ATTACHMENT 13 - Pre-Construction Risk Assessment.pdf

PDF 292 KB Posted

Attached to
Y1DA--EHRM Infrastructure Upgrades Construction San Juan Federal contract opportunity
Solicitation number
36C77624B0012
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This document is a Pre-Construction Risk Assessment and Exposure Control Checklist for a federal contract opportunity related to the VA Caribbean Healthcare System in San Juan, Puerto Rico. The project involves EHRM Infrastructure Upgrades across multiple buildings, including general construction, infrastructure upgrades, reconfiguration, and renovation work. Key hazards identified include asbestos, dust, moisture/water leaks, vapors/fumes, noise, vibration, air pressure relationships, and proximity to immune-suppressed patients. Control measures are detailed, such as asbestos abatement, dust containment, negative air pressure, scheduling work after hours, and relocating patients. The related federal contract opportunity is Solicitation Number 36C77624B0012 for the "EHRM Infrastructure Upgrades Construction San Juan" project, which is being solicited by the Department of Veterans Affairs Technology Acquisition Center Austin.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--EHRM Infrastructure Upgrades Construction San Juan, newest first.
File Type Posted
36C77624B0012 0004.pdf PDF
AE302.pdf PDF
Clarifications to Technical Questions 7-17-24.pdf PDF
014535.pdf PDF
283100 Fire Detection and Alarm.pdf PDF
VASJ iSTAR Controller COMM ROOMS Inventory Jun 28 2024.xls XLS spreadsheet
36C77624B0012 0003.pdf PDF
AE500.pdf PDF
Fig 2 Borings Logs Location-Soil Report 2010.pdf PDF
GI103.pdf PDF
Mechanical_Addendum01.pdf PDF
Technical Questions - FINAL - San Juan - 6-28-24.pdf PDF
01-AE103b.pdf PDF
VACHS San Juan Geotehcnical Engineering Report on Sobsoil Exploration .pdf PDF
VASJ APC COMM ROOM Controller Inventory Jun 28 2024.xls XLS spreadsheet
Electrical_Addendum01.pdf PDF
GI300.pdf PDF
Structural_Addendum01.pdf PDF
Technology_Addendum01.pdf PDF
36C77624B0012 0002.pdf PDF
Site Visit Sign-in Sheet - San Juan 5-14-24.pdf PDF
36C77624B0012 0001.pdf PDF
36C77624B0012 - 4-25-24.pdf PDF
ATTACHMENT 2 - Specifications Vol 2.pdf PDF
ATTACHMENT 5 - Drawings Vol 1 - Part 3.pdf PDF
ATTACHMENT 8 - Drawings Vol 2 - Part 1.pdf PDF
ATTACHMENT 12 - CFD Analysis Report.pdf PDF
ATTACHMENT 1 - Specifications Vol 1.pdf PDF
ATTACHMENT 6 - Drawings Vol 1 - Part 4.pdf PDF
ATTACHMENT 7 - Drawings Vol 1 - Part 5.pdf PDF
ATTACHMENT 10 - Drawings Vol 2 - Part 3.pdf PDF
ATTACHMENT 11 - Hazmat Report.pdf PDF
ATTACHMENT 3 - Drawings Vol 1 - Part 1.pdf PDF
ATTACHMENT 4 - Drawings Vol 1 - Part 2.pdf PDF
ATTACHMENT 9 - Drawings Vol 2 - Part 2.pdf PDF
ATTACHMENT 14 - Brand Name Justification - San Juan.pdf PDF
ATTACHMENT 15 - DOL Prevailing Wage Resource Book.pdf PDF
ATTACHMENT 16 - Limitations on Subcontracting - Construction.docx DOCX document
ATTACHMENT 17 - Site Visit Instructions.pdf PDF
Show all 39

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT Z

CENTER MEMORANDUM NO. 00-16-81

APRIL 2016

VA CARIBBEAN HEALTHCARE SYSTEM

SAN JUAN, PUERTO RICO

PRECONSTRUCTION RISK ASSESSMENT AND EXPOSURE CONTROL CHECKLIST

Project Name: 672-21-700 EHRN Infrastructure Upgrade San Juan PR Date: 01/19/2024

Hazard Concern?

(Y/N)

Control

Measure Remarks

Asbestos Y h, a Asbestos will be removed only on new Telecommunication Rooms

Dust Y a, e, f

Moisture/Water Leaks Y a

Vapors/Fumes Y b

Noise Y b Moderated Noise Level

Vibration Y b

Air Pressure Relationships Y a

Traffic Flow Y b

Open Outside Walls N

Impact to Levels Above and Below Y a, b

Proximity of Air Intakes N

Pest Control Within Construction Area Y b

Proximity of Immune Suppressed Patients N

Approval Signatures:

Project Manager: _________________________________

Chief Engineering Section: __________________________

Infection Control: __________________________________

Industrial Hygienist: ________________________________

Contractor: ____________________________________

Service/Section/Program Chief: _________________________

APRIL 2016

Control Measures

Asbestos

a. Contractor has hired an asbestos abatement contractor for control and cleanup.

b. VA to hire independent Industrial Hygienist to inspect and clear area for re-occupancy based on monitoring and/or professional judgment.

c. Published asbestos protocol to be followed for work through ceilings.

d. Published asbestos protocol to be followed for work above ceilings.

e. Perimeter barrier will be constructed in the interstitial space to isolate the construction area with other areas in the interstitial.

f. Project area will be encased with spray-applied hard surface encasement material.

g. Provide mini containments under negative air in public areas.

h. Sealed gypsum board barrier will be constructed to isolate the construction area from the public.

i. Transit panels will be removed, which is considered Class B removal.

Dust

a. Sealed gypsum board barrier will be constructed to isolate the construction area from the public.

b. Trash carts will be covered when transported through the building.

c. Provide negative air machine exhausted to outside.

d. Provide mini containments under negative air in public areas.

e. Provide negative air machine in space as air scrubber.

f. Provide walk off mats at entrances to work area.

g. Perimeter barrier will be constructed in the interstitial space to isolate the construction area with other areas in the interstitial.

Moisture Water Leaks

a. Contain any water from core drilling activities.

b. Dike any floor penetrations to minimize risk of leaks from construction zone.

Vapors/Fumes

a. Use of products with low Volatile Organic Compounds (VOCs).

b. Provide negative air in construction zone exhausted to outside, away from intakes.

c. Seal work area airtight barrier.

d. Cut all metal outside the building.

e. Seal any floor penetrations to minimize risk of fumes through construction zone.

f. Shut down air handler to minimize infiltration of fumes from outside.

Noise

Schedule demolition work after normal work hours.

Cut all metal outside the building.

Vibration

a. Schedule demolition work after normal work hours.

b. Coordinate with occupants in surrounding areas to explain the work occurring.

a.

b.

APRIL 2016

Air Pressure Relationships

a. Provide negative air during asbestos abatement.

b. Provide negative air during construction.

c. Seal off supply and exhaust Heating, Ventilation, and Air Conditioning (HVAC) registers.

d. Provide anteroom under negative pressure at entrance to project zone.

Traffic Control

Access construction area via exterior door.

Schedule delivery of large quantities of material and demolition haul out after hours.

Open Outside Walls

a. Construct temporary outside wall to limit the infiltration of wind, air, and temperature differences into the project site.

Impact to Levels Above and Below

a. Coordinate with occupants in surrounding areas to explain the work occurring.

b. Follow asbestos protocol when doing under floor work.

c. Vacate areas when doing below floor work off of the catwalk.

Proximity of Air Intakes

a. Shut down air handlers to reduce infiltration of fumes from exterior activities such as painting, gasoline powered engines, roofing operations, equipment, etc.

Pest Control within Construction Area

a. Provide barriers to any open outside walls.

b. Contact pest controller if any evidence of pests is found during the course of the work.

Proximity of Immune Suppressed Patients

a. Relocate patients away from construction zone for entire project.

b. Relocate patients away from construction zone during demolition operations.

a.

b.

2024-01-19T15:21:25-0400
RADAMES PERDOMO
2024-01-19T15:28:31-0400
VICTOR MEDINA-MASSANET
2024-01-22T06:22:00-0400
NANCY ROMAN-DE LEON
2024-01-22T11:18:47-0400
RICHARD CINTRON-ORTIZ
2024-01-22T13:51:40-0400
WILFREDO QUINONES MENDEZ

File details come from the government source that posted it. Updated .