Attachment 1 - SOW XDAT 23-1040 03.21.2024.pdf
PDF 134 KB Posted
- Attached to
- PKA - B10 Windows - Travis AFB (AMENDED v5) Federal contract opportunity
- Solicitation number
- FA442724R0019
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity to demolish and replace windows at the flight line control tower at Travis Air Force Base. The contractor is required to provide all design, labor, materials, and supervision to replace 11 windows in the tower and 26 windows in the cab at the top of the control tower. The contractor must comply with various construction codes and standards, and obtain approval for all materials and designs prior to commencing work. The work must be coordinated with the flight control tower operations to allow continued work during construction. The solicitation number is FA442724R0019, and the agency is the Department of the Air Force Air Mobility Command. Questions are due by June 12, 2024 at 11:00 AM PDT.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
Project Name: Flight line Control Tower Windows
XDAT # 23-1040
21 MAR 2024
1. GENERAL DESCRIPTION
1.1 The contractor (Ktr) shall provide all design, labor, materials, and supervision to demolish and replace and existing windows at Building 10. There are 11 windows to be replaced in the tower and 26 windows in the cab at the top of the control tower. Contractor shall comply with most recent codes and standards to include:
UFC 1-200-01
UFC 4-133-01
UFC 4-010-01
UFGS 01-33-00
IEBC 2021
IBC 2021
Spec 01000 Travis AFB Facilities Excellence Guide Travis AFB Maintainability and Durability List
Contractor shall have approved drawings and submittals for all materials prior to any new work or installation of equipment, including accessory items. Contractor shall review existing as-built drawings and make corrections to apply with proposed new scope designs with final review by government for approval. All work must comply with environmental laws and regulations, including abatement of any hazardous materials. All work to be completed, is to be coordinated through CE with flight control tower so that they may continue work while construction is taking place.
2. TESTING
2.1 Contractor to conduct Hazardous testing of lead and asbestos immediately after the notice to proceed and prior to mobilization.
3. DEMOLITION
3.1 Demolish old windows, approximately 3’6” x 3’ 10” in size, on 6th and 8th floor of the tower.
6th floor has 4 west facing windows within the entire window assembly. 8th floor has 7 south facing windows within the entire window assembly that need to be replaced. Tower cab consists of 26 windows to be removed for replacement, approximately 6’x 7’ Gypsum board around windows will need to be removed where needed for construction and damaged from water intrusion as well as stucco siding which is an estimated 322SQF.
4. CONSTRUCTION
UFGS 01 14 00
UFGS 01 35 26
UFGS 01 45 00.00 40
UFGS 01 50 00
SECTION 01 03 00
SECTION 01 56 00
SECTION 26 20 00
EM 385-1-1
4.1 Replace all windows at top of flight tower in cab. All 26 windows to be replaced shall meet UFC 4-133-01 requirements as well as UFC 4-010-01. The following additional windows shall meet the UFC requirements as well, 4 west facing windows on the 6th floor, and 7 south facing windows on the 8th floor. Windows on the 6th and 8th floor shall be replaced in kind to match existing windows. Patching and repair of stucco and dry wall where demolition occurred shall be completed and finished with color to match existing finishes.