Att 2 Reqd Perf Metrics.pdf

PDF 22 KB Posted

Attached to
O&M Services SBIWTP Federal contract opportunity
Solicitation number
191BWC20R0002
Issued by
International Boundary and Water Commission U.S.-Mexico

About this file

This document outlines required performance metrics and incentives for an operation and maintenance services contract for the South Bay International Wastewater Treatment Plant in San Diego County, California. The contractor will be responsible for full facility O&M including management, staffing, sampling, equipment maintenance, capital improvements, vehicle fleet maintenance, and reporting. Performance will be evaluated on metrics such as average daily wastewater inflows, staffing levels, regulatory compliance, equipment uptime, and reporting timeliness. Incentives include monthly payment deductions for failures to meet standards on items like inflows, vacancies, permits, cleaning times, disposal timelines, and reporting deadlines. The related solicitation is for a firm fixed price O&M contract with a base year starting October 1, 2020 and four option years. The services required include plant O&M, sampling, maintenance, improvements, and vehicle fleet management. The contract will be awarded by the International Boundary and Water Commission U.S. Section.

View the file

Other files for this federal contract opportunity

Other files attached to O&M Services SBIWTP, newest first.
File Type Posted
191BWC20R0002 006.pdf PDF
Att 32 SBIWTP OM Revised Equipment List 06.02.2020.pdf PDF
Att 31 QandA correction and clarification.pdf PDF
191BWC20R0002 0055.pdf PDF
191BWC20R0002 004.pdf PDF
Att 30 Attachment 19 Updated .pdf PDF
Att 29 Answers to Pending Responces.pdf PDF
Att 11 REV2 Chemicals Usage Summary.pdf PDF
Att 27 SBIWTP SCADA NW Diagram.pdf PDF
Att 28Questions an Answers.pdf PDF
Att 25 CanyonCollectors.pdf PDF
191BWC20R0002 0003.pdf PDF
Att 24c 2019 Monthly SBIWTP OandM Report.pdf PDF
Att 24b 2018 Monthly SBIWTP OandM Report.pdf PDF
Att 16 REV SBIWTP Capital Plan Report 2020 2024.pdf PDF
Att 23 SWIWTP Condition Assessment V4 2020 1 28.pdf PDF
Att 1 SBIWTP OM Contract PWS 2020 Revised 05.15.2020.pdf PDF
Att 22 Q and A.pdf PDF
191BWC20R0002 0002.pdf PDF
Att 21 Sign-In PreProposal Conf.pdf PDF
Att 2 SBIWTP OandM QASP 2020V2.pdf PDF
191BWC20R0002 0001.pdf PDF
Att 20 WD 2015-5636 Rev 12 .pdf PDF
Att 1 SBIWTP OM Contract PWS final 04.27.2020.pdf PDF
Att-16_SBIWTP-Capital Plan Report 2020-2024.pdf PDF
Att-7_2019_Maintenance-Tasks.pdf PDF
Att-12_Form99_Canyon-Inspections.pdf PDF
Att-15_List-of-Permits.pdf PDF
Att-5-SBIWTP Site Latest Layout.pdf PDF
Att-9_2019_Flows.pdf PDF
Att-8_2019_Maintenance-Expenses.pdf PDF
Att-4_Stormwater-Permit_wqo2014_0057_dwq_rev_mar2015.pdf PDF
Att-13_Equipment-Inventory.pdf PDF
Att-11-REV_Chemicals-Usage-Summary.pdf PDF
Att-14_Section 508-Compliance-Template.pdf PDF
Att-18-SBIWTP_SOO_V2_06192018.pdf PDF
Att-6a_FY19 Preventive Maintenance.pdf PDF
Att-17_SBIWTP_SSP_042020.pdf PDF
Att-3_Permit_R9-2014-0009_Amended.pdf PDF
191BWC20R0002 South Bay.pdf PDF
Att-19_PLC_Replacements_Table.pdf PDF
Att-10-REV_2019_Chemicals-Dosage.pdf PDF
Att-6b_FY19 Unplanned Corrective Repairs.pdf PDF
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

South Bay International Wastewater Treatment Plant Required Performance Metrics (RPM)

Required Service Performance Standards

Acceptable Quality Levels

(AQL)

Method Of

Surveillance

Incentive (Negative)

(Impact on Contractor Payments)

The Contractor shall coordinate with Mexican Pumping Station No. 1 and 1A operators in a manner to maintain an average daily/monthly inflow of 25 million gallons per day

PWS section C, Paragraph C.3.2.b(1)

100%

Monthly flow report review, files review, periodic and/or random inspection, complaints

$10,000 shall be deducted from the monthly progress payment amount for each month that the inflow from Mexico is less than an average of twenty-five (25) million gallons per day

Final work plan and work plan updates

PWS Section

C.3.1.a files review, periodic and/or random

$5,000 shall be deducted payment amount for each late submission of the work plan and work plan updates.

Staffing levels

C, Paragraphs C.3.1.a and C.3.2.a random

If within thirty (30) calendar days of notification the Contractor has failed to provide additional staff or perform necessary work, the Contracting Officer may cause the work to be done by a third party. The cost of said work shall be the responsibility of the Contractor, and the gross salary of each vacant position shall be deducted from the monthly progress payment amount. Also $10,000 shall be deducted from the monthly progress payment amount for each month for each vacant position that is not filled within thirty (30) calendar days.

Acceptable Quality Levels

(AQL)

Method Of

Surveillance

Incentive

Risk Assessment

C3.1.b and C.3.2.g(12)

Files review;

random inspection payment amount if the Contractor did not submit the initial Risk Assessment and annual updates to the COR by the contract due dates

Complying with all governmental agencies having jurisdiction permits and requirements.

Paragraphs C.3.2.b(2) and C.3.2.f(6) random

The Contractor shall be responsible for the payment of fines and or civil penalties levied against the Government and/or the Contractor by any regulatory agency having jurisdiction, as a result of failure to comply with the terms and conditions of any duly authorized permit, court order, administrative order, law, statute, or ordinance, for reasons resulting from the Contractor's negligence or poor performance during the period of the contract.

Also $15,000 shall be deducted from the monthly progress payment amount for each failure of compliance stated above.

Canyon Collector structures cleaning

C.3.2.b(7) random payment amount for each Canyon Collector structures if the structure is not fully cleaned of all debris and put back into service within forty-eight (48) hours of the end of a rainfall event

Acceptable Quality Levels

(AQL)

Method Of

Surveillance

Incentive

Canyon Collectors, off-site disposal of the debris (trash, garbage, sand, rocks, miscellaneous materials, etc.).

C.3.2.b(7) random

$15,000 shall be deducted payment amount for each canyon if off-site disposal is not completed within seven

(7) calendar days of each cleaning event.

Annual inventory

C.3.2.c(2) random payment amount if the Contractor did not submit the inventory results to the COR no later than ninety

(90) calendar days after receipt of the contract award or did not submit the annual inventory results by September 30th.

Chemicals

C.3.2.c(5) random payment amount if the Contractor did not report the current unit cost and total quantities used monthly for each chemical

Assessment and Five Year Capital Plan

C.3.2.c(9)

C.3.2g(10) random payment amount if the Contractor did not submit the initial assessment and Five Year Capital Plan to the COR by the contract due dates

Deferred Maintenance and Repairs Report

C.3.2.c(10)

C.3.2g(11)

Files review, payment amount if the Contractor did not submit the Deferred Maintenance and Repairs Report to the COR by the contract due

Acceptable Quality Levels

(AQL)

Method Of

Surveillance

Incentive

Maintain and repair of all equipment, machinery, instrumentation, structures, and plant furnishings to a fully operational condition.

C.3.2.d(1)

95% of all equipment are operational at all times.

random

$10,000/ month shall be deducted from the monthly progress payment amount if AQL not met.

Laboratory Management

C.3.2.e random

$3,000/month shall be deducted from the monthly progress payment amount if samples or test results are missing or incomplete.

Twenty-four hour reporting

C.3.2.g(4) random

$10,000/ event shall be deducted from the contract amount if the Contractor did not deliver report to the COR within Twenty-four

(24) hours.

Spill and Transboundary Wastewater Flow Events.

Paragraphs C.3.2.g(3)

C.3.2.g(4) random from the contract amount if the Contractor did not report spills and transboundary wastewater flows in accordance with Section VI.C.2.d of the NPDES Permit No.

CA018928, Order No. R9- 2014-0009, As Amended.

The Contractor did not report to COR within two

(2) hours Category 1 flow event specified in Section VI.C.2.d.i.a) of the NPDES Permit No. CA018928, Order No. R9-2014-0009, As Amended. The Contactor did not notify by telephone the County of San Diego Health Department and the City of Imperial Beach within two

(2) hours of discovery of Category 1 flow event.

Acceptable Quality Levels

(AQL)

Method Of

Surveillance

Incentive

Draft and final Monthly NPDES Monitoring Report (influent and effluent sampling)

C.3.2.g(6) random the Contractor did not deliver report to the COR by contract due dates

Annual Report for Storm Water Discharges

(SWPPP)

Paragraphs Paragraph C.3.1.c and C.3.2.g(7) random

$1,000 shall be deducted the Contractor did not deliver report to the USIBWC by contract due

Monthly Operations and Maintenance Report

Paragraphs C.3.2.d(1)

C.3.2.g(8) random the Contractor did not deliver report to the USIBWC by contract due

Markups/red-lines to the Plant as-builts

C.3.2.g(13) random

$3,000 shall be deducted the Contractor did not provide markups/red-lines to the Plant as-builts within 30 calendar days of completion of each modification to the Plant.

Daily Canyon Collector inspections

C.3.2.b (8) random the Contractor did not submit Form IBWC-99 by Wednesday of each week for the preceding week's inspections.

Acceptable Quality Levels

(AQL)

Method Of

Surveillance

Incentive

Receive favorable adjudication of background investigation and/or fingerprint check prior to physically working at the SBIWTP.

1) Contractor employees requiring a Moderate or High Risk investigation must receive a favorable adjudication of their background investigation prior to physically working at the SBIWTP and 2) Contractor employees requiring a Low Risk investigation must receive a favorable fingerprint check prior to physically working at the

SBIWTP.

C.4.14.j daily observations, periodic and/or from the contract amount for each new employee the Contractor allows to physically work at the SBIWTP prior to the favorable adjudication of their background investigation and/or fingerprint check.

Immediate removal of contractor employees that have not received a favorable adjudication of their background investigation prior to physically working at the

SBIWTP

C.4.14.j daily observations, periodic and/or from the contract amount for each day the employee is found on-site after the removal notification is received from USIBWC security office