Attachment 1 Performance Work Statement.pdf

PDF 310 KB Posted

Attached to
CCTV, IDS, and ACS Maintenance Services for DFAS Indianapolis, IN
Solicitation number
HQ042326QE076
Issued by

About this file

Performance Work Statement Summary

This is a Performance Work Statement (PWS) for maintenance and on-call service support of Closed-Circuit Television (CCTV), Intrusion Detection System (IDS), and Access Control System (ACS) at the Defense Finance and Accounting Service-Indianapolis facility located at 8899 East 56th Street, Indianapolis, IN 46249. The contract consists of a one-year base period with four one-year option periods for a total potential performance period of five years. The contractor must furnish all labor, supervision, tools, and contractor-furnished parts necessary to maintain the systems in full operational condition, with major equipment and hardware provided as Government Furnished Equipment (GFE). Normal hours of operation are Monday through Friday, 7:00 am to 5:00 pm, with no work performed on federal holidays.

The contractor must provide 24/7/365 support with telephone response within four hours and emergency on-site response within four hours for critical assets and 24 hours for non-critical assets. Non-emergency repairs must be completed within five business days. The contractor shall submit a Preventative Maintenance Plan within 30 days after award and maintain system availability at ≥98% monthly uptime per standalone system. Key performance requirements include annual UL 2050 certification, monthly uptime reporting, and compliance with manufacturer recommendations for Lenel OnGuard, Bosch, and DMP systems. The contractor must maintain authorized reseller status for Lenel (Value Added Reseller) and both Bosch and DMP products, employ certified technicians with minimum three years of documented IDS experience, and comply with extensive security requirements including personnel security investigations (Tier 3 minimum), security training, CAC requirements, and CMMC Level 1 self-assessment for Federal Contract Information protection. Personnel must be U.S. citizens, registered for Selective Service, and submit to continuous vetting programs and incident reporting for violations of National Security Adjudicative Guidelines.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement Defense Finance and Accounting Service Indianapolis, IN (DFAS-IN) Closed-Circuit Television (CCTV), Intrusion Detection System (IDS), and Access Control System (ACS)

1 | P a g e

1.0 Introduction

This contract provides for maintenance and on-call service support for Closed-Circuit Television (CCTV), Intrusion Detection System (IDS), and Access Control System (ACS) at the Defense Finance and Accounting Service-Indianapolis, IN (DFAS-IN). Services include routine and Government directed maintenance, diagnostics, troubleshooting, repair, system administration, and installation and/or removal of system components as directed by the Government. The specific responsibilities for furnishing parts and equipment are defined within this Performance Work Statement (PWS).

2.0 General Information

2.1 Place of Performance:

Defense Finance and Accounting Service-Indianapolis 8899 East 56th Street Indianapolis, IN 46249.

The Contractor shall perform work only in areas designated and approved by the Contracting Officer Representative (COR).

Smoking and tobacco use is prohibited in all Federal facilities and government owned vehicles. Tobacco products include cigarettes, cigars, cigarillos, smokeless tobacco, electronic cigarettes, inhaled tobacco, all new and emergent tobacco products, as well as all other tobacco products designed for human consumption. Smoking and tobacco use is only permitted in designated smoking areas which are clearly marked.

2.2 Period of Performance: The contract shall consist of a one (1) year base period beginning on the date of award and four (4) one-year option periods. The total period of performance, including all option periods, shall not exceed five (5) years.

2.3 Hours of Operation and Recognized Holidays:

Days and Hours of Operation: Normal hours of operation at DFAS-IN are Monday through Friday, 7:00 am to 5:00 pm. There may be occasions requiring extended work hours for contractor personnel. Any extended work hours must be coordinated with and approved by the COR.

DFAS-IN shall close when the Federal Government announces closure over local radio and television stations due to unusually severe weather or other unforeseen conditions. When unforeseen closure of the facility occurs on a regularly scheduled day of work, the contractor personnel shall reschedule the work on any day satisfactory to both parties.

No work shall be performed on all Federal holidays observed at DFAS-IN. A full list of Federal Holidays can be viewed at: https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2026 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2026 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2026

2 | P a g e

3.0 Scope

The Contractor shall furnish all labor, supervision, tools, and contractor-furnished parts necessary to install, repair, and maintain the Government's Access Control System (ACS) and Intrusion Detection System (IDS) and ensure they remain fully operational and properly installed. Major equipment, hardware, and software shall be provided as Government Furnished Equipment (GFE) in accordance with Section 6.3.

The Contractor shall perform routine and corrective maintenance on an as-needed basis or as directed by the Government. Preventative maintenance shall not be performed on a fixed schedule; however, the Contractor shall perform preventative actions in accordance with manufacturer recommendations, including system updates, recalls, diagnostics, and other preventative measures necessary to prevent system failures and maintain system integrity.

Within thirty (30) calendar days after award, the Contractor shall submit a proposed Preventative Maintenance Plan to the COR or requirement owner POC review and approval. The plan shall identify the Contractor’s recommended preventative maintenance approach, procedures, and frequencies, staffing methodology, personnel coverage, escalation procedures, and technician qualification requirements based on manufacturer recommendations and system-specific requirements. The plan shall also describe the Contractor’s approach for ensuring adequate certified technical support and response capability necessary to maintain continuous and reliable operation of the CCTV, ACS, and IDS systems. The approved plan shall serve as the baseline for preventative maintenance performance under the contract.

3.1 Access Control System (ACS)

The ACS includes:

• LENEL System Administration

• Alarm Monitoring

• Video viewer support

• Automatic door openers.

3.2 Intrusion Detection System (IDS)

The IDS includes DMP and Bosch system panels and associated components.

The IDS Protected Areas:

1. Client Systems 1 Alarm: UL Required

2. Client Systems 2 Alarm: UL Required

3. Agency Force Protection: No UL

4. Force Protection Operations Center: No UL

5. The Office of Preparedness: No UL

6. Client Systems 2 Server Room: No UL

7. Disbursing Vault: No UL

8. Room 139V: No UL

3.3 System Components and Estimated Quantities: The IDS and ACS currently include the following approximate quantities and equipment that may require maintenance under this contract:

• 140-180 card readers

• 114-150 IP cameras

3 | P a g e

• Axis camera models including: P3354, P3719, P3364, P3367-5MP, Q3819-PVE, M3045, P5624- E

• Bosch and DMP panels and expansion modules

• Power supplies

• Door contacts (standard and high security),

• Motion detectors

• Cabinet tamper switches

• Phone line modules

• Internet modules

Quantities are estimates and may fluctuate based on operational needs and facility expansion.

4.0 Maintenance Requirements

4.1 General: The contractor shall perform routine and Government-directed maintenance for all systems covered under this requirement. Services include preventative maintenance, diagnostics, troubleshooting, repair, system administration, and installation or removal of equipment as directed by the COR, requirement owner POC or Contracting Officer.

4.2 Preventative Maintenance: Preventative maintenance shall not be performed on a fixed schedule.

The contractor shall perform preventative actions in accordance with manufacturer recommendations, including system updates, recalls, and diagnostics, to prevent system failures and ensure continued system functionality. Within thirty (30) calendar days after award, the Contractor shall submit a proposed Preventative Maintenance Plan to the COR or requirement owner POC review and approval. The plan shall identify the Contractor’s recommended preventative maintenance approach, procedures, and frequencies based on manufacturer recommendations and system-specific requirements. The approved plan shall serve as the baseline for preventative maintenance performance under the contract.

4.3 Routine and Corrective Maintenance: The contractor shall perform routine and corrective maintenance on an as-needed basis or as directed by the COR, requirement owner POC or Contracting Officer. This includes troubleshooting, repairing, and resolution of system issues to restore full operational capability.

4.4 Recurring Requirements: The contractor shall perform annual UL 2050 certification requirements.

The Contractor shall complete all annual UL 2050 certification requirements no later than the anniversary date of the Contractor’s current UL 2050 certification. Additional recurring tasks may include password verification and system diagnostics as required by the COR or requirement owner POC.

4.5 Performance Approach: Maintenance services shall be both proactive and reactive in nature to ensure system reliability, security, and continuity of operations.

4.6 Certification Requirements: All maintenance shall be performed by certified technicians in accordance with Lenel, Bosch, and DMP system requirements. Technicians must possess current certifications and qualifications necessary to access proprietary systems, tools, and software.

4 | P a g e

5.0 Service Response and Performance Requirements

5.1 Telephone Consultation: The COR or requirement owner POC will initiate all requests for repair and technical assistance. The Contractor shall respond to all service calls within four (4) hours of notification, 24 hours per day, seven (7) days per week, 365 days a year. If the issue cannot be resolved through telephone consultation, the COR will determine whether the situation constitutes an Emergency.

5.2 In-Person Emergency Repair/Service

5.2.1 Emergency Response: The Contractor shall provide a qualified technician trained to repair the DFAS-IN ACS and IDS within four (4) hours for critical assets and within 24 hours of DFAS Notification for non-critical assets; 24 hours per day, seven (7) days per week, including federal holidays, when the Government determines the situation to be an Emergency.

An Emergency is defined as any condition requiring immediate corrective action to:

• Eliminate risk of injury or threat to personnel

• Prevent damage to Government property

• Maintain the security and integrity of DFAS-IN assets

The COR or requirement owner POC will determine whether a condition qualifies as an Emergency and will notify the Contractor accordingly.

5.2.2 Personnel and Equipment: The Contractor shall provide, at no additional cost, to the Government under the monthly FFP maintenance rate, all routine consumables, wiring, batteries, standard door contacts, and minor parts required to maintain the systems in a fully operational condition.

All required support, including outside services (e.g., electrician, lift equipment, specialty equipment), shall be provided at the Contractor’s expense unless otherwise authorized by the Contracting Officer. The Contractor shall provide the COR or requirement owner POC with a minimum of 72 hours advanced notice of when facility support is required prior to dispatching a technician.

5.2.3 Completion Timeline: emergency repairs shall be completed within twenty-four (24) hours of notification by the COR that the repair constitutes an emergency requirement. Emergency repairs for non-critical assets shall be completed within forty-eight (48) hours of notification by the COR, including weekends and federal holidays, unless otherwise authorized by the COR. The Contractor shall maintain adequate personnel, equipment, tools, and inventory necessary to support required response and completion timelines.

5.2.4 Testing and Verification: upon completion of repairs, the Contractor shall test the affected system to ensure full operational capability prior to considering the repair complete. Testing shall be conducted in the presence of DFAS-IN Security Officials. A DFAS-IN Security Official will verify and validate system functionality.

5.2.5 Work Authorization and Documentation: the COR or requirement owner POC will issue a work request for service. The Contractor shall ensure the assigned work order number is referenced on all documentation, reports, and invoices associated with the completed work.

5 | P a g e

5.3 In-Person Non-Emergency Repair/Service

5.3.1 Response Time: the Contractor shall maintain a qualified technician trained to service the DFAS- IN ACS and IDS within twenty-four (24) hours of DFAS Notification for non-emergency repairs., DFAS Notification is defined as the original call placed for a telephone consultation. Non-emergency repairs shall be performed during normal business hours, as indicated in paragraph 5.0. If the 24-hour response period falls on a Saturday, Sunday, or Federal holiday, the Contractor shall report on the next business day following the initial Government notification.

5.3.2 Personnel and Equipment: Major system equipment (including but not limited to Network Video Recorders, system controller boards, readers, cameras, lock hardware, and master alarm panels) shall be Government-Furnished Equipment (GFE). In the event of a major equipment failure, the Contractor shall perform diagnostic services and submit a formal technical report to the COR identifying the required replacement hardware. The Government will procure and furnish the required GFE component as indicated in Component Responsibility Mapping Chart in section 6.3. The Contractor shall be responsible for the physical installation, programming, integration, and testing of the Government-furnished component. Installation and troubleshooting labor shall be billed against the Time-and-Materials (T&M) repair labor CLIN.

All required support, including outside services (e.g., electrician, lift equipment, specialty equipment), shall be provided at the Contractor’s expense unless otherwise authorized by the Contracting Officer. The Contractor shall provide the COR or requirement owner POC with a minimum of 72 hours of advanced notice if coordination of facility support is required prior to dispatching a technician.

5.3.3 Completion Timeline: Non-Emergency Repairs shall be completed within five (5) business days of being reported, unless otherwise approved by the COR.

5.3.4 Testing and Verification: Upon completion of repairs, the Contractor shall test the affected system to ensure full operational capability prior to considering the repair complete. Testing shall be conducted in the presence of DFAS-IN Security Officials. A DFAS-IN Security Official will verify and validate system functionality.

5.3.5 Work Authorization and Documentation: The COR or requirement owner POC will issue a work request for service. The Contractor shall ensure the assigned work order number is referenced on all documentation, reports, and invoices associated with the completed work.

6.0 Government and Contractor Parts Responsibility: This section defines the division of responsibility for providing parts, equipment, and materials required to maintain the DFAS-IN ACS, IDS, and CCTV systems in a fully operational condition. This policy supersedes any conflicting language in other sections of the PWS.

6.1 Government Furnished Equipment (GFE):

6 | P a g e

The Government will provide all major replacement equipment required for repairs. The contractor’s responsibility is to diagnose a system failure, notify the COR that a major component has failed, and prepare for the installation of the GFE. Major equipment provided by the Government includes, but is not limited to, items listed in the "Government Provides" column of the Component Responsibility Chart in Section 6.3.

6.2 Contractor Furnished Parts & Materials:

The Contractor shall provide, at no additional cost to the Government, all minor parts, routine consumables, and materials necessary for preventative maintenance and repairs. The cost for these items must be included in the Contractor’s Firm-Fixed-Price (FFP) monthly maintenance CLIN. These items include, but are not limited to, those listed in the "Contractor Provides" column of the Component Responsibility Chart in Section 6.3. All contractor-provided parts shall be new or manufacturer-certified remanufactured parts compatible with the existing system.

6.3. Component Responsibility Mapping Chart:

To provide clear operational boundaries, the table below maps common system components to their respective contractual responsibilities.

System / Component Classification Material Provider (Who Pays for the Part?)

Installation Labor (Which CLIN?)

Backup Batteries (Altronix/PSU/Panel)

Routine Consumable Contractor (Fully covered under FFP

CLIN 0001)

Covered under FFP

CLIN 0001

Standard Door Contacts & BMS

Minor Part Contractor (Fully covered under FFP

CLIN 0001)

Covered under FFP

CLIN 0001 / FFP

PM

Standard Motion Detectors (PIR)

Minor Part Contractor (Fully covered under FFP

CLIN 0001)

Covered under FFP

CLIN 0001 / FFP

PM

Cabinet Tamper Switches

Minor Part Contractor (Fully covered under FFP

CLIN 0001)

Covered under FFP

CLIN 0001 / FFP

PM

7 | P a g e

System Wiring, Connectors, & Consumables

Consumables Contractor (Fully covered under FFP

CLIN 0001)

Covered under FFP

CLIN 0001 / FFP

PM

Master Access Control Panels (e.g., Lenel)

Major Equipment Government (Furnished as GFE)

Billed to T&M Repair Labor CLIN

Reader Interface Modules (RIMs)

Minor Equipment Contractor (Fully covered under FFP

CLIN 0001)

Covered under FFP

CLIN 0001 / FFP

PM

Card Readers (HID/PIV/Encrypted)

Minor Equipment Contractor (Fully covered under FFP

CLIN 0001)

Covered under FFP

CLIN 0001 / FFP

PM

Electric Strikes & Magnetic Locks

Minor Equipment Contractor (Fully covered under FFP

CLIN 0001)

Covered under FFP

CLIN 0001 / FFP

PM

Badging Printers & Enrollment Stations

Major Equipment Government (Furnished as GFE)

Billed to T&M Repair Labor CLIN

Master IDS Alarm Panels (Bosch/DMP)

Major Equipment Government (Furnished as GFE)

Billed to T&M Repair Labor CLIN

IDS Keypads & Expansion Modules

Minor Equipment Contractor (Fully covered under FFP

CLIN 0001)

Covered under FFP

CLIN 0001 / FFP

PM

Specialized Long- Range Motion Sensors

Major Equipment Government (Furnished as GFE)

Billed to T&M Repair Labor CLIN

8 | P a g e

IP Cameras (Fixed, Dome, Multi-sensor)

Major Equipment Government (Furnished as GFE)

Billed to T&M Repair Labor CLIN

High-End PTZ Cameras

Major Equipment Government (Furnished as GFE)

Billed to T&M Repair Labor CLIN

Network Video Recorders (NVR Servers)

Major Equipment Government (Furnished as GFE)

Billed to T&M Repair Labor CLIN

Core Network Switches & Power Injectors

Major Equipment Government (Furnished as GFE)

Billed to T&M Repair Labor CLIN

ADO (Automatic Door Opener)

Major Equipment Government (Furnished as GFE)

Billed to T&M Repair Labor CLIN

6.4 Cost Allocation:

The Time-and-Materials (T&M) Repair CLIN is for labor only. No parts, materials, or equipment of any kind shall be billed against the T&M CLIN. All costs for contractor-provided minor parts must be included in the FFP Maintenance CLIN. All major equipment will be provided as GFE at no cost to the contractor.

7.0 Limitations on Scope System Expansions: This contract covers maintenance, repair, and replacement-in-kind of existing DFAS-IN ACS and IDS components. New system installations, capacity increases, or expansions of existing systems beyond replacement-in-kind are outside the scope of this contract and shall require separate procurement action or contract modification issued by the Contracting Officer following a scope determination.

The Contractor shall not perform new installations, system expansions, or non-replacement upgrades without prior written authorization from the Contracting Officer.

7.1 Fiber Replacement: Replacement of fiber modules, cabling, and similar components required to restore existing system functionality shall be considered replacement-in-kind. The responsibility for providing these components shall be in accordance with the Component Responsibility Chart in Section 6.3.

9 | P a g e

7.2 Network Video Recorders (NVRs): NVRs are classified as Major Equipment. If NVR replacement is required, the contractor shall notify the COR in accordance with the GFE procedures outlined in Section 6.3.

8.0 Submittals

The Contractor shall submit the following reports and records to the contracts COR:

8.1 Test Reports: The Contractor shall submit written test reports documenting procedures performed and results obtained for all required field testing and inspections. Test reports shall be submitted within three (3) business days following completion of testing.

8.2 Manufacturer’s Field Reports: The Contractor shall submit Manufacturer’s Field Reports detailing:

• On-site activities performed

• Deficiencies identified

• Corrective actions taken

• Recommendations for follow-on action

Reports shall be submitted within three (3) business days following completion of service. The COR or requirement owner POC will review submitted reports for completeness and identify any required follow-on actions. Submission of the report does not constitute Government acceptance of any recommended follow-on work. Any work requiring Government action shall be coordinated through the COR, requirement owner POC and Contracting Officer, as applicable.

8.3 Service Records: The Contactor shall maintain service records in an electronic recordkeeping system and provide access to the COR or requirement owner POC within three (3) business days upon request. Records shall be available for review during normal business hours.

Service records, maintenance reports, test documentation, deficiency reports, and other deliverables generated specifically for performance under this contract shall be provided to the Government upon request or at contract completion.

9.0 System Equipment Requirements

9.1 ACS: The Contractor shall provide all labor, supervision, hardware, software, and equipment necessary to maintain the DFAS-IN ACS. The ACS includes, but is not limited to:

• Lenel OnGuard System Administration

• Alarm Monitoring

• Video Viewer

• Approximately 98 automatic door openers

• System hardware includes:

o 7 CPUs o 1 Server o 1 badge printer o Approximately 120-180 card readers o Door hardware (electrified mortise cylinders, panic devices, strikes) o Power supplies

10 | P a g e o Electric power transfer devices o Door contracts and sensors o 3-8 Network Video Recorders (NVRs) o 114-150 IP Cameras (including parapet cameras) o Associated wiring and related video equipment.

The Contractor shall maintain all wiring associated with the ACS.

9.2 IDS: The Contractor shall provide all labor, supervision, hardware, software, and equipment necessary to maintain the DFAS-IN IDS. The IDS includes, but are not limited to:

• Bosch and DMP panels

• Expansion modules

• Power supplies

• Standard and high-security door contacts

• Motion detectors

• Cabinet tamper switches

• Phone line modules

• Associated wiring and related hardware

The Contractor shall maintain all wiring associated with the IDS.

9.3 Quality Assurance and Surveillance Plan (QASP): The Government will monitor Contractor performance in accordance with the QASP. Performance standards and acceptable quality levels (AQLs) are defined in the Performance Requirements Summary (PRS), located in Section 11.0 of this PWS.

9.4 Monthly Uptime Report: The Contractor shall submit a Monthly Uptime Report to the COR or requirement owner POC for each standalone system. The report shall be submitted no later than the fifth

(5) business day of the following month. The report shall calculate system availability based on the following:

• Total minutes the system was expected to operational during the reporting month

• Total minutes the system was operational

Allowable repair time per incident shall be deducted as follows:

• Emergency Repair: 24 hours per incident

• In-Person Non-Emergency Repair: 50 hours per incident (5 business days at 10 hours per day)

The lesser of the allowable repair time or actual repair time shall be applied in the calculation.

10.0 Contractor Qualifications

10.1 Bosch and DMP System Qualifications: the Contractor shall possess and demonstrate a working knowledge of the Bosch and DMP IDS panels and associated devices to support full system operation as DFAS-IN. The Contractor shall maintain authorized reseller status for both Bosch and DMP products.

Annual proof of current reseller authorization shall be submitted to the COR or requirement owner POC.

The Contractor shall:

1. Maintain current authorized reseller status for Bosch and DMP products.

11 | P a g e

2. Employ technicians assigned to this contract who hold current manufacturer certifications specific to Bosch and DMP IDS panels and associated system components.

3. Ensure technicians assigned to this contract possess either:

a. minimum of three (3) years of documented experience servicing commercial or Government intrusion detection systems of similar size and complexity or

b. equivalent relevant experience and training, including a combination of current OEM manufacturer certifications and demonstrated hands on experience supporting Bosh and DMP IDS panels and associated system components.

10.2 Technical Knowledge: the Contactor shall possess demonstrated working knowledge of Lenel OnGuard software applications.

10.3 Certifications: The Contractor shall maintain and submit annual proof of LENEL/On-Guard Certifications for personnel supporting this contract to the COR or requirement owner POC shall be within five (5) business days of any certification expiration or personnel change.

10.4 Authorized Reseller Status: the contractor shall maintain status as a LENEL Value Added Reseller (VAR) and shall submit annual proof of current VAR authorization to the COR or requirement owner POC within five (5) business days of any certification expiration or personnel change.

Failure to maintain required reseller status or technician certifications may result in removal of affected personnel from contact performance and may constitute grounds for contract remedies in accordance with the applicable contract clauses.

11.0 Performance Requirements Summary Standards:

Performance Objective

Performance Standard

Acceptable Quality Level (AQL)

Surveillance Method

Preventative Maintenance Plan

Submitted for COR Review 30 calendar days after award.

100% COR review and approval.

Telephone Response Respond within 2 hours of DFAS Notification, 24/7/365

100% COR review of call logs

Emergency On-Site Response

Technician onsite within 4 hours of Emergency determination

100% COR verification of dispatch records

12 | P a g e

Emergency Repair Completion

Completed within 24 hours of report

95% monthly COR review of work orders

Non-Emergency On- Site Response

Onsite within 24 hours (next business day if applicable)

95% monthly COR review of service logs

Non-Emergency Repair Completion

Completed within 5 business days

95% monthly COR review of work orders

System Testing & Verification

Systems tested and verified prior to closeout

100% COR witnessing or documentation review

Service Documentation Submission

Reports submitted within 3 business days

95% monthly COR tracking log

Service Record Maintenance

Records provided within 3 business days of request

100% COR review

Monthly Uptime Report

Submitted by 5th business day of following month

100% COR review

System Availability (Uptime)

Maintain ≥ 98% monthly uptime per standalone system

98% minimum Government calculation using submitted data

Lenel Certification Compliance

Annual proof of certification submitted and current

100% COR document review

13 | P a g e

VAR Status Compliance

Maintain current Lenel VAR status annually

100% COR verification

Bosch & DMP Reseller Status

Maintain current authorized Bosch and DMP reseller status throughout contract performance

100% Annual documentation review by COR

Bosch & DMP Technician Certification

All technicians assigned to IDS work maintain current manufacturer certifications

100% COR review of certification documentation prior to performance and annually

Bosch & DMP Experience Requirement

Assigned technicians possess minimum three

(3) years of documented IDS experience

100% Resume and qualification review by COR at onboarding

Certification Maintenance & Updates

Updated certification documentation submitted within 5 business days of expiration or personnel change

100% COR tracking log

12.0 Invoice Submissions: Contractors shall comply with the Wide Area Workflow (WAWF) electronic invoice system when submitting invoices for payment. All invoices and receiving reports must be submitted electronically through the WAWF in accordance with the DFARS 252.232-7006, WAWF Payment Instructions. The Contractor shall ensure that all required data fields are completed accurately, and that appropriate supporting document is attached. Failure to comply with WAWF submission requirements may result in payment delays. Specific WAWF instructions, including document types and routing codes, will be provided by the CO or designated representative at the time of the award.

12.1 Inspection/Acceptance: The COR is designated as the Government’s representative for final inspection and acceptance of services performed under this contract. All services are subject to inspection to ensure compliance with contract requirements prior to acceptance.

12.3 Contracting Officer Representative (COR): A COR will be appointed in writing by the Contracting Officer to provide technical oversight and contact administration support. The written designation letter will define the scope of the CORs authority and any limitations. The COR is authorized to provide technical directions to the Contactor, providing such directions:

• Are within the scope of the contract.

• Does not constitute a change to the contract terms and conditions.

• Does not result in any funding obligation or modification.

14 | P a g e

The COR is not authorized to make changes to the contact’s terms, conditions, scope, price, or period of performance. Only the Contacting Officer has authority to modify the contract. Any proposed changes or requests for modification shall be submitted to the Contracting Officer for review and written approval.

Upon contract award, a formal letter of designation will be issued to the COR and provided to the Contactor.

13.0 Security Requirements for Unclassified Information

General Requirements. Contractor personnel must meet the following conditions of employment:

1. Must be a U.S Citizen or National.

2. Registered for Selective Service (males born after 12-31-1959). A Status Information Letter is required for any male born after 12-31-1959 that is not registered with Selective Service.

3. This is a national security position which requires favorable fitness review and background investigation as a condition of employment. Failure to maintain security eligibility may result in the denial or revocation of access to Government facilities, systems, or information and may require removal of the individual from performance under this contract.

Personnel Security Investigation (PSI) Requirements

Contractor personnel performing work under this contract must possess a favorably adjudicated Tier 3 investigation, or equivalent Noncritical-Sensitive (formerly IT-II) investigation, or a higher-level investigation granting National Security eligibility. At a minimum, Contractor personnel must have a favorably adjudicated Tier 1 investigation.

Contractor personnel must also have current enrollment (within 5 years) in the Continuous Vetting program, in accordance with Trusted Workforce 2.0 standards. No access to classified information is required. In accordance with standard DFAS Personnel Security policy, ALL incoming contractors must submit a new set of fingerprints (taken within the last 30 days) *.

Contractor personnel must apply for a fingerprint appointment immediately (the next business day) upon award date.

Contractor personnel shall submit the Contractor Request for Investigation (CRI) (DFAS Form 9035) immediately (the next business day after providing fingerprints) to the Contracting Officer Representative (COR). The information needed in the Declaration for Federal Employment (OF-306) also is submitted to the COR by contractor personnel.

The COR will submit the OF-306, DFAS Form 9035, and proof of fingerprints to DFAS Personnel Security all at once. Under no circumstances should this documentation be submitted less than fifteen

(15) calendar days prior to the intended performance start date. DFAS Personnel Security will review all submitted documentation to validate whether contractor personnel meet personnel security requirements to perform work on the contract or if a new background investigation is required.

15 | P a g e

Contractors obtaining favorable security evaluations and DoD CACs for required contractor employees performing on this contract are a prerequisite for contractor performance and invoicing. Also, the failure of a contractor to provide employees who can obtain a favorable security adjudication and a DoD CAC in a timely manner may be considered negatively when assessing contractor performance, termination, or other.

*New fingerprints are not required if any of the following are applied:

1. The person has been fingerprinted for the Defense Counterintelligence and Security Agency (DCSA) within the past 30 days.

2. The person is currently undergoing a background investigation, or reinvestigation, by DCSA or any other Federal agency.

3. The person has a background investigation currently being adjudicated by the DCSA Adjudication and Vetting Services (DCSA TD(a) or another TD(a).

4. The person has been favorably adjudicated within the past 30 days by the DCSA TD(A) or a TD(a) from any other Federal agency: or

5. The person comes directly from another DoD agency, with no break in service. This includes any of the military branches as well as the U.S. Coast Guard; however, service members in an inactive reserve status are not included.

6. The DFAS Personnel Security Office otherwise determines that no new fingerprints are required.

Regulatory Requirements

Contractor personnel shall follow the security and training requirements in DoDM 5220.23, “Industrial Security Procedures For Government Activities,” DoDM 5200.01, Volumes 1-3, “DoD Information Security Program,” DoDI, 5200.48, “Controlled Unclassified Information,” DFAS 2000.1-I, “Force Protection Mission,” DFAS 5200.1-I, “Information Security Program,” DFAS 5200.8-I, “Physical Security Program,” and DFAS 5200.10-I, “Counter Insider Threat Program.”

Contractor personnel shall follow all host security requirements in accordance with Part 117 of Title 32, Code of Federal Regulations; paragraph 117.16. Ensure that all contracting officers include applicable clauses in all contracts that require work to be performed for a DFAS location. The contractor shall immediately report any occurrences of violation of stated regulations to the DFAS Manager of the area to which they are assigned, Contracting Officer (CO), COR, Director, Force Protection, and the DFAS Personnel Security Office. DoD Issuances can be located at the following web link:

https://www.esd.whs.mil/dd/dod-issuances/

DFAS Instructions can be located at the following agency portal web link:

Official Forms and Pubs - All Documents https://www.esd.whs.mil/dd/dod-issuances/ https://dfasportal.dfas.mil/docs/Documents/Forms/AllItems.aspx?RootFolder=%2fdocs%2fDocuments%2fOfficial%20Forms%20and%20Pubs&FolderCTID=0x012000C5AD4BBE89E91A47852CADC95291E394

16 | P a g e

DFAS Personnel Security Incident Reporting Requirements, the National Industrial Security Program and Due Process as it Relates to DFAS Contractor Personnel

The National Industrial Security Program (NISP) is a partnership between the federal government and private industry to safeguard classified information and CUI.

Executive Order 12829, as amended, "National Industrial Security Program," further amended by Section 6 of E.O. 13691, was established to achieve cost savings and to ensure that industry safeguards the classified information with which it is entrusted while performing work on contracts, programs, bids, or research and development efforts while working for the United States Government.

It is important to note that personnel employed as contractors for DFAS are not covered under the National Industrial Security Program (NISP) and are exempt from the provisions of 5 C.F.R. 731. This means that DFAS contractor personnel involved in an incident that potentially violates one or more of the National Security Adjudicative Guidelines found at https://www.dni.gov/files/NCSC/documents/Regulations/SEAD-4-Adjudicative-Guidelines-U.pdf , are not entitled to Due Process rights normally afforded to federal civilian employees and those personnel covered under NISP; more specifically, DFAS Personnel Security may suspend or revoke contractor personnel access to DFAS IT systems, sensitive information and/or DFAS facilities.

Incident Reporting Requirements

In all cases, whenever a DFAS contractor displays conduct, or is involved in any incident, which is in violation of any of the thirteen National Security Adjudicative Guidelines*, the contractor must immediately report the incident to the contractor company Security Office/Facility Security Officer, the DFAS Manager of the area to which they are assigned, the CO, the COR, the Director, Force Protection, and the DFAS Personnel Security Office. Reporting to DFAS Personnel Security may be made by phone to (317) 212-7888, by email to dfas.indianapolis-in.zh.mbx.dfas-inhrsecurity@mail.mil, or, in the case of personnel physically located at DFAS Indianapolis Center, in person to the DFAS Personnel Security Office located on the third-floor center hallway at Column 320T.

All incidents will be investigated by DFAS Personnel Security and, depending on the date of the subject’s most recent investigation, may need to have an updated background investigation initiated. Those that do not require a new investigation will have all relevant information regarding the incident forwarded to the DCSA TD(a) for review and re-adjudication.

*The thirteen National Security Adjudicative Guidelines are:

1. GUIDELINE A: Allegiance to the United States

2. GUIDELINE B: Foreign Influence

3. GUIDELINE C: Foreign Preference

4. GUIDELINE D: Sexual Behavior

5. GUIDELINE E: Personal Conduct

6. GUIDELINE F: Financial Considerations

7. GUIDELINE G: Alcohol Consumption

8. GUIDELINE H: Drug Involvement and Substance Misuse

9. GUIDELINE I: Psychological Conditions

10. GUIDELINE J: Criminal Conduct

11. GUIDELINE K: Handling Protected Information

12. GUIDELINE L: Outside Activities https://www.dni.gov/files/NCSC/documents/Regulations/SEAD-4-Adjudicative-Guidelines-U.pdf mailto:dfas.indianapolis-in.zh.mbx.dfas-inhrsecurity@mail.mil

17 | P a g e

13. GUIDELINE M: Use of Information Technology

Some Examples of Incidents That Require Reporting to DFAS Personnel Security:

a) An arrest for any criminal offense, not including minor traffic violations, by any law enforcement agency. This DOES include the traffic offenses of Driving Under the Influence of Alcohol or Drugs, and Reckless Driving.

b) Violation of any court order.

c) Civil judgements.

d) Delinquencies on any debt for 180 days or longer.

e) Federal, State or Local tax issues or delinquencies.

f) Delinquencies on any Federal debt (including Federal Student Loans and Federally backed home mortgage loans).

g) Child Support delinquencies.

h) Filing for Chapter 7 or Chapter 13 bankruptcy in any Federal Bankruptcy Court.

i) Foreign Travel.

j) Marriage or Cohabitation with a Foreign National (person from a foreign country).

k) Having a close personal friendship with a Foreign National with regularly occurring contact.

l) Ownership of property or financial accounts in a foreign country; and

m) Being approached by a person know to be, or suspected to be, working as an agent of a foreign government or terrorist organization, or any other person, who seeks any information about DFAS, the Department of Defense, or the U.S. Government, especially if the person offers money or something of value to the contractor employee.

It should be noted that a person’s delinquency on Federal debt of any kind may not obtain or maintain favorable personnel security adjudication or be considered for a contractor position with DFAS unless they can provide documentary proof that a payment plan has been established with the Government agency to whom the debt is owed, and that regularly recurring payments are being made. Contractor personnel who cannot obtain and maintain a favorable personnel security adjudication may not have access to government data, facilities, and/or equipment required under the contract.

NOTE: This list does not cover every potential incident or offense; any incident in which a contractor is involved, and a question exists as to whether it should be reported, should report the incident to DFAS Personnel Security, who will then determine if further action is warranted. Failure to report an incident is, in and of itself, an incident involving personal conduct, and may, in some cases, be more serious than the original incident.

18 | P a g e

Foreign Travel by DFAS Contractor Personnel

Official and Unofficial (Personal) Travel: Official U.S. Government Business: persons employed as contractor employees with DFAS, to include those with Noncritical Sensitive (formerly IT-II) access, Critical Sensitive (formerly IT-I) access, access to critical program information (related to Research, Development, Test, and Evaluation), sensitive compartmented information, and/or special access program information, in accordance with DoD Directive 5240.06, are required to complete a DFAS Form 9133, Notification of Foreign Travel, not less than 30 calendar days prior to the scheduled travel.

One copy shall be sent the DFAS Personnel Security group box at dfas.indianapolis-in.zh.mbx.dfas-inhrsecurity@mail.mil and one copy shall be turned into the Site Force Protection Office of the DFAS site where they are stationed. Site Force Protection POC information:

https://dfasportal.dfas.mil/ddss/force_protection/Pages/SiteSpecificForceProtectionSecurityServices.aspx

Upon receipt of the complete Form 9133, the Site Force Protection Office will contact the contractor employee to validate training, complete the country/theater clearance package, as required, and schedule a Foreign Travel briefing. Immediately prior to travel, contractor employees will check with the State Department at https://travel.state.gov/en/international-travel/travel-advisories.html/ for any travel advisories for the country or region being traveled to and take the appropriate steps to ensure their safety for any location covered by a travel advisory or warning.

Security Education and Training

Contractor personnel shall receive initial, continuous and refresher security education training in accordance with DoDM 5200.01, Volume 3, “DoD Information Security Program – Protection of Classified Information,” DoDI 5200.48, DFAS 2000.1-I, DFAS 5200.1-I, DFAS 5200.8-I, and DFAS 5200.10-I. Contractor personnel shall also complete all required contractor training requirements identified in this PWS.

Access To, Accountability For, and Safeguarding of Controlled Unclassified Information (CUI)

The DFAS manager of the required office will determine what CUI contractor personnel are given access

to. CUI may not be disclosed to contractor personnel unless required for contract performance.

Contractor personnel shall safeguard CUI in accordance with DoDI 5200.48 and DFAS 5200.1-I. The sponsoring DFAS activity will provide storage capability for all CUI required for contract performance.

Contractor personnel must monitor CUI for aggregation and compilation based on the potential to generate classified information. Contractor personnel must report the potential classification of aggregated or compiled CUI to the DFAS Manager of the area to which they are assigned, the CO, the COR, and the Director, Force Protection.

Installation Entry and Common Access Card (CAC) Requirements

The Contractor shall comply with established security procedures for entering government installations and facilities. Contractor employees shall be required to obtain and wear identification (ID) badges that will permit access into the facility.

https://dfasportal.dfas.mil/ddss/force_protection/Pages/SiteSpecificForceProtectionSecurityServices.aspx https://travel.state.gov/en/international-travel/travel-advisories.html/

19 | P a g e

Contractors shall work with the assigned DFAS COR/Mission Partner Account Sponsor (MPAS) to obtain a CAC using Mission Partner Identity Credential Account Management (MP ICAM). Under no circumstances will a CAC be issued to any person unless that person has been cleared up by the DFAS Personnel Security Office to work on the contract.

All CACs and badges issued to Contractor personnel are government property and must be returned to the assigned DFAS COR/MPAS upon departure from the program or at the conclusion of the contract, whichever comes first. CACs can also be mailed in or turned into RAPIDS locations. Contractors whose CAC is lost or stolen must report the loss as soon as possible to the assigned DFAS COR/MPAS and present documentation that the CAC is missing and describe the circumstances under which the loss occurred. The assigned DFAS COR/MPAS will follow agency CAC procedures to issue a new CAC.

Contractors must not share their CACs and passwords with any other staff members. The assigned DFAS COR/MPAS will report any violation or suspected violation to the Contracting Officer and DFAS MP ICAM Account Security Manager (MPASM). Any violators will be temporarily or permanently removed from the project. If a Contractor has a CAC issued from another agency, that CAC must be revoked and returned before issuance of a new CAC.

Training

DoD Mandatory Contractor Personnel Training Requirements: The contractor shall direct that its employees performing under this contract complete the annual mandatory training in accordance with the DoD mandate identified for each training module.

Contractor personnel working at a DFAS site who require a CAC, or contractor personnel working remote via VPN, need to complete the following training modules within 30 days after receipt of CAC, (note for Cyber Awareness Challenge Module 003, completion of this module is required prior to requesting a new DFAS network or VPN account), as a precondition for continued attendance and/or network access.

In addition, these modules shall be completed annually to retain accessibility. Noncompliance will negatively impact on contract performance and lead to the loss of CAC and/or network access for contractor personnel.

Continuity of Operations and Crisis Management Organization

Contractor personnel will take the training through the DFAS Portal upon receipt of Network access.

Cyber Awareness Challenge

Completion of this module is required prior to requesting a new DFAS network or VPN account. For contractor personnel unable to access the DFAS Portal, the same training is available at:

Cyber Awareness Challenge

Upon completion of the training Contractor personnel shall maintain a copy of the training certificate in PDF, submit a copy to the COR, attached to the request for network access as proof of completion.

https://usg01.safelinks.protection.office365.us/?url=https%3A%2F%2Fwww.cyber.mil%2Fcyber-awareness-challenge&data=05%7C02%7Ckaren.l.ault.civ%40mail.mil%7Ceb3f4a7fb9ec43594c3108de01b9ce1b%7C102d0191eeae4761b1cb1a83e86ef445%7C0%7C0%7C638950094712890442%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=EUR7F2s47NvdCJN5HXRgI0sS8otbbHGjP3RTi5pGADA%3D&reserved=0

20 | P a g e

Keeping DFAS Safe: Physical Security, Information Security, Personnel Security, CBRNE, Counterintelligence and Operations Security

Contractor personnel shall take the training through the DFAS Portal upon receipt of Network access.

Level I Antiterrorism Awareness Training

All contractor personnel shall take this training. For contractor personnel who will not require or receive access to the DFAS Portal, this training is available at:

Level I Antiterrorism Awareness Training

All other contractor personnel shall take the training through the DFAS Portal upon receipt of network access.

Privacy Act (PA) and Personally Identifiable Information (PII)

Contractor personnel shall take the training through the DFAS Portal upon receipt of Network access.

Records Management

Contractor personnel shall take the training through the DFAS Portal upon receipt of Network access.

Insider Threat (InT) Awareness Training

Contractor personnel shall take the training through the DFAS Portal upon receipt of Network access.

DoD Mandatory Controlled Unclassified Information (CUI) Training

All contractor personnel shall take this CUI training. For contractor personnel who will not require or receive access to the DFAS Portal, this training is available at:

DoD Mandatory Controlled Unclassified Information (CUI) Training

All other contractor personnel will take the training through the DFAS Portal upon receipt of network access.

Unauthorized Disclosure of Classified Information and CUI

All contractor personnel shall take this training. For contractor personnel who will not require or receive access to the DFAS Portal, this training is available at:

Unauthorized Disclosure of Classified Information and Controlled Unclassified Information https://usg01.safelinks.protection.office365.us/?url=https%3A%2F%2Fjko.jten.mil%2Fcourses%2FAT-level1%2Flaunch.html&data=05%7C02%7Ckaren.l.ault.civ%40mail.mil%7Ceb3f4a7fb9ec43594c3108de01b9ce1b%7C102d0191eeae4761b1cb1a83e86ef445%7C0%7C0%7C638950094712922744%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=UMsAJtnZEt0R5ZX%2BVTTsNtnIJzEcFq%2BPpBQY3dvEkEU%3D&reserved=0 https://usg01.safelinks.protection.office365.us/?url=https%3A%2F%2Fsecurityawareness.dcsa.mil%2Fcui%2Findex.html&data=05%7C02%7Ckaren.l.ault.civ%40mail.mil%7Ceb3f4a7fb9ec43594c3108de01b9ce1b%7C102d0191eeae4761b1cb1a83e86ef445%7C0%7C0%7C638950094712942520%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=hKaM21diAU2Rwa24sjm5NDdqk1h7KWSLP2HYjt1k6n0%3D&reserved=0 https://usg01.safelinks.protection.office365.us/?url=https%3A%2F%2Fsecurityawareness.dcsa.mil%2Fdisclosure%2Findex.html&data=05%7C02%7Ckaren.l.ault.civ%40mail.mil%7Ceb3f4a7fb9ec43594c3108de01b9ce1b%7C102d0191eeae4761b1cb1a83e86ef445%7C0%7C0%7C638950094712958991%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=3zxgscj6HL1CPoi6yFIP2KSgRT0c5jXKIMn2CvwTD%2BA%3D&reserved=0

21 | P a g e

All other contractor personnel will take the training through the DFAS Portal upon receipt of network access.

NOTE: This list of training requirements is subject to change.

Training Time

The average estimated time for completion of each training module is approximately one hour or less.

Keeping DFAS Safe: Physical Security, Information Security, and Personnel Security training module will take approximately 90 minutes to complete.

Training Methods

Network Training: Network training through the DFAS Portal is the required method for those Contractor personnel who have an existing DFAS network account.

Web-based Training: All contractor personnel are required to take the…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .