Att J-11_Seed Project Schedule of Material Submittals.pdf

PDF 251 KB Posted

Attached to
FY25 Multiple Award Construction Contract (MACC) recompete Federal contract opportunity
Solicitation number
FA448424R0017
Issued by
Department of the Air Force Air Mobility Command

About this file

This document is a Schedule of Material Submittals related to a federal contract opportunity to convert Room 420 on the 4th floor of Building 481 into a kitchenette. The schedule outlines 37 items that the contractor must submit for review and approval prior to the start of work, including accident hazard analysis, construction schedule, quality control plan, material approval list, product data, shop drawings, samples, and warranties. The required submission date for most items is 10 days after the award or kickoff meeting. The document provides details on the type of submittal required (e.g., catalog data, shop drawings, samples) and designates whether the item requires final approval. The related federal contract opportunity is for the FY25 Multiple Award Construction Contract (MACC) recompete at JB MDL NJ, which includes a variety of construction and renovation tasks across multiple trades.

View the file

Other files for this federal contract opportunity

Other files attached to FY25 Multiple Award Construction Contract (MACC) recompete, newest first.
File Type Posted
Solicitation Amendment FA448424R00170003 SF 30.pdf PDF
Att J-13_Seed Project Site Visit Requests For Information and Solicitation Q and A-REV 10.24.24.pdf PDF
Att J-15_Seed Project Bldg 481-4th Floor Relevant Drawings.pdf PDF
Att J-10_Seed Project Statement of Objectives-REV 10.10.24.pdf PDF
Att J-12_Seed Project Site Visit List of Attendees.pdf PDF
Att C-1_Statement of Work-REV 10.10.24.docx DOCX document
Att J-14_JBMDL Installation Facility Standards (IFS).pdf PDF
Att C-2_Ordering Procedures-REV 10.10.24.pdf PDF
Solicitation Amendment FA448424R00170002 SF 30.pdf PDF
Att J-13_Seed Project Site Visit Requests For Information and Solicitation Q and A.pdf PDF
Solicitation Amendment FA448424R00170001 SF 30.pdf PDF
Att C-1_Statement of Work.docx DOCX document
Att J-5_ Medical Statement.pdf PDF
Att J-6_Anti-Terorism Awareness Guide for Contractors.pdf PDF
Att J-7_Section L and M.docx DOCX document
Att J-9_Seed Project Floor Plan.pdf PDF
Att J-10_Seed Project Statement of Objectives.pdf PDF
Att J-1_Past Performance Letter and Questionnaire.docx DOCX document
Att J-3_Wage Determinations_Burlington and Ocean_Building_7.12.24.pdf PDF
Att J-8_Seed Project Bid Schedule.pdf PDF
Solicitation - FA448424R0017.pdf PDF
Att J-4_ Security Forces Appendix.pdf PDF
Att C-2_Ordering Procedures.pdf PDF
Att J-2_ Environmental Compliance Statement.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION/CONTRACT NUMBER

Page 1 of 1 DO# TBD

ITEM OR DESCRIPTION OF CONTRACT

REFERENCE TYPE OF SUBMITTAL

NOTE: 3 copies required per submittal, 1 electric copy required APPROVED

Accident Hazard Analysis x 10 days after

AWD

Construction Schedule x

10 days after

Kick-off Meeting

Progress Schedule x

10 days after

Kick-off Meeting

Quality Control Plan x 10 days after

Kick-off Meeting

Material Approval Submittal List from Contractor x

10 days after

Kick-off Meeting

Salvage Material List x

10 days after

Kick-off Meeting

Safety Data Sheets x x Prior to start of work

Notification and Permit x Prior to start of work

9 Metal Stud Framing - Walls & Soffits x x x x Prior to start of work

10 Plumbing Piping & Accessories x x x Prior to start of work

FINAL APPROVAL REMARKS

L I N E

N U M B E R

REQUIRED

SUBMISSION DATE

DATE CONTRACTOR NOTIFIED

C A T A L O G

D A T A

O P E R A T I O N

I

S T R U C T I O N S

S P E C I F I C A T I O N S

S T Y L E D E S I G N

CONTRACTOR

RESUBMITTAL

DATE RECEIVED IN

CONTRACT

DATE TO CIVIL

ENGINEERS

RETURN DATE FOLLOW UP

TO BE COMPLETED BY PROJECT ENGINEER (Fill in numbers of each submittal required) TO BE COMPLETED BY CONTRACT ADMINISTRATOR C E R T I F I C A T I O

S

F

C O M P L I A N C E

S H O P

D R A W I N G S

S A M P L E S

C O L O R

S E L E C T I O N

M A N U F A C T U R E R

E C O M M E N D A T I O N S

M A N U F A C T U R E

W A R R A N T Y

Schedule of Material Submittals

PROJECT NUMBER: PROJECT TITLE:

MSBL - 24-1023

Convert Room 420 on 4th floor of

Building 481 into a Kitchenette

TBD

DIS-APPROVED

Page 1 of 1 DO# TBD

ITEM OR DESCRIPTION OF CONTRACT

REFERENCE TYPE OF SUBMITTAL

NOTE: 3 copies required per submittal, 1 electric copy required APPROVED

FINAL APPROVAL REMARKS

L I N E

N U M B E R

REQUIRED

SUBMISSION DATE

DATE CONTRACTOR NOTIFIED

C A T A L O G

D A T A

O P E R A T I

S T R U C T I O N S

S P E C I F I C A T I O N S

S T Y L E D E S I G N

CONTRACTOR

RESUBMITTAL

DATE RECEIVED IN

CONTRACT

DATE TO CIVIL

ENGINEERS

RETURN DATE FOLLOW UP

TO BE COMPLETED BY PROJECT ENGINEER (Fill in numbers of each submittal required) TO BE COMPLETED BY CONTRACT ADMINISTRATOR C E R T I F I C A T I O

C O M P L I A N C E

S H O P

D R A W I N G S

S A M P L E S

C O L O R

S E L E C T I O N

M A N U F A C T U R E

C O M M E N D A T I O N S

M A N U F A C T U R E

R R A N T Y

Schedule of Material Submittals

PROJECT NUMBER: PROJECT TITLE:

MSBL - 24-1023

Convert Room 420 on 4th floor of

Building 481 into a Kitchenette

TBD

DIS-APPROVED

11 Electrical Wiring and Accessories x x x Prior to start of work

12 HVAC Ductwork and Accessories x x x Prior to start of work

Sprinkler / Fire Protection x x x x Prior to start of work

14 Gypsum Board and Accessories x x x Prior to start of work

15 Electrical Devices & Accessories x x x x x x x Prior to start of work

16 Life Safety Devices & Accessories x x x x x x x Prior to start of work

17 Lighting Equipment & Accessories x x x x x x x Prior to start of work

18 Low Voltage Wiring and Accessories x x x x x x x Prior to start of work

19 HVAC Fixtures and Accessories x x x x x x x Prior to start of work

20 Plumbing Fixtures and Accessories x x x x x x x Prior to start of work

21 Ceramic Tile and Accessories x x x x x x x x Prior to start of work

Page 1 of 1 DO# TBD

ITEM OR DESCRIPTION OF CONTRACT

REFERENCE TYPE OF SUBMITTAL

NOTE: 3 copies required per submittal, 1 electric copy required APPROVED

FINAL APPROVAL REMARKS

L I N E

N U M B E R

REQUIRED

SUBMISSION DATE

DATE CONTRACTOR NOTIFIED

C A T A L O G

D A T A

O P E R A T I

S T R U C T I O N S

S P E C I F I C A T I O N S

S T Y L E D E S I G N

CONTRACTOR

RESUBMITTAL

DATE RECEIVED IN

CONTRACT

DATE TO CIVIL

ENGINEERS

RETURN DATE FOLLOW UP

TO BE COMPLETED BY PROJECT ENGINEER (Fill in numbers of each submittal required) TO BE COMPLETED BY CONTRACT ADMINISTRATOR C E R T I F I C A T I O

C O M P L I A N C E

S H O P

D R A W I N G S

S A M P L E S

C O L O R

S E L E C T I O N

M A N U F A C T U R E

C O M M E N D A T I O N S

M A N U F A C T U R E

R R A N T Y

Schedule of Material Submittals

PROJECT NUMBER: PROJECT TITLE:

MSBL - 24-1023

Convert Room 420 on 4th floor of

Building 481 into a Kitchenette

TBD

DIS-APPROVED

22 Porcelain Floor Tile and Accessories x x x x x x x x Prior to start of work

Lower Cabinets x x x x x x x x x Prior to start of work

Upper Cabinets x x x x x x x x x Prior to start of work

Countertops x x x x x x x x x Prior to start of work

Appliances - Ref., Range & Range Hood Dishwasher, Microwave x x x x x x x Prior to start of work

27 Acoustical Ceiling Tile System & Accessories x x x x x x x x Prior to start of work

Door, Frame & Hardware x x x x x x Prior to start of work

Door Locksets x x x x x x x x Prior to start of work

Fire Alarm System x x x x x x x Prior to start of work

Painting x x x x x x Prior to start of work

32 Corner Guards & other Accessories x x x x x x x Prior to start of work

Page 1 of 1 DO# TBD

ITEM OR DESCRIPTION OF CONTRACT

REFERENCE TYPE OF SUBMITTAL

NOTE: 3 copies required per submittal, 1 electric copy required APPROVED

FINAL APPROVAL REMARKS

L I N E

N U M B E R

REQUIRED

SUBMISSION DATE

DATE CONTRACTOR NOTIFIED

C A T A L O G

D A T A

O P E R A T I

S T R U C T I O N S

S P E C I F I C A T I O N S

S T Y L E D E S I G N

CONTRACTOR

RESUBMITTAL

DATE RECEIVED IN

CONTRACT

DATE TO CIVIL

ENGINEERS

RETURN DATE FOLLOW UP

TO BE COMPLETED BY PROJECT ENGINEER (Fill in numbers of each submittal required) TO BE COMPLETED BY CONTRACT ADMINISTRATOR C E R T I F I C A T I O

C O M P L I A N C E

S H O P

D R A W I N G S

S A M P L E S

C O L O R

S E L E C T I O N

M A N U F A C T U R E

C O M M E N D A T I O N S

M A N U F A C T U R E

R R A N T Y

Schedule of Material Submittals

PROJECT NUMBER: PROJECT TITLE:

MSBL - 24-1023

Convert Room 420 on 4th floor of

Building 481 into a Kitchenette

TBD

DIS-APPROVED

Fire Extinguishers x x x x x Prior to start of work

Window Shade x x x x x x x x Prior to start of work

35 Manufacturers & Contractors Warranties x x 10 days after C/O

As-Built Drawings x x 10 days after C/O

Dumpster Tickets x 10 days after C/O

File details come from the government source that posted it. Updated .