This document package includes mechanical drawings and specifications for a mental health building and parking lot project for the Alaska VA Health Care System. Key project details include the construction of a new two-story mental health building, replacement of an existing parking lot, and installation of related mechanical systems. The scope of work covers demolition, HVAC, plumbing, controls, and commissioning. Major equipment includes VRF heat pumps, a heat recovery unit, gas boilers, pumps, expansion tanks, and air handlers. Bidders must meet material and installation standards, obtain permits, and coordinate with other trades. The contract will be awarded on a best value basis.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CEILING AIR TERMINAL (ROUND)
FLEXIBLE DUCT
DUCT DOWN (ROUND)
DUCT UP (ROUND)
CD-1 12X12
100 CFM
PL105
A
DETAIL NUMBER
DRAWING NUMBER WHERE SHOWN
SECTION LETTER
DRAWING NUMBER WHERE DRAWN
PL105
REDUCER OR INCREASER
DIRECTION OF FLOW
SIDE CONNECTION
DIRECTION OF PIPE PITCH (DOWN)
UNION
CAPPED OUTLET
POINT OF CONNECTION BETWEEN NEW AND
STRAINER
BALL VALVE
CHECK VALVE
BUTTERFLY VALVE
MODULATING CONTROL VALVE
THREE-WAY MODULATING CONTROL VALVE
AUTOMATIC OR MANUAL AIR VENT
PIPE OR DUCT BREAK (GRAPHIC ONLY -
COLD WATER PIPING
CONTINUOUS PIPE/DUCT)
(WALL TYPE)
DN
DN
UP
UP EXHAUST DUCT (UP & DOWN)
SUPPLY TOP REGISTER OR GRILLE (WALL TYPE)
EXHAUST OR RETURN CEILING REGISTER OR GRILLE
EXHAUST OR RETURN REGISTER OR TOP GRILLE
DNUP RETURN DUCT (UP & DOWN)
SQUARE 3-WAY CEILING DIFFUSERS
SQUARE 2-WAY CEILING DIFFUSERS
SQUARE 1-WAY CEILING DIFFUSERS
EXHAUST OR RETURN CEILING REGISTER OR GRILLE
ROUND AND SQUARE 4-WAY CEILING DIFFUSERS
SECTION.)
10x8
VANED ELBOW (PROVIDE ALL SQUARE OR
RECTANGULAR ELBOWS WITH VANES EVEN IF
SYMBOL IS MISSING)
STANDARD RADIUS ELBOW (LONG RADIUS)
NEW DUCT (INSIDE DIMENSIONS: WIDTH x DEPTH)
LOUVER (LOUVER SPECIFIED IN ARCHITECTURAL
MANUAL VOLUME DAMPER
SUPPLY
RETURN45°
RETURN, NO SPLITTER (45° TAP)
STANDARD BRANCH SUPPLY OR
45°
COMBINATION FIRE/SMOKE DAMPER
F/S DPR
AUTOMATIC CONTROL DAMPER MODULATING
EXISTING WORK
PUMP
DEMOLITION SCOPE
S
T
DUCT SMOKE DETECTOR LOCATION (DETECTOR
PROVIDED BY DIVISION 16)
THERMOSTAT
TE
TI
PI
M
DP
TEMPERATURE SENSOR
TEMPERATURE GAUGE
PRESSURE GAUGE
MOTOR CONNECTION
DIFFERENTIAL PRESSURE SENSOR
VFD VARIABLE FREQUENCY DRIVE
DIFFUSER CALLOUT ( TYPE, SIZE, CFM)
PLUG VALVE
PETE'S PLUG
CIRCUIT SETTER
STRAINER WITH BLOWDOWN VALVE & 3/4'' HOSE
CONNECTION
DRAIN/BLOWDOWN VALVE WITH 3/4'' HOSE
CONNECTION
SYMBOL
SYMBOL LEGEND
DESCRIPTION SYMBOL DESCRIPTION
RD REFRIGERANT DETECTOR
FS FLOW SWITCH
HE HUMIDITY SENSOR
MANUAL VOLUME DAMPER
COMBINATION FIRE/SMOKE DAMPER
1 HR FIRE RATED WALL
CEILING / WALL ACCESS PANEL
SS SNOW MELT SENSOR
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
12" = 1'-0"
MJ001
463-301
DEC. 7, 2020 JB KT
LEGEND, ABBREVIATION
LIST, AND GENERAL
NOTES
MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
GENERAL NOTES
1. PROVIDE SYSTEM STARTUP, TESTING, & ADJUSTMENTS OF INSTALLED SYSTEMS TO MEET PERFORMANCE
REQUIREMENTS INDICATED IN THE CONTRACT DOCUMENTS.
2. CONTRACTOR SHALL SUPPORT SYSTEM COMMISSIONING AND SHALL COORDINATE WITH PROJECT COMMISSIONING
AGENT.
3. CONTRACTOR SHALL PROVIDE ALL DOCUMENTATION REQUIRED TO SUPPORT SYSTEM COMMISSIONING.
4. CONTRACTOR SHALL OBTAIN AND PAY FOR ALL REQUIRED PERMITS AND CONSTRUCTION FEES. FURNISH COPIES OF
ALL CONSTRUCTION PERMITS, FINAL APPROVED PERMITS, AND SIMILAR DOCUMENTS TO OWNER SHOWING
COMPLIANCE WITH CODE REQUIREMENTS.
5. PROVIDE EACH ZONE WITH THERMOSTATIC CONTROLS THAT PROVIDE A DEADBAND OF AT LEAST 5 DEGREES FAHRENHEIT IN WHICH HEATING AND COOLING ENERGY IS CAPABLE OF BEING SHUT OFF OR REDUCED TO A MINIMUM.
THERMOSTATS AND CONTROLS SHALL BE CAPABLE OF THERMOSTATIC SETBACK, AUTOMATIC SETBACK AND
SHUTDOWN, AND AUTOMATIC START.
6. LOCATE ALL VALVES, TRAPS, TEST PORTS, DAMPERS, CONTROLS, CLEANOUTS, ETC. TO BE ACCESSIBLE FOR MAINTENANCE, ADJUSTMENT, & TESTING. PROVIDE ACCESS PANELS FOR ALL CONCEALED DEVICES. ACCESS PANEL
LOCATIONS SHALL BE COORDINATED WITH ARCHITECT.
7. ALL PIPING & DUCTWORK IN FINISHED ROOMS OR SPACES SHALL BE CONCEALED IN A FURRED CHASE OR ABOVE THE
SUSPENDED CEILING SYSTEM.
8. THE FIRST FIGURE OF DUCT SIZE CALLOUTS INDICATES DIMENSION OF FACE SHOWN OR INDICATED. DUCT SIZES ARE NET INSIDE DIMENSIONS. WHERE DUCT INSULATION OR LINING IS REQUIRED, DUCT SIZE SHALL BE INCREASED TO
MAINTAIN INDICATED NET INSIDE DIMENSIONS.
9. DUCTWORK SHALL BE 2.0" PRESSURE CLASS UNLESS OTHERWISE NOTED ON THESE DRAWINGS.
10. CONSTRUCT DUCTWORK ACCORDING TO INTERNATIONAL ENERGY CONSERVATION CODE SECTION C403.11.2.
11. PROVIDE TURNING VANES IN ALL MITERED RECTANGULAR DUCT ELBOWS & TEES.
12. PROVIDE BALANCING DEVICES ON ALL NEW AIR INLETS & OUTLETS AS WELL AS OUTSIDE AIR BRANCH DUCTS TO
DEVICES.
13. PROVIDE MOTORIZED DAMPERS ON OUTDOOR AIR SUPPLY, EXHAUST OUTLETS, AND RELIEF OUTLETS. DAMPERS SHALL
HAVE A MAXIMUM LEAKAGE RATE OF 4 CFM PER SQUARE FOOT AT 1” W.C.
14. RELIEF GRAVITY DAMPERS SHALL HAVE A MAXIMUM LEAKAGE RATE OF 20 CFM PER SQUARE FOOT AT 1” W.C. DAMPERS
SMALLER THAN 24” IN EITHER DIRECTION SHALL HAVE A MAXIMUM LEAKAGE RATE OF 40 CFM PER SQUARE FOOT AT 1” W.C.
15. ALL SUPPLY AND RETURN DUCTWORK SHALL BE INSULATED PER INTERNATIONAL ENERGY CONSERVATION CODE
SECTION C403.11.1.
16. PROVIDE OUTSIDE AIR DUCTWORK WITH R-12 INSULATION FROM THE BUILDING ENVELOPE TO THE HEAT RECOVERY UNIT. PROVIDE VAPOR BARRIER PER INTERNATIONAL BUILDING CODE METAL FRAMED WALL REQUIREMENTS.
CONSTRUCTED DUCT ASSEMBLY LEAKAGE RATE SHALL NOT EXCEED 0.4 CFM PER SQUARE FOOT AT 0.3” W.C.
17. PROVIDE COMPLETE CONDENSATE DRAINAGE SYSTEM FOR ALL VRF EQUIPMENT, HEAT RECOVERY UNITS, BOILERS, WATER HEATERS, AND FLUES. FIELD ROUTE DRAINAGE PIPING FROM EQUIPMENT TO NEAREST DRAIN LOCATION (SUCH AS SERVICE SINK, FUNNEL DRAIN, ETC.). SLOPE NON-PRESSURIZED DRAIN PIPING TO DRAIN LOCATION. PIPING & FITTINGS SHALL BE TYPE L COPPER WITH BRAZED, SOLDERED, OR PRESS FITTINGS. MINIMUM PIPE SIZE SHALL BE 3/4".
INCREASE PIPE SIZE WHERE APPLICABLE PER IMC 307.2.2.
18. PROVIDE COMPLETE IMC 307.2.3-COMPLIANT SECONDARY CONDENSATE DRAINAGE SYSTEM FOR ALL VRF EQUIPMENT, INCLUDING PIPING, FITTINGS, DRAIN PANS, AND WATER LEVEL DETECTION DEVICES. FIELD ROUTE DRAINAGE PIPING FROM EQUIPMENT TO NEAREST CONSPICUOUS DRAIN LOCATION. COORDINATE DRAIN LOCATION WITH OWNER'S TECHNICAL REPRESENTATIVE. SLOPE NON-PRESSURIZED DRAIN PIPING TO DRAIN LOCATION. PIPING & FITTINGS SHALL BE TYPE L COPPER WITH BRAZED, SOLDERED, OR PRESS FITTINGS. MINIMUM PIPE SIZE SHALL BE 3/4". INCREASE PIPE
SIZE WHERE APPLICABLE PER IMC 307.2.2.
19. SIZE REFRIGERANT PIPING ON VRF AND OTHER REFRIGERANT-BASED SYSTEMS PER EQUIPMENT MANUFACTURER'S
RECOMMENDATION.
20. PROVIDE 10W/FT HEAT TRACE FOR ALL HYDRONIC PIPING, CONDENSATE DRAIN PIPING, & P-TRAPS IN UNHEATED
SPACES OR EXPOSED TO EXTERIOR ENVIRONMENT.
21. TOTAL STATIC PRESSURE NOTED IN SCHEDULES SHALL BE ASSUMED TO INCLUDE DUCT SYSTEM, TERMINAL UNITS, FILTERS, COILS, ETC.
22. ALL SUPPLY AIR FILTERS SHALL BE MINIMUM MERV-8 RATED.
23. ALL RETURN/EXHAUST/OUTSIDE AIR FILTERS SHALL BE MINIMUM MERV-8 RATED.
24. AIR INLET & OUTLET SIZES SHOWN ON PLANS ARE NECK SIZES. PROVIDE ADDITIONAL PANS, HARDWARE, ETC., REQUIRED TO INSTALL AIR INLETS & OUTLETS AT LOCATION SHOWN ON DRAWINGS (IN CEILING SYSTEM, IN WALLS, ON
DUCTWORK, ETC.).
25. WALL REGISTER-TYPE AIR INLETS & OUTLETS SHALL BE INSTALLED AT 7" AFF MINIMUM ELEVATION.
26. AIR INLETS & OUTLETS IN UNFINISHED SPACES OR OPEN CEILING AREAS SHALL BE INSTALLED AT 84" AFF (MINIMUM)
UNLESS OTHERWISE NOTED ON THESE DRAWINGS.
27. WATER PIPE CONNECTIONS TO AIR HEATING AND COOLING COILS SHALL BE MANUFACTURED & CONNECTED IN
COUNTER-FLOW CONFIGURATION BETWEEN WATER & AIR.
28. HYDRONIC HEATING WATER SYSTEMS SHALL BE PROVIDED WITH 40% PROPYLENE GLYCOL BY SYSTEM VOLUME.
29. CHILLED WATER SYSTEMS SHALL BE PROVIDED WITH 40% ETHYLENE GLYCOL BY SYSTEM VOLUME.
30. SNOWMELT HEATING WATER SYSTEMS SHALL BE PROVIDED WITH 50% PROPYLENE GLYCOL BY SYSTEM VOLUME.
31. ALL PRESSURES LISTED ARE GAGE PRESSURES UNLESS OTHERWISE NOTED.
32. PROVIDE MANUAL/AUTOMATIC AIR VENTS AT ALL LOCAL HIGH POINTS FOR HEATING WATER & CHILLED WATER
SYSTEMS.
33. PROVIDE SEISMIC SUPPORT AND ATTACHMENT FOR PIPING, DUCTWORK, AND EQUIPMENT.
34. ALL ELECTRICAL WORK SHALL BE PERFORMED IN ACCORDANCE WITH NFPA 70 STANDARDS AND LOCAL REQUIREMENTS.
35. ALL FIELD WIRING SHALL REQUIRE AN ELECTRICAL PERMIT AND SHALL BE PERFORMED BY A LICENSED ELECTRICIAN.
36. A SHORT DASH IN A SCHEDULE TABLE CELL INDICATES THAT THE COLUMN HEADING IS NOT USED OR NOT APPLICABLE
TO THAT SCHEDULED ITEM.
37. MAINTAIN AND RESTORE (IF INTERRUPTED) ALL CONDUITS & CONDUCTORS, PIPING, & DUCTWORK PASSING THROUGH
RENOVATED AREAS AND SERVICING UNDISTURBED AREAS.
38. REMOVE ALL ABANDONED DUCTWORK, PIPING, CONTROLS, WIRING, ETC., WHERE ACCESSIBLE IN RENOVATED AREAS.
39. WHERE CONTROLS ARE DEMOLISHED, REMOVE WIRING BACK TO NEAREST CONTROL PANEL OR JUNCTION BOX.
REMOVE ACCESSIBLE CONDUIT, JUNCTION BOXES, ETC.
40. OWNER SHALL HAVE FIRST RIGHT OF REFUSAL FOR ALL EQUIPMENT AND COMPONENTS REMOVED DURING
DEMOLITION.
41. COORDINATE ALL MECHANICAL WORK WITH OTHER TRADES TO INSURE PROPER AND ADEQUATE INTERFACE OF THEIR
WORK WITH THE WORK OF MECHANICAL CONTRACTOR. PROVIDE COORDINATED SHOP DRAWINGS FOR APPROVAL
PRIOR TO FABRICATION AND INSTALLATION.
42. REFRIGERANT DETECTORS ARE TO HAVE AN ALARM CONNECTED TO THE DDC SYSTEM.
WB WET BULB
W WATT
W/ WITH
VRF VARIABLE REFRIGERANT FLOW
VOLT VOLTAGE
VFD VARIABLE FREQUENCY DRIVE
VA UNITED STATES DEPARTMENT OF VETERAN'S AFFAIRS
TYP TYPICAL
TEMP TEMPERATURE
T THERMOSTAT
ST STEAM
SQ FT SQUARE FEET
SF SQUARE FEET
SENS SENSIBLE
RPM REVOLUTIONS PER MINUTE
RH RELATIVE HUMIDITY
RD REFRIGERANT DETECTOR
RA RETURN AIR
PVC POLYVINYL CHLORIDE
PSIG POUNDS PER SQUARE INCH GAUGE
PSI POUNDS PER SQUARE INCH
PH PHASE
PD PRESSURE DROP
OSHA OCCUPATIONAL SAFETY & HEALTH ADMINISTRATION
OSA OUTSIDE AIR
OA OUTSIDE AIR
NRC NOISE REDUCTION CRITERIA
NPSHR NOMINAL PUMP SUCTION HEAD REQUIRED
NFPA NATIONAL FIRE PROTECTION ASSOCIATION
N/A NOT APPLICABLE
MRT MEAN RADIANT TEMPERATURE
MOCP MAXIMUM OVERCURRENT PROTECTION
MIN MINIMUM
MFG MANUFACTURER
MERV MINIMUM ENERGY REPORTING VALUE
MCA MINIMUM CIRCUIT AMPACITY
MBH THOUSAND BRITISH THERMAL UNITS PER HOUR
MAX MAXIMUM
LWT LEAVING WATER TEMPERATURE (DEGREES FAHRENHEIT)
LWB LEAVING WET BULB
LDB LEAVING DRY BULB
LBS POUNDS
LAT LEAVING AIR TEMPERATURE (DEGREES FAHRENHEIT)
L LENGTH
KWH KILOWATT PER HOUR
KW KILOWATT
IPLV INTEGRATED PART LOAD VALUE
IPC INTERNATIONAL PLUMBING CODE
IN INCH
IMC INTERNATIONAL MECHANICAL CODE
IEER INTEGRATED ENERGY EFFICIENCY RATIO
HWS HEATING WATER SUPPLY
HWR HEATING WATER RETURN
HSPF HEATING SEASON PERFORMANCE FACTOR
HR HOUR
HP HORSEPOWER
H HEIGHT
GYP GYPSUM
GPM GALLONS PER MINUTE
GHS GLYCOL HEATING SUPPLY
GAL GALLON
G GAS
FT FEET
F/S FIRE SMOKE
FPM FEET PER MINUTE
FLR FLOOR
FLA FULL LOAD AMPERES
EWT ENTERING WATER TEMPERATURE (DEGREES FAHRENHEIT)
EWB ENTERING WET BULB TEMPERATURE (DEGREES FAHRENHEIT)
ESP EXTERNAL STATIC PRESSURE
EFF EFFICIENCY
EER ENERGY EFFICIENCY RATIO
EDB ENTERING DRY BULB TEMPERATURE (DEGREES FAHRENHEIT)
EAT ENTERING AIR TEMPERATURE (DEGREES FAHRENHEIT)
EA EXHAUST AIR
DDC DIRECT DIGITAL CONTROL
DB DRY BULB
CW COLD WATER
COP COEFFICIENT OF PERFORMANCE
CHS CHILLED WATER SUPPLY
CHR CHILLED WATER RETURN
CFM CUBIC FEET PER MINUTE
CF CUBIC FEET
BTUH BRITISH THERMAL UNITS PER HOUR
BTU BRITISH THERMAL UNIT
BFP BACKFLOW PREVENTER
BC BRANCH CIRCUIT CONTROLLER
ASME AMERICAN SOCIETY OF MECHANICAL ENGINEERS
ASHRAE AMERICAN SOCIETY OF HEATING, REFRIGERATION, AND AIR CONDITIONING
ASJ ALL SERVICE JACKET
AMP AMPERES
AFUE ANNUAL FUEL UTILIZATION EFFICIENCY
AFF ABOVE FINISHED FLOOR
A/E ARCHITECT/ENGINEER
ACH AIR CHANGES PER HOUR
(E) EXISTING
°F DEGREES FAHRENHEIT
ABBREVIATIONS LIST
150'0 S
180'0 S
210'0 S
240'0 S
270'0 S
300'0 S
9'0 W
T V
9'0 W
180'0 S
210'0 S
240'0 S
270'0 S
300'0 S
GLAZING NOT SHOWN ON PLANS
H O
S E
B
IB
B
20/14 DN 14/20
12" DIFFUSER (3 TYP)
(E) FINNED TUBE
RADIATORS
(E) FINNED TUBE
RADIATORS
(E) FINNED TUBE
RADIATORS
(E) 20"/14" UP
(E)ACU-15
(E) 1" GHS
(E)1-1/4" GHS
(E)1-1/2" GHS
(E) FINNED TUBE RADIATOR
(E) FINNED TUBE RADIATORS
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
1/8" = 1'-0"
MD101
463-301
DEC. 7, 2020 JB KT
HVAC DEMOLITION PLAN MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
- SCALE:MD101 1/8" = 1'-0"MD101
SECOND FLOOR HVAC DEMOLITION PLAN22
- SCALE:MD101 1/8" = 1'-0"MD101
FIRST FLOOR HVAC DEMOLITION PLAN11
UP
FIRE
SPRINKLER
1A301
ELEVATOR
RM
1A300
STAIRS
STORAGE
1A401
CORRIDOR
C1-1A
CORRIDOR
C1-1B
INTERSTITIAL
SPACE
1A403
MECHANICAL
ROOM
1A402
S300
W9
W0
W32
W33
W34
S21
S22
S23
S270 S240 S210 S180 S150 S120 S90 S60
S24 S25 S26 S27 S28
E31
E30
E29
EXISTING SNOW
MELT SYSTEM
PU-6B
PU-6A
3"ø HWR
3"ø HWS
HX-2
AS-2
AREA OF SNOW MELT SYSTEM
3"ø HWS
3"ø HWR
1 1/2"ø HWS
M-1
M-4
M-3
M-2
1 1/4"ø HWR
2"ø HWR
1 1/4"ø HWS
2"ø HWS M-5
M-6
M-8
M-7
15' - 8"
MECHANICAL VAULT
3"ø HWS
3"ø HWR
1 1/2"ø HWR
MH502
MH502
SS
SS
SS
SS
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
3/32" = 1'-0"
MH101
463-301
DEC. 7, 2020 JB KT
SNOW MELT PLAN MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
- SCALE:MH101 3/32" = 1'-0"MH101
SNOW MELT PLAN11
TRUE
NORTH
PROJECT
NORTH
1. SNOWMELT SYSTEM DESIGN BASED ON 50% PROPYLENE GLYCOL MIXTURE BY VOLUME.
NOTES:
9,100.00 150 1,365,000.00 25.00
(SF) ( °F)
TOTAL AREA BTUH/SF TOTAL BTUH DESIGN DELTA-T
SNOWMELT SYSTEM CALCULATION
SPRINKLER
1A301
ELEVATOR
RM
1A300
STAIRS
STORAGE
1A401
CORRIDOR
C1-1A
CORRIDOR
C1-1B
INTERSTITIAL
SPACE
1A403
MECHANICAL
ROOM
1A402
S300
W9
W0
W32
W33
W34
S21
S22
S23
S270 S240 S210 S180 S150 S120 S90
S24 S25 S26 S27 S28
E31
E30
E29
MH301
IU-19
IU-18
MH302
UH-2
PU-6A
PU-6B
B-2
MH401
WSHP-2
BT-2
HRU-1
PU-9
WH-1
20"x16" OA
20"x16" EA
26"x24" OA
40"x18" OA
UH-3
UH-4 UH-5
UH-1
6"x6" EA
6"x6"EG-2
50 CFM
WC-1
WC-1
WC-1
FSD-4
WSHP-1
FSD-3
20"x16" OA
24"x24" OA
20"x16" EA
MH501
4(TYP)
LOCATION OF FUTURE WATER SOURCE
HEAT PUMPS FOR FIRST FLOOR
B-3
B-1
FSD-5
HX-2
HX-1
8"x6"TG-1
50 CFM
8"x6"TG-1
50 CFM
DC-1
1 HR FIRE WALL (TYP)
OU-1
HU-1
PU-4A
PU-4B
6"Ø OA
6"Ø EA
UH-6
6"x6"EG-2
65 CFM
6"x6"SD-2
65 CFM
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
1/8" = 1'-0"
MH102
463-301
DEC. 7, 2020 JB KT
FIRST FLOOR HVAC PLAN MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
- SCALE:MH102 1/8" = 1'-0"MH102
FIRST FLOOR HVAC PLAN11
TRUE
NORTH
PROJECT
NORTH
OFFICE
COUNSELOR
2A311
SUPERVISOR
OFFICE
2A313
CONSULTATION
OFFICE
2A317
CONSULTATION
OFFICE
2A321
CONSULTATION
OFFICE
2A329
SUPERVISOR
OFFICE
2A312
CONSULTATION
ROOM
2A306
EXAM
ROOM
2A308
EXAM
ROOM
2A309
MULTISTATION
WORK
ROOM
2A305
STORAGE
2A302
CORRIDOR
C2-2F
EXAM
2A330
EXAM
2A332
OFFICE
COUNSELOR
2A331
CONSULTATION
OFFICE
2A333
CONSULTATION
OFFICE
2A335
CONSULTATION
OFFICE
2A334
CONSULTATION
OFFICE
2A345
EXAM
2A348
PATIENT
TOILET
2A325
CORRIDOR
C2-2C
CORRIDOR
C2-2G
ELECTRICAL
2A400
GROUP
THERAPY
2A307
MULTISTATION
WORK
ROOM
2A304
CONSULTATION
ROOM
2A306
CONSULTATION
OFFICE
2A314
CORRIDOR
C2-2D
MH CHIEF
2A310
OFFICE
COUNSELOR
2A315
CONSULTATION
OFFICE
2A323
CONSULTATION
OFFICE
2A327
STAFF
TOILET
2A318
IT/DATA
2A351
TELEHEALTH
2A350
CONSULTATION
OFFICE
2A347
CONSULTATION
OFFICE
2A343
STAFF
TOILET
2A340
BREAK RM
2A339
MULTISTATION
WORK
ROOM
2A338
CONSULTATION
OFFICE
2A342
CONSULTATION
OFFICE
2A336
EXAM
2A346
CONSULTATION
OFFICE
2A344
PATIENT
TOILET
2A324
JANITOR
2A326
STOR.
2A328
WAITING
AREA
2A352
CHECK IN
2A353
CHECK
OUT
2A354
MULTISTATION
WORK
ROOM
2A319
SUPERVISOR
OFFICE
2A320
TELEHEALTH
2A349
CORRIDOR
C2-2E
STORAGE
2A341
CORRIDOR
C2-2C
STAIRS
OFFICE
COUNSELOR
2A322
ELEVATOR
P-3 CORRIDOR
C2-2B
CORRIDOR
C2-2A
S300
W9
W0
W32
W33
W34
S21
S22
S23
S270 S240 S210 S180 S150 S120 S90
S24 S25 S26 S27 S28
E31
E30
E29
MH3011
MH302
6"x6" EA
IU-42
IU-40
IU-38
IU-37
IU-36
IU-35
IU-24IU-23
IU-22IU-21
IU-20
IU-11
IU-10IU-9
IU-8
IU-7
IU-1
IU-3
IU-2
IU-15
IU-16
IU-14
IU-13
IU-12
IU-5
IU-6
IU-17
IU-4
IU-43
IU-29 IU-28
IU-27
IU-30
IU-31
IU-32
IU-33
BC-2.5
IU-25
BC-1
BC-1.5
IU-41
IU-26
BC-2 IU-34
6"Ø OA
10"x10" OA
20"x12" EA
20"x16" EA
10"Ø EA
6"Ø EA
18"x12" OA
10"Ø OA
6"Ø SA
6"Ø EA
8"Ø SA
8"Ø SA
6"Ø OA
12"x10" OA
14"x10" OA
6"Ø OA
10"x10" SA
8"Ø SA
6"Ø OA
6"Ø OA
6"Ø SA
6"Ø SA
14"x10" SA
6"Ø OA
6"Ø RA
6"Ø EA
8"Ø EA
6"Ø EA
10"Ø EA
10"Ø RA
18"x12" RA
10"Ø RA
6"Ø EA
14"x12" OA
32"x32" OA
16"x10" SA
8"Ø SA
8"Ø SA
20"x16" OA
18"x12" OA
8"Ø RA
6"Ø RA
12"x10" OA
10"Ø OA
10"x10" OA
10"Ø OA
10"Ø OA
10"Ø OA
8"Ø OA
6"Ø OA
6"Ø EA
6"Ø EA8"Ø EA
8"Ø EA
10"Ø EA
6"Ø EA6"Ø EA
6"Ø EA6"Ø EA6"Ø EA
6"Ø EA
10"Ø EA
8"Ø EA
6"Ø EA
8"x6" EA
8"Ø OA
6"Ø EA 6"Ø EA
6"Ø OA
8"Ø OA12"x8" OA
6"Ø OA
6"Ø EA
6"Ø EA
6"Ø EA
6"Ø OA
6"Ø OA
8"Ø RA
18"x10" RA
8"Ø OA
6"Ø EA
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T
T T T T T
T TTT
T T T T
TT
T
T
TT
T
T
MH501
4(TYP)
MH501
1(TYP)
MH501
2(TYP)
FSD-2
FSD-1
MH501
3 (TYP)
8"Ø SA
8"Ø RA
6"Ø EA
6"Ø OA
8"Ø SA
8"Ø SA
8"Ø RA
6"Ø EA
12"x8" RA
6"Ø OA
6"Ø OA
16"x10" SA
6"Ø OA
TT
T
8"Ø SA
6"Ø OA
6"Ø OA
6"Ø EA
6"Ø OA
6"Ø EA
14"x12" OA
6"Ø EA
6"Ø OA
6"Ø OA
6"Ø EA
6"Ø OA
6"Ø EA
6"Ø OA
6"Ø EA
6"Ø EA
6"Ø OA
6"Ø OA
8"Ø RA
6"Ø EA
6"Ø OA
6"Ø EA
6"Ø OA
8"Ø EA
6"Ø OA
6"Ø OA
6"Ø OA
6"Ø EA
6"Ø EA
8"Ø EA
6"Ø OA
6"Ø OA
12"x8" OA
8"Ø RA
FSD-6
8"x6" TA
6"Ø OA6"Ø OA
6"Ø OA
6"Ø OA
6"Ø SA
FSD-7
1 HR FIRE WALL (TYP)
FSD-8
6"Ø EA
8"x6" TA
6"Ø EA
12"x10" EA
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
1/8" = 1'-0"
MH103
463-301
DEC. 7, 2020 JB KT
SECOND FLOOR HVAC
PLAN
MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
- SCALE:MH103 1/8" = 1'-0"MH103
SECOND FLOOR HVAC PLAN11
TRUE
NORTH
PROJECT
NORTH
CONSTRUCTION NOTES
1. PROVIDE 5’ OF FLEX DUCT FOR EACH AIR INLET AND OUTLET IN HARD LID OR T-BAR CEILINGS. (TYPICAL)
PLAN NOTES
1 UNDERCUT DOOR TO ALLOW TRANSFER AIR INTO SPACE.
S300
W0
W32
W33
W34
S21
S22
S23
S270 S240 S210 S180 S150 S120 S90
S24 S25 S26 S27 S28
E31
E30
E29
MH301
MH302
IU-12
IU-13
IU-14
IU-9
IU-10
IU-11
IU-8
IU-7
IU-3
IU-2
IU-1
IU-4
IU-5
IU-6
IU-20
IU-21
IU-22
IU-23 IU-24
6"ØSD-1
30 CFM
6"ØEG-1
30 CFM
8"ØSD-1
185 CFM
1 1 13 33
3 3
IU-38
IU-37IU-40
6"x6"SD-2
150 CFM
8"x8"SD-2
225 CFM
8"x8"SD-2
225 CFM
10"x10"RG-2
405 CFM
6"x6"SD-2
65 CFM
6"ØSD-1
30 CFM
3 3
1 1
1 1
8"ØSD-1
185 CFM
IU-15
6"x6"SD-2
150 CFM
6"x6"SD-2
200 CFM
6"x6"SD-2
200 CFM
6"x6"SD-2
200 CFM
6"ØEG-1
30 CFM
6"ØSD-1
30 CFM
6"ØSD-1
30 CFM
3 1
6"x6"SD-2
50 CFM
6"x6"EG-2
100 CFM
6"x6"EG-2
40 CFM
6"x6"SD-2
40 CFM
6"x6"RG-2
45 CFM
6"ØSD-1
30 CFM
1 1
6"ØEG-1
30 CFM
IU-25
IU-36
IU-34
IU-27IU-28
IU-31 IU-32 IU-33
IU-26
IU-30
IU-29
1 1
6"x6"EG-2
80 CFM
6"x6"RG-2
50 CFM
MH501
2(TYP)
20"x20" ACCESS PANEL (TYP)
IU-39
3 4
6"x6"SD-2
45 CFM
6"x6"RG-2
135 CFM
8"x6"TG-1
50 CFM
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
1/8" = 1'-0"
MH104
463-301
DEC. 7, 2020 JB KT
SECOND FLOOR HVAC
CEILING PLAN
MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
TRUE
NORTH
PROJECT
NORTH- SCALE:MH104 1/8" = 1'-0"MH104
SECOND FLOOR HVAC CEILING PLAN11
AIR INLETS & OUTLETS
31 RG-2 8"x8" 140 CFM
32 SD-2 6"x6" 145 CFM
33 SD-2 6"x6" 150 CFM
34 EG-1 6"Ø 150 CFM
35 SD-2 6"x6" 155 CFM
36 RG-1 8"Ø 165 CFM
37 RG-1 6"Ø 180 CFM
38 SD-1 8"Ø 185 CFM
39 SD-1 8"Ø 200 CFM
40 SD-2 6"x6" 200 CFM
41 SD-2 8"x8" 225 CFM
42 RG-2 8"x8" 270 CFM
43 RG-2 10"x10" 405 CFM
44 SD-2 22"x16" 1200 CFM
45 EG-2 22"x22" 1200 CFM
46 L-1 36"x48" 5520 CFM
AIR INLETS & OUTLETS
16 SD-2 6"x6" 50 CFM
17 EG-1 6"Ø 50 CFM
18 EG-2 6"x6" 50 CFM
19 RG-2 6"x6" 50 CFM
20 TG-1 8"x6" 50 CFM
21 SD-2 6"x6" 65 CFM
22 EG-2 6"x6" 65 CFM
23 TG-1 6"x6" 80 CFM
24 EG-2 6"x6" 80 CFM
25 SD-2 6"x6" 100 CFM
26 EG-2 6"x6" 100 CFM
27 SD-2 6"x6" 115 CFM
28 RG-2 8"x8" 130 CFM
29 RG-2 6"x6" 135 CFM
30 SD-1 6"Ø 140 CFM
AIR INLETS & OUTLETS
1 SD-1 6"Ø 30 CFM
2 SD-2 6"x6" 30 CFM
3 EG-1 6"Ø 30 CFM
4 EG-2 6"x6" 30 CFM
5 RG-2 6"x6" 30 CFM
6 SD-1 6"Ø 35 CFM
7 EG-1 6"Ø 35 CFM
8 EG-2 6"x6" 35 CFM
9 SD-2 6"x6" 40 CFM
10 EG-2 6"x6" 40 CFM
11 SD-2 6"x6" 45 CFM
12 RG-1 6"Ø 45 CFM
13 RG-2 6"x6" 45 CFM
14 EG-2 6"x6" 45 CFM
15 SD-1 6"Ø 50 CFM
SPRINKLER
1A301
ELEVATOR
RM
1A300
STAIRS
STORAGE
1A401
CORRIDOR
C1-1A
CORRIDOR
C1-1B
INTERSTITIAL
SPACE
1A403
MECHANICAL
ROOM
1A402
S300
W9
W0
W32
W33
W34
S21
S22
S23
S270 S240 S210 S180 S150 S120 S90
S24 S25 S26 S27 S28
E31
E30
E29
MH301
MH302
IU-19
IU-18
UH-2
MH401
UH-5
UH-4
UH-3
1 1/4"ø HWS
1 1/4"ø HWR
1 1/4"ø HWS 1 1/4"ø HWR
1 1/4"ø HWS
1 1/4"ø HWR 1 1/2"ø HWS
1 1/2"ø HWR
2"ø HWS
2"ø HWR
HRU-1
B-1
AS-1
ET-4
BT-1
B-2
B-3
BT-2
PU-5A
ET-3
PU-4A
PU-4B
AS-3 PU-5B
WSHP-2
ET-2
PU-6B
PU-6A
UH-1
WSHP-1
MH501
5 (TYP)
LOCATION OF FUTURE WATER SOURCE
HEAT PUMPS FOR FIRST FLOOR
RD
RD
3" HWS/HWR DN TO
SNOW MELT MANIFOLD
LOCATION OF BACKFLOW PREVENTERS.
REFER TO PLUMBING PLANS.
2"ø ST
MULTIPLE INJECTION TUBE
SYSTEM FOR HUMIDIFIER
LOCATED IN SUPPLY AIR DUCT
HU-1
1"ø HWS
1"ø HWR
REF
REF
HX-2
HX-1
PU-1
PU-2
PU-3
RD
PU-7
PU-8
M-4
M-3
M-2
DC-1
OU-1
3"ø CWR 3"ø CWS
PU-9
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
1/8" = 1'-0"
MH105
463-301
DEC. 7, 2020 JB KT
FIRST FLOOR HVAC PIPING
PLAN
MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
- SCALE:MH105 1/8" = 1'-0"MH105
FIRST FLOOR HVAC PIPING PLAN11
TRUE
NORTH
PROJECT
NORTH
PLAN NOTES
1 ADD HIGH POINT VENT TO FACILITATE DRAINING AT THIS LOGATION.
OFFICE
COUNSELOR
2A311
SUPERVISOR
OFFICE
2A313
CONSULTATION
OFFICE
2A317
CONSULTATION
OFFICE
2A321
CONSULTATION
OFFICE
2A329
SUPERVISOR
OFFICE
2A312
CONSULTATION
ROOM
2A306
EXAM
ROOM
2A308
EXAM
ROOM
2A309
MULTISTATION
WORK
ROOM
2A305
STORAGE
2A302
CORRIDOR
C2-2F
EXAM
2A330
EXAM
2A332
OFFICE
COUNSELOR
2A331
CONSULTATION
OFFICE
2A333
CONSULTATION
OFFICE
2A335
CONSULTATION
OFFICE
2A334
CONSULTATION
OFFICE
2A345
EXAM
2A348
PATIENT
TOILET
2A325
CORRIDOR
C2-2C
CORRIDOR
C2-2G
ELECTRICAL
2A400
GROUP
THERAPY
2A307
MULTISTATION
WORK
ROOM
2A304
CONSULTATION
ROOM
2A306
CONSULTATION
OFFICE
2A314
CORRIDOR
C2-2D
MH CHIEF
2A310
OFFICE
COUNSELOR
2A315
CONSULTATION
OFFICE
2A323
CONSULTATION
OFFICE
2A327
STAFF
TOILET
2A318
IT/DATA
2A351
TELEHEALTH
2A350
CONSULTATION
OFFICE
2A347
CONSULTATION
OFFICE
2A343
STAFF
TOILET
2A340
BREAK RM
2A339
MULTISTATION
WORK
ROOM
2A338
CONSULTATION
OFFICE
2A342
CONSULTATION
OFFICE
2A336
EXAM
2A346
CONSULTATION
OFFICE
2A344
PATIENT
TOILET
2A324
JANITOR
2A326
STOR.
2A328
WAITING
AREA
2A352
CHECK IN
2A353
CHECK
OUT
2A354
MULTISTATION
WORK
ROOM
2A319
SUPERVISOR
OFFICE
2A320
TELEHEALTH
2A349
CORRIDOR
C2-2E
STORAGE
2A341
CORRIDOR
C2-2C
STAIRS
OFFICE
COUNSELOR
2A322
ELEVATOR
P-3 CORRIDOR
C2-2B
CORRIDOR
C2-2A
S300
W9
W0
W32
W33
W34
S21
S22
S23
S270 S240 S210 S180 S150 S120 S90
S24 S25 S26 S27 S28
E31
E30
E29
MH301
MH302
IU-16
IU-15
IU-42
IU-41
IU-40
IU-38
IU-37
IU-36
IU-34
IU-35
IU-25
IU-24
IU-23IU-22IU-21
IU-20IU-11
IU-10
IU-9
IU-43
IU-29
IU-28
IU-27
BC-2
BC-2.5
IU-33
IU-32
IU-31IU-30
IU-26
IU-14
IU-13
IU-6
IU-12
IU-4
IU-17
IU-5
IU-8
IU-7
IU-1
IU-2
IU-3
BC-1.5
BC-1
REFRIGERANT DN
TO FIRST FLOOR
REFRIGERANT PIPES
DN TO FIRST FLOOR
IU-39
LOCATION OF SOLENOID
VALVES FOR REFRIGERANT
LEAK DETECTION AND
PREVENTION SYSTEM
LOCATION OF SOLENOID VALVES
FOR REFRIGERANT LEAK DETECTION
AND PREVENTION SYSTEM
LOCATION OF SOLENOID VALVES FOR
REFRIGERANT LEAK DETECTION AND
PREVENTION SYSTEM.
LOCATION OF SOLENOID VALVES
FOR REFRIGERANT LEAK DETECTION
AND PREVENTION SYSTEM
RD
RD
RD
RD
RD
RD
RD
RD
RD RD
RD
RD
RD
RD
RD
RD
RD
RD
RD RD RD
RD
RD RD RD RD RD
RD RD RD
RD RD
RD
RDRDRDRD
RD
RD
RD
MH501
5 (TYP)
MH502
2 (TYP)
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
1/8" = 1'-0"
MH106
463-301
DEC. 7, 2020 JB KT
SECOND FLOOR HVAC
PIPING PLAN
MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
- SCALE:MH106 1/8" = 1'-0"MH106
SECOND FLOOR HVAC PIPING PLAN11
TRUE
NORTH
PROJECT
NORTH
PLAN NOTES
1 12"X12" WALL ACCESS PANEL.
2 24"X24" FIRE RATED WALL ACCESS PANEL.
S300
W9
W0
W32
W33
W34
S21
S22
S23
S270 S240 S210 S180 S150 S120 S90
S24 S25 S26 S27 S28
E31
E30
E29
EF-1
LP-1
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
1/8" = 1'-0"
MH107
463-301
DEC. 7, 2020 JB KT
ROOF HVAC PLAN MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
TRUE
NORTH
PROJECT
NORTH
- SCALE:MH107 1/8" = 1'-0"MH107
ROOF HVAC PLAN11
T.O. PARAPET
31' - 8"
SECOND FLR
14' - 6"
FIRST FLR
0' - 0"
IU-17
B-3
B-2 B-1
BT-1 PU-6BPU-6A
IU-1 10"x16" SA 8"Ø SA12"x18" RA6"Ø OA
30"x22" EA
AS-1
BFP-4
BFP-3
BFP-2
BFP-1
AS-2
AS-3
ET-4
6"Ø EA 10"Ø RA
6"Ø OA
3"ø HWS
3"ø HWR
HX-2
HX-1
HU-1
ET-3
2 1/2"ø HWR
2 1/2"ø HWS
3/4"ø HWS
3/4"ø HWR
3"ø HWS
3"ø HWS
3"ø HWS
3"ø HWS
ET-2
3"ø HWS
3"ø HWR
WC-1
1"ø G
1"ø G1"ø G
6"Ø OA
8"Ø EA
2 1/2"ø HWS
PU-3
4"ø HWS
3"Ø EA
3"Ø OA
2"ø ST
3/4"ø COND
3/4"ø COND
REF
1 1/2"ø HWS
1 1/2"ø HWR
M-1
M-2
2"ø HWS
2"ø HWR
T.O. BEAM
29' - 8"
SECOND FLR
14' - 6"
FIRST FLR
0' - 0"
LP-1
18"x12" OA
16"x20" OA
6"Ø OA
8"Ø EA
16"x20" EA
24"x26" OA
IU-12
16"x20" EA
24"x24" OA
24"x26" OA
16"x20" OA
FSD-3
HRU-1
1 1/4"ø HWR
1 1/4"ø HWS
PU-7
4"ø HWR
PU-4B
PU-4A
16"x10" SA
8"Ø SA
8"Ø OA
22"x16"SD-2
1200 CFM
2"ø ST
3"ø HWR
3"ø HWS
1 1/2"ø HWS
4"ø HWS
ET-4
3"Ø EA
3"Ø OA
AS-1
4"ø HWS
BT-1
22"x22"EG-2
1200 CFM
REFRIGERANT PIPING
HU-1
HUMIDIFIER MULTIPLE
INJECTION TUBE SYSTEM
32"x24" OA
REF
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
1/4" = 1'-0"
MH301
463-301
DEC. 7, 2020 JB KT
MECHANICAL SECTIONS MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
- SCALE:MH301 1/4" = 1'-0"MH301
MECHANICAL SECTION 111
- SCALE:MH301 1/4" = 1'-0"MH301
MECHANICAL SECTION 222
T.O. PARAPET
31' - 8"
SECOND FLR
14' - 6"
FIRST FLR
0' - 0"
W32 W33 W34
HRU-1
18"x40" OA
22"x30" EA
22"x16"SD-2
1200 CFM
BT-2
WSHP-1
WH-1
UH-1
WSHP-2
12"x18" OA
30"x22" EA
24"x26" EA
12"x14" OA
IU-2
LOCATION FOR FUTURE WATER SOURCE
HEAT PUMPS FOR FIRST FLOOR
6"Ø EA
24"x24" OA
24"x24" EA
26"x24" OA
18"x40" OA
8"Ø OA
22"x22"EG-2
1200 CFM
PU-9
PU-5B
PU-5A
2 1/2"ø HWS
2 1/2"ø HWR1 1/4"ø HWS
3/4"ø HWR
3/4"ø G
3"Ø EA
BFP-4
BFP-3
BFP-2
BFP-1
20"x16" OA
6"Ø OA
3/4"ø COND6"Ø EA
HUMIDIFIER MULTIPLE
INJECTION TUBE SYSTEM
2 1/2"ø HWS
2 1/2"ø HWR
3"ø HWS
2"ø ST
1 1/2"ø HWS
1 1/2"ø HWR
REFRIGERANT CONNECTIONS
TO/FROM OU-1
REF
REF
REF
REF
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
1/4" = 1'-0"
MH302
463-301
DEC. 7, 2020 JB KT
MECHANICAL SECTIONS MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
- SCALE:MH302 1/4" = 1'-0"MH302
MECHANICAL SECTION 111
ELEVATOR
RM
1A300
MECHANICAL
ROOM
1A402
W32 W33 W34
S21
MH301
MH302
HRU-1
BT-2
WSHP-2
WSHP-1
PU-5A
PU-5B
B-3
B-2
B-1
BT-1
AS-1
ET-4
PU-4A
PU-4B
ET-3
AS-3
ET-2
PU-6A
PU-6B
PU-9
AS-2
2"ø HWR
2"ø HWS
6"Ø OA
6"Ø OA
6"Ø OA
4"ø HWR
2 1/2"ø HWR
3/4"ø HWR
3/4"ø HWS
UH-1
BFP-1
BFP-3
BFP-4
BFP-2
3" CWS/CWR
TO DC-1
3"ø CWS
3"ø CWR
8"Ø EA
8"Ø EA
8"Ø EA
2 1/2"ø HWR
26"x24" OA
20"x16" EA
40"x18" OA
24"x24" OA
24"x24" EA
WC-1
WC-1
WC-1
30"x22" EA
22"x16"SD-2
1200 CFM
WH-1
6"x6"EG-2
50 CFM
1"ø HWS
1"ø HWR
20"x16" OA
PU-7
REFRIGERANT UP
REFRIGERANT
PIPES UP
LOCATION FOR FUTURE WATER SOURCE
HEAT PUMPS FOR FIRST FLOOR
3"ø HWS
3"ø HWS
2 1/2"ø HWR2 1/2"ø HWS
1 1/2"ø HWS
3"Ø EA
2"ø ST
3"Ø EA
PU-3
PU-2
PU-1
3"Ø OA
36"x48"L-1
5520 CFM
4"ø HWR 3"ø HWR
4"ø HWS
3"ø HWR
3"ø HWR
3"ø HWS
3"ø HWS 3"ø HWR
1 1/2"ø HWR
1 1/2"ø HWS
HX-1
HX-2
2 1/2"ø HWR
2"ø HWR
HU-1
MH301
REF
M-1
1 1/2"ø HWS
1 1/2"ø HWR
M-4
M-3
M-2
PU-8
CP-1
REF PIPES
TO OU-1
VFD-2
VFD-1
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
3/8" = 1'-0"
MH401
463-301
DEC. 7, 2020 JB KT
ENLARGED MECHANICAL
ROOM HVAC PLAN
MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
TRUE
NORTH
PROJECT
NORTH
- SCALE:MH401 3/8" = 1'-0"MH401
ENLARGED MECHANICAL ROOM HVAC PLAN 1ST11
PLAN NOTES
1 1-1/4" STEAM DOWN TO MULTIPLE INJECTION TUBE SYSTEM IN
DUCT. PROVIDE WITH DRAINAGE PER MANUFACTURER'S
RECOMMENDATIONS.
UNIT MOUNTING BRACKETS, TYP. 4.
PROVIDE DOUBLE NUTS AND WASHERS EACH
SIDE OF MOUNTING BRACKET, TYP.
CEILING PER ARCHITECTURAL DRAWINGS.
HANGING ROD, TYP. 4
SUPPLY DUCT.
RETURN DUCT.
NUTS AND WASHERS, TYP.
STRUT CHANNEL TO SPAN A
MINIMUM OF 2 FLUTES.
3/8" BOLT.
CHANNEL NUT.
CHANNEL STRUT.
METAL DECK.
FINISHED FLOOR OR ROOF
DECKING AS APPLICABLE.
INSULATION FILLER MATERIAL.
1/8" DIAMETER
AIRCRAFT CABLE.
1 MIN.
2 MAX.
18 GAGE BENT PLATE
CLIP 1-1/2" x 3/4".
LOOP ON CABLE OVER WIRE
ROPE THIMBLE. SECURE 3/8"
DIAMETER PIN SHACKLE TO
CLIP.
CABLE CLAMP, TYP.
SPRING VIBRATION ISOLATORS
IN CEILING
CASSETTE
1 MIN.
2 MAX.
ELECTRICAL AND CONTROLS
CONNECTION JUNCTION BOX.
1/8" DIAMETER
AIRCRAFT CABLE.
18 GAGE BENT PLATE
CLIP 1-1/2" x 3/4".
REFRIGERANT LINES.
COORDINATE SIZES IN FIELD.
CONDENSATE DRAIN. COORDINATE SIZE
AND ROUTING IN FIELD.
6" DIAMETER COLLAR FOR
OUTSIDE AIR DUCT
CONNECTION
LOOP ON CABLE OVER WIRE
ROPE THIMBLE. SECURE 3/8"
DIAMETER PIN SHACKLE TO
CLIP.
CABLE CLAMP, TYP.
UNIT MOUNTING BRACKETS, TYP. 4
PROVIDE DOUBLE NUTS AND WASHERS
EACH SIDE OF MOUNTING BRACKET, TYP
CEILING PER ARCHITECTURAL DRAWINGS.
INDOOR UNIT
PLAN VIEWHANGER ROD, TYP. 4
3/8" BOLT.
CHANNEL NUT.
CHANNEL STRUT.
METAL DECK.
FINISHED FLOOR OR ROOF
DECKING AS APPLICABLE.
INSULATION FILLER MATERIAL.
NOTE:
1. WHERE UNIT IS MOUNTED IN A WOOD OR METAL STUD FRAMED BUILDING, CONTRACTOR IS TO PROVIDE ADDITIONAL FRAMING MEMBERS IN ORDER TO MOUNT UNIT WITH ALL REQUIRED SUPPORTS AND CLEARANCES.
1" MAX.
MOUNTING BRACKET,
TYP.
1/8" DIAMETER
AIRCRAFT CABLE, TYP.
SPRING VIBRATION
ISOLATORS
METAL DECK
FINISHED FLOOR OR ROOF DECKING AS APPLICABLE
INSULATION FILLER MATERIAL
16 GAUGE x 1" WIDE
HANGER STRAP.
3/16" DIAMETER SELF-TAPPING
SHEET METAL SCREWS, TYP.
SECURE EACH STRAP TO DUCT
WITH (2) #10 SELF TAPPING SHEET
METAL SCREWS.
SUPPLY DUCT. SEE
PLANS FOR DUCT SIZE.
NOTE:
1. PROVIDE AND CONSTRUCT DUCT HANGERS AND SUPPORTS PER 2006 SMACNA HVAC DUCT CONSTRUCTION STANDARDS FIGURE 5-5.
2. LENGTH OF SUPPORTS, STRAP SIZES, AND SIZES OF STEEL ANGLES AS REQUIRED FOR DUCT SIZE AND CONFIGURATION.
3. MAXIMUM 10' SPACING BETWEEN SUPPORTS.
METAL DECK
FINISHED FLOOR OR ROOF DECKING AS APPLICABLE
INSULATION FILLER MATERIAL
16 GAUGE x 1" WIDE
HANGER STRAP.
3/16" DIAMETER SELF-TAPPING
SHEET METAL SCREWS, TYP.
SECURE EACH STRAP TO DUCT
WITH (2) #10 SELF TAPPING SHEET
METAL SCREWS.
SUPPLY DUCT. SEE
PLANS FOR DUCT SIZE.
SPRING VIBRATION
ISOLATORS SPRING VIBRATION
ISOLATORS
FLANGED DUCT OR BULKHEAD
COMBINATION FIRE/SMOKE DAMPER
ASTME 119 ON 4L
263 RATED CAULKING
ACTUATOR
FASTNER PER MANUFACTURER'S
RECOMMENDATIONS
1-1/2"X 1-1/2"X 1/8" ANGLE
ASTME 119 ON 4L 263
RATED CAULKING
CEILING PER
ARCHITECTURAL DRAWINGS
STRUCTURE
STUD
CEILING PER
ARCHITECTURAL DRAWINGS
PIPE INSULATION
PIPE HANGER
RIGID INSULATION
6" MIN
10" MIN
PIPE INSULATION
PIPE
THREADED ROD;
ATTACH TO STRUCTUREGALVANIZED METAL OR RUBBER SHIELD
BETWEEN HANGER AND INSULATION UP TO
CENTERLINE OF PIPE
LOCK NUT
TURNBUCKLE
STEEL STRAP
INSULATION
STEEL CLEVIS
DOMESTIC WATER PIPE 18 GA. SM SHEILD
RIGID INSULATION
PIPE HANGER
6" MIN
PIPE
THREADED ROD;
ATTACH TO STRUCTURE
PLASTIC PIPE
PROVIDE RUBBER OR GALVANIZED PIPE SHIELD TO
PROTECT PLASTIC PIPING (PIPE SHIELDS SHALL
SURROUND ENTIRE PIPE CIRCUMFERENCE)
PLASTIC PIPE
PROVIDE RUBBER OR GALVANIZED PIPE SHIELD TO
PROTECT PLASTIC PIPING (PIPE SHIELDS SHALL
SURROUND ENTIRE PIPE CIRCUMFERENCE)
PROVIDE RUBBER OR GALVANIZED
PIPE SHIELD TO PROTECT PLASTIC
PIPING (PIPE SHIELDS SHALL
SURROUND ENTIRE PIPE
CIRCUMFERENCE)
TURNBUCKLE
STEEL STRAP
PIPING (TYP)
LOCKING NUTS TOP
AND BOTTOM
PROVIDE INSULATION ON
PIPE MOUNTING STRAP
PIPE MOUNTING STRAP (TYP)
UNISTRUT CHANNEL
COORDINATE WITH
NUMBER OF PIPES
EXHAUST DUCT SEE
PLANS FOR SIZE.
UNIT SEALING
GASKET.
WOOD NAILER PER
MANUFACTURER.
MINIMUM 26 GAUGE SHEET
METAL COUNTER
FLASHING.
RIGID INSULATION ALL
SIDES OF CURB.
STRUCTURAL FRAMING AT
ROOF PENETRATION. REFER
TO 11/SF FOR ADDITIONAL
INFORMATION.
FINISHED ROOF.
ROOF DECKING AND
INSULATION
INFILLING.
STRUCTURAL FRAMING AT ROOF
PENETRATION. REFER TO 3/SF
501 FOR ADDITIONAL
INFORMATION.
LOW LEAK AUTOMATIC
CLOSE-OFF DAMPER
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
As indicated
MH501
463-301
DEC. 7, 2020 JB KT
DETAILS MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
SCALE: NONEMH501
CEILING CONCEALED INDOOR UNIT MOUNTING DETAIL11
SCALE: NONEMH501
INDOOR UNIT CASSETTE MOUNTING DETAIL22
SCALE: NONEMH501
TYPICAL DUCT SUPPORT DETAIL44
SCALE: NONEMH501
COMBINATION FIRE/SMOKE DAMPER DETAIL33
SCALE: NONEMH501
MECHANICAL PIPE SUPPORT55
SCALE: NONEMH501
ROOF MOUNTED EXHAUST FAN DETAIL66
2" ALUMINUM "PRESS-LOCKED"
BAR GRATING PER STRUCTURAL
DRAWING 10/SF521.
ANTI-VIBRATION RUBBER PAD.
PAD TO COVER THE ENTIRE
WIDTH OF EACH UNIT LEG.
TYPICAL HEAT PUMP.
PROVIDE DOUBLE NUT AT
EACH ATTACHMENT POINT.
BEAM PER PLANS.
METAL ROOF DECK PER PLANS.
FINISHED ROOF DECK PER PLANS.
PRE-MOLDED TYPE SLEEVE PENETRATION.
REFER TO ARCHITECTURAL DRAWING 5/AE501.
3" DIAMETER SUPPORTING TUBE STEEL.
6" x 3" x 3/16" STEEL PLATE TYPICAL
BOTH SIDES OF VIBRATION ISOLATOR,
PROVIDE PLATES WITH PRIMER
FINISH PRIOR TO INSTALLATION.
MINIMUM 3/8" DIAMETER x 4" CADMIUM
PLATED BOLT WITH WASHER EACH
SIDE OF EACH BOLT, TYPICAL 2
LOCATIONS EACH ISOLATOR.
REFRIGERANT DETECTOR WITH
AUDIO ALARM TO BE LOCATED 1'-0"
AFF. CONNECT TO DDC SYSTEM.
VISUAL INDICATOR FOR REFRIGERANT
DETECTION SYSTEM. LOCATE IN AN AREA THAT IS
EASILY VISIBLE AND 2'-0" FROM CEILING.
FINISHED CEILING
FINISHED FLOOR
TYPICAL ROOM SERVED
BY VRF SYSTEM
CONCRETE SLABWIRE TIE
SLAB INSULATION
EDGE INSULATION
PEX TUBING
WIRE MESH, REBAR OR
STAPLE TO RIGID FOAM
SLAB
STAINLESS-STEEL
MANIFOLD
ISOLATION VALVE BODY
COIN AIR VENT
MOUNTING BRACKET
FILL VALVE
STAINLESS-STEEL
MANIFOLD FLOW METER
PEX TUBING
PROPEX FITTING ASSEMBLIES
STAINLESS-STEEL MANIFOLD
PROPEX BRASS MALE THREADED ADAPTER
STAINLESS-STEEL MANIFOLD
SUPPLY/RETURN BALL VALVE, SET OF 2
TEMPERATURE GAUGE
SHEET METAL CAN SAME
SIZE AS DIFFUSER NECK
T-BAR/HARDLID
COLLAR
FLEXABLE DUCT
AIR TERMINAL
NOTE:
USE THIS TYPE OF CONNECTION IN
CONSTRICTED CELING SPACES
NOTE:
USE THIS TYPE OF CONNECTION WHERE
THERE IS ENOUGH CEILING SPACE TO
KEEP KINKS OUT OF FLEXABLE DUCT
FLEXABLE DUCT
AIR TERMINAL
T-BAR/HARDLID
SQUARE TO ROUND
TRANSISTION WALL
COVERPLATE
JBOX
CONDUIT & WIRING
TO CONTROL SYSTEM
CONCRETE FLOOR
ASSEMBLY
RADIANT HEATING
LOOP LINE (TYP)3/4" COPPER CONDUIT
TEMPERATURE SENSING
ELEMENT
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
As indicated
MH502
463-301
DEC. 7, 2020 JB KT
DETAILS MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
SCALE: NONEMH502
HEAT PUMP MOUNTING DETAIL11
SCALE: NONEMH502
REFRIGERANT DETECTOR AND INDICATOR DETAIL22
SCALE: NONEMH502
SNOW MELT SYSTEM SLAB DETAIL33
SCALE: NONEMH502
SNOW MELT MANIFOLD DETAIL44
SCALE: NONEMH502
AIR TERMINAL DETAIL66
SCALE: NONEMH502
FLOOR TEMPERATURE SENSOR INSTALLATION DETAIL55
Location
Issue Date
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
MH601
463-301
DEC. 7, 2020 JB KT
SCHEDULES MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
THE PRODUCTS OR SERVICES IN THE BASIS OF DESIGN AND EQUIPMENT/PRODUCT
SCHEDULES ON THIS DRAWING WERE PURPOSELY SELECTED BY THE A/E TO MEET
THE OWNERS PROGRAMMING REQUIREMENTS AND ARE NOT BEING "SOLE-
SOURCED" BY THE VA UNLESS NOTED OTHERWISE. OTHER MANUFACTURERS WITH
EQUAL SALIENT CHARACTERISTICS, EQUAL QUALITY, EQUAL LEAD TIMES, AND
EQUAL MAINTENANCE COSTS MAY USE THOSE PRODUCTS OR EQUIPMENT TO BID
AND CONSTRUCT THE PROJECT. BIDDERS SHALL CONTACT THE A/E VIA THE VA
PROJECT CONTRACTING OFFICER DURING THE BID PHASE FOR APPROVAL OF THE
SUBSTITUTION REQUEST ON EACH ITEM. IN THE EVENT A CONTRACTOR IS
AWARDED THE PROJECT WITHOUT OBTAINING VA APPROVAL OF THE SUBSTITUTION
REQUEST DURING THE BID PHASE AND THE SHOP DRAWINGS AND SUBMITTALS OF
ALTERNATE MANUFACTURERS ARE NOT APPROVED BY THE A/E OR THE VA THEN
THE CONTRACTOR MUST INSTALL THE BASIS OF DESIGN PRODUCTS OR SERVICES
AT THE CONTRACTOR'S EXPENSE. NON-APPROVED PRODUCTS OR SERVICES ARE
AT THE CONTRACTOR'S RISK AND NO EQUITABLE ADJUSTMENT TO TIME OR MONEY
WILL BE MADE FOR COST DIFFERENCES BETWEEN APPROVED VERSUS NON-
APPROVED AFTER BIDDING HAS BEEN CLOSED. ALLOW SEVEN CALENDAR DAYS
BEFORE BIDS ARE DUE TO OBTAIN APPROVAL.
BASIS OF DESIGN NOTES
2. NOMINAL HEATING CAPACITIES ARE BASED ON INDOOR COIL EAT OF 70 °F (DB).
1. NOMINAL COOLING CAPACITIES ARE BASED ON INDOOR COIL EAT OF 80/67 °F (DB/WB).
NOTES:
WSHP-2 BC-2, BC-2.5 MITSUBISHI TQRY-P1204AL41AN 10 120,000 135,000 25.4 8.0 15.6 5.6 460 3 - 13 20 406 1, 2
WSHP-1 BC-1, BC-1.5 MITSUBISHI TQRY-P1204AL41AN 10 120,000 135,000 25.4 8.0 15.6 5.6 460 3 - 13 20 406 1, 2
TONS (BTUH) (BTUH) (FT) VOLT PHASE FLA MCA MOCP (LBS)
SYMBOL SERVICES MANUFACTURER MODEL NOMINAL NOMINAL COOLING NOMINAL HEATING GPM PD EER COP ELECTRICAL WEIGHT NOTES
VRF WATER SOURCE HEAT PUMP SCHEDULE
4. DUCT SMOKE DETECTOR SHALL BE COMPATIBLE WITH FIRE ALARM SYSTEM. REFER TO DIVISION 26 FOR FIRE ALARM REQUIREMENTS.
3. PROVIDE WITH ACTUATORS & FUSIBLE LINKS.
2. PROVIDE ADDRESSIBLE TYPE DUCT SMOKE DETECTOR WITH EACH DAMPER PER APPLICABLE CODE REQUIREMENTS.
1. ALL WIRING & SAFETY INTERLOCKS SHALL BE PROVIDED BY EC.
NOTES:
FSD-8 GREENHECK FSD-331 3 HR 8 6 - 6 120 1 - 1,2,3,4
FSD-7 GREENHECK FSD-331 3 HR 8 6 - 6 120 1 - 1,2,3,4
FSD-6 GREENHECK FSD-331 3 HR 8 6 - 6 120 1 - 1,2,3,4
FSD-5 GREENHECK FSD-331 3 HR 8 6 - 6 120 1 - 1,2,3,4
FSD-4 GREENHECK FSD-331 3 HR 20 16 - 6 120 1 - 1,2,3,4
FSD-3 GREENHECK FSD-331 3 HR 20 16 - 6 120 1 - 1,2,3,4
FSD-2 GREENHECK FSD-331 3 HR 20 16 - 6 120 1 - 1,2,3,4
FSD-1 GREENHECK FSD-331 3 HR 20 16 - 6 120 1 - 1,2,3,4
W H DIA THICKNESS (IN) VOLT PHASE AMPS
SYMBOL MANUFACTURER MODEL TYPE DUCT SIZE (IN) WALL/FLOOR ELECTRICAL NOTES
FIRE/SMOKE DAMPER SCHEDULE
7. REFER TO THE HEAT RECOVERY UNIT SCHEDULE FOR OUTSIDE AIR TEMPERATURES AND CONDITIONS.
6. INDOOR UNITS ARE EQUIPED WITH AN INTERNAL WATER LEVEL DETECTION DEVICE CONFORMING TO UL 508 PER IPC 314.2.3.
5. THE CORRECTED CAPACITIES INCLUDE THE DE-RATE ASSOCIATED WITH INDOOR UNITS VS. OUTDOOR UNITS CONNECTED CAPACITY INDICATED ON THE OUTDOOR UNIT SCHEDULE FOR ASSOCIATED SYSTEMS.
4. SEE SCHEMATIC PIPING/CONTROL DIAGRAM FOR INDICATION OF REQUIRED INDOOR UNIT REMOTE CONTROLLERS, SYSTEM CONTROLLERS, AND INTEGRATION DEVICES.
3. SEE OUTDOOR UNIT SCHEDULE FOR OUTDOOR AMBIENT CONDITIONS, CONNECTED CAPACITY, AND OTHER FACTORS ASSOCIATED WITH CORRECTED CAPACITIES.
2. NOMINAL HEATING CAPACITIES ARE BASED ON INDOOR COIL EAT OF 70 °F (DB), OUTDOOR OF 43 °F (WB).
1. NOMINAL COOLING CAPACITIES ARE BASED ON INDOOR COIL EAT OF 80/67 °F (DB/WB), OUTDOOR AMBIENT TEMPERATURE OF 95 °F (DB).
NOTES:
IU-43 BC-1.5 MITSUBISHI TPEFY-P006MA143A CEILING CONCEALED 300 0.6 6 5.6 5.6 80 / 67 55 75 6.7 - 70 / 43 95 70 100 208 1 1.05 15 49 1, 2, 3, 4, 5, 6, 7
IU-19 BC-1 MITSUBISHI TPKFY-P030KM142A WALL MOUNTED 918 - 30 28.47 21.47 80 / 67 55 75 34 - 70 / 43 95 70 80 208 1 0.63 15 46 1, 2, 3, 4, 5, 6, 7
IU-18 BC-1 MITSUBISHI TPKFY-P006BM142B WALL MOUNTED 208 - 6 5.6 4.1 80 / 67 55 75 6.7 - 70 / 43 95 70 - 208 1 0.19 15 22 1, 2, 3, 4, 5, 6, 7
IU-17 BC-1 MITSUBISHI TPEFY-P018143A CEILING CONCEALED 600 0.6 18 17 13.3 80 / 67 55 75 20 - 70 / 43 95 70 165 208 1 1.56 15 58 1, 2, 3, 4, 5, 6, 7
IU-16 BC-1 MITSUBISHI TPEFY-P006MA143A CEILING CONCEALED 300 0.6 6 5.6 5.6 80 / 67 55 75 6.7 - 70 / 43 95 70 100 208 1 1.05 15 49 1, 2, 3, 4, 5, 6, 7
IU-15 BC-1 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 150 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-14 BC-1.5 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-13 BC-1 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-12 BC-1 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-11 BC-1.5 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-10 BC-1.5 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-9 BC-1 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-8 BC-1 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-7 BC-1 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-6 BC-1 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-5 BC-1 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-4 BC-1 MITSUBISHI TPMFY-P06BM140F CEILING 1 WAY CASSETTE 305 - 6 5.6 4.9 80 / 67 55 75 6.7 - 70 / 43 95 70 80 208 1 0.25 15 38 1, 2, 3, 4, 5, 6, 7
IU-3 BC-1 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-2 BC-1 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-1 BC-1 MITSUBISHI TPLFY-P005140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
CFM ESP
NOMINAL MBH
(TOTAL)
CORRECTED MBH
(TOTAL)
CORRECTED MBH
(SENSIBLE)
EDB / EWB
DESIGN SUPPLY
TEMP
ROOM SETPOINT TEMP MBH (TOTAL)
CORRECTED MBH
(TOTAL)
EDB / EWB DESIGN SUPPLY TEMP
ROOM
SETPOINT
OA VOLT PHASE MCA MOCP (LBS)
SYMBOL SERVED BY MANUFACTURER MODEL TYPE SUPPLY FAN COOLING HEATING MIN ELECTRICAL WEIGHT NOTES
WSHP-1 - VRF INDOOR UNIT SCHEDULE
1. VIBRATION ISOLATOR TYPES REFERENCE SPECIFICATION SECTION 23 05 41.
NOTES:
IU-XX VRF INDOOR UNITS S 0.75 1
OU-1 CONDENSING UNIT SS 0.75 1
DC-1 DRY COOLER SP 0.75 1
PU-6A/6B BASE-MOUNTED PUMPS D, L, OR W - 1
PU-4A/4B/5A/5B/9 INLINE PUMPS S 0.75 1
SYMBOL TYPE DEFLECTION (IN)
EQUIPMENT EQUIPMENT TYPE VIBRATION ISOLATOR MIN NOTES
EQUIPMENT VIBRATION ISOLATION SCHEDULE
2. WEIGHT INDICATED IS OPERATING WEIGHT.
1. PROVIDE WITH DRAIN VALVE WITH 3/4" HOSE CONNECTION.
NOTES:
CF-3 JL WINGERT DB-5HD BYPASS FEEDER SNOWMELT LOOP 6.3 - 200 - - - - 90 1,2
CF-2 JL WINGERT DB-5HD BYPASS FEEDER VRF HYDRONIC LOOP 6.3 - 200 - - - - 90 1,2
CF-1 JL WINGERT DB-5HD BYPASS FEEDER BOILER LOOP 6.3 - 200 - - - - 90 1,2
(GAL) (GPD) PRESS (PSI) VOLT PHASE MCA MOCP (LBS)
SYMBOL MANUFACTURER MODEL TYPE SERVICE CAP OUTPUT MAX ELECTRICAL WEIGHT NOTES
CHEMICAL FEEDER SCHEDULE
Project Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
FACILITY
MANAGEMENT
SERVICE
(FMS)
Phase
Scale
Revisions: Date:
100% CONSTRUCTION
SUBMITTAL
A/E: STAMP
HOOD RIVER ENGINEERS
1784 MAY STREET
HOOD RIVER, OR 97031
541-436-4723
ADAM GODDIN, PE
VA FORM 08 - 6231
A
B
C
D
E
321 4 5 6 7 8 9 10 11 12
321 4 5 6 7 8 9 10 11 12
F
G
H
12/07/2020100% CONSTRUCTION SUBMITTAL
MH602
463-301
DEC. 7, 2020 JB KT
SCHEDULES MENTAL HEALTH BUILDING AND
PARKING LOT
AVAHS Muldoon Clinic
1201 N. MULDOON RD, ANCHORAGE AKDEC. 7, 2020
THE PRODUCTS OR SERVICES IN THE BASIS OF DESIGN AND EQUIPMENT/PRODUCT
SCHEDULES ON THIS DRAWING WERE PURPOSELY SELECTED BY THE A/E TO MEET
THE OWNERS PROGRAMMING REQUIREMENTS AND ARE NOT BEING "SOLE-
SOURCED" BY THE VA UNLESS NOTED OTHERWISE. OTHER MANUFACTURERS WITH
EQUAL SALIENT CHARACTERISTICS, EQUAL QUALITY, EQUAL LEAD TIMES, AND
EQUAL MAINTENANCE COSTS MAY USE THOSE PRODUCTS OR EQUIPMENT TO BID
AND CONSTRUCT THE PROJECT. BIDDERS SHALL CONTACT THE A/E VIA THE VA
PROJECT CONTRACTING OFFICER DURING THE BID PHASE FOR APPROVAL OF THE
SUBSTITUTION REQUEST ON EACH ITEM. IN THE EVENT A CONTRACTOR IS
AWARDED THE PROJECT WITHOUT OBTAINING VA APPROVAL OF THE SUBSTITUTION
REQUEST DURING THE BID PHASE AND THE SHOP DRAWINGS AND SUBMITTALS OF
ALTERNATE MANUFACTURERS ARE NOT APPROVED BY THE A/E OR THE VA THEN
THE CONTRACTOR MUST INSTALL THE BASIS OF DESIGN PRODUCTS OR SERVICES
AT THE CONTRACTOR'S EXPENSE. NON-APPROVED PRODUCTS OR SERVICES ARE
AT THE CONTRACTOR'S RISK AND NO EQUITABLE ADJUSTMENT TO TIME OR MONEY
WILL BE MADE FOR COST DIFFERENCES BETWEEN APPROVED VERSUS NON-
APPROVED AFTER BIDDING HAS BEEN CLOSED. ALLOW SEVEN CALENDAR DAYS
BEFORE BIDS ARE DUE TO OBTAIN APPROVAL.
BASIS OF DESIGN NOTES
4. CONNECTED CAPACITY TO BC SHOULD NOT EXCEED 189,000 BTU/H FOR DOUBLE BC'S AND 126,000 BTU/H FOR SUB BC'S.
3. INCLUDE DIAMONDBACK BALL VALVES BV-SERIES, 700 PSIG WORKING PRESSURE, FULL PORT, R410A RATED TO ISOLATE INDIVIDUAL REFRIGERANT LINES AT UNIT.
2. PROVIDE MANUFACTURER'S JOINT PIPE TO COMBINE BRANCH REFRIGERANT LINES WHEN CONNECTED INDOOR UNIT CAPACITY ON A SINGLE BRANCH EXCEEDS 54,000 BTUH.
1. VRF BRANCH CIRCUIT CONTROLLER PROVIDED WITH MANUFACTURER'S STANDARD REDUCERS WHEN THE INDOOR UNIT CAPACITY IS 18,000 BTUH OR LESS.
NOTES:
BC-2.5 CU-2 MITSUBISHI TCMB-S0108KB11N4 SUB 8 47,000 208 1 0.74 69 1, 2, 3, 4
BC-2 CU-2 MITSUBISHI TCMB-M1016JA11N4 MAIN 16 141,000 208 1 1.57 150 1, 2, 3, 4
BC-1.5 CU-1 MITSUBISHI TCMB-S0104KB11N4 SUB 4 21,000 208 1 0.34 51 1, 2, 3, 4
BC-1 CU-1 MITSUBISHI TCMB-M1016JA11N4 MAIN 16 142,000 208 1 1.57 150 1, 2, 3, 4
(BTU) VOLT PHASE MCA (LBS)
SYMBOL SERVED BY MANUFACTURER MODEL TYPE PORTS CONNECTED CAPACITY ELECTRICAL WEIGHT NOTES
VRF BRANCH CIRCUIT CONTROLLER SCHEDULE
NOTES:
M-8 UPONOR 1-1/4" STAINLESS STEEL WITH FLOW METER AND BALL VALVE 9 18.35 12.1 13.5 25.5
M-7 UPONOR 1-1/4" STAINLESS STEEL WITH FLOW METER AND BALL VALVE 9 17.61 11.1 12.5 23.6
M-6 UPONOR 1-1/4" STAINLESS STEEL WITH FLOW METER AND BALL VALVE 10 20.6 14.5 13.2 27.7
M-5 UPONOR 1-1/4" STAINLESS STEEL WITH FLOW METER AND BALL VALVE 8 16.07 10.2 13 23.2
M-4 UPONOR 1-1/4" STAINLESS STEEL WITH FLOW METER AND BALL VALVE 7 13.01 7.5 11.7 19.1
M-3 UPONOR 1-1/4" STAINLESS STEEL WITH FLOW METER AND BALL VALVE 7 11.56 5.6 9.3 15.2
M-2 UPONOR 1-1/4" STAINLESS STEEL WITH FLOW METER AND BALL VALVE 7 8.64 3.3 4.8 8.1
M-1 UPONOR 1-1/4" STAINLESS STEEL WITH FLOW METER AND BALL VALVE 10 20.63 14.6 13.7 28.3
(GPM) LOSS (FT WG) LOSS (FT WG) LOSS (FT WG)
SYMBOL MANUFACTURER DESCRIPTION CIRCUITS FLOW MANIFOLD HEAD CIRCUIT HEAD TOTAL HEAD NOTES
SNOW MELT MANIFOLD SCHEDULE
NOTES:
WC-1 BROAN 641 EXHAUST PAINT TO MATCH EXISTING EXTERIOR COLOR
SYMBOL MANUFACTURER MODEL TYPE FINISH NOTES
WALL CAP SCHEDULE
7. REFER TO THE HEAT RECOVERY UNIT SCHEDULE FOR OUTSIDE AIR TEMPERATURES AND CONDITIONS.
6. INDOOR UNITS ARE EQUIPED WITH AN INTERNAL WATER LEVEL DETECTION DEVICE CONFORMING TO UL 508 PER IPC 314.2.3.
5. THE CORRECTED CAPACITIES INCLUDE THE DE-RATE ASSOCIATED WITH INDOOR UNITS VS. OUTDOOR UNITS CONNECTED CAPACITY INDICATED ON THE OUTDOOR UNIT SCHEDULE FOR ASSOCIATED SYSTEMS.
4. SEE SCHEMATIC PIPING/CONTROL DIAGRAM FOR INDICATION OF REQUIRED INDOOR UNIT REMOTE CONTROLLERS, SYSTEM CONTROLLERS, AND INTEGRATION DEVICES.
3. SEE OUTDOOR UNIT SCHEDULE FOR OUTDOOR AMBIENT CONDITIONS, CONNECTED CAPACITY, AND OTHER FACTORS ASSOCIATED WITH CORRECTED CAPACITIES.
2. NOMINAL HEATING CAPACITIES ARE BASED ON INDOOR COIL EAT OF 70 °F (DB), OUTDOOR OF 43 °F (WB).
1. NOMINAL COOLING CAPACITIES ARE BASED ON INDOOR COIL EAT OF 80/67 °F (DB/WB), OUTDOOR AMBIENT TEMPERATURE OF 95 °F (DB).
NOTES:
IU-42 BC-2 MITSUBISHI TPEFY-P012MA143A CEILING CONCEALED 370 0.6 12 11.2 8 80 / 67 55 75 13.5 - 70 / 43 95 70 160 208 1 1.2 15 49 1, 2, 3, 4, 5, 6, 7
IU-41 BC-2 MITSUBISHI TPKFY-P012HM142A WALL MOUNTED 413 - 12 11.2 8.5 80 / 67 55 75 13.5 - 70 / 43 95 70 - 208 1 0.38 15 29 1, 2, 3, 4, 5, 6, 7
IU-40 BC-2 MITSUBISHI TPLFY-P005FM140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-39 BC-2 MITSUBISHI TPLFY-P005FM140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-38 BC-2 MITSUBISHI TPLFY-P005FM140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30 208 1 0.24 15 29 1, 2, 3, 4, 5, 6, 7
IU-37 BC-2 MITSUBISHI TPLFY-P005FM140A CEILING 4 WAY CASSETTE 265 - 5 4.7 4.2 80 / 67 55 75 5.6 - 70 / 43 95 70 30…