Attach 19 SOO Appendix D - DES TO 0001 QASP 12032020.docx

DOCX document 35 KB Posted

Attached to
Defense Enclave Services (DES) RFP
Solicitation number
HC104720R0014
Issued by

About this file

This document outlines a Quality Assurance Surveillance Plan (QASP) for the Defense Enclave Services Task Order #001 contract. Key details include that the contractor will provide network operations and cybersecurity support services for 22 Defense Agencies and Field Activities. Performance will be monitored using random sampling, periodic inspections, and customer input to evaluate metrics such as system uptime, change management success rates, alert detection timeliness, and customer interaction reductions. The QASP defines acceptable quality levels, performance standards, and a rating system for contractor performance assessments. It provides guidance on documenting contractor performance reports, addressing deficiencies, and ensuring regulatory compliance.

View the file

Other files

File Type Posted
Attach 33 Additional Q A RFP 02052021.xlsx XLSX spreadsheet
Reading Library 8 - DISANet Authorized Hardware List 11092020.xlsx XLSX spreadsheet
Amd 06 final.pdf PDF
Reading Library 12 - DoDNet Equipment Management Consolidated Product List (2020).xlsx XLSX spreadsheet
Attach 21 SOO Appendix F DES TO 0001 DAFA Data Calls 02052021.xlsx XLSX spreadsheet
Amd 05 final.pdf PDF
Attach 15 SOO Appendix F DES IDIQ DAFA Data Calls 01282021.xlsx XLSX spreadsheet
Attach 8 IDIQ Labor Rates 01272021 (v1) (PROTECTED).xlsx XLSX spreadsheet
Attach 15 SOO Appendix F DES IDIQ DAFA Data Calls 01272021.xlsx XLSX spreadsheet
Reading Library 11-DISANet Authorized Software List NIPR-SIPR 01272021.xlsx XLSX spreadsheet
Attach 23 TO 0001 DD254 01272021.pdf PDF
Attach 11 SOO Appendix B DES IDIQ places of performance 01272021.docx DOCX document
Attach 9 TO 0001 SOO 01272021.docx DOCX document
Attach 31 SOO Appendix A-DES TO 001 Services Summary 01272021.docx DOCX document
Attach 21 SOO Appendix F DES TO 0001 DAFA Data Calls 01272021.xlsx XLSX spreadsheet
Attach 32 Q A RFP.xlsx XLSX spreadsheet
Attach 27 Labor Category Descriptions 01272021.docx DOCX document
Attach 14 SOO Appendix E - DES IDIQ PWS Template 01272021.docx DOCX document
Amd 04 final.pdf PDF
Attach 17 SOO Appendix B DES TO 0001 Places of Performance 01272021.docx DOCX document
Reading Library 13 DISA High Performing Sites 01272021.xlsx XLSX spreadsheet
Attach 28 DES TO 001 CLIN Structure 01272021 (DON).xlsx XLSX spreadsheet
Attach 29 SOO Appendix A Services Summary 01272021.docx DOCX document
Attach 22 SOO Appendix G DES TO 0001 Glossary 01272021.docx DOCX document
Reading Library 2 - DISANET NIPR World Wide - May 2019-redacted.jpg JPG image
Reading Library 2 - DISANET NIPR World Wide - May 2019-redacted17Dec.pdf PDF
Reading Library 2 - DISANET NIPR World Wide - May 2019-redacted.pdf PDF
Attach 30 QA DRFP_12032020.xlsx XLSX spreadsheet
Attach 8 IDIQ Labor Rates 12102020 (v1) (PROTECTED).xlsx XLSX spreadsheet
HC104720R0014 amd 01.pdf PDF
Reading Library 3 - DSMC Event Management SOP_4 August 2020_Redacted.pdf PDF
Attach 10 Non disclosure agreements contractors.docx DOCX document
Attach 16 SOO Appendix G -Glossary 09232020.docx DOCX document
Reading Library 5 - Legacy SOP_ DSMC Event Management_Redacted.pdf PDF
Attach 9 TO 0001 SOO 12032020.docx DOCX document
Attach 6 Past Performance Questionnaires.docx DOCX document
Attach 7 Sample Consent Letter.docx DOCX document
Attach 22 SOO Appendix G -DES TO 0001 Glossary.docx DOCX document
Attach 29 SOO Appendix A Services Summary.docx DOCX document
Reading Library 12 - Equipment Management Consolidated Product List (2020).xlsx XLSX spreadsheet
Reading Library 9 - DISA ITSM Flow Chart.pptx PPTX presentation
Reading Library 11 - DISANet Authorized Software List NIPR 2020-11-17.xlsx XLSX spreadsheet
Attach 13 SOO Appendix D- DES IDIQ GSC Workload - 09222020.docx DOCX document
Attach 31 SOO Appendix A-DES TO 001 Services Summary 120220.docx DOCX document
Attach 3 Subcontracting Plan Checklist.docx DOCX document
Attach 28 DES TO 0001 CLIN Structure 12082020.xlsx XLSX spreadsheet
Reading Library 8 - Approved Hardware List 11092020.xlsx XLSX spreadsheet
Reading Library 4 - Legacy Process_After Hours Outage Notification_Redacted.pdf PDF
Reading Library 7 - Legacy SOP_Problem Management_Redacted.pdf PDF
Attach 23 TO 0001 DD254.pdf PDF
Show 40 more

Latest 50 of 73 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)

1. Contract or Task Order Title: Defense Enclave Services Task Order #001, Pathfinder Agencies

2. Purpose:

This QASP provides a systematic method to evaluate performance for the stated contract. This QASP explains the following:

· What will be monitored?

· How monitoring will take place.

· Who will conduct the monitoring?

· How monitoring efforts and results will be documented.

This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance. In addition, the QASP should recognize that unforeseen and uncontrollable situations may occur.

This QASP is a “living document” and the Government may unilaterally review and revise it on a regular basis. Updates shall ensure that the QASP remains a valid, useful, and enforceable document. Copies of the original QASP and revisions shall be provided to the contractor and Government officials implementing surveillance activities.

3. Roles and Responsibilities:

The following personnel shall oversee and coordinate surveillance activities.

Program/Project Manager (PM) – The PM provides program oversight and supports the COR’s performance assessment activities.

Contracting Officer (KO) – The KO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The KO shall also ensure that the contractor receives impartial, fair, and equitable treatment under this contract. Determine the final assessment of the contractor’s performance.

Contracting Officer’s Representative (COR) – The COR is responsible for providing continuous technical oversight of the contractor’s performance. The COR uses the QASP to conduct the oversight/surveillance process. The COR shall keep a Quality Assurance file that accurately documents the contractor’s actual performance. The purpose is to ensure that the contractor meets the performance standards contained in the contract. The COR is responsible for reporting early identification of performance problems to the KO. The COR is required to provide an annual performance assessment to the KO which will be used in documenting past performance. The QASP is the primary tool for documenting contractor performance. The COR is not empowered to make any contractual commitments or to authorize any contractual change on the Government’s behalf.

Alternate Contracting Officer’s Representative (ACOR) – The ACOR acts as a COR when the COR is unavailable and shares the same responsibilities.

Other Key Government Personnel - This may include performance monitors, inspectors, technical experts, workforce service division and center directorate level security personnel, requirements office, or others (i.e. users) who provide information that helps the COR monitor contractor performance.

4. Primary Method of Surveillance:

· Random Sampling. This is usually the most appropriate method for recurring tasks. With random sampling, services are sampled to determine if the level of performance is acceptable. Random sampling works best when the number of instances of the services being performed is very large and a statistically valid sample can be obtained. Computer programs (such as self-diagnostic systems logs) may be employed for this surveillance method.

· Periodic Inspection. These services are monitored weekly, monthly, quarterly, semiannually, annually, etc. Periodic types of activities are perfect for periodic inspection because not only are they infrequent, but there is normally a predetermined, specified time frame within which the tasks must be accomplished. Therefore, you know exactly when to conduct the evaluations. Periodic inspections automatically become 100 percent evaluations or "100 percent checks." Inspections should be divided and scheduled by frequency: annual, semiannual, quarterly, monthly, weekly and as required. Sometimes services are required for which the time or frequency cannot be predicted, such as accident investigations, one-time special tasking by higher headquarters, etc. These would be labeled "as required inspections." Others are known and predictable such as the quarterly status report or the monthly travel report currently included in some DISA service contracts.

· Customer Input. Although usually not a primary method, this is a valuable supplement to more systematic methods. For example, in a case where random sampling indicates unsatisfactory service, customer complaints can be used as substantiating evidence. In certain situations where customers can be relied upon to complain consistently when the quality of performance is poor, e.g., dining facilities, building services, customer surveys and customer complaints may be a primary surveillance method, and customer satisfaction an appropriate performance standard. In all cases, complaints should be documented, preferably on a standard form.

Surveillance Matrix

Performance objectives define the desired outcomes. Performance Standards define the level of service required under the contract to successfully meet the performance objective. The inspection methodology defines how, when, and what will be assessed in measuring performance. The Government performance surveillance, using this QASP, to determine the quality of the contractor’s performance as it relates to the performance element standards. The AQL performance Standard Table should be used to form the foundation of the COR’s inspection checklist.

5. Performance Standards:

The Contractor shall deliver services in accordance with Table 2 - Network Operations below.

Performance Standard (Network Operations)
Acceptable Quality Levels (AQLs)
System and Tool Availability for High Performing Sites
>=99.99% system uptime for supported systems, not to include Authorized Service Interruptions (ASI)/routine maintenance or higher level outages
System and Tool Availability for Standard Sites
>=99% system uptime for supported applications, not to include Authorized Service Interruptions (ASI)/routine maintenance or higher level outages
Change and Release without Incident
>=95% of changes and releases result in no adverse impact on production services, or require significant re-work with the application of additional resources/time
Alert detection and escalation
>=90% 24 x 7 x 365; Priority 1 alerts detected and reported (via trouble ticket) to the service desk within 30 minutes of initial occurrence
Decrease customer interactions
>=5% decrease in customer interactions, to begin after 1 year and reported every 6 months thereafter
Cybersecurity Support
RMF documentation will be maintained and updated daily, to include cybersecurity architecture, requirements, objectives and policies, and maintaining DoDNet security posture with minimal re-work at least 95% of the time

Table 2 - Network Operations

6. Documenting Performance:

Acceptable Performance.

The Government shall document positive performance. A Performance Assessment Report (PAR) template is attached (Appendix 2). Any report may become part of the supporting documentation for fixed price payments, award/incentive fee payments, Contractor Performance Assessment Reporting System (CPARS) entries, or other actions. Government acceptance of services permits the contractor to invoice for the service fee.

Unacceptable performance.

When unacceptable performance occurs, the COR shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication. The COR shall document the discussion and place it in the COR file and provide a copy to the KO.

When the COR determines formal written communication is required, the COR shall prepare a Corrective Action Report (CAR). The CAR is forwarded to the KO for dissemination to the contractor. A CAR template is attached to this QASP (Appendix 4).

The contractor shall acknowledge receipt of the CAR in writing. The CAR will specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CAR will also state how long after receipt the contractor has to present this corrective action plan to the KO and COR. The Government may withhold payment for services until corrective action is taken. The Government shall review the contractor's corrective action plan to determine acceptability. Upon Government acceptance of the corrected services the contractor will be permitted to invoice for the services rendered fee.

Any CAR may become a part of the supporting documentation for contract payment deductions, CPARS or other actions deemed necessary by the KO.

7. Mandatory or regulatory compliance items:

The contractor will provide initial proof of compliance with regulatory and compliance items contained in the contract and task order. The Contracting Officer's Representative (COR) and the Contracting Officer (KO) will evaluate the initial submission and will conduct ad hoc reviews of the contractor's compliance throughout the remainder of the period of performance. The contractor will monitor compliance as required by FAR 52.222-50, Combating Trafficking in Persons, and report any issues to the KO.

8. Acceptable Quality Level (AQL):

See section 5 above.

9. Evaluation Method:

The COR will evaluate customer satisfaction based on input received from the Division and Branch level as well as with random sampling and periodic inspections. The COR will evaluate product timeliness in accordance with the Delivery Schedule; considering document quality and applicability in accordance with requirements set forth in the PWS. The COR will obtain additional feedback on document quality from members of the Division and Branch level government management team. The COR will review self-diagnostic systems logs, conduct a comparison with actual maintenance performance and otherwise verify and validate contractor performance.

10. Performance Rating

In evaluating the quality of contractor’s performance, the following performance ratings may be used (same as CPAR ratings).

Performance Rating Criteria

Exceptional
Performance meets contractual requirements and exceeds many to the government’s benefits. The contractual performance of the element or sub-element being assessed was accomplished with no problems and contractor actions were highly effective.
Very Good
Performance meets contractual requirements and exceeds some to the government benefits. The contractual performance was accomplished with few minor problems for which corrective actions taken by the contractor were effective.
Satisfactory
Performance meets contractual requirements. The contractual performance contains some minor problems for which corrective actions taken by the contractor were satisfactory.
Marginal
Performance does not meet some contractual requirements. The contractual performance reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear marginally effective or were not fully implemented.
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

Appendix 1 - Reserved

Appendix 2 – Performance Assessment Report

PERFORMANCE ASSESSMENT REPORT (PAR)

(If more space is needed, use reverse and identify by number)

1. CONTRACT/TASK ORDER NUMBER
2. CONTRACTOR
3. TYPE OF SERVICES

4. QUALITY ASSURANCE PERSONNEL (COR) SIGNATURE AND DATE

5. COR PHONE
6. SUSPENSE DATE

I. PERFORMANCE

7. |_| DEFICIENCY (CHECK ALL BOXES THAT APPLY)

|_| NEW

|_| REPEAT

|_| NO DEFICIENCY NOTED

8. SERVICES SUMMARY or PWS PARAGRAPH ITEM REVIEWED

9. BRIEF DESCRIPTION OF DEFICIENCY (IF DEFICIENCY BOX WAS CHECKED)
10. DETAILED PERFORMANCE ASSESSMENT

II. CONTRACTOR VALIDATION

11. CONTRACTOR REPRESENTATIVE |_| CONCUR |_| NON-CONCUR

12. CORRECTIVE ACTION ESTIMATED COMPLETION DATE

13. CONTRACTOR REPRESENTATIVE CORRECTIVE ACTION AND PREVENTION OF RECURRENCE OR REASON FOR NON-CONCURRENCE OF COR CITED DEFICIENCY

III. ACTION CORRECTED

14. |_| CONCUR |_| NON-CONCUR COR SIGNATURE AND DATE

15. COR REMARKS (REQUIRED)

6. CONTRACTOR REPRESENTATIVE REMARKS

Appendix 3 – Customer Complaint Record

CUSTOMER COMPLAINT RECORD

DATE/TIME OF COMPLAINT

SOURCE OF COMPLAINT

ORGANIZATION

BUILDING NUMBER

INDIVIDUAL

PHONE NUMBER

NATURE OF COMPLAINT

CONTRACT REFERENCE

VALIDATION

DATE/TIME CONTRACTOR INFORMED OF COMPLAINT

ACTION TAKEN BY CONTRACTOR

RECEIVED/VALIDATED BY

Appendix 4 – Corrective Action Report

CORRECTIVE ACTION REPORT (CAR)

(If more space is needed, use reverse and identify by number)

1. CONTRACTOR

2. CONTRACT NUMBER

3. TYPE OF SERVICES

4. FUNCTIONAL AREA

5. SUSPENSE DATE

6. CONTROL NUMBER

7. DEFICIENCY |_| MAJOR |_| MINOR

FINDING:

FINDING IMPACT:

Please respond with a written corrective action plan that details the corrective action of the cited deficiency, the cause of the deficiency, and actions taken to prevent recurrence by Suspense Date in Block 5. If date was not entered in Block 5, the contractor is not required to provide a response.

8. QUALITY ASSURANCE PERSONNEL (COR)

TYPED NAME AND GRADE

SIGNATURE AND DATE

9. ISSUING AUTHORITY

TYPED NAME AND GRADE

SIGNATURE AND DATE

10. COR RESPONSE TO CONTRACTOR CORRECTIVE ACTION AND ACTION TAKEN TO PREVENT RECURRENCE

11. COR DETERMINATION

|_| ACCEPTED |_| REJECTED

12. CLOSE DATE

Enclosure 6, Page 1 of 2 Pages 17Jul2013/Version 2