Att J-11_Seed Project Schedule of Material Submittals.pdf
PDF 251 KB Posted
- Attached to
- FY25 Multiple Award Construction Contract (MACC) recompete Federal contract opportunity
- Solicitation number
- FA448424R0017
About this file
This document is a Schedule of Material Submittals related to a federal contract opportunity to convert Room 420 on the 4th floor of Building 481 into a kitchenette. The schedule outlines 37 items that the contractor must submit for review and approval prior to the start of work, including accident hazard analysis, construction schedule, quality control plan, material approval list, product data, shop drawings, samples, and warranties. The required submission date for most items is 10 days after the award or kickoff meeting. The document provides details on the type of submittal required (e.g., catalog data, shop drawings, samples) and designates whether the item requires final approval. The related federal contract opportunity is for the FY25 Multiple Award Construction Contract (MACC) recompete at JB MDL NJ, which includes a variety of construction and renovation tasks across multiple trades.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION/CONTRACT NUMBER
Page 1 of 1 DO# TBD
ITEM OR DESCRIPTION OF CONTRACT
REFERENCE TYPE OF SUBMITTAL
NOTE: 3 copies required per submittal, 1 electric copy required APPROVED
Accident Hazard Analysis x 10 days after
AWD
Construction Schedule x
10 days after
Kick-off Meeting
Progress Schedule x
10 days after
Kick-off Meeting
Quality Control Plan x 10 days after
Kick-off Meeting
Material Approval Submittal List from Contractor x
10 days after
Kick-off Meeting
Salvage Material List x
10 days after
Kick-off Meeting
Safety Data Sheets x x Prior to start of work
Notification and Permit x Prior to start of work
9 Metal Stud Framing - Walls & Soffits x x x x Prior to start of work
10 Plumbing Piping & Accessories x x x Prior to start of work
FINAL APPROVAL REMARKS
L I N E
N U M B E R
REQUIRED
SUBMISSION DATE
DATE CONTRACTOR NOTIFIED
C A T A L O G
D A T A
O P E R A T I O N
I
S T R U C T I O N S
S P E C I F I C A T I O N S
S T Y L E D E S I G N
CONTRACTOR
RESUBMITTAL
DATE RECEIVED IN
CONTRACT
DATE TO CIVIL
ENGINEERS
RETURN DATE FOLLOW UP
TO BE COMPLETED BY PROJECT ENGINEER (Fill in numbers of each submittal required) TO BE COMPLETED BY CONTRACT ADMINISTRATOR C E R T I F I C A T I O
S
F
C O M P L I A N C E
S H O P
D R A W I N G S
S A M P L E S
C O L O R
S E L E C T I O N
M A N U F A C T U R E R
E C O M M E N D A T I O N S
M A N U F A C T U R E
W A R R A N T Y
Schedule of Material Submittals
PROJECT NUMBER: PROJECT TITLE:
MSBL - 24-1023
Convert Room 420 on 4th floor of
Building 481 into a Kitchenette
TBD
DIS-APPROVED
Page 1 of 1 DO# TBD
ITEM OR DESCRIPTION OF CONTRACT
REFERENCE TYPE OF SUBMITTAL
NOTE: 3 copies required per submittal, 1 electric copy required APPROVED
FINAL APPROVAL REMARKS
L I N E
N U M B E R
REQUIRED
SUBMISSION DATE
DATE CONTRACTOR NOTIFIED
C A T A L O G
D A T A
O P E R A T I
S T R U C T I O N S
S P E C I F I C A T I O N S
S T Y L E D E S I G N
CONTRACTOR
RESUBMITTAL
DATE RECEIVED IN
CONTRACT
DATE TO CIVIL
ENGINEERS
RETURN DATE FOLLOW UP
TO BE COMPLETED BY PROJECT ENGINEER (Fill in numbers of each submittal required) TO BE COMPLETED BY CONTRACT ADMINISTRATOR C E R T I F I C A T I O
C O M P L I A N C E
S H O P
D R A W I N G S
S A M P L E S
C O L O R
S E L E C T I O N
M A N U F A C T U R E
C O M M E N D A T I O N S
M A N U F A C T U R E
R R A N T Y
Schedule of Material Submittals
PROJECT NUMBER: PROJECT TITLE:
MSBL - 24-1023
Convert Room 420 on 4th floor of
Building 481 into a Kitchenette
TBD
DIS-APPROVED
11 Electrical Wiring and Accessories x x x Prior to start of work
12 HVAC Ductwork and Accessories x x x Prior to start of work
Sprinkler / Fire Protection x x x x Prior to start of work
14 Gypsum Board and Accessories x x x Prior to start of work
15 Electrical Devices & Accessories x x x x x x x Prior to start of work
16 Life Safety Devices & Accessories x x x x x x x Prior to start of work
17 Lighting Equipment & Accessories x x x x x x x Prior to start of work
18 Low Voltage Wiring and Accessories x x x x x x x Prior to start of work
19 HVAC Fixtures and Accessories x x x x x x x Prior to start of work
20 Plumbing Fixtures and Accessories x x x x x x x Prior to start of work
21 Ceramic Tile and Accessories x x x x x x x x Prior to start of work
Page 1 of 1 DO# TBD
ITEM OR DESCRIPTION OF CONTRACT
REFERENCE TYPE OF SUBMITTAL
NOTE: 3 copies required per submittal, 1 electric copy required APPROVED
FINAL APPROVAL REMARKS
L I N E
N U M B E R
REQUIRED
SUBMISSION DATE
DATE CONTRACTOR NOTIFIED
C A T A L O G
D A T A
O P E R A T I
S T R U C T I O N S
S P E C I F I C A T I O N S
S T Y L E D E S I G N
CONTRACTOR
RESUBMITTAL
DATE RECEIVED IN
CONTRACT
DATE TO CIVIL
ENGINEERS
RETURN DATE FOLLOW UP
TO BE COMPLETED BY PROJECT ENGINEER (Fill in numbers of each submittal required) TO BE COMPLETED BY CONTRACT ADMINISTRATOR C E R T I F I C A T I O
C O M P L I A N C E
S H O P
D R A W I N G S
S A M P L E S
C O L O R
S E L E C T I O N
M A N U F A C T U R E
C O M M E N D A T I O N S
M A N U F A C T U R E
R R A N T Y
Schedule of Material Submittals
PROJECT NUMBER: PROJECT TITLE:
MSBL - 24-1023
Convert Room 420 on 4th floor of
Building 481 into a Kitchenette
TBD
DIS-APPROVED
22 Porcelain Floor Tile and Accessories x x x x x x x x Prior to start of work
Lower Cabinets x x x x x x x x x Prior to start of work
Upper Cabinets x x x x x x x x x Prior to start of work
Countertops x x x x x x x x x Prior to start of work
Appliances - Ref., Range & Range Hood Dishwasher, Microwave x x x x x x x Prior to start of work
27 Acoustical Ceiling Tile System & Accessories x x x x x x x x Prior to start of work
Door, Frame & Hardware x x x x x x Prior to start of work
Door Locksets x x x x x x x x Prior to start of work
Fire Alarm System x x x x x x x Prior to start of work
Painting x x x x x x Prior to start of work
32 Corner Guards & other Accessories x x x x x x x Prior to start of work
Page 1 of 1 DO# TBD
ITEM OR DESCRIPTION OF CONTRACT
REFERENCE TYPE OF SUBMITTAL
NOTE: 3 copies required per submittal, 1 electric copy required APPROVED
FINAL APPROVAL REMARKS
L I N E
N U M B E R
REQUIRED
SUBMISSION DATE
DATE CONTRACTOR NOTIFIED
C A T A L O G
D A T A
O P E R A T I
S T R U C T I O N S
S P E C I F I C A T I O N S
S T Y L E D E S I G N
CONTRACTOR
RESUBMITTAL
DATE RECEIVED IN
CONTRACT
DATE TO CIVIL
ENGINEERS
RETURN DATE FOLLOW UP
TO BE COMPLETED BY PROJECT ENGINEER (Fill in numbers of each submittal required) TO BE COMPLETED BY CONTRACT ADMINISTRATOR C E R T I F I C A T I O
C O M P L I A N C E
S H O P
D R A W I N G S
S A M P L E S
C O L O R
S E L E C T I O N
M A N U F A C T U R E
C O M M E N D A T I O N S
M A N U F A C T U R E
R R A N T Y
Schedule of Material Submittals
PROJECT NUMBER: PROJECT TITLE:
MSBL - 24-1023
Convert Room 420 on 4th floor of
Building 481 into a Kitchenette
TBD
DIS-APPROVED
Fire Extinguishers x x x x x Prior to start of work
Window Shade x x x x x x x x Prior to start of work
35 Manufacturers & Contractors Warranties x x 10 days after C/O
As-Built Drawings x x 10 days after C/O
Dumpster Tickets x 10 days after C/O