Group ORC Document List.pdf PDF
Solicitation Amendment FA890326R00010003 SF 30.pdf PDF
1. Solicitation Amendment No. 0002 SF 30.pdf PDF
2. Amendment No. 0002 Responses.pdf PDF
Attachment 1-Performance Work Statement dated 20260331.pdf PDF
Attachment 19 PWS Enclosure 5_Essential Information-MS Group ORC.pdf PDF
Attachment 13a 2026 DOD Memo Guidance on Destruction or Disposal of Materials Containing PFAS.pdf PDF
Solicitation Amendment FA890326R00010001 SF 30.pdf PDF
Responses QA-RFP_20260406.pdf PDF
Attachment 21 Section M-MS Group ORC Evaluation Criteria-RFO.pdf PDF
Attachment 20 Section L-MS Group ORC Instructions to Offerors-RFO.pdf PDF
Attachment 13a DOD Guidance on Destruction or Disposal of Materials Containing PFAS.pdf PDF
Attachment 17 - PWS Enclosure 1-FY26 ORC Acronyms and Definitions.pdf PDF
Attachment 16a - L1_Labor Category Qualifications.pdf PDF
Attachment 13b - DOD Memorandum-for-Incineration-Prohibition-Policy-Update.pdf PDF
Attachment 4 - Representation by Corporations Regarding Delinquent Tax or a Felony Conviction.pdf PDF
Attachment 3 - Contract Insurance Compliance Notification.pdf PDF
Attachment 2 - MS Group ORC_Base Support Letter_12 March 2025.pdf PDF
Attachment 19-Section L-MS Group ORC Instructions to Offerors.pdf PDF
Attachment 14 - AFCEC Chemistry Data Quality Fact Sheet.pdf PDF
Attachment 12 - Optimization Benefit Template.pdf PDF
Attachment 8 - CPSMR Template.pdf PDF
Attachment 7 - QA Template.xlsx XLSX spreadsheet
Solicitation - FA890326R0001.pdf PDF
Attachment 15 - Guidance on 1-4 Dioxane Environmental Restoration Program.pdf PDF
Attachment 10b - WD 2015-5157 Rev. No. 28 - Columbus AFB.pdf PDF
Attachment 10a - WD 2015-5147 Rev. No. 28 - Keesler AFB.pdf PDF
Attachment 5 - Representation Regarding Certain Telecommunications and Video Surveillance.pdf PDF
Attachment 20-Section M-MS Group ORC Evaluation Criteria.pdf PDF
Attachment 16c-L3_Notice of Non-Government Advisors.pdf PDF
Attachment 16b - L2_Past Performance Questionnaire.docx DOCX document
Attachment 11 - ORC PMP Guidance.pdf PDF
Attachment 9 - Schedule B MS Group.xlsx XLSX spreadsheet
Attachment 6 - Annual Representations and Certifications.pdf PDF
Attachment 1-Performance Work Statement dated 18FEB2026.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ENCLOSURE 4: COMMUNITY INVOLVEMENT PLAN

Background

IAW DoDM 4715.20, §16.a.(1), DERP Management, AFI 32-7020, Environmental Restoration Program, §11.3, installations conducting environmental restoration in accordance with CERCLA shall establish a formal community involvement program, and documented in a Community Involvement Plan (CIP), also known as a Community Relations Plan (CRP).

CIPs address how DoD will conduct outreach about cleanup activities and how the public can participate in decision-making throughout the cleanup process. Installations use their CIP to ensure the community is informed about and involved in the cleanup process. The CIP enables an installation to specify activities that address community needs, concerns, and expectations;

serves as a site-specific strategy for the project team’s outreach activities during the cleanup process to inform and engage community members; educates the affected community about the cleanup program and processes; and provides resources to help the community understand and participate meaningfully in the cleanup process. CIPs provide a strategy to engage community members in the cleanup process and involve them in decisions that may affect their community. CIPs are an effective communications tool. They enable outreach to a broad audience; facilitate DoD interactions and engagement with community members; educate the affected community about the cleanup program and processes so that they can more effectively articulate their concerns and needs; show DoD’s commitment to community outreach and involvement; and promote trust and constructive dialogue.

Specific Tasks

1. The Contractor shall prepare a CIP or update the existing CIP to enable meaningful community involvement using the attached DAF CIP outline/template. CIPs are prepared as early as possible in the CERCLA process, prior to the RI phase and CIP updates are completed after the DD/ROD is signed and every five (5) years thereafter. CIP updates also are required for Removal Actions with planning periods greater than six (6) months and removal activities lasting more than four (4) months. The CIP or the update should discuss community involvement procedures and engagement strategies to ensure the public is afforded an equal opportunity to participate in the DAF’s cleanup program at the installation.

For example, off-base migration of PFAS in groundwater has raised concerns with agricultural operators and other private property owners around some installations and the CIP shall evaluate such impacts and include community engagement strategies to address community concerns.

2. The Contractor shall integrate site-specific emerging contaminant issues (e.g., PFAS) per DoD and DAF policy and directives.

3. The Contractor shall ensure the CIP and all updates:

3.1 Describes the Installation Restoration Program (IRP) and the Military Munitions Response Program (MMRP), as applicable.

3.1.1 Describes the site, including relevant history, type and extent of contamination, human health risks, and environmental exposures and concerns, which are directly related to the site and in a broader sense.

3.2 Describes the community in a comprehensive profile that includes demographic information, local government structure, and any relevant community characteristics

3.2.1 Summarizes past community involvement activity strategies to include how community concerns have been evaluated and addressed.

3.3 Describes the community interest assessment process to include assessment methodology, assessment responses, and recommended community involvement activities. The community assessment must be included as an appendix.

3.3.1 Community interest assessments must be able to reach the community, and installations may want to consider use of one or more of the following tools depending on the makeup of the local community and stakeholders. Consult with the Base PA for best way to reach the community members. The contractor shall assess the interest of community members in the installation RAB and cleanup programs (IRP and/or MMRP) by contacting at least one percent (1%) of the population surrounding the installation and obtaining feedback from at least 100 community members. In rural areas or low population areas, the area may need to be increased to obtain a commensurate number of completed community interest assessments. Installations with off-base contamination need to ensure residents within the impacted area are contacted and given the opportunity to participate during the community assessment process. Estimate the population reached via outreach efforts or the various social media platforms and provide a comprehensive summary of the results in the CIP. Additionally, community outreach efforts and community assessment implementation practices need to be thoroughly documented.

Community Interest Assessment Flyer Template (DAF Document)

• Public Notices – Paid advertising in major publications

• Announcements on social media pages (e.g., Installation Commander or Base

PA’s Facebook page, Twitter)

• Public-facing websites used by Installations

• Public Service Announcements on local media, including radio station

• Press releases to major media

• Civic Leader engagement

3.3.2 Consult the Best Practices for Community Interest Assessments document for additional assistance with developing and describing the community assessment process.

3.4 Identifies key community needs, questions, and concerns as a result of interviews with community members.. This information is also typically collected through community interviews and assessments described in the community profile section of the CIP.

3.5 Discusses the need for technical assistance services and, if appropriate, identifies programs and mechanisms for providing access to technical assistance for communities (such as TAPP grants).

3.6 Includes an Action Plan that specifies the installation’s planned outreach activities, strategies, and community involvement mechanisms, describes the objective and intention of the activity, outlines a projected sequence of project milestones tied to site activities (with projected time frames, whenever possible), and discusses the mechanisms that will be used to explain to the public how community feedback is considered during the cleanup process.

3.7 Identifies any additional special services or approaches that the installation may use to address unique needs of the community. These may include encouraging facilitation or dispute resolution services for community meetings or groupsor supporting an approach for the community to discuss and consider site reuse options.

3.8 Allows for community comment on the draft CIP and updates discusses the mechanisms used to receive and consider feedback before issuing the final CIP or updates (e.g., formal or informal public comments, community meetings, public meetings, etc.).

3.9 Discusses plans to evaluate accomplishments, including a schedule for updating or revising the CIP and updates.

3.10 Consults with regulatory agencies in developing the CIP and updates.

4.0 Deliverable Template

Description How Many Development of Community Interest Assessment 1

Consult with the Base PA (to identify the best methods and/or strategies to reach out to the communities around the installation)

As necessary

Summary Table of Community Outreach Efforts (undertaken to reach the communities around the installation)

Community Outreach Completed Assessments 100 Community Interest Assessment Flyer Template Minimum of 1

Public Notices Minimum of 1 Social Media Announcements Minimum of 1 Public-facing Websites Minimum of 1 Public Service Announcements Minimum of 1 Press Releases Minimum of 1 Civic Leader Engagement Minimum of 1

Summary Table of Community Comments on draft CIP and updates 1 Draft CIP and updates 1 Final CIP and updates 1

References

Best Practices for Community Interest Assessment, 07Feb23, (AFCEC/CZO document)

EPA Superfund Community Involvement Handbook, March 2020, https://semspub.epa.gov/work/HQ/100002505.pdf

EPA Superfund Community Involvement Tools and Resources, https://www.epa.gov/superfund/superfund-community-involvement-tools-and-resources

Public Outreach, CIPs-RABs-TAPP; Per- and Polyfluoroalkyl Substances (PFAS), Environmental Cleanup and Compliance; Department of Defense website:

https://www.acq.osd.mil/eie/eer/ecc/pfas/po/cip-rab-tapp.html https://semspub.epa.gov/work/HQ/100002505.pdf https://www.epa.gov/superfund/superfund-community-involvement-tools-and-resources https://www.acq.osd.mil/eie/eer/ecc/pfas/po/cip-rab-tapp.html

OUTLINE FOR

COMMUNITY INVOLVEMENT PLAN

(Community Relations Plan) i Revision History ii Distribution List iii Table of Contents

1 Introduction

1.1 Purpose

1.2 Overview of the Community Involvement Plan

2 Installation Background

2.1 History of the Installation

2.2 Installation Environmental Program

2.3 Installation Restoration Program (IRP)

2.3.1 IRP Objectives

2.3.2 Current Status

3 Installation Restoration Sites

3.1 General Site Information

3.2 NPL Listing (if applicable)

3.3 Risk Evaluation

3.4 Site Descriptions and Status

3.5 Emerging Contaminates

4 Community Background

4.1 Community Profile

4.2 History of Community Engagement (if applicable)

4.3 Community Interest Assessment (Tools and Methodology)

4.4 Community Concerns

4.4.1 Previous Assessment Results (if applicable)

4.4.3 Prior Activities (if applicable)

4.4.3 Previous Assessment Conclusions and Recommendations (if applicable)

4.4.4 Recent Assessment Results

4.4.5 Recent Assessment Conclusions and Recommendations

5 Community Engagement Program

5.1 Community Engagement Process

5.2 Community Involvement Plan

5.2.1 Key Community Needs and Concerns

5.2.2 Key Communication Methods

5.2.3 Technical Assistance Services, e.g., TAPP (if needed)

5.2.4 Special Services or Approaches (if needed)

5.3 Community Involvement Objectives and Targets (Action Plan)

5.4 Additional Community Involvement Activities (if needed)

5.5 CRP Review and Update Requirements

6 References

7 Acronyms

8 Tables

9 Figures

10 Appendices