Attachment 15 AFMC Form 718.docx

DOCX document 29 KB Posted

Attached to
AN/TRN-41 MP TACAN Replacement Federal contract opportunity
Solicitation number
FA8102-23-R-2000
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Tinker Air Force Base

View the file

Other files for this federal contract opportunity

Other files attached to AN/TRN-41 MP TACAN Replacement, newest first.
File Type Posted
1 MP TACAN QnA 21Dec22.pdf PDF
FINAL AF PreProposal Conference Provisioning 9 Dec 22.pptx PPTX presentation
FINAL DLA DLIS Pre-Guidance Conf 09Dec22.pptx PPTX presentation
FA810223R2000_______0001 06 Dec 22.pdf PDF
EXHIBIT H CDRL B0XX CDRLs 5Dec22.pdf PDF
Attachment 04 Section L ITO Risk Price 5Dec22.pdf PDF
EXHIBIT D CDRL A0XX CDRLs 5Dec22.pdf PDF
EXHIBIT D CDRL A0XX CDRLs 27Oct22.pdf PDF
EXHIBIT E CDRL B026 27Oct22.pdf PDF
EXHIBIT B CDRL A028 27Oct22.pdf PDF
EXHIBIT G CDRL B047 27Oct22.pdf PDF
Attachment 10 Wage Determination 2015-5105.pdf PDF
Attachment 09 Wage_Determination_2015-5489.pdf PDF
Attachment 05 Section M Risk Price 7 Nov 22.pdf PDF
EXHIBIT F CDRL B028 27Oct22.pdf PDF
EXHIBIT H CDRL B0XX CDRLs 27Oct22.pdf PDF
Attachment 11 Wage_Determination_2015-5487.pdf PDF
FA810223R2000 18Nov22.pdf PDF
Attachment 02 SRD V1 13Oct22.pdf PDF
EXHIBIT C CDRL A047 27Oct22.pdf PDF
Attachment 04 Section L ITO Risk Price 15Nov22.pdf PDF
Attachment 03 Delivery Locations Basic List.pdf PDF
Attachment 14 DO 1 Location Min Order.pdf PDF
Attachment 06 AFMC Form 158.pdf PDF
Attachment 13 WarrantyTrackingInformation_V2.6.xlsx XLSX spreadsheet
Attachment 01 MP_TACAN_SOW_11_Nov_ 22.pdf PDF
EXHIBIT A CDRL A026 27Oct22.pdf PDF
Attachment 12 Warranty Tracking Info.pdf PDF
Attachment 07 AFMC Form 158 Attmnt Vendor Packaging Inst.pdf PDF
Appendix 3 Pricing Matrix 14Nov22.xlsx XLSX spreadsheet
Appendix 2 CDRL Assertion Matrix 27Oct22.xlsx XLSX spreadsheet
Attachment 08 AFMC Form 807 19 Apr 22.pdf PDF
Appendix 1 SRD Cross Reference 13Oct22.xlsx XLSX spreadsheet
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROVISIONING PERFORMANCE SCHEDULE

DATE

20221103

OMB NO 0704-0188

Public reporting burden for this collection of information is estimated to average 8 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Washington Headquarters Services, Directorate of Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project

END ARTICLE

Man-Portable TACAN (MP TACAN)

CONTRACTOR

END ARTICLE DELIVERY DATES
SOLICITATION OR CONTRACT NUMBER

FA8102-23-R-2000

TYPE OF CONTRACT

DATE OF FIRST DELIVERY

EMD PROD

EMC W/PROD OPT

REVISION

DATE OF LAST DELIVERY

NUMBER
DATE
NO
EVENT
ACTION AGENCY
TIMING
CALENDAR DATE
1
CONTRACT AWARD
GOVT
CONTRACT MAILING DATE
20230929
2
GUIDANCE CONFERENCE
GOVT AND CONTR
NLT 45 DAYS AFTER MAILING DATE OF CONTRACT
3
DLSC SCREENING
CONTR
SUBMIT TO DLSC NOT EARLIER THEN 30 DAYS PRIOR TO SUBMITTING PTD
4
SAIP

a. CANDIDATE LIST

CONTR
NLT 165 DAYS PRIOR TO CONTRACTOR'S ORDER NEED DATE
b. SELECTED ITEM NOTIFICATION
GOVT
NLT 30 DAYS AFTER RECEIPT OF CANDIDATE LIST
c. CONTRACTOR PROCUREMENT SCHEDULE PTD, EDFP SCREENING
CONTR
NLT 90 DAYS PRIOR TO CONTRACTOR'S ORDER NEED DATE
d. PROVISIONING CONFERENCE
GOVT AND CONTR
NLT 60 DAYS PRIOR TO CONTRACTOR'S ORDER NEED DATE
START

FINISH

e. PIOs RELEASED TO CONTRACTOR
GOVT
NLT 30 DAYS PRIOR TO CONTRACTOR'S ORDER NEED DATE
5
LONG LEAD ITEMS LIST (LLIL) WITH EDFP AND DLSC SCREENING RESULTS
CONTR
NLT 30 DAYS AFTER RELEASE FOR FABRICATION OR PROCUREMENT OF
START

FINISH

b. RECOMMENDED ITEMS
CONTR
45 DAYS PRIOR TO RELEASE OF PPL
c. PROVISIONING CONFERENCE
GOVT AND CONTR
NLT 90 DAYS PRIOR TO CONTRACTOR'S ORDER NEED DATE
d. PIOs RELEASED TO CONTRACTOR
GOVT
NLT 30 DAYS AFTER RECEIPT OF LLIL FROM CONTRACTOR
6
PTD/EDFP REQUIREMENTS
CONTR
NLT 60 DAYS PRIOR TO PROVISIONING CONFERENCE
7
PROVISIONING CONFERENCE
GOVT AND CONTR
NLT 60 DAYS AFTER RECEIPT OF PTD/EDFP
START

FINISH

8
PIOs w/DELIVERY SCHEDULE
GOVT
DUE 90 DAYS AFTER RECEIPT OF PTD/EDFP
9
ACCEPTANCE/REVISION OF DELIVERY SCHEDULE
CONTR
NLT 60 DAYS AFTER RECEIPT OF PIO's
10
SPARES NEED DATE
GOVT
IAW PROGRAMMING CHECKLIST BUT NLT 90 DAYS PRIOR TO OND
11
TRAINING START DATE
GOVT
12
OPERATIONAL NEED DATE
GOVT

20251031

REMARKS (Continue on reverse) SEE PAGE 2

APPROVED BY

AF PROV CHAIRPERSON
CONTRACTOR
PROGRAM MANAGER

AFMC FORM 718, 20181207

Prescribed by: AFMCMAN20-106

PREVIOUS EDITION IS OBSOLETE.

REMARKS (Continued) By submitting this form with the MP TACAN Replacement Program RFP FA8102-23-2000 response, the offeror understands that the dates on this form initially and proposed by the Offeror are subject to change based on feedback from the Tinker AFB Program Office and Tinker AFB Provisioning Office. This form will be reviewed during the Provisioning Guidance Conference and periodically during performance of the MP TACAN Replacement contract.

AFMC FORM 718, 20181207, Reverse