Attachment 14 TE13-CCTV Acceptance (PVT) - 2021.pdf

PDF 1 MB Posted

Attached to
JBLM ICIDS IV SOLE SOURCE Federal contract opportunity
Solicitation number
W911S824R0010
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Joint Base Lewis-McChord

About this file

This document appears to be an attachment titled "Attachment 14 TE13-CCTV Acceptance (PVT) - 2021.pdf" that outlines a checklist for the acceptance testing and inspection of a CCTV system. The checklist covers items such as camera picture quality, alarm point settings, camera mounting and positioning, outdoor enclosures, and required CCTV system documentation and training.

The related federal contract opportunity is for a sole source contract (Solicitation Number W911S824R0010) for the Joint Base Lewis-McChord (JBLM) Integrated Commercial Intrusion Detection Systems IV (ICIDS IV). The contractor shall provide all personnel, equipment, tools, labor, materials, supervision, and non-personal services necessary to monitor, maintain, repair, replace, survey, and manage the current JBLM ICIDS IV systems, which include CCTV equipment, sensors, and other security systems. The overall objective is to ensure the ICIDS IV systems remain fully operational until a follow-on contract can be awarded.

View the file

Other files for this federal contract opportunity

Other files attached to JBLM ICIDS IV SOLE SOURCE, newest first.
File Type Posted
Attachment 01 ICIDS PWS (SOLE SOURCE BRIDGE (6 Aug 24 V3)).pdf PDF
Attachment 02 TE-1 - ICIDS CCTV-GBR SOP.docx DOCX document
Attachment 04 TE3 - Open Accounts Report example - 2021.pdf PDF
Attachment 06 TE5- Contract Service Order - 2021.pdf PDF
Attachment 08 TE-07-Catastrophic Failure Report 19 Jan 24.pdf PDF
Attachment 15 TE14-QUALITY CONTROL CHECK SHEET - 2021.pdf PDF
Attachment 16 TE15-ICIDS and CCTV Addition-Removal.pdf PDF
Attachment 22 TE-21-ICIDS CCTV GBR Master PM Sheet.xlsx XLSX spreadsheet
Attachment 05 TE4 - ARMS ROOM TEST LOG - 2021.pdf PDF
Attachment 10 TE9 - LMT example - 2021.pdf PDF
Attachment 13 TE12-IDS PerformanceVerificationTest (PVT) - 2021.pdf PDF
W911S824R0010 ICIDS SOLICIATION.pdf PDF
Attachment 11 TE10-MCA-ICIDS II MaterialOrder.pdf PDF
Attachment 17 TE16 -Activation Checklist.pdf PDF
Attachment 18 TE17 -Deactivation.pdf PDF
Attachment 20 TE19 - New Account Activation Request - 2021.pdf PDF
Attachment 23 Mission-Essential Contractor Services.pdf PDF
Attachment 03 TE-2 - ICIDS-DailyAlarmEventLog_example - 2021.pdf PDF
Attachment 07 TE6-FieldReport w-CSO - 2021.pdf PDF
Attachment 09 TE8 - MFR-ICIDS-PIN User Policy-Dec 21.pdf PDF
Attachment 12 TE11 MCA-ICIDS IV-MaterialOrder.pdf PDF
Attachment 19 TE18 -ICIDS Account Map - 2021.pdf PDF
Attachment 21 TE-20 - ICIDS IV Master Worksheet A 27 January 2023.xlsx XLSX spreadsheet
Attachment 24 WD Pierce 2015-5539 Rev26.pdf PDF
Attachment 25 WD Yakima 2015-5543 Rev 23.pdf PDF
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CCTV - Headend: Com Switch Location:

Cameras Labeled Y N

Camera picture quality (Day & Night) Y N

Camera Alarm Points Set Y N

Camera angle and view as designed w/ no obstructions Y N

Camera mounts anchored tight (Not impacted by wind or other means) Y N

2. CCTV - Location: Com Switch Location:

Hardware and components securely fastened and tight Y N

Outdoor applications – Equipment & Fittings weather tight Y N

Camera components function correctly (Locally) Y N

Camera angle and view as designed w/ no obstructions Y N

Camera mount sufficient and anchored correctly Y N

Housing/Enclosure has heater Y N

For PTZ, dome tint is clear / smoked

Conduit and fittings secured and anchored Y N

Camera location is sufficient to prevent tampering Y N

Other Y N

Other Y N

3. CCTV Submittals:

Project narrative page Y N

Recommended spare parts list Y N

Equipment in place (location, component description, mod/ser#) Y N

Equipment suppliers contact information Y N

Contractor contact information Y N

Camera naming scheme & Settings Updated Y N

Camera and software pre-sets Y N

Alarm pre-sets Y N

DVR recording storage capacity (Note Size and storage retrieval Time) Y N

Software user level/restriction set Y N

Password protection (if required) Y N

Drawings & Block Diagrams Y N

Other Y N

4. Training:

Facility manager trained on the system operation & maintenance Y N

Comments/Problems:______________________________________________________________________

PS Inspector:___________Print(PSS)_________________________Sign________________________________

Sub Contractor:_________Print(Sub)_________ ______________Sign_________________________________

Project Manager:_______ Print (USACE)______________________Sign_____________________________________

Contractor Rep:_________ Print(PrimeContractor)_______________Sign________________________________