Attachment 07 - Bedford MA EHRM Specifications IFC 20250604 Part1of3.pdf
PDF 17 MB Posted
- Solicitation number
- 36C77626R0003
About this file
This file is a comprehensive project specifications document (Attachment 07, Part 1 of 3) for EHRM Infrastructure Upgrades at Bedford VAMC, Department of Veterans Affairs Project Number 518-22-700, issued for construction on June 4, 2025. The document was prepared by Triple C - The A&E Group and includes detailed technical specifications across all construction divisions, plus the Infrastructure Standard for Telecommunications Spaces (ISTS) Version 4.0.
The project scope encompasses phased infrastructure upgrades to multiple buildings on the Bedford VAMC campus over a projected 730-calendar-day performance period. Key construction work includes: replacement of all communications cabling with fiber optic (OM4/OS2-10GB plenum rated) and CAT 6A copper cabling with 20 percent additional capacity; new telecommunications rooms (TR) and main computer room (MCR) infrastructure with redundant power distribution units, uninterruptible power supplies, and patch panels; new electrical distribution systems including service panels, transformers, and automatic transfer switches; dedicated mechanical cooling units with condensate management; fire suppression system modifications and new clean agent systems for MCR; new CCTV cameras integrated with existing video management systems; physical access control systems for all TR doors; site fiber conduit in concrete with trenching and hand-digging at utility crossings; and site work including concrete walkways, landscaping, and fencing. The contractor must provide all labor, materials, testing, and third-party inspections; maintain continuous medical center operations with no service interruptions except as approved; complete initial building commissioning before multi-building concurrent work; submit comprehensive project schedules and coordination drawings; and provide warranty management, operations and maintenance manuals, and training. Critical requirements include BICSI-licensed telecommunications contractors with five years' experience, registered communications distribution designers on-site throughout the project, certified testing laboratories, compliance with VA IT security and infection control standards, daily superintendent presence on-site with no concurrent project assignments, and phased utility shutdowns coordinated with the contracting officer at least two to three weeks in advance.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Veteran Affairs
Project Number: 518-22-700
EHRM Infrastructure Upgrades - Bedford
VAMC
Issued for Construction
PROJECT SPECIFICATIONS
Prepared For:
Department of Veteran Affairs 200 Springs Road Bedford, MA 01730
Prepared By:
Triple C - The A&E Group
100 Pearl Street Hartford, CT 06103
Project Team:
Triple C - Architecture/ Interiors/
MEP
Warren Bickerstaff
BICSI ID# 39965
Expires 12-31-2026
06/04/2025
06/04/2025
This page intentionally left blank.
EHRM Infrastructure Upgrades - Bedford VAMC Project #: 518-22-700
06-01-21
00 01 10 - 1
DEPARTMENT OF VETERAN AFFAIRS
EHRM INFRASTRUCTURE UPGRADES - BEDFORD VAMC
TABLE OF CONTENTS
SECTION 00 01 10
SECTIONS DIVISION AND SECTION TITLES DATE
NOT USED
NOT USED
00 01 01
NOT USED
00 01 10 06-2021 00 31 33
01 00 00 05-2021 01 00 00.A 01 00 00.B 01 00 00.C 01 00 00.D 01 32 16.15 01 33 23 06-2021 01 33 24
PROJECT FILES
COVER & TABLE OF CONTENTS
COVER PAGE
Project Title
DIVISION 00 — PROCUREMENT AND CONTRACTING REQUIREMENTS
DIVISION 00 — SPECIAL SECTIONS
Table of Contents Subsurface Drilling and Sampling Information
DIVISION 01 — GENERAL REQUIREMENTS
General Requirements Appendix A - OIT-InfrastrucStdTelecomSpaces Appendix B - Submittal Log Appendix C - VHA ICRA-1.2 (Oct 1 2024) Appendix D - VHA PCRA 2024 1.1 Final.Template Fillable Project Schedules (Small Projects) Shop Drawings, Product Data, and Samples Electronic Submittal Procedures
01 35 26 Safety Requirements 10-2022 01 42 19 Reference Standards 11-2020
01 45 00 QUALITY CONTROL 05-2021
01 45 00.01 Quality Control Sample Forms
01 45 29 TESTING LABORATORY SERVICES
01 45 35 Special Inspections 06-2021 01 45 35.01 Schedule of Special Inspections Template 04-2018 01 57 19 Temporary Environmental Controls 01-2021 01 58 16 Temporary Interior Signage 07-2015 01 74 19 Construction Waste Management 04-2022 01 81 13 Sustainable Construction Requirements 10-2017 01 91 00 General Commissioning Requirements 04-2022 01 91 00.A Commissioning Plan
DIVISION 02 — EXISTING CONDITIONS
02 21 13 Site Surveys 01-2021 02 41 00 Demolition 08-2017 02 82 11 Traditional Asbestos Abatement 02 82 13.13 Glovebag Asbestos Abatement 02 83 33.13 Lead-Based Paint Removal and Disposal 01-2021
06-01-21
00 01 10 - 2
DIVISION 03 — CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 04 — MASONRY
04 01 00 Maintenance of Masonry 04 05 13 Masonry Mortaring 04 05 16 Masonry Grouting
04 20 00 UNIT MASONRY
DIVISION 05 — METALS
05 12 00 STRUCTURAL STEEL FRAMING
05 31 00 STEEL DECKING
05 36 00 COMPOSITE METAL DECKING
05 40 00 COLD-FORMED METAL FRAMING
05 50 00 Metal Fabrications 08-2018
DIVISION 06 — WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry 06 20 00 Finish Carpentry
DIVISION 07 — THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 07 08 00 Facility Exterior Closure Commissioning 01-2021 07 21 13 Thermal Insulation 07 22 00 Roof and Deck Insulation 07 27 26 Fluid-Applied Membrane Air Barrier, Vapor Permeable 07 31 26 Slate Shingles 01-2021 07 32 13 Clay Roof Tiles 01-2021 07 54 23 TPO Roofing 07 60 00 Flashing and Sheet Metal 07 71 00 Roof Specialties 07 72 00 Roof Accessories 07 81 00 Applied Fireproofing 07 84 00 Firestopping 07 92 00 Joint Sealants
DIVISION 08 — OPENINGS
08 11 13 Hollow Metal Doors and Frames 08 14 00 Interior Wood Doors
08 31 13 ACCESS DOORS AND FRAMES
08 39 54 BLAST RESISTANT DOOR ASSEMBLIES
08 71 00 Door Hardware 08 80 00 Glazing
DIVISION 09 — FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 09 22 16 Non-Structural Metal Framing 09 29 00 Gypsum Board 09 30 13 Ceramic Porcelain Tiling 01-2021 09 51 00 Acoustical Ceilings 09 65 13 Resilient Base and Accessories 09 65 19 Resilient Tile Flooring 09 91 00 Painting
DIVISION 10 — SPECIALTIES
10 14 00 Signage 10 26 00 Wall and Door Protection 01-2021 10 44 13 Fire Extinguisher Cabinets
DIVISION 11 — EQUIPMENT
06-01-21
00 01 10 - 3
NOT USED
DIVISION 12 — FURNISHINGS
12 32 00 Manufactured Wood Casework 01-2021 12 36 00 Countertops 12-2018
DIVISION 13 — SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for non-structural Components
DIVISION 14 — CONVEYING EQUIPMENT
NOT USED
DIVISION 20 — MECHANICAL SUPPORT
NOT USED
DIVISION 21 — FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-2016 21 13 13 Wet-Pipe Sprinkler System 21 22 00 Clean Agent Fire Suppression Systems 05-2015
DIVISION 22 — PLUMBING
22 05 11 Common Work Results for Plumbing 01-2023 22 05 12 General Motor Requirements for Plumbing Equipment 09-2020 22 05 19 Meters and Gauges for Plumbing Piping 09-2020 22 05 23 General-Duty Valves for Plumbing Piping 11-2022 22 07 11 Plumbing Insulation 22 08 00 Commissioning of Plumbing Systems 22 11 00 Facility Water Distribution 05-2021 22 11 23 Domestic Water Pumps 09-2015 22 13 00 Facility Sanitary and Vent Piping 09-2020 22 14 00 Facility Storm Drainage 09-2015 22 35 00 Domestic Water Heat Exchangers 09-2020 22 40 00 Plumbing Fixtures 12-2022
DIVISION 23 — HEATING VENTILATING AND AIR CONDITIONING
23 05 11 Common Work Results for HVAC 04-2022 23 05 12 General Motor Requirements for HVAC and Steam Generation Equipment 03-2023 23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 03-2023 23 05 93 Testing, Adjusting, and Balancing for HVAC 03-2023 23 07 11 HVAC, Plumbing, and Boiler Plant Insulation 02-2020 23 08 00 Commissioning of HVAC Systems 03-2023 23 09 23 Direct-Digital Control System for HVAC 03-2023 23 22 13 Steam and Condensate Heating Piping 04-2023 23 23 00 Refrigeration Piping 03-2023 23 31 00 HVAC Ducts and Casings 03-2023 23 34 00 HVAC Fans 03-2023 23 36 00 Air Terminal Units 03-2023 23 37 00 Air Outlets and Inlets 03-2023 23 40 00 HVAC Air Cleaning Devices 03-2023 23 73 00 Indoor Central-Station Air-Handling Units 03-2023 23 81 00 Decentralized Unitary HVAC Equipment 03-2023 23 81 23 Computer-Room Air-Conditioners 03-2023 23 82 00 Convection Heating and Cooling Units 03-2023 23 82 16 Air Coils 03-2023
DIVISION 25 — INTEGRATED AUTOMATION
25 10 10 Advanced Utility Metering System 02-2010
DIVISION 26 — ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-2022
06-01-21
00 01 10 - 4
26 05 13 Medium-Voltage Cables 11-2022 26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-2022 26 05 26 Grounding and Bonding for Electrical Systems 11-2022 26 05 33 Raceway and Boxes for Electrical Systems 11-2022 26 05 41 Underground Electrical Construction 11-2022 26 05 73 Overcurrent Protective Device Coordination Study 11-2022 26 08 00 Commissioning of Electrical Systems 11-2016 26 09 23 Lighting Controls 11-2022 26 11 16 Secondary Unit Substations 11-2022 26 12 19 Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers 11-2022 26 13 13 Medium-Voltage Circuit Breaker Switchgear 11-2022 26 13 16 Medium-Voltage Fusible Interrupter Switches 11-2022 26 22 00 Low-Voltage Transformers 11-2022 26 23 00 Low-Voltage Switchgear 11-2022 26 24 13 Distribution Switchboards 11-2022 26 24 16 Panelboards 11-2022 26 25 11 Busways 11-2022 26 26 00 Power Distribution Units for Static Uninterruptible Power Systems 11-2022 26 27 26 Wiring Devices 11-2022 26 29 11 Motor Controllers 11-2022 26 29 21 Enclosed Switches and Circuit Breakers 11-2022 26 33 53 Static Uninterruptible Power Supply 11-2022 26 35 26 Harmonic Filters 11-2022 26 36 23 Automatic Transfer Switches 11-2022 26 41 00 Facility Lightning Protection 11-2022 26 42 00 Cathodic Protection 11-2022 26 43 13 Surge Protective Devices 11-2022 26 51 00 Interior Lighting 11-2022 26 56 00 Exterior Lighting 11-2022
DIVISION 27 — COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-2019 27 05 26 Grounding and Bonding for Communications Systems 27 05 33 Raceways and Boxes for Communications Systems 27 05 36 Cable Trays for Communications Systems 27 05 53 Identification for Communications Systems 27 08 00 Commissioning of Communications Systems 27 10 00 Control, Communication and Signal Wiring 27 10 00.1 Structured Cabling 27 11 00 Telecommunications Room Fittings 27 11 16 Communications Cabinets, Racks, Frames, and Enclosures 27 11 19 Communications Termination Blocks and Patch Panels 27 11 26 Communications Rack Mounted Power Protection and Power Strips 27 13 13 Communications Copper Backbone Cabling 27 13 13.13 Communications Copper Cable Splicing and Terminations 27 13 23 Communications Optical Fiber Backbone Cabling 27 15 00 Communications Structured Cabling 27 15 13 Communications Copper Horizontal Cabling 27 15 13.13 Communications Optical Fiber Cable Splicing and Terminations 27 16 19 Communications Patch Cords, Station Cords, and Cross Connect Wire
DIVISION 28 — ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-2018 28 05 13 Conductors and Cables for Electronic Safety and Security 28 05 26 Grounding and Bonding for Electronic Safety and Security 28 05 28.33 Conduits and Backboxes for Electronic Safety and Security 28 08 00 Commissioning of Electronic Safety and Security Systems 11-2016
06-01-21
00 01 10 - 5
28 13 00 Physical Access Control Systems 28 23 00 Video Surveillance 09-2011 28 31 00 Fire Detection and Alarm
DIVISION 31 — EARTHWORK
31 20 00 Earthwork 31 23 19 Dewatering 10-2012 31 23 23.33 Flowable Fill 10-2012
DIVISION 32 — EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 32 12 16 Asphalt Paving
32 17 23 PAVEMENT MARKINGS
32 84 00 Planting Irrigation 32 90 00 Planting
DIVISION 33 — UTILITIES
33 08 00 Commissioning of Site Utilities
33 10 00 WATER UTILITIES
33 30 00 SANITARY SEWER UTILITIES
33 40 00 STORM SEWER UTILITIES
33 63 00 STEAM ENERGY DISTRIBUTION
DIVISION 34 — TRANSPORTATION
34 71 13 PASSIVE VEHICLE BARRIERS
DIVISION 35 — WATERWAYS AND MARINE CONSTRUCTION
NOT USED
DIVISION 40 — PROCESS INTERCONNECTIONS
NOT USED
DIVISION 41 — MATERIAL PROCESSING AND HANDLING EQUIPMENT
NOT USED
DIVISION 42 — PROCESS HEATING, COOLING, AND DRYING EQUIPMENT
NOT USED
DIVISION 43 — PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND
STORAGE EQUIPMENT
NOT USED
DIVISION 44 — POLLUTION CONTROL EQUIPMENT
NOT USED
DIVISION 45 — INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT
NOT USED
DIVISION 46 — WATER AND WASTEWATER EQUIPMENT
NOT USED
DIVISION 48 — ELECTRICAL POWER GENERATION
NOT USED
VA Bedford Health Care System
Project #: 518-22-700
Subsurface Drilling and Sampling Information
00 31 33 - 1
SECTION 00 31 33
SUBSURFACE DRILLING AND SAMPLING INFORMATION
PART 1 - GENERAL
1.1 GEOTECHNICAL REPORT
A. Geotechnical Report dated _________________ has been prepared by ___________________________ for Owner. Report was prepared to assist in design process.
Copies are available upon request.
B. No representation or warranty is made by Architect, Engineer, Owner or any other party regarding completeness, accuracy, adequacy, or contents of report or of the subsurface investigation upon which report is based.
C. Copies of report are on file and may be reviewed at office of testing laboratory and VA Medical Center and attached to this section.
D. Samples of core borings recovered may be observed at ____.
1.2 OFFEROR RESPONSIBILITY
A. Offerors accept full responsibility for using soil information in preparing offers.
B. Offerors is responsible to obtain, at its expense, any additional information necessary to offer and perform Work.
C. Offerors agree they will make no claim, exceeding actual cost of work, if, in performing the Work, they find actual subsurface conditions encountered do not conform to those indicated by soil borings, test excavations, and other subsurface investigations.
PART 2 - PRODUCTS - NOT USED
PART 3 - EXECUTION - NOT USED
END OF SECTION
Project #: 518-22-700
General Requirements
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 - GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for EHRM Infrastructure Upgrades - Bedford VAMC as required by drawings and specifications.
B. All installed cables shall be terminated at each end and documentation, labeling, and (where applicable) test results provided. This applies to all permanently installed cable types. Building fiber will be plenum rated OM4 and OS2-10GB.In addition to replacing all of the communications cabling, an additional 20% capacity, in terms of cable count, shall be provided as shown on the drawings and specifications. All Copper replacement will be CAT 6A. CAT 6A Patch Cords shall be provided and installed for all locations, including patch cords at the End User Device and at the TR.
C. The VA Contracting Officer will schedule an organized site visit during the solicitation process.
Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting Officer.
D. Offices of Triple C - The A&E Group at 100 Pearl Street, 14th Floor, Hartford, CT 06103, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
E. Prime Contractor Personal Minimum Requirements:
1. As Required in other parts of the Project Manual and Contract Requirements the following are minimum requirements:
a. The Superintendent shall be an employee of the Prime Contractor with authority to act as the contractor, responsible for the day-to-day operations at the construction site, planning, quality control, verification of delivery of approved material and equipment, subcontractor coordination responsibilities and execution of the complete project as per the contract documents.
1) Superintendent shall have no hands-on construction interaction. In addition, the superintendent shall provide proof to the COR regarding completion of 30 hour OSHA.
2) Superintendent assigned to this project shall not be assigned to any other project and shall only have duties on one project at a time.
3) The Superintendent shall sign-in at the beginning of each day of work and Sign-out at the end of the work day at the Office of Engineering Service. No work shall be performed by any contractors or subcontractors without the presence of the superintendent at the actual work site.
4) The Superintendent shall be responsible for submitting daily work logs to the COR at the end of every work day.
b. Site Safety and Health Officer (SSHO) shall be a separate qualified individual from the Prime Contractor’s Superintendent or CQC System Manager with duties only as the SSHO. See 01 35 26 SAFETY REQUIREMENTS for more information on roles and responsibilities for General Contractor’s staff.
Project #: 518-22-700
General Requirements
01 00 00 - 2
c. CQC System Manager shall be a separate qualified individual from the Prime Contractor’s Superintendent or Site Safety and Health Officer (SSHO) with duties only as the CQC System Manager. See Section 01 45 00 Quality Control for more information on roles and responsibilities for CQC Personnel.
d. The Prime contractor shall provide services of a Project Manager whose responsibilities would include but not be limited to providing support to the Superintendent at the job site and shall be responsible for finance related tasks and scheduling.
F. Dig Permit
1. The contractor shall complete the VA dig permit with the COR and submit the Dig Safe notification prior to start of any excavation work.
G. Electrical Work Permit
1. The contractor shall complete the VA Electrical Work Permit with the COR and submit to the COR a minimum of 72 hours prior to start of electrical work within the facility.
H. Welding and Cutting
1. A Hot Work Permit is required. See Section 01 35 26, SAFETY REQUIREMENTS for requirements.
I. Contract Work Hours
1. With the exception of all network cable replacements (which shall be performed after-hours), work shall be accomplished during normal work hours. Normal working hours for this contract will be 7:00am to 4:30pm (local time) Monday through Friday except for weekends and established Federal Holidays.
2. Performing on-site work outside normal working hours will require approval from the Contracting Officer and the COR. Requests shall be submitted via email at least 72 hours prior to the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.
3. For certain aspects of work the Contractor shall be required to work off duty hours to perform that part of the work, for continued operations of the Medical Center. After duty hours work shall be coordinated with and approved by the COR.
a. Noisy demolition work, work at building entrances, electrical or other utility work necessary to pass within, above, traverse hallway corridors, temporary shutdowns of utilities for tie-in.
J. Contractor shall perform work in accordance with requirements of “ASHE Construction in a Healthcare Facility”.
K. Contractor shall adhere to all requirements documented in the “Infrastructure Standard for Telecommunications Spaces, Version 4.0”, “OEHRM Site Infrastructure and Und User Device (EUD) Requirements, Version 2.0” and the “VA Physical Security and Resiliency Design Manual”. Deviation from VA standards is not allowable.
L. Contractor shall execute electrical, communications and security systems installations in accordance with TIA, VA and BICSI installation standards. The telecommunications contractor shall be a BICSI licensed Contractor with a minimum of five (5) years’ experience installing and servicing systems of similar scope and complexity. The Contractor shall provide four (4) current references from clients with systems of similar scope and complexity which became operational in the past three (3) years. At least three (3) of the references shall be utilizing the same system components, in a similar configuration as the proposed system. The references must include a current point of contact, company or agency name, address, telephone number, complete system description, date of completion, and approximate cost of the project. The owner reserves the option to visit the reference sites, with the site owner’s permission and representative, to verify the quality of installation and the references’ level of satisfaction with the system. The Contractor shall provide copies of system manufacturer certification for all technicians. The Contractor shall provide proof project superintendent with BICSI Certified
Project #: 518-22-700
General Requirements
01 00 00 - 3
Commercial Installer Level 1, Level 2, or Technician to provide oversight of the project. Cable installer must have on staff a Registered Communication Distribution Designer (RCDD) certified by Building Industry Consulting Service International (BICSI). The RCDD licensed staff member shall be on-site throughout the life of the project to oversee all telecommunications and security scope and shall provide consistent oversight of the project cabling throughout design, layout, installation, termination, and testing.
M. All testing shall be by certified testing laboratories subcontracted by the Contractor. The Government shall not be required to contract testing for any trade.
N. All employees of general contractor and subcontractors shall comply with VA IT security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access. All employees of general contractor and subcontractors shall have successfully passed VA IT background checks or be escorted to work on Government networks. VA Engineering IT staff are not available to continuously escort and monitor Contractor activities.
O. The Government does not provide courtesy, pre-inspections of area during the construction.
The Contractor shall request progress inspections and communicate requests for inspections at least one week in advance.
P. Contractor’s Daily Logs shall be submitted to the VA COR on a weekly basis.
Q. The Contractor shall submit on a weekly basis to the Contracting Officer's Representative (COR) completed Interim Life Safety Measures (ILSM) Forms.
R. The Contractor shall submit on a weekly basis to the Contracting Officer's Representative (COR) completed Infection Control Risk Assessment (ICRA) Forms
S. Contractor shall provide Submittal Exchange®, Autodesk Build® and/or ProCore Project Site dedicated for this project or approved equal (substitutions must be submitted with Contractor Bid), for the duration of the contract. Contractor will provide VA access to the site. Contractor will keep this site current and will use it for all submittals, RFIs, change documents, Record Drawing, electronic file management, and communication logs for the duration of the contract.
T. Contractor shall provide Infection Control Plan as required by Memorandum 111-40, Subj: VHA Directive 7715 Safety and Health During Construction dated April 6, 2017. Submit to COR for approval prior to the start of work.
U. Prior to commencing work, general contractor shall provide proof that an OSHA designated “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present. CP will have authority letter.
V. The General Contractor’s Superintendent assigned to this project shall not be assigned to any other project and shall only have duties on one project at a time. See 01 35 26 SAFETY REQUIREMENTS for more information on roles and responsibilities for General Contractor’s staff. The Superintendent shall be a separate qualified individual from the Prime Contractor’s Quality Control Manager (QCM) or Site Safety and Health Officer (SSHO) with duties only as the Superintendent. SSHO shall be a separate qualified individual from the Prime Contractor’s Superintendent or QCM with duties only as the SSHO. QCM shall be a separate qualified individual from the Prime Contractor’s Superintendent or SSHO with duties only as the QCM.
W. Refer to specifications for installation requirements for each Division. Refer to drawings for estimated quantities and schematic layouts/locations. Contractor to provide a complete, commissioned, functioning product. The VA is not required to inspect or install any portion of this project. Contractor bears all installation and testing costs. Contractor to provide all testing reports prior to the start of commissioning. This project requires phased commissioning and turnover by building. This project may require limited night and weekend work during utility changeover; however all cable replacements will occur during normal business hours, using the phasing plans developed by the Contractor to maintain continuous network service.
Project #: 518-22-700
General Requirements
01 00 00 - 4
X. Per VA Directive 1085, smoking, vaping and smokeless tobacco are prohibited on the grounds of VA facilities, including in vehicles. This Directive applies to all Prime Contractor and Subcontractor employees.
Y. Pricing Proposal transparency requirements:
1. This project requires pricing proposals to include breakdown pricing for the General
Contractor and all subcontractors.
2. All price proposals, shall including subcontractor pricing must include a breakdown of pricing per the format included with this Project Manual. Third-party inspections must be included as a line item in the price proposal. See example at the end of Section 00 41 13
BID FORM.
Z. The commissioning agent (CxA) shall be a third-party entity provided by the VA under a separate contract.
1. The Firm and designated Commissioning Authority shall have been the principal commissioning authority on a least three (3) comparable projects that have been completed within the previous five (5) years.
2. The proposed commissioning firm should be certified by at least one of the following agencies:
a. National Environmental Balancing Bureau (NEBB)
b. AABC Commissioning Group (AGC)
c. Building Commissioning Association (BCxA)
3. The Fire Protection Commissioning Specialist should be a registered Fire Protection Engineer in at least one state.
a. He/she should have a minimum of 5 years’ experience with design, installation, inspection, or testing of fire protection systems, and/or smoke control systems.
4. The Building Envelope Commissioning Specialist should be a Registered Architect in at least one state.
a. He/she should also have a minimum of five (5) years’ experience with design, installation, or inspection of building envelope components.
5. The Controls Commissioning Specialist should have a minimum of 5 years’ experience in design, installation, programming, inspection, or testing of direct digital control systems for HVAC systems.
6. Key members of the Commissioning Authority’s commissioning team should have:
a. Bachelor’s degree in Mechanical, Electrical, Architectural engineering.
b. Professional Engineer license in at least one jurisdiction is desired.
c. Over 5 years field experience in building systems operations, maintenance, and troubleshooting, HVAC system installation, maintenance, and troubleshooting, HVAC Direct Digital Control system installation, programming, maintenance, and troubleshooting, electrical system installation, maintenance, and troubleshooting, other applicable trade contracting experience may be deemed equivalent experience for the bachelor’s degree.
7. Commissioning Services will be provided in accordance with the Department of Veterans Affairs Commissioning Process Manual. Prospective proposers shall review the Whole Building Commissioning Process Manual available on the VA Technical Information Library at http://www.cfm.va.gov/til/.
a. The following tables describe the commissioning services and deliverables to be provided by the Commissioning Agent:
http://www.cfm.va.gov/til/
Project #: 518-22-700
General Requirements
01 00 00 - 5
Commissioning Team Task/Deliverables Description Construction Phase
Project Phase/ Cx Task
Commissioning Task Description Commissioning Deliverables
Commissioning Kick Off
Meeting
(Construction Phase)
(The kickoff meeting should occur within 60 days of Notice to
Proceed.)
Conduct a “Commissioning Kickoff Meeting” with the Construction Team
Establish the purpose and process for commissioning the project.
Establish the individual roles of each participating commissioning team member.
Review the Construction Phase Commissioning
Plan and Commissioning Specifications.
Review the Commissioning Documents
Review the Project Schedule and discuss how commissioning activities will be incorporated into the master schedule.
Review Draft PFC and FPT; identify pre-requisites for functional testing.
ATTENDEES:
Commissioning Agent, A/E Design Team
Representatives, Contractor’s Commissioning
Representative, Subcontractor’s Commissioning
Representatives, VA RE.
Meeting Minutes
Revised Project
Commissioning Plan
(Include Names/Contact
Information for selected
Commissioning Team
Members)
Duration Schedule for
Commissioning
Activities
Based on the Construction Phase
Commissioning Plan, prepare a duration schedule for the commissioning activities required by the commissioning plan. This duration schedule should be incorporated into the contractor’s project schedule to track all commissioning activities of the commissioning team.
Commissioning Duration
Schedule
(Schedule shall be periodically updated to reflect changes in the project schedule and/or scope.)
Project #: 518-22-700
General Requirements
01 00 00 - 6
Commissioning Team Task/Deliverables Description Construction Phase
Project Phase/ Cx Task
Commissioning Task Description Commissioning Deliverables
Submittal & Shop
Drawing Review
Review all pertinent project shop drawings necessary to support the Commissioning
Process. Review of the shop drawings is for the purpose of developing appropriate Pre-
Functional Checklists and Systems Functional
Performance Test Procedures. Submittals &
Shop drawings shall be reviewed for commissionability, maintainability and for compliance to the Construction Documents.
Note any issues identified in the Shop Drawing
Review that might compromise the final commissioned system on the ‘Commissioning
Review Log’ and submit comment to the Design
Team and the RE contemporaneously with the
A/E review for resolution.
Comments shall be submitted in accordance with the contractual submittal review time.
Comments shall be provided to the Design
Team no less than 7 days prior to the Submittal
Review Due Date provided that the Cx Agent has no less than 7 days to review the submittals.
ANY ISSUES IDENTIFIED IN THE SUBMITTAL
REVIEW THAT MIGHT REQUIRE A
CONTRACT CHANGE BUT IS NECESSARY
TO MEET DESIGN INTENT SHOULD BE
SPECIFICALLY REFERRED TO THE RE.
Shop Drawing Cx Review
List
Shop Drawing Review
Comments
Construction Phase
Commissioning Plan
Based on the work completed in the items above, the Construction Phase Commissioning
Plan for the project shall be periodically reviewed with the Commissioning Team and updated to reflect changes in project equipment, sequences of operations, scope or schedule and with project personnel.
Revised Project
Commissioning Plan
Project #: 518-22-700
General Requirements
01 00 00 - 7
Commissioning Team Task/Deliverables Description Construction Phase
Project Phase/ Cx Task
Commissioning Task Description Commissioning Deliverables
Commissioning
Construction
Observations
During the course of construction, the
Commissioning Agent will visit the site to observe the progress of construction with respect to the systems being commissioned.
The focus of the observations will to verify that systems being installed comply with the
Construction Documents and can be successfully configured, operated and maintained.
In addition, site observations visits will be scheduled to include
● Witnessing factory testing and/or contractor equipment/system start up activities;
● Verification of Completed Pre
Functional Checklists
● Verification that the Contractor and his subcontractors are completing and documenting Pre-Test procedures required by the specifications.
● Clarification and technical support for understanding and resolving
Commissioning Issues.
Site Observation Reports
Updated Commissioning
Issues Log
Project #: 518-22-700
General Requirements
01 00 00 - 8
Commissioning Team Task/Deliverables Description Construction Phase
Project Phase/ Cx Task
Commissioning Task Description Commissioning Deliverables
Commissioning Team
Meetings
The Commissioning Agent will hold regular commissioning team meetings to review progress of the commissioning effort and reinforce individual responsibilities. The team will review schedule, construction sequence, and completed work (PFC, PFT and FPT’s) and outstanding issues on the Commissioning
Issues Log.
Commissioning Team Meetings may be held at the jobsite or by teleconference depending upon the status of construction. While it is imperative that many of the Commissioning Team
Meetings be held in person, during early construction phases, some meetings may be more cost effectively conducted remotely.
Scheduling and location of meetings shall occur by consultation between the Commissioning
Agent and the VA-RE.
The Prime Contractor’s scheduler should attend approximately every other Commissioning
Team Meeting to review the master schedule and any changes that will affect commissioning activities.
Commissioning Meeting
Agenda and Minutes
Updated Commissioning
Issues Log
Develop Final Pre-
Functional Checklists
(PFC’s)
The Commissioning Agent will prepare Pre-
Final Pre Functional Checklists (PFC) for the project and distribute to all Cx Team members for review and comment. The Commissioning
Agent will incorporate review comments and prepare Final PFCs.
An executed PFC submitted by the Prime
Contractor indicates the system and its related equipment is ready for Systems Functional
Performance Testing.
The requirements for Pre Functional Checklists shall be coordinated with the startup requirements specified for each commissioned system. The PFC’s shall be constructed to leverage the specified contractor and vendor start activities to avoid unnecessary duplication.
Pre Functional Checklists
(PFC’s)
Project #: 518-22-700
General Requirements
01 00 00 - 9
Commissioning Team Task/Deliverables Description Construction Phase
Project Phase/ Cx Task
Commissioning Task Description Commissioning Deliverables
Final Systems
Functional Performance
Test (FPT’s)
Procedures
Based on construction documents and approved submittals, the Commissioning Agent will prepare Pre-Final Systems Functional
Performance Test Procedures (FPT’s) for systems to be commissioned.
Completed Final FPT’s will be distributed to all appropriate members of the Commissioning
Team for review and comment.
Final FPT’s will be issued once comments are reviewed and incorporated into final documents as appropriate.
Pre-Final and Final
Systems Functional
Performance Test
Procedures (FPT’s)
Review Operations &
Maintenance Manuals
The Commissioning Agent shall review
Operations and Maintenance Manuals submitted by contractors for general conformance with specifications and VA’s requirements, including:
If provided with the manuals, Review Preventive
Maintenance Schedules provided as part of the
O&M Manuals for completeness. Verify that data is provided in a manner consistent with VA process for managing Preventive Maintenance tasks.
Review of O&M Manuals will include a review of system and component warranties to confirm conformance with contract requirements and adequate documentation of warranty contact information and VA obligations.
Review of O&M Manuals shall be completed in accordance with the Submittal Review schedule requirements.
Updated Commissioning
Issues Log
Review Contractor
Equipment Startup
Checklists, TAB
Reports and PFC’s
The Commissioning Agent will review all contractor prepared Equipment Startup
Checklists, TAB Reports (including “pencil” daily test results) and PFC’s to confirm that the systems have been subject to appropriate
Quality Control and Start Up procedures prior to initiation of Functional Performance Testing.
Incomplete work, inadequate preparation and deficiencies will note noted and tracked on the
Commissioning Issues Log.
Commissioning Issues Log
Project #: 518-22-700
General Requirements
01 00 00 - 10
Commissioning Team Task/Deliverables Description Construction Phase
Project Phase/ Cx Task
Commissioning Task Description Commissioning Deliverables
TAB Verification The Commissioning Agent shall work with the
TAB Contractor to verify that all Testing and
Balancing work is conducted in strict accordance with the specified Procedural
Standards for Testing, Adjusting and Balancing by either NEBB or AABC. The Commissioning
Agent shall execute the following tasks:
● Review the TAB Agenda provided by the TAB Contractor to verify that it is complete, thorough and in compliance with the specification and Procedural
Standards requirements.
● On the project site, the CxA shall review the calibration certificates for the instrumentation being used by the TAB
Contractor during the execution of TAB activities to confirm that the instrumentation meets the requirements of the spec and the appropriate
Procedural Standard.
● The CxA shall periodically visit the project site and review the TAB documentation for method, reasonable values, and compliance with the specification, Procedural Standard and
TAB Agenda.
● Upon completion of the TAB activities, the CxA shall visit the project site with the TAB Contractor and the RE. The
TAB Contractor shall demonstrate readings selected by the CxA that demonstrate that the system performance is consistent with the submitted values on the TAB report.
Readings shall include Air Handling Unit total flows, static pressure control values, select outlet flows, building, and space pressures selected by the CxA as critical system operating values.
TAB Agenda Review
Comments
TAB Agenda Review
Meeting Minutes
Field Observation Reports of TAB Inspections
Summary Report of TAB
Verification Readings
Project #: 518-22-700
General Requirements
01 00 00 - 11
Commissioning Team Task/Deliverables Description Construction Phase
Project Phase/ Cx Task
Commissioning Task Description Commissioning Deliverables
Systems Functional
Performance Testing
The Commissioning Agent will oversee, facilitate, and document all FPT testing.
Execution of FPT’s shall be executed in accordance with the Functional Testing
Procedures published by the Commissioning
Agent. All systems tested in accordance with the FPT’s shall be operated by the contractors in accordance with the approved FPT.
Contractors shall retain responsibility for the installed systems during and after functional testing until substantial completion or final acceptance as determined by the VA.
The Commissioning Agent, in collaboration with the control contractor shall include long term trends (greater than 7 days) of integrated system performance once all systems have been commissioned. The Commissioning
Agent shall provide analysis of these trends to confirm that the installed systems are stable and reliable
Executed Functional
Performance Tests and support documentation.
Long Term Trend Data and
Analysis
Prepare Systems
Manuals
The Commissioning Agent shall work with the design team, contractor and VA to develop
Systems Manuals. Manuals will contain system design, operations and sequence information that describes the design intent, operational features and appropriate operational practices necessary to sustain the system operation in accordance with the Design Narrative and the
VA’s overall objectives for the facility.
Systems Manual will include sections for each major system included in the commissioning process.
Project Systems Manual
Project #: 518-22-700
General Requirements
01 00 00 - 12
Commissioning Team Task/Deliverables Description Construction Phase
Project Phase/ Cx Task
Commissioning Task Description Commissioning Deliverables
Training Plan Review
The Commissioning Agent shall collaborate with the Prime Contractor and installing subcontractors to develop effective contractor and manufacturer training plans and agendas for general conformance with specifications and
VA’s requirements. Observe training for quality of training and for general conformance with the training plan and agenda.
The CxA shall observe contractor and vendor training for critical systems. The Contractor shall provide and the CxA shall maintain all attendance records and associated agendas and presentations for all training sessions.
Attendance records shall be written original sign in sheets for each training session.
Compiled Training Plan
Individual Training Agendas
Training Attendance Sign In
Sheets
Systems Training
The Commissioning Agent will conduct training sessions to provide systems-level training for
O&M personnel. Training will include:
● Review of system design, capacity, and equipment selection
● Review of system operating sequences
● Review of interconnection with other systems
● Review of Emergency operating procedures
● Review of the Project Systems Manual and its Use
● Student Evaluation forms
The number, duration and scope of the Systems
Training sessions shall be determined by the specific requirements of the project.
The training provided by the CxA does not in any way relieve the Contractor from any specified training obligations.
Systems Training
Presentations (electronic)
Project #: 518-22-700
General Requirements
01 00 00 - 13
Commissioning Team Task/Deliverables Description Construction Phase
Project Phase/ Cx Task
Commissioning Task Description Commissioning Deliverables
Final Commissioning
Report
The Commissioning Agent shall compile a comprehensive commissioning report documenting all commissioning activities, including but not limited to the following:
● Executive Summary
● Commissioning Scope of Work
● Test methods and results
● Outstanding commissioning issues
● Comprehensive Commissioning Issues
Log, including resolved items and a description of their resolution,
● Commissioning plan,
● Field Observation Reports, Status reports and other field activity documentation,
● Submittal and O&M manual reviews
● Training record
● Completed Pre Functional Checklists
● Completed Functional Performance
Test protocols and support documentation
● Other support documentation developed as part of the execution of the project Construction Phase
Commissioning Process
Final Commissioning
Report
Project #: 518-22-700
General Requirements
01 00 00 - 14
Commissioning Team Task/Deliverables Description Construction Phase
Project Phase/ Cx Task
Commissioning Task Description Commissioning Deliverables
Deferred and/or
Seasonal Testing
The Commissioning Agent shall witness and document Systems Functional Performance
Testing that was deferred to allow systems to be tested in appropriate seasonal conditions.
Testing will be conducted in accordance with
Systems Functional Performance Test
Procedures. Testing support will be required from the installing contractors, EMCS Vendor and VA. Requirement for seasonal testing will be incorporated into the project specifications.
As part of the Seasonal Testing Effort, the
Commissioning Agent shall review systems operations with the onsite operations team and reinforce training and best operating practices of the operations team.
Executed Functional
Performance Test and
Support Documents
Commissioning Issues Log
Warranty Period Site
Visits
The Commissioning Agent shall make quarterly visits to the project site to reinforce training, evaluate performance of the installed systems and provide technical support to the operating team to sustain commissioned performance of the systems.
Warranty Site Visit Reports
Project #: 518-22-700
General Requirements
01 00 00 - 15
Commissioning Team Task/Deliverables Description Construction Phase
Project Phase/ Cx Task
Commissioning Task Description Commissioning Deliverables
Post-Occupancy
Inspection
Return to the project approximately 10 months after substantial completion to review the building operation with the facility occupants and O&M staff, and to discuss outstanding issues related to commissioning. Provide suggestions for improvements to systems operation including,
● Measurement & Verification Issues,
● Re-Commissioning Tasks, and
● Improvements in Preventive
Maintenance or Operational Strategies
Assist facility staff in developing warranty issues, documents and requests for service to remedy outstanding problems.
As part of the Post Occupancy Inspection, the
Commissioning Agent shall analyze the energy consumption records from the project site (both utility and system generated reports) and provide the team with an analysis of actual system energy performance versus predicted performance. To the extent possible, deficiencies in performance shall be analyzed to provide an understanding of the systems, components or operating strategies that may be operating outside predicted parameters.
Post Occupancy Field Visit
Report
Commissioning Issues Log
Warranty Issues Report
Systems Energy Review
Report
Final Commissioning
Report Amendment
Amend Final Commissioning Report to document the Warranty Phase commissioning activities.
Final Report Amendment
1.3 STATEMENT OF BID ITEM(S)
A. Contractor shall completely prepare project site for operations, including demolition and removal of existing site elements, and furnish labor and materials and perform construction work for Project 518-22-700, EHRM Infrastructure Upgrades - Bedford VAMC as required by drawings and specifications. Period of performance is projected to be Seven-Hundred and Thirty (730) calendar days.
B. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, alterations, and necessary removal of existing structures and construction and certain other items. Contract documents, drawings, and specifications, indicate the scope of work. The purpose of this project is to address deficiencies and upgrade communications cabling Telecommunications Rooms (TR) and Main Computer Room (MCR) located within multiple
Project #: 518-22-700
General Requirements
01 00 00 - 16 buildings on campus and site infrastructure. Project scope also includes the phased replacement existing with a new Main Computer Room building. Temporary fiber shall be provided between existing MCR and New MCR and existing demarcation rooms and new. This project provides the new construction, renovation, and infrastructure required to provide new telecommunications infrastructure, including (but limited to): new Fiber Optic Cable and new CAT 6a telecommunications cable to all locations, Work Area Outlets (WAO), racks, UPS, power supplies and associated electrical distribution equipment, new HVAC, new CCTV, new Fire Protection and Fire Alarm, new Advanced Utility Monitoring System and new PACS and doors for all buildings in this project.
1. Construction addresses deficiencies including new electrical service, new dedicated mechanical units, new UPS, new grounding and bonding conditions within each TR, new racks and cable management equipment within the TRs and new cable tray for each building as shown on the plans.
2. Provide new equipment rack(s) furnished with redundant PDU, both horizontal and vertical cable managers, vertical bonding bars, UPS and base unit, patch panel and an optical fiber termination shelf. All telecommunications equipment and cabling shall be tested, approved, and accepted by the VA prior to connecting to active, ongoing operations. Any modifications required to existing systems (HVAC, smoke detectors, fire alarm, fire sprinklers, lights, other devices, etc..) are the responsibility of the Contractor.
The VA will not assist with any modification.
3. Includes all labor, material, equipment, and supervision to perform the required electrical and telecommunications construction work on this project including materials and construction equipment to provide new telecommunications Cat 6A and Fiber cable throughout, new outlets, and new racks, patch panels, UPS, fiber panels and associated equipment for all buildings.
4. Provide new electrical distribution boards, panels, transformers, circuit breakers, automatic transfer switches and all associate equipment to serve the new or renovated spaces and equipment.
5. For communications functions, provide cable trays, equipment racks with vertical/horizontal wire management. Replace all fiber optic lines serving the TRs.
Provide network drops from each TR to all existing drop locations.
6. Provide a new digital, wall mounted CCTV (Closed Circuit Television) camera at each TR, camera shall comply with Campus standards (IP addressable network camera, POE+, motion sensor, dome with wall/ceiling mount. Integrate camera into existing VMS.
provide controllability through existing IT network).
7. Temporary fiber shall be provided between existing entrance room and new Main Computer Room and from the existing Data Center.
8. Provide Physical Security Access Control (PACS) for all the TR doors (including controllers and power supplies), coordinate with the door hardware specification for additional requirements.
9. Contractor shall provide a 30-day load test on all existing source panels serving new work at each building. This test is required by NEC 220.87 for verification that no loads have been added since the design level survey. Contractor shall provide load monitoring data to the COR/AE. New electrical panels and electrical service branch circuits are specified by the scope of work and shall be furnished by the contractor. Load monitoring shall also be performed on all panels upstream of the new branch circuit panels.
10. The existing fire alarm system will be modified by relocating and/or adding compatible devices to the existing building fire alarm system. A new Fire Alarm system shall be provided for the new MCR building.
11. Work includes all labor, material, equipment, and supervision to perform the required Mechanical and Plumbing construction work on this project including new dedicated cooling, condensate piping pumps and drains.
12. Contractor shall submit coordination drawings for approval showing all trades including equipment locations, proposed routing, supports and penetrations prior to beginning any work. Also indicate new and existing systems and all provisions for coordinating existing utilities.
Project #: 518-22-700
General Requirements
01 00 00 - 17
13. For fire suppression, contractor shall reconfigure and/or provide additional sprinkler heads to the existing building automatic sprinkler system as shown on the drawings.
Provide wet-pipe and clean agent fire suppression system for the renovated MCR.
14. Site Work: Site work includes all labor, material, equipment and supervision to perform the required hardscape and landscape construction work on this project including materials and construction equipment to provide new concrete walkways, planting beds, artificial turf, fencing, trees and additional landscape materials to the new building and renovations detailed by the construction drawings and specifications. Protection for existing plantings, trees and hardscape to remain shall be installed, maintained and enforced by contractor
15. New site fiber conduit shall be encased in concrete. Base bid shall include trenching, concrete duct bank and hand digging at existing utility crossings.
16. For all telecommunications rooms (TR), the contractor is responsible for providing a new fire extinguisher cabinet with a Type 2A:10B:C clean agent fire extinguisher located no greater than 75 feet away from the new TR. New MCR shall have FEC provided at each exit. Contractor to coordinate the new locations with the COR. Contractor shall bid a new FEC for each TR and all MCR building locations in the Scope of Work. See specification 10 44 13.
1.4 PROPOSED PROJECT SCHEDULE
A. At project commencement, the contractor shall complete and commission a single building
(selected by the Owner) prior to being approved for work in multiple locations. This initial Building will demonstrate compliance with all project requirements. This project will require working on multiple buildings simultaneously with multiple crews to achieve the overall construction period duration for the entire project.