Attachment 14 TE13-CCTV Acceptance (PVT) - 2021.pdf
PDF 1 MB Posted
- Attached to
- JBLM ICIDS IV SOLE SOURCE Federal contract opportunity
- Solicitation number
- W911S824R0010
About this file
This document appears to be an attachment titled "Attachment 14 TE13-CCTV Acceptance (PVT) - 2021.pdf" that outlines a checklist for the acceptance testing and inspection of a CCTV system. The checklist covers items such as camera picture quality, alarm point settings, camera mounting and positioning, outdoor enclosures, and required CCTV system documentation and training.
The related federal contract opportunity is for a sole source contract (Solicitation Number W911S824R0010) for the Joint Base Lewis-McChord (JBLM) Integrated Commercial Intrusion Detection Systems IV (ICIDS IV). The contractor shall provide all personnel, equipment, tools, labor, materials, supervision, and non-personal services necessary to monitor, maintain, repair, replace, survey, and manage the current JBLM ICIDS IV systems, which include CCTV equipment, sensors, and other security systems. The overall objective is to ensure the ICIDS IV systems remain fully operational until a follow-on contract can be awarded.
View the file
Other files for this federal contract opportunity
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. CCTV - Headend: Com Switch Location:
Cameras Labeled Y N
Camera picture quality (Day & Night) Y N
Camera Alarm Points Set Y N
Camera angle and view as designed w/ no obstructions Y N
Camera mounts anchored tight (Not impacted by wind or other means) Y N
2. CCTV - Location: Com Switch Location:
Hardware and components securely fastened and tight Y N
Outdoor applications – Equipment & Fittings weather tight Y N
Camera components function correctly (Locally) Y N
Camera angle and view as designed w/ no obstructions Y N
Camera mount sufficient and anchored correctly Y N
Housing/Enclosure has heater Y N
For PTZ, dome tint is clear / smoked
Conduit and fittings secured and anchored Y N
Camera location is sufficient to prevent tampering Y N
Other Y N
Other Y N
3. CCTV Submittals:
Project narrative page Y N
Recommended spare parts list Y N
Equipment in place (location, component description, mod/ser#) Y N
Equipment suppliers contact information Y N
Contractor contact information Y N
Camera naming scheme & Settings Updated Y N
Camera and software pre-sets Y N
Alarm pre-sets Y N
DVR recording storage capacity (Note Size and storage retrieval Time) Y N
Software user level/restriction set Y N
Password protection (if required) Y N
Drawings & Block Diagrams Y N
Other Y N
4. Training:
Facility manager trained on the system operation & maintenance Y N
Comments/Problems:______________________________________________________________________
PS Inspector:___________Print(PSS)_________________________Sign________________________________
Sub Contractor:_________Print(Sub)_________ ______________Sign_________________________________
Project Manager:_______ Print (USACE)______________________Sign_____________________________________
Contractor Rep:_________ Print(PrimeContractor)_______________Sign________________________________
File details come from the government source that posted it. Updated .