Attachment 0006 - 2025-0083 Submittal List.pdf
PDF 18 KB Posted
- Solicitation number
- W519TC-25-R-A015
About this file
The document is a Submittal List for the Repair Roof Building 222 Annex project at Rock Island Arsenal. The submittal list outlines various required documentation to be submitted by the contractor during different phases of the project, categorized into eight types of submittals: Preconstruction Submittals, Shop Drawings, Product Data, Design Data, Test Reports, Certificates, Manufacturer's Instructions, and Closeout Submittals. These submittals must be provided for specific sections of work, including sections 01 14 00, 01 30 00, 07 53 23, 07 22 00, and others, covering areas such as construction management, roofing, woodwork, and mechanical systems.
The submittal requirements include specific timelines and documentation types, such as government-approved preconstruction submittals to be submitted within 15 and 30 workdays after the Notice to Proceed, shop drawings illustrating work portions, product data with catalog cuts and performance charts, design calculations, test reports from authorized testing laboratories, manufacturer certificates attesting to product specifications, and manufacturer installation instructions. The submittals are designed to ensure comprehensive documentation and compliance with technical and administrative requirements throughout the roof repair project for Building 222 Annex at Rock Island Arsenal.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2025_0083 Repair Roof Building 222 Annex REROOFB222 May 21, 2025 10:53 AM
SUBMITTAL LIST
SD-01 Preconstruction Submittals
Government approved Division 01 preconstruction submittals that are required prior to or commencing with the start of work must be submitted within 15 and 30 workdays after the issuance of the Notice to Proceed .
SECTION: 01 14 00 SUBPART: 1.1
SECTION: 01 30 00 SUBPART: 1.2
SECTION: 01 32 16.00 20 SUBPART: 1.1
SECTION: 01 33 00 SUBPART: 1.3
SECTION: 01 35 26 SUBPART: 1.3
SECTION: 01 45 00 SUBPART: 1.2
SECTION: 01 74 19 SUBPART: 1.4
SECTION: 02 41 00 SUBPART: 1.4
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
SECTION: 07 53 23 SUBPART: 1.3
SECTION: 07 60 00 SUBPART: 1.3
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
SECTION: 01 78 00 SUBPART: 1.5
SECTION: 07 22 00 SUBPART: 1.2
SECTION: 07 53 23 SUBPART: 1.3
Submittal List
SECTION: 07 92 00 SUBPART: 1.2
SECTION: 23 30 00 SUBPART: 1.3
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
SECTION: 07 53 23 SUBPART: 1.3
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
SECTION: 01 35 26 SUBPART: 1.3
SECTION: 06 10 00 SUBPART: 1.2
SECTION: 07 22 00 SUBPART: 1.2
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
SECTION: 01 32 16.00 20 SUBPART: 1.1
SECTION: 01 35 26 SUBPART: 1.3
SECTION: 07 22 00 SUBPART: 1.2
SECTION: 07 53 23 SUBPART: 1.3
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and Safety Data Sheets(SDS)concerning impedances, hazards and safety precautions.
SECTION: 07 22 00 SUBPART: 1.2
SECTION: 07 53 23 SUBPART: 1.3
SECTION: 07 60 00 SUBPART: 1.3
SECTION: 23 30 00 SUBPART: 1.3
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
SECTION: 01 78 00 SUBPART: 1.5
SECTION: 01 78 23 SUBPART: 1.2
SECTION: 02 41 00 SUBPART: 1.4
SECTION: 07 53 23 SUBPART: 1.3