This document contains engineering standards for electrical, mechanical, and plumbing systems on federal facilities. It specifies requirements for various systems including electrical work, ductwork, piping, HVAC equipment, controls, fire protection, and equipment identification. Standards are provided for materials, design, installation, testing and commissioning of these systems. Inspections and approvals are required from the contracting agency. Contractors must follow all applicable industry codes and federal criteria, and submit documents like drawings, manuals and certifications per the standards outlined.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page T-1

December 2015

T.1.2 Electrical

T.1.2.1 Electrical work shall comply with the latest versions of the National Electrical Code (NEC), National Electrical Safety Code (ANSI C2), the Life Safety Code (except as noted in the UFC standards), Americans with Disabilities Act and Architectural Barriers Act Accessibility Guidelines, all NFPA standards (except as noted in the UFC standards) and all applicable federal regulations. All electrical work shall also comply with the latest editions of all applicable UFC (Unified Facilities Criteria) standards, unless directed otherwise by the Government.

T.1.2.2 Structural sleeves shall be installed at any location where penetrations are required through load bearing walls or fire walls.

Examples of applications (not an all-inclusive list) where sleeves shall be installed are water piping, sewer piping, fire protection piping, and electrical conduit or cabling.

T.1.2.3 Do not use PVC conduit indoors, as this gives off toxic fumes when it burns. Provide plastic bushings at the terminations of EMT, Rigid galvanized, or IMC conduits at boxes.

Rock Island Arsenal

Engineering

Standards

Page T-2

T.1.2.4 ALL IDG LAND USE ZONES

a. General Guidelines

i. Voltage Systems: Project designs shall incorporate standard voltage systems. The standard voltage systems shall be one of following: 480 Volt delta 3 phase 3 wire, 480/277 Volt wye 3 phase 4 wire, 208/120 wye 3 phase 4 wire, and 240/120 1 phase 3 wire. 480/277 volts is preferred over 480 volts delta, and shall be used for new services to buildings. A ground conductor shall be extended for every circuit.

ii. Wire: Use only copper conductors except as specifically permitted by the Government. Use THHN or THWN insulated copper conductors for branch circuit and feeder applications. Use twisted shielded wire or other special conductors as recommended by the equipment manufacturer or as specified by the Government. Type NM cable will not be used except for residential construction or where specifically permitted by the Government.

Type NM cabling will also not be allowed in mechanical spaces, office areas or industrial areas. Type MC or AC cable shall only be used for lengths of 6 feet or less as permitted by Code for final connections to equipment subject to movement or vibration. For 120 volt 20 amp lighting and receptacle circuits with receptacles located over 100 circuit feet from the receptacle panel, utilize minimum 10 gauge wire, except that 12 gauge pigtails, properly spliced, may be used for the last 6 feet for connection to the receptacle. Do not allow shared neutrals for branch circuit wiring.

Run separate hot(s) neutral, and ground to the panel board for every branch circuit. For lighting fixtures recessed in suspended

Page T-3 ceilings, utilize short lengths (6 feet or less) of flexible metallic conduit, or 6 feet or less of type AC or MC cable for final connections. All feeders shall also be run with separate hot(s), neutral, and ground.

iii. Conduit: Unless noted otherwise, utilize EMT conduit in dry areas indoors where allowed by Code. Utilize compression type connectors.

Short lengths (6 feet maximum) of flexible metal conduit may be used for connection to light fixtures or equipment subject to vibration or movement where allowed by Code. Longer sections of flexible metal conduit or liquid tight flexible metal conduit may be used for fishing down hollow walls or other inaccessible spaces where allowed by Code. Utilize rigid galvanized steel conduit outdoors above grade. Provide an insulated bushing for box or equipment connections for all types of conduit.

iv. Conduit installation: Arrange conduit to maintain maximum headroom. Unless specifically permitted by the Government, do not create any new low spots, especially in hallways. When running above suspended ceilings, run conduit as high above suspended ceiling as possible. Conceal in new walls and partitions and above suspended ceilings.

Conceal conduit to the maximum extent possible. Conduit may be exposed in unfinished areas such as open basement areas. However, do not create new low spots, especially in areas such as corridors. Maintain 12 inch clearance between conduits and heat sources such as steam pipes. Conduits shall not block access to repairing valves or other mechanical or architectural features. Conduits shall not be supported from other conduit or piping or ductwork. In suspended ceiling

Page T-4 construction, raceways shall not be fastened to the ceiling supports or to the suspended ceiling. When penetrating walls or floors, core drill holes of a size no larger than required.

Locate floor penetrations close to walls to cause the least interference with usage of the space. Floor penetrations shall be located in mechanical or electrical rooms wherever feasible. Except for wiring related to the stairwell, do not use the stairwells as chases for conduit runs. Provide firestopping for floors and fire rated walls, and seal holes in non-fire rated walls. Unless noted otherwise, conduit installed outdoors and conduit exposed to view in finished spaces indoors such as offices shall be painted to match the adjacent surfaces.

v. The minimum box size shall be 4 inches by 4 inches, except that 2 inches by 4 inches shall be permitted for boxes that contain the final device and do not feed through to other devices. Boxes shall be a minimum of 1-1/2 inches deep. Plastic boxes are not allowed except where specifically permitted by the Government.

vi. All nuts, bolts, washers, and other hardware installed outdoors shall be galvanized or stainless steel.

vii. Provide engraved plastic nameplates with 3/16 inch high letters to identify all disconnect switches, starters, panelboards, circuit breakers(other than in lighting panelboards and load centers), and other major pieces of equipment by name and function, operating voltage, and maximum fuse size (if applicable). Submit nameplate wording to Government for approval. Labeling switches, Page T-5 for example, as SA, S-B, which are convenient labels used by a project designer for a specific project but which obviously do not follow any installation-wide naming convention, does not satisfy this requirement, since every job could potentially have switches with this name. The wording should use the naming conventions established or agreed to by the Government.

Use screws to attach nameplates.

viii. Switchboards: all switchboards must have copper busses, copper ground bar, with at least 25% extra ampacity and 25% extra distribution mounting space. Also provide room for extending the switchboard busses.

ix. Panelboards: All new panelboards must have at least 25% spare distribution device mounting space and 25% spare ampacity. All panelboards will be complete with copper bus bars and bolt on circuit breakers for general purpose lighting, receptacle, and appliance branch circuits. Each panelboard shall have a neutral bus and separate ground bar.

Panelboards will be used in the vast majority of electrical installations instead of load centers. There are some limited exceptions where load centers will be allowed, as is specified in the rest of this paragraph. Load centers will be allowed in family and troop housing areas, or in other areas as specifically permitted by the Government. Provide an engraved nameplate to indicate the operating voltage and phases and name of panelboard.

The nameplate shall be permanently mounted to the panelboard by means of screws or rivets. The identification label shall be laminated plastic. There shall be a main breaker or main disconnecting means integral to the panelboard. There are limited exceptions to this rule. If there is a

Page T-6 disconnecting means within sight of the panelboard, and also within 10 feet of the panelboard, with proper engraved nameplates indicating that this disconnecting means controls power to the panelboard, and if the Government has no other specific requirement for a main breaker or main disconnecting means to be integral to the panelboard, then the panelboard may be main lug construction.

If the panelboard is rated 400 amps or above and is a major distribution point for building feeders or is also the main service for a nonhousing building, incorporate feed-thru lugs in the panelboard, and allow room to permit a conduit or conduits to connect to these lugs.

x. Circuit Breakers: Circuit breakers shall be sized for the load being served. Unless permitted otherwise by the Government, 20 amp 1 pole, with standard interrupting capacity of 10,000 amps, shall be used for receptacle and branch lighting circuits.

Ground-fault interrupting circuit breakers shall be used for all 120 volt circuits supplying devices in wet or damp locations or outdoors, unless receptacle ground fault protecting receptacles are being used with the device.

Circuit breakers shall be of the bolt-on type for all panelboards.

xi. Disconnect Switches: Use heavy duty fused/non fused disconnect switches complete with visible switch blades.

xii. All motors shall be equipped with a disconnecting device (or plug if 120 volt plug and cord connected) capable of being locked out, located within 10 feet of the motor.

Exception: if the motor is part of a piece of

Page T-7 equipment that was manufactured with one lockable in the off position disconnecting device located at the equipment that controls all the motors on that piece of equipment, separate disconnecting devices are not required for each of the motors, unless specifically required by the Government or by Code.

xiii. Receptacles: Use specification grade, 20 ampere 120 volt, 3 wire grounding type, duplex, NEMA configuration 5-20R for all convenience outlets.

xiv. Loading of circuits feeding relocatable office partition cubicles: When refeeding relocatable office cubicles, provide at least one 20 amp 120 volt circuit for every three cubicles.

Provide additional receptacles for special office loads as required.

b. Fire Alarm System

i. Regulations: The designer shall ensure that the Fire Alarm System design complies in all respects to the most current editions of the UFC Criteria and the Fire Codes, especially

NFPA 72, 90A, and 101, except as modified by UFC 1-200-01, “Design: General Building Requirements”. Also pay special attention to UFC 3-600-01, “Fire Protection Engineering for Facilities”. The system must also comply with the latest edition of the Architectural Barriers Act Accessibility Guidelines.

ii. Wire and Cable: Use wire types and gauges as recommended by the equipment

Page T-8 manufacturer. Copper conductors shall be used.

iii. Initiation Devices: Utilize addressable devices for all new initiation devices, unless specifically approved otherwise by the Government.

iv. Notification Devices: Except as permitted by the Government, install speaker-strobes (or separate speakers and strobes) for all new notification devices. The strobe shall have an amber lens with “ALERT” and a clear lens with “FIRE” lettering. In this manner, these devices can be used for augmenting the mass notification system for the island and will not be dedicated to fire alarm alone. Also provide a means of activating the “ALERT” strobe.

New speakers in normally inhabited areas such as office spaces must be spaced for intelligibility in mass notification systems.

v. Control Panel: Ensure that each new fire control panel has 25% spare capacity for adding circuits. Provide the following four special bypass buttons to be programmed to perform the following functions: bypass notification devices, bypass elevator recall, bypass door release, bypass air handling unit shutdown. Locate all end-of-line resistors in the

Fire Alarm System control panel for maintenance purposes. In addition, provide for fire alarm outputs for control of HVAC shutdown and door release and elevator recall to be controlled by the fire panel rather than directly by the initiation devices in the field.

Such releases and recalls and shutdowns shall be arranged such that loss of 120VAC or 24VDC power by the fire panel will not activate the shutdowns or releases or recall functions.

Page T-9

vi. The circuitry configuration for initiation and notification devices may be class B unless specified otherwise for a particular project or unless specified otherwise by the Government.

vii. Wiring must also comply with NFPA 72

(National Fire Alarm Code) and NFPA 70 (National Electrical Code). Materials and methods must comply with the latest edition of Unified Facilities Criteria UFC 3-600-01.

(Design: Fire Protection Engineering for Facilities).

viii. All fire alarm wiring is to be in conduit. Utilize

EMT conduit in dry areas where permitted by Code.

ix. The Contractor must supply a NICET certified fire alarm technician to make all final connections at the fire panel and to supervise all final connections at all field devices.

x. All junction boxes which contain fire alarm wiring must be painted red.

xi. AC power or AC control wiring is not to be run in the same conduit as 24VDC fire alarm wiring or fire alarm communication wiring.

xii. Provide services of manufacturer's representative to test operation of Fire Alarm system after installation of the fire alarm and all associated wiring is complete.

Manufacturer's representative shall provide written certification to Contracting Officer Representative (COR) that equipment has been properly installed and is operating satisfactorily. Written certification shall include information required in NFPA 72. The Contractor shall notify the Government of the proposed times and dates

Page T-10 of the testing, at least 7 working days prior to any tests of the fire alarm system, to allow the Arsenal Fire Inspector and COR the opportunity to witness the test of the system.

The Government shall have final approval of the times and dates of the tests.

xiii. All testing of fire alarm systems which involves activation of the speakers, horns or strobes in a building must be conducted after normal working hours. Also, any testing which involves the shutdown of HVAC equipment shall be conducted after normal working hours. The COR has final approval of the times and dates of the testing of the speakers, strobes or HVAC shutdowns. However, the COR may, at his option, allow some testing during normal working hours.

xiv. Comply with UFC 4-021-01, Design and O&M:

Mass Notification Systems. Note that UFC 4021-01 requires, among other things, that LOC be installed in certain renovated spaces.

See the UFC Criteria for other details. The Rock Island Arsenal (RIA) Fire Department shall have final approval of the location or locations for the LOC. The LOC shall incorporate all of the standard voice messages already approved by the Fire Department, plus it should incorporate a microphone all set up in the system for voice announcements over the speakers. The LOC shall also incorporate the HVAC shutdown. This shutdown shall be independent of the DDC controls and shall also not shut down any HVAC just because the fire alarm system loses AC or DC power.

Page T-11

T.1.3 Mechanical

T.1.3.1 Structural sleeves shall be installed at any location where penetrations are required through load bearing walls or fire walls. Examples of applications (not an all-inclusive list) where sleeves shall be installed are water piping, sewer piping, fire protection piping, and electrical conduit or cabling.

T.1.3.2 Heating, Ventilating, and Air Conditioning (HVAC) Standards

a. Provide detailed demolition and new work plans for all HVAC system and DDC system designs. The 100 percent HVAC design shall include, but not be limited to, mechanical notes, details, and legends.

The design shall also include drawings and specifications showing the locations and product schedules for all new mechanical equipment, ductwork layouts with duct sizes, and air flow requirements. In addition, louver sizes, schedules, and locations, supply air diffuser schedules and locations, return air grille schedules and locations, fire damper schedules and locations, damper schedules and locations shall be provided. All new and existing pipe routing and pipe sizes, DDC system control drawings, DDC network layouts (riser diagrams), sequences of operation, point schedules, and panel locations shall also be provided as part of the 100 percent mechanical design. The 100 percent mechanical design shall also include demolition plans for equipment, piping, ductwork, and appurtenances. Plans shall include plan view design drawings. The 100 percent mechanical design shall be submitted to COR before project construction begins in hardcopy format, Adobe Acrobat format, and MicroStation computer-aided design and drafting (CADD) format.

Page T-12

b. Provide heating, ventilating, and air conditioning load calculations. Provide a hard copy and electronic copy of the load calculations to COR.

Trane Trace or a similar software program shall be used to generate the HVAC load reports.

c. Provide as-built drawings of HVAC systems in hardcopy format, Adobe Acrobat format, and MicroStation CADD format to COR within 14 days after the final HVAC system test

d. Provide three copies of Operation and

Maintenance (O and M) manuals to COR for all new mechanical equipment in hardcopy format.

Provide electronic copies of O and M manuals to COR for all new mechanical equipment in Adobe Acrobat format. Electronic and hardcopy O and M manuals shall be provided within 14 days after the final HVAC system test.

e. Install DDC electronic controlled VAV (variable air volume) boxes to supply air to various zones in a space to allow temperature control of the various zones and to allow flexibility to move various walls around in future remodel jobs

f. Rock Island Arsenal (RIA) Directorate of Public

Works (DPW) no longer is installing pneumatic control systems for VAV boxes, air handling units (AHUs), and other HVAC equipment because of their inherent problems (air leaks, difficulty to calibrate and keep in calibration, and reduced flexibility)

g. VAV boxes can be configured for cooling only (in the case perimeter heat is installed) or they can serve both cooling and heating needs if the VAV box is equipped with heating

h. RIA DPW standard for heating is to install:

Page T-13

i. Hot water perimeter fin-tube convectors mounted at the base of exterior walls or VAV boxes with hot water heating coils, wherein the air coming out of the zone’s VAV box is heated to meet the zone’s heating requirements

ii. Hot water heating gives better control than steam radiators and requires less maintenance

iii. Third in desirability for a heating system for a zoned area are steam wall convectors

i. Provide commissioning of all mechanical equipment. Sheaves and tension belts shall be aligned per the manufacturer’s recommendations.

Test, adjust, and balance all air handling units and diffusers to proper air flow and provide COR with a Test and Balance Report. Demonstrate the full functionality of new HVAC system sequences of operation to COR.

j. All new HVAC systems and equipment shall conform to the Energy Policy Act (EPAct) of 2005.

HVAC systems shall be designed to 30% better than the current ASHRAE Standard 90.1, Energy Standard for Buildings Except Low-Rise Residential Buildings if it is life-cycle cost-effective.

k. Conform to Executive Order 13423, Strengthening Federal Environmental, Energy, and Transportation Management

l. All flexible ductwork shall be stretched tightly to prevent sags and reduce air friction. Any sagging or loose flexible duct shall be shortened and reinstalled. Flexible duct length shall be no greater than 5 feet.

m. Piping systems shall utilize reverse return design

Page T-14

n. Do not use zone control valves on fin-tube designs

o. Control of fin-tube with outdoor reset

p. Avoid rooftop designs (special approval is required)

q. Heating coils in AHUs shall use steam

r. Use ball valves where ever possible

s. Provide isolation valves on all equipment

t. Use auto flow control valves rather than balancing valves

u. Use combination pot feeder and side stream filter

v. Steam is not available during the summer

w. If de-humidification is required then use electric

T.1.3.3 Due to the production halt of R-22 HVAC equipment in 2010 and R-22 refrigerant production ceasing in 2020, RIA DPW no longer allows the installation of new equipment using R-22 refrigerant. Green refrigerants shall be used in new HVAC equipment. All green refrigerants shall comply with the Environmental Protection Agency’s (EPA) Significant New Alternatives Policy (SNAP) program.

T.1.3.4 Piping System Requirements

Piping System Material Type Joining Steam, High

Pressure

Steel Schedule 40 Weld

Steam, Low

Steel Schedule 40 Thread or Weld

Steam Condensate Steel Schedule 80 Thread Heating Water Copper Type L 95-5 Chilled Water, Mains Steel Schedule 40 Weld

Page T-15

Chilled Water, Branch Copper Type L 95-5

Chilled Water, Branch Steel Schedule 40 Thread

Domestic Water, Above Ground Copper Type L 95-5

Domestic Water, Underground Copper Type K Seamless

Gas Piping, <1# Steel Schedule 40 Thread Gas Piping, >1# Steel Schedule 40 Weld

Sprinkler - Dry Steel Schedule 40 -galvanized

Thread or Grooved

Sprinkler - Wet Steel Schedule 40 Thread or Grooved

Refrigeration Copper Type ACR 95-5 Flush all Piping

T.1.3.5 Mechanical Insulation Requirements

Mechanical Insulation ASHRAE Energy

Standard

Supply Ducts Wrap Return Ducts Liner Outdoor Air Intake Wrap Refrigeration Rubber UV Protection

Chilled Water Rubber or Closed Cell Material

T.1.3.6 Ductwork (Sheet Metal)

a. Conform to SMACNA duct construction standard

b. Note pressure class and sealing requirements - 2" minimum

Page T-16

c. Provide SMACNA 45o take-offs (no spin-in types)

d. Provide volume dampers on all take-offs

T.1.3.7 Mechanical Identification

a. Conform to the RIA Standard Mechanical Equipment Labeling System (see Equipment Labeling System table below)

b. After new mechanical equipment is installed, fill out the mechanical equipment manual input forms that will be provided by COR. Provide the complete forms to COR in Microsoft Excel format via e-mail.

After RIA DPW enters the information provided into the RIA Mechanical Equipment Database, RIA DPW will assign a Standard Name for the equipment which shall be tagged on units as described under Equipment Identification below.

c. Drawings shall conform to the RIA Standard Equipment Labeling System

d. Provide data on all equipment that is replaced.

Provide the Standard Name of the equipment that was replaced via e-mail to COR.

e. Notify COR when any equipment is removed.

Provide the Standard Name of the equipment that was replaced via e-mail to COR.

T.1.3.8 Direct Digital Controls (DDC) Systems

a. All controllers are to be BACnet Testing Laboratory (BTL) listed

b. Protocol Implementation Conformance Statements (PICS) shall be provided in Adobe Acrobat format for every controller type installed

Page T-17

c. All controller names and point names shall follow the RIA DDC Point Name Standard

d. BACnet Device Identification (ID) Numbers for all new devices and controllers will be provided by RIA DPW. The BACnet Device ID Numbers shall be requested via an e-mail message to COR.

e. Devices shall communicate via the BACnet MS/TP protocol whenever possible. The use of LAN connections is reserved for areas not having an accessible building controller.

f. Provide COR with IP addresses, MAC addresses, UDP/IP Network Numbers, MS/TP Network Numbers, Port Numbers and all other pertinent network data for the RIA DPW DDC LAN Database

g. A Delta Control System is the front-end for the RIA DPW BACnet DDC system. RIA DPW will normally create the graphics for the BACnet frontend unless explicitly stated otherwise in the project specifications.

h. Provide 2 hours of graphics creation assistance to

RIA DPW.

i. Provide alarms and trends on all important system points. Trends shall last 72 hours in 15 minute increments. Alarms shall be descriptive for e-mail notification and shall be able to be monitored from the BACnet front-end.

a. For typical trend and alarm points see the RIA Equipment Standard DDC Points List

j. All BACnet controllers shall have the RIA Standard Event Classes programmed into them in the order specified below.

Page T-18

Description

EVC1 Maintenance EVC2 Network EVC3 Security EVC4 Critical EVC5 Notification EVC6 Fire EVC7 Access Control Event EVC8 Access Control Alarm EVC9 Archival EVC10 Boiler Emergency EVC11 Boiler Notification EVC12 HVAC Emergency EVC13 HVAC Notification EVC14 General Emergency EVC15 General Notification EVC16 Chiller Emergency EVC17 Chiller Notification

k. Alarms shall be categorized as appropriate

a. HVAC Alarms and Notifications

i. Air handling units, makeup air units, fan coil units, computer room air conditioning units, steam traps, steam pressure reducing valves, condensate pumping units, etc.

b. Chiller Alarms and Notifications

i. Chillers, chilled water pumps, cooling towers, cooling tower pumps, chemical feed systems, etc.

Page T-19

c. Boiler Alarms and Notifications

i. Boilers, boiler feed units, steam pressure supply, make-up water supply, etc.

l. Final sequences of operation shall be provided to COR in Microsoft Word and Adobe Acrobat formats

m. Final control drawings shall be provided in Microstation V8 or AutoCAD format and Adobe Acrobat format

n. The RTD material used for temperature measurement shall be platinum

o. All motors shall be monitored through motor current proof devices

p. Point Name Structure:

Supply Air Temperature (Point Type)

AHU #2 (Sequence Number from Equipment Label)

Air Handling Unit (see Unit Label)

Floor # (R-Roof, G-Ground, B-Basement, 1, 2, 3…)

Building # (always 3 digits)

Examples 348_1_Bldg_CWS Temperature

Building 348 Chilled Water Supply

_AHU_02_SAT 350_3

SAT

AHU

Page T-20

348_1_CWCC_1_CWS

Temperature

348 Chiller 1 Chilled Water Supply

348_1_CWSB_390 CWS Temperature to Bldg 390

348_1_CWRB_390 CWR Temperature from Bldg 390

332_G_CT_1_CTS

Supply Water Temperature

332 Cooling Tower 1 Cooling Tower

225_1_AHU_1_SAT

Temperatures

225 Air Handling Unit 1 Supply Air

225_1_AHU_1_SAT_TL

Temperature Trend Log

225 Air Handling Unit 1 Supply Air

225_1_AHU_1_SAT_SP

Temperature Setpoint

225 Air Handling Unit 1 Supply Air

T.1.3.9 Plumbing Systems

a. Conform to Unified Facilities Criteria (UFC) 3-420- 01 and the International Plumbing Code

b. Provide backflow preventers in conformance with the Illinois Plumbing Code

c. For each new backflow preventer installed, provide RIA DPW mechanical engineers with the building number, the floor, the bay or wing, the direction, the manufacturer, the model number, the serial number, the style, the type of device, the size, the date installed, and the device’s application via e-mail in Microsoft Excel format for cross-connection database updating. Provide the exact location of the new device on a floor plan to RIA DPW mechanical engineers in electronic Adobe Acrobat format via e-mail. For each backflow preventer removed or replaced report the building number, the floor, the bay or wing, the manufacturer, the model number, and the serial number of the device to RIA DPW mechanical engineers via e-mail in Microsoft Excel format for

Page T-21 cross-connection database updating. Provide the exact location of the removed device on a floor plan to RIA DPW mechanical engineers in electronic Adobe Acrobat format via e-mail.

d. Plumbing fixtures shall meet the EPA’s WaterSense program requirements

e. Provide service valves at each fixture

f. Provide hot water recirculation

g. Provide floor drains in all restrooms

h. Plastic casing on in-line water filters are not allowed on drinking fountains

T.1.3.10 Fire Suppression Systems

a. Fire suppression systems shall conform to UFC 3- 600-01

b. Use of halon for fire extinguishing systems or fire extinguishers is prohibited

c. Use area/density method of National Fire Protection Association (NFPA) 13, except that the design density, design area, hose stream allowance, and duration of supply requirements must be in accordance with UFC 3-600-01

d. The project Fire Protection Engineer shall certify in writing that the design is in compliance with UFC 3-600-01 and all applicable criteria. This certification shall be submitted with the 100 percent design submission.

e. Submit the designer's credentials to the COR

f. The COR and the RIA Fire Department shall be notified two weeks prior to work on fire sprinkler systems when fire alarms are to be disconnected

Page T-22

g. Fire suppression system designs shall include all demolition and new work design plans, specifications, and calculations

h. System testing shall be witnessed by RIA DPW representatives and RIA Fire Protection and Prevention Division representatives

i. Submit manufacturers’ technical product data and installation instructions for all fire protection materials and products. Submit working plans and supporting hydraulic calculations. Design plans and calculations shall be provided in hardcopy and electronic format. Electronic design plans shall be provided in MicroStation CADD format and Adobe Acrobat format. Submit the designer’s credentials.

Submit the fire protection engineer’s certification letter referenced above. Submit the Contractor’s material and test certificate. Submit record drawings of installed fire sprinkler piping and products. Hardcopy and electronic as-built drawings shall be provided. The electronic as-built drawings shall be provided in MicroStation format and shall be in accordance with the RIA CADD Standards. The electronic as-built drawings shall also be provided in Adobe Acrobat format. Submit operating and maintenance data and parts lists for fire protection materials and products. Include in this data: product data, shop drawings, approved drawings, approved calculations, certificate of installation, and record drawings in the maintenance manual. The operation and maintenance manuals shall be provided in hardcopy and electronic formats. Electronic manuals shall be provided in Adobe Acrobat format.

T.1.3.11 Equipment Identification

a. All equipment not easily identifiable; such as, controls, relays, and gauges and all equipment located in an area remote from its function; such

Page T-23 as, air handling units, exhaust fans, filters, reheat coils, and dampers shall be identified by name, function, and drawing symbol. For example, for AHU-060-1-5, provide unit label, building number, floor, and sequence number.

b. Identification shall be by machine engraved laminated plastic identification plate. Color shall be metallic blue on white core. Letters shall be not less than 1/4 inch in height. Fasten in place with stainless steel self-tapping screws or permanently bonding cement.

c. Submit a list of the devices and identification wording proposed to the COR for approval prior to creation and installation

T.1.3.12 Piping and Ductwork Identification

a. Piping and ductwork shall be identified by type of service; for instance steam supply, condensate, supply air duct, direction of flow, and operating pressure. Piping shall also be banded with color coded, arrowed tape for the full circumference of the pipe and shall be overlapped a minimum of 1 inch.

b. Method of identification shall be according to ANSI A13.1 latest edition occurring every 10 feet above drop-in ceilings, continuously in wall cavities, and every 20 feet in exposed areas; such as, basements and tunnels. Markings shall occur on both sides, top, and bottom. In mechanical rooms, provide markings every 10 ft or whenever there is a change in pipe direction.

c. Service valves shall be tagged with a brass numbered tag and listed in the nearest mechanical room of the type of service it will isolate

T.1.3.13 Control System Identification

Page T-24

a. Control components out of the panel will be identified with laminated plastic plate, as described above, stating the name, function, and drawing symbol. DDC systems shall have wiring diagrams with labeled terminals.

b. Valve and damper actuators shall, on a brass label, state spring range and operating range in psig

T.1.3.14 Equipment Labeling System

Sequence Number is for

General the entire floor Unit

Equipment TYPE including Label

Type existing units (check with RIA

DPW)

Air Control Air AC AHU 102 1 1 1 Floor

Compressors Compressor Air-Cooled Air-Cooled ACC 2 Floor Examples

Condensers Condensers Air-Cooled Air-Cooled

ACCU-090-

Condensing ACCU Condensing 3 Floor

G-2 Units Units

PRE-212-

Air Dryer AD Air Dryer 4 Floor

Page T-25

R-10 Air Handling FCU-350- ACUR Air Curtain 5 Floor

Unit 2-13 Air Handling Air Handling AHU-102- AHU 6 Floor

Unit Unit 1-1 Air Handling Blower Coil BCU B Basement

Unit Unit Air Handling FUR Furnace G Ground

Unit Heating Air Handling HVU Ventilating R Roof

Unit Unit Air Handling Make-Up Air

MAU

Unit Unit

Low Pressure Boiler BS

Steam Boiler BW Hydronic

Water Cooled Chiller CWCA

Absorption Air Cooled

Page T-26

Chiller CACR

Reciprocating Air Cooled Chiller CACS

Rotary Screw Air Cooled Chiller CACO

Rotary Scroll

Split System Chiller CSSB

Chiller Barrel

Chiller CACC Package Chiller with

ACC

Chiller CWCC Water Cooled

Centrifugal

Chiller CWCR

Reciprocating

Chiller CWCS

Rotary Screw

Control Panel

CLP

Pneumatic

CLE

Electric

CLD

DDC Control

Panel

Computer

CCLP Communicatio n Control Panel

Room Air Conditioner Computer

CRAC CW Downflow

Page T-27

Room Air Conditioner Computer

CRAC CW Upflow

Room Air Conditioner Computer

CRAC DX Downflow

Room Air Conditioner

CRAC DX Upflow

Condensate Return Unit CP

Condensate

Pump Condensate Return Unit LM Liquid Mover Condensate Return Unit VP Vacuum Pump Cooling Tower CT Closed Circuit Cooling Tower CT Draw-Thru Cooling Tower CT Forced Draft Cooling Tower CT Induced Draft

Dry Cooler DC Closed Circuit

Glycol

Dehumidifier DHMD Dehumidifier Electric Water Cooler EWC

Floor

Mounted Electric EWC Handicap Water Cooler Electric Water Cooler EWC Recessed Electric Water Cooler EWC Wall Handicap Electric Water Cooler EWC Wall Mounted Fan AF Attic Fan CF Ceiling Fan EF Exhaust

Fan FAN Fan (Utility

Set)

Fan RAF Return Air Fan

Page T-28

Fan PRE Power Roof

Exhauster

Fan Coil Unit UV Unit Ventilator

Fan Coil Unit FCU Ceiling

Mounted

Fan Coil Unit FCU Horizontal Fan Coil Unit FCU Recessed Fan Coil Unit FCU Remote Fan Coil Unit FCU Vertical Fan Coil Unit FCU Wall Mounted Heat Exchangers HE

Steam to Hot

Water

Heat Pump HAAP Air to Air -

Packaged Unit

Heat Pump HAAS Air to Air -

Split System

Heat Pump HAWP Air to Water -

Packaged Unit

Heat Pump HWWP Water to Water - Packaged Unit

Heat Pump HWRP Water to Refrig. - Packaged Unit

Humidifier HMDF Steam

Humidifier

HMDF

Electric Boiler

Disposable Humidifier HMDF Inferred

Package Unit RTU Rooftop AC

Unit

Package Unit VACU Vertical AC

Package Unit

TWACU

Thru-Wall AC

Pump BP Booster Pump

Page T-29

Pump CCP Condenser Water

Circulating

Cooling Tower

Pump CTP Pump

Pump CWP Cooling Water

Pump DHWCP

Domestic Hot Water

Circulating

Pump DPP Cooling / Heating Water Pump

Pump HCP Heating Water

Pump SEP Sewage

Ejector Pumps

Pump SP Sump Pumps

Pump STP Storm Water

Pumps

Refrigeration FZ Freezer Refrigeration IM Ice Machines

Refrigeration RC Refrigerant

Compressor

Refrigeration RF Refrigerator

Refrigeration RIC Reach-in

Cooler

Refrigeration RIF Reach-in

Freezer

Refrigeration RR Refrigerated

Rack

Refrigeration SC Serving Cooler Refrigeration WIC Walk-in

Page T-30

Coolers

Refrigeration UC Unit Cooler

Refrigeration Steam

WIF Walk-in

Freezers

Reducing Valve

SPRV

Side Stream Filters SSF

Steam Trap STD Dynamic Trap

Steam Trap STF Float & Thermostatic Trap

Steam Trap STI Inverted

Bucket Trap

Steam Trap STO Orifice Trap

Steam Trap STT Thermostatic

Trap

Terminal Air Box ATU

Air Terminal

Terminal Air Fan Powered

FPVAV

Box VAV Terminal Air Fan Powered

FPVAVR

Box VAV - Reheat

Terminal Air Box VAV

Variable Air

Volume Terminal Air Box VAVR

Variable Air Volume - Reheat

Unit Heater SH Space Heater Unit Heater UH Horizontal Unit Heater UH Vertical

Unit Heater Variable

CUH Cabinet Unit

Heater Frequency Drive

VFD

Page T-31

Water Heater WHE Electric Water Heater WHG Natural Gas Water Heater WHS Steam Window AC Unit WACI Indoor Unit Window AC Unit WACO Outdoor Unit Window HP Unit WHPU Indoor Unit Window HP Unit WHPU Outdoor Unit General Appliances DRY Clothes Dryer General Appliances DW Dishwasher General Appliances MIC Microwave General Appliances OV Oven General Appliances RH Range Hood General Appliances ST Stove General Appliances WASH

Clothes

Washer

T1.3.15 Demolition Work

Remove all abandoned systems, equipment, pipes, ducts, controls, and any other unused appurtenances. Investigate all piping and ductwork passing thru spaces to determine if it is still active and remove all piping and ductwork no longer being used.

T.1.2 Electrical
T.1.3 Mechanical
Examples