Att. (2) - RDT Template.xls
XLS spreadsheet 109 KB Posted
- Attached to
- Contractor Logistics Support for C-40A - Request for Proposal Federal contract opportunity
- Solicitation number
- N00019-20-R-0013
About this file
This document provides details for a solicitation requesting proposals for Contractor Logistics Support services for C-40A aircraft. The Naval Air Systems Command intends to award an Indefinite-Delivery/Indefinite-Quantity contract to provide C-40A Contractor Logistics Support for seventeen Navy and two Marine Corps aircraft, including maintenance, repair, engineering support and aircraft parts. Interested offerors may submit questions by April 15th, and proposals must be submitted by May 14th to be considered for the award, which will be determined utilizing full and open competition procedures. The document outlines relevant requirements and response deadlines for this federal contracting opportunity.
View the file
Other files for this federal contract opportunity
Show all 43
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RDT
| Resource Distribution Table (RDT) | ||||||||||||
| Sustainment WBS Template - TBD | ||||||||||||
| Prime Contractor | Subcontractors | |||||||||||
| Prime Contractor or Sub-Contractor | Total | In-House | Total | Sub | Sub | |||||||
| Description | ||||||||||||
| Contractor/Organization Name | TBD | |||||||||||
| Contractor/Organization Location | ||||||||||||
| Contract Number | ||||||||||||
| Total Program Office or Contract/Effort Value (Estimated), TY$M | ||||||||||||
| Subtotal Software Contract Value (Estimated), TY$M | ||||||||||||
| Government Organization or PARM | ||||||||||||
| CSDR Direct Reporting per CWIPT (Yes/No) | ||||||||||||
| SRDR Direct Reporting per CWIPT (Yes/No) | ||||||||||||
| WBS NUMBERS | WBS Element Name | |||||||||||
| L1 | L2 | L3 | L4 | L5 | L6 | L7 | ||||||
| 1.0 | Sustainment Effort | X | ||||||||||
| 1.1 | Unit-Level Manpower (System Level Cost Only) | X | ||||||||||
| 1.1.1 | Operations Manpower | X | ||||||||||
| 1.1.2 | Unit-Level Maintenance Manpower | X | ||||||||||
| 1.1.3 | Other Unit-Level Manpower (Specify In Remarks) | X | ||||||||||
| 1.2 | Unit Operations (System Level Cost Only) | X | ||||||||||
| 1.2.1 | Operating Material | X | ||||||||||
| 1.2.1.1 | Energy | X | ||||||||||
| 1.2.1.1.1 | Fuel | X | ||||||||||
| 1.2.1.1.2 | Petroleum, Oil and Lubricants (POL) | X | ||||||||||
| 1.2.1.1.3 | Electricity | X | ||||||||||
| 1.2.1.2 | Training Munitions/Expendable Stores | X | ||||||||||
| 1.2.1.2.1 | Ammunition | X | ||||||||||
| 1.2.1.2.2 | Bombs | X | ||||||||||
| 1.2.1.2.3 | Rockets | X | ||||||||||
| 1.2.1.2.4 | Training Missiles | X | ||||||||||
| 1.2.1.2.5 | Sonobuoys | X | ||||||||||
| 1.2.1.2.6 | Pyrotechnics | X | ||||||||||
| 1.2.1.2.7 | Other Munitions | X | ||||||||||
| 1.2.1.3 | Other Operating Material (Specify in Remarks) | X | ||||||||||
| 1.2.2 | Support Services (Including Non-Maintenance FSRs) | X | ||||||||||
| 1.2.2.1 | Non-Maintenance Field Service Reps | X | ||||||||||
| 1.2.2.2 | Communication Services | X | ||||||||||
| 1.2.2.3 | Facility/Storage Services | X | ||||||||||
| 1.2.2.4 | Transportation Services | X | ||||||||||
| 1.2.2.5 | Other Support Services | X | ||||||||||
| 1.2.3 | Temporary Duty | X | ||||||||||
| 1.3 | Maintenance | X | ||||||||||
| 1.3.1 | Consumables and Repair Parts | X | ||||||||||
| 1.3.1.1 | Airframe/Hull/Vehicle Consumables and Repair Parts | X | ||||||||||
| 1.3.1.2 | Propulsion Consumables and Repair Parts | X | ||||||||||
| 1.3.1.3 | Electronics/Avionics Consumables and Repair Parts | X | ||||||||||
| 1.3.1.4 | Other Major Subsystem Consumables and Repair Parts 1..n (Specify) | X | ||||||||||
| 1.3.1.5 | Other Consumables and Repair Parts | X | ||||||||||
| 1.3.2 | Depot Level Reparables (DLRs) / Repair of Reparables (RORs) | X | ||||||||||
| 1.3.2.1 | Airframe/Hull/Vehicle DLRs | X | ||||||||||
| 1.3.2.2 | Propulsion DLRs | X | ||||||||||
| 1.3.2.3 | Electronics/Avionics DLRs | X | ||||||||||
| 1.3.2.4 | Other Major Subsystems DLRs 1..n (Specify) | X | ||||||||||
| 1.3.2.5 | Other DLRs | X | ||||||||||
| 1.3.3 | Intermediate Maintenance | X | ||||||||||
| 1.3.3.1 | Intermediate Maintenance Consumable Materials and Repair Parts | X | ||||||||||
| 1.3.3.2 | Intermediate-Level Government Maintenance | X | ||||||||||
| 1.3.3.3 | Intermediate-Level Contractor Maintenance | X | ||||||||||
| 1.3.3.4 | Other Intermediate-Level Maintenance | X | ||||||||||
| 1.3.4 | Depot Maintenance | X | ||||||||||
| 1.3.4.1 | Scheduled Overhaul | X | ||||||||||
| 1.3.4.1.1 | Airframe/Hull/Vehicle Scheduled Overhaul | X | ||||||||||
| 1.3.4.1.2 | Propulsion Scheduled Overhaul | X | ||||||||||
| 1.3.4.1.3 | Electronics/Avionics Scheduled Overhaul | X | ||||||||||
| 1.3.4.1.4 | Other Major Subsystems Scheduled Overhaul 1..n (Specify) | X | ||||||||||
| 1.3.4.1.5 | Other Scheduled Overhaul | X | ||||||||||
| 1.3.4.2 | Unscheduled Overhaul | X | ||||||||||
| 1.3.4.2.1 | Airframe/Hull/Vehicle Unscheduled Overhaul | X | ||||||||||
| 1.3.4.2.2 | Propulsion Unscheduled Overhaul | X | ||||||||||
| 1.3.4.2.3 | Electronics/Avionics Unscheduled Overhaul | X | ||||||||||
| 1.3.4.2.4 | Other Major Subsystems Unscheduled Overhaul 1..n (Specify) | X | ||||||||||
| 1.3.4.2.5 | Other Unscheduled Unscheduled Overhaul | X | ||||||||||
| 1.3.5 | Other Maintenance | X | ||||||||||
| 1.3.6 | Packing, Handling, Shipping and Transportation | X | ||||||||||
| 1.4 | Sustaining Support (System Level Cost Only) | X | ||||||||||
| 1.4.1 | System Specific Training | X | ||||||||||
| 1.4.1.1 | Operator Training | X | ||||||||||
| 1.4.1.2 | Maintenance Training | X | ||||||||||
| 1.4.1.3 | Other Training | X | ||||||||||
| 1.4.2 | Support Equipment Replacement and Repair | X | ||||||||||
| 1.4.2.1 | Support Equipment Replacement | X | ||||||||||
| 1.4.2.2 | Support Equipment Repair | X | ||||||||||
| 1.4.3 | Sustaining/Systems Engineering | X | ||||||||||
| 1.4.3.1 | Reliability And Maintainability Engineering | X | ||||||||||
| 1.4.3.2 | Logistics Engineering (LSA Updates, Logistics Analysis) | X | ||||||||||
| 1.4.3.3 | Supply Analysis Efforts | X | ||||||||||
| 1.4.3.4 | Safety/Human Systems Integration Engineering | X | ||||||||||
| 1.4.3.5 | Affordability Engineering | X | ||||||||||
| 1.4.3.6 | Obsolescence Engineering | X | ||||||||||
| 1.4.3.7 | Availability Management | X | ||||||||||
| 1.4.3.8 | Product Engineering Support | X | ||||||||||
| 1.4.3.9 | Certification and Accreditation | X | ||||||||||
| 1.4.3.10 | Configuration Management | X | ||||||||||
| 1.4.3.11 | System Performance Analysis | X | ||||||||||
| 1.4.3.12 | Supply | X | ||||||||||
| 1.4.3.13 | Data Analysis | X | ||||||||||
| 1.4.3.14 | Physical Security | X | ||||||||||
| 1.4.4 | Program Management | X | ||||||||||
| 1.4.4.1 | Contractor Logistics Support (CLS) Management | X | ||||||||||
| 1.4.4.2 | CLS Supply Management | X | ||||||||||
| 1.4.4.3 | Financial/Schedule Planning and Reporting | X | ||||||||||
| 1.4.4.4 | Transition to Lead Service | X | ||||||||||
| 1.4.4.5 | Quality Assurance (Program Level) | X | ||||||||||
| 1.4.4.6 | Administrative Security | X | ||||||||||
| 1.4.4.7 | Transition to Performance Based Logistics (PBL) | X | ||||||||||
| 1.4.4.8 | Risk Mitigation | X | ||||||||||
| 1.4.5 | Information Systems | X | ||||||||||
| 1.4.5.1 | Tech Refresh | X | ||||||||||
| 1.4.5.1.1 | Servers | X | ||||||||||
| 1.4.5.1.1.1 | Web Servers | X | ||||||||||
| 1.4.5.1.1.2 | Application Servers | X | ||||||||||
| 1.4.5.1.1.3 | Database Servers | X | ||||||||||
| 1.4.5.1.1.4 | Other Servers | X | ||||||||||
| 1.4.5.1.2 | Data Storage | X | ||||||||||
| 1.4.5.1.3 | Workstations | X | ||||||||||
| 1.4.5.1.4 | Communication Hardware | X | ||||||||||
| 1.4.5.1.4.1 | Wide-Area Gateways | X | ||||||||||
| 1.4.5.1.4.2 | Wide-Area Networks (Wan) | X | ||||||||||
| 1.4.5.1.4.3 | Local Area Networks (Lan) | X | ||||||||||
| 1.4.5.1.4.4 | Modems And Switches | X | ||||||||||
| 1.4.5.1.4.5 | CRYPTO | X | ||||||||||
| 1.4.5.1.4.6 | Other Communication Hardware | X | ||||||||||
| 1.4.5.1.5 | Peripheral Devices | X | ||||||||||
| 1.4.5.1.6 | Other Hardware | X | ||||||||||
| 1.4.5.2 | IS Related License Fees | X | ||||||||||
| 1.4.5.3 | System Support / Maintenance | X | ||||||||||
| 1.4.5.3.1 | Help Desk | X | ||||||||||
| 1.4.5.3.1.1 | Tier 1 | X | ||||||||||
| 1.4.5.3.1.2 | Tier 2 | X | ||||||||||
| 1.4.5.3.1.3 | Tier 3 | X | ||||||||||
| 1.4.5.3.2 | System Database Administration | X | ||||||||||
| 1.4.5.3.3 | Follow On User Training | X | ||||||||||
| 1.4.5.3.4 | Independent Verification and Validation (IV&V) | X | ||||||||||
| 1.4.6 | Data and Technical Publications | X | ||||||||||
| 1.4.7 | Simulator/Training Device Operations and Repair | X | ||||||||||
| 1.4.7.1 | Simulator/Training Device Operations | X | ||||||||||
| 1.4.7.2 | Simulator/Training Device Hardware Repair and Replace | X | ||||||||||
| 1.4.7.3 | Simulator/Training Device Software Support | X | ||||||||||
| 1.4.8 | Other Sustaining Support (Specify in Remarks) | X | ||||||||||
| 1.5 | Continuing System Improvements | X | ||||||||||
| 1.5.1 | Hardware Modifications | X | ||||||||||
| 1.5.1.1 | Mod Kit Development | X | ||||||||||
| 1.5.1.2 | Mod Kit Procurement | X | ||||||||||
| 1.5.1.3 | Mod Kit Initial Spares | X | ||||||||||
| 1.5.1.4 | Mod Kit Installation | X | ||||||||||
| 1.5.2 | Software Support | X | ||||||||||
| 1.5.2.1 | Software Changes | X | ||||||||||
| 1.5.2.1.1 | Release 1...n (Specify) | X | ||||||||||
| 1.5.2.1.1.1 | WBS Name 1...n (Specify) | X | ||||||||||
| 1.5.2.1.1.1.1 | Correction of Deficiencies | X | ||||||||||
| 1.5.2.1.1.1.2 | Enhancements | X | ||||||||||
| 1.5.2.2 | Software License Management | X | ||||||||||
| 1.5.2.3 | System Facilities | X | ||||||||||
| 1.5.2.4 | Field Software Engineering (FSE) | X | ||||||||||
| 1.5.2.5 | Operational Management | X | ||||||||||
| 1.6 | Installation and Personnel Support (System Level Only) | X | ||||||||||
| 1. Contract/subcontract information provided in the Contract Plan RDT must be consistent with the information provided in the | ||||||||||||
| Program Plan RDT. It must reflect the most current contract or subcontract value (including all mods or CLINs) and must conform | ||||||||||||
| to the applicable rules established for the Program Plan RDT | ||||||||||||
| 2. If known, the assigned contract number for each subcontract between the prime and a subcontractor must be included. |
&R&"Cambria,Regular"N0001920R0013 &L&"Cambria,Regular"&9 31 MAR 2020&C&"Cambria,Regular"&9 &P of &N&R&"Cambria,Regular"&9Attachment (2) Resource Distribution Table
File details come from the government source that posted it. Updated .