This document is a Statement of Work (SOW) for a federal contract opportunity to demolish and replace windows at the flight line control tower at Travis Air Force Base. The contractor is required to provide all design, labor, materials, and supervision to replace 11 windows in the tower and 26 windows in the cab at the top of the control tower. The contractor must comply with various construction codes and standards, and obtain approval for all materials and designs prior to commencing work. The work must be coordinated with the flight control tower operations to allow continued work during construction. The solicitation number is FA442724R0019, and the agency is the Department of the Air Force Air Mobility Command. Questions are due by June 12, 2024 at 11:00 AM PDT.

View the file

Other files for this federal contract opportunity

Other files attached to PKA - B10 Windows - Travis AFB (AMENDED v5), newest first.
File Type Posted
Attachment 14 - B10 Window Replacements Bid schedule.xlsx XLSX spreadsheet
Amendment 0005 SF 30.pdf PDF
Solicitation - FA442724R00190005.pdf PDF
Attachment 1 - SOW Rev.2 - B10 Windows 21 August 2024.pdf PDF
Solicitation Amendment - FA442724R00190004.pdf PDF
Attachment 14 - B10 - Window replacements Bid schedule.xlsx XLSX spreadsheet
Attachment 15 - B10 Windows - RFIs Answered 30 July 24.pdf PDF
Amendment 0004 SF 30.pdf PDF
Attachment 1 - SOW Rev.1 - B10 Windows 25 July 2024.pdf PDF
Amendment 0003 SF 30.pdf PDF
Solicitation Amendment - FA442724R00190003.pdf PDF
Solicitation Amendment - FA442724R00190002.pdf PDF
Amendment 0002 SF 30.pdf PDF
Amendment 0001 SF 30.pdf PDF
Solicitation Amended - FA442724R00190001.pdf PDF
Attachment 4 - Travis Facilities Excellence Guide.pdf PDF
Attachment 6 - SECTION 01 03 00 PROJECT CLOSEOUT.pdf PDF
Attachment 8 - SECTION 26 20 00 INTERIOR DISTRIBUTION SYSTEM.pdf PDF
Attachment 2 - WD - CA20240007.pdf PDF
Attachment 10 - SWD Contractor Requirements - Soil - TSDF.PNG PNG image
Attachment 11 - B10 Vicinity Map.pdf PDF
Attachment 12 - TAFB Security Clause.pdf PDF
Solicitation - FA442724R0019.pdf PDF
Attachment 3 - Travis AFB MaintDurList.pdf PDF
Attachment 5 - Travis AFB Spec 01000 Word DocWithHyperlinks 1-04-23.pdf PDF
Attachment 7 - SECTION 01 56 00 Environmental Specifications.pdf PDF
Attachment 9 - Tab 1. 2023 ISWMP.pdf PDF
Attachment 13 - Sponsorship Site Visit Info.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

Project Name: Flight line Control Tower Windows

XDAT # 23-1040

21 MAR 2024

1. GENERAL DESCRIPTION

1.1 The contractor (Ktr) shall provide all design, labor, materials, and supervision to demolish and replace and existing windows at Building 10. There are 11 windows to be replaced in the tower and 26 windows in the cab at the top of the control tower. Contractor shall comply with most recent codes and standards to include:

UFC 1-200-01

UFC 4-133-01

UFC 4-010-01

UFGS 01-33-00

IEBC 2021

IBC 2021

Spec 01000 Travis AFB Facilities Excellence Guide Travis AFB Maintainability and Durability List

Contractor shall have approved drawings and submittals for all materials prior to any new work or installation of equipment, including accessory items. Contractor shall review existing as-built drawings and make corrections to apply with proposed new scope designs with final review by government for approval. All work must comply with environmental laws and regulations, including abatement of any hazardous materials. All work to be completed, is to be coordinated through CE with flight control tower so that they may continue work while construction is taking place.

2. TESTING

2.1 Contractor to conduct Hazardous testing of lead and asbestos immediately after the notice to proceed and prior to mobilization.

3. DEMOLITION

3.1 Demolish old windows, approximately 3’6” x 3’ 10” in size, on 6th and 8th floor of the tower.

6th floor has 4 west facing windows within the entire window assembly. 8th floor has 7 south facing windows within the entire window assembly that need to be replaced. Tower cab consists of 26 windows to be removed for replacement, approximately 6’x 7’ Gypsum board around windows will need to be removed where needed for construction and damaged from water intrusion as well as stucco siding which is an estimated 322SQF.

4. CONSTRUCTION

UFGS 01 14 00

UFGS 01 35 26

UFGS 01 45 00.00 40

UFGS 01 50 00

SECTION 01 03 00

SECTION 01 56 00

SECTION 26 20 00

EM 385-1-1

4.1 Replace all windows at top of flight tower in cab. All 26 windows to be replaced shall meet UFC 4-133-01 requirements as well as UFC 4-010-01. The following additional windows shall meet the UFC requirements as well, 4 west facing windows on the 6th floor, and 7 south facing windows on the 8th floor. Windows on the 6th and 8th floor shall be replaced in kind to match existing windows. Patching and repair of stucco and dry wall where demolition occurred shall be completed and finished with color to match existing finishes.