Solicitation # FA441720R0009 Water Tower Maintenance IDIQ Hurlburt Field, FL
LINE
ITEM SPEC DESCRIPTION Unit Quantity UNIT PRICE
0001 01 10 00 (DEP 2005,
62 555 350) Annual Inspection
EA 4
0002 01 10 00 (DEP 2005,
62 555 350) Washout 250,000 gal.
EA 1
0003 12400 Exterior Paint 250,000 gal. (Towers #2 or #808) EA 1 0004 Paint Graphics EA 1
0005 Replace multiple corroded upper riser and windage rods EA 10
0006 05 51 33 Replace interior ladder or at minimum replace upper section EA 1
0007 Reattach or replace obstruction lighting on top EA 1
0008 Properly cover catholic protection system opening on roof EA 1
BID SCHEDULE
BASE YEAR
BASE YEAR TOTAL
LINE
ITEM SPEC DESCRIPTION Unit Quantity UNIT PRICE
1001 01 10 00 (DEP 2005,
62 555 350) 5 Year Inspection
EA 4
1002 01 10 00 (DEP 2005,
62 555 350) Washout 125,000 gal.
EA 1
1003 01 10 00 (DEP 2005,
62 555 350) Washout 250,000 gal.
EA 1
1004 12200 Interior Paint 125,000 gal. (Tower #5) EA 1
1005 12200 Interior Paint 250,000 gal. (Towers #2 or #808) EA 1
1006 12400 Exterior Paint 250,000 gal. (Towers #2 or #808) EA 1 1007 Reattach or replace obstruction lighting on top EA 1 1008 05 51 33 Re-install safetly cable on primary ladder EA 1 1009 05 51 33 Replace or repair exterior ladder EA 1 1010 05 51 33 Replace ladder brackets of roof ladder EA 1
OPTION YEAR 1
BID SCHEDULE
OPTION YEAR 1 TOTAL
LINE
ITEM SPEC DESCRIPTION Unit Quantity UNIT PRICE
2001 01 10 00 (DEP 2005,
62 555 350) Annual Inspection
EA 4
2002 01 10 00 (DEP 2005,
62 555 350) Washout 250,000 gal.
EA 1
2003 12400 Exterior Paint 125,000 gal. (Tower #5) EA 1
2004 Replace multiple corroded upper riser and windage rods EA 10
2005 Reattach or replace obstruction lighting on top EA 1 2006 05 51 33 Replace/repair top portion of leg ladder EA 1
2007 Remove Cathodic Protection and weld plates to holes to seal tank. EA 5
BID SCHEDULE
OPTION YEAR 2 TOTAL
OPTION YEAR 2
LINE
ITEM SPEC DESCRIPTION Unit Quantity UNIT PRICE
3001 01 10 00 (DEP 2005,
62 555 350) Annual Inspection
EA 4
3002 01 10 00 (DEP 2005,
62 555 350) Washout 125,000 gal.
EA 1
3003 01 10 00 (DEP 2005,
62 555 350) Washout 250,000 gal.
EA 2
3004 12200 Interior Paint 250,000 gal. (Tower #7) EA 1 3005 12400 Exterior Paint 250,000 gal. (Tower #7) EA 1 3006 Repair anchor bolts EA 20 3007 Repair platform holes EA 1
BID SCHEDULE
OPTION YEAR 3 TOTAL
OPTION YEAR 3
LINE
ITEM SPEC DESCRIPTION Unit Quantity UNIT PRICE
4001 01 10 00 (DEP 2005,
62 555 350) Annual Inspection
EA 4
4002 01 10 00 (DEP 2005,
62 555 350) Washout 250,000 gal.
EA 1
4003 12200 Interior Paint 250,000 gal. (Towers #2 or #808)
EA 1
OPTION YEAR 4 TOTAL
BID SCHEDULE
OPTION YEAR 4
Bid Schedule
| UNIT PRICE4: |
| UNIT PRICE1: |
| UNIT PRICE1_2: |
| UNIT PRICE1_3: |
| UNIT PRICE10: |
| UNIT PRICE1_4: |
| UNIT PRICE1_5: |
| UNIT PRICE1_6: |
| UNIT PRICE4_2: |
| UNIT PRICE1_7: |
| UNIT PRICE1_8: |
| UNIT PRICE1_9: |
| UNIT PRICE1_10: |
| UNIT PRICE1_11: |
| UNIT PRICE1_12: |
| UNIT PRICE1_13: |
| UNIT PRICE1_14: |
| UNIT PRICE1_15: |
| UNIT PRICE4_3: |
| UNIT PRICE1_16: |
| UNIT PRICE1_17: |
| UNIT PRICE10_2: |
| UNIT PRICE1_18: |
| UNIT PRICE1_19: |
| UNIT PRICE5: |
| UNIT PRICE4_4: |
| UNIT PRICE1_20: |
| UNIT PRICE2: |
| UNIT PRICE1_21: |
| UNIT PRICE1_22: |
| UNIT PRICE20: |
| UNIT PRICE1_23: |
| UNIT PRICE4_5: |
| UNIT PRICE1_24: |
| UNIT PRICE1_25: |
File details come from the government source that posted it. Updated .