Att 2 Reqd Perf Metrics.pdf
PDF 22 KB Posted
- Attached to
- O&M Services SBIWTP Federal contract opportunity
- Solicitation number
- 191BWC20R0002
About this file
This document outlines required performance metrics and incentives for an operation and maintenance services contract for the South Bay International Wastewater Treatment Plant in San Diego County, California. The contractor will be responsible for full facility O&M including management, staffing, sampling, equipment maintenance, capital improvements, vehicle fleet maintenance, and reporting. Performance will be evaluated on metrics such as average daily wastewater inflows, staffing levels, regulatory compliance, equipment uptime, and reporting timeliness. Incentives include monthly payment deductions for failures to meet standards on items like inflows, vacancies, permits, cleaning times, disposal timelines, and reporting deadlines. The related solicitation is for a firm fixed price O&M contract with a base year starting October 1, 2020 and four option years. The services required include plant O&M, sampling, maintenance, improvements, and vehicle fleet management. The contract will be awarded by the International Boundary and Water Commission U.S. Section.
View the file
Other files for this federal contract opportunity
Show all 43
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
South Bay International Wastewater Treatment Plant Required Performance Metrics (RPM)
Required Service Performance Standards
Acceptable Quality Levels
(AQL)
Method Of
Surveillance
Incentive (Negative)
(Impact on Contractor Payments)
The Contractor shall coordinate with Mexican Pumping Station No. 1 and 1A operators in a manner to maintain an average daily/monthly inflow of 25 million gallons per day
PWS section C, Paragraph C.3.2.b(1)
100%
Monthly flow report review, files review, periodic and/or random inspection, complaints
$10,000 shall be deducted from the monthly progress payment amount for each month that the inflow from Mexico is less than an average of twenty-five (25) million gallons per day
Final work plan and work plan updates
PWS Section
C.3.1.a files review, periodic and/or random
$5,000 shall be deducted payment amount for each late submission of the work plan and work plan updates.
Staffing levels
C, Paragraphs C.3.1.a and C.3.2.a random
If within thirty (30) calendar days of notification the Contractor has failed to provide additional staff or perform necessary work, the Contracting Officer may cause the work to be done by a third party. The cost of said work shall be the responsibility of the Contractor, and the gross salary of each vacant position shall be deducted from the monthly progress payment amount. Also $10,000 shall be deducted from the monthly progress payment amount for each month for each vacant position that is not filled within thirty (30) calendar days.
Acceptable Quality Levels
(AQL)
Method Of
Surveillance
Incentive
Risk Assessment
C3.1.b and C.3.2.g(12)
Files review;
random inspection payment amount if the Contractor did not submit the initial Risk Assessment and annual updates to the COR by the contract due dates
Complying with all governmental agencies having jurisdiction permits and requirements.
Paragraphs C.3.2.b(2) and C.3.2.f(6) random
The Contractor shall be responsible for the payment of fines and or civil penalties levied against the Government and/or the Contractor by any regulatory agency having jurisdiction, as a result of failure to comply with the terms and conditions of any duly authorized permit, court order, administrative order, law, statute, or ordinance, for reasons resulting from the Contractor's negligence or poor performance during the period of the contract.
Also $15,000 shall be deducted from the monthly progress payment amount for each failure of compliance stated above.
Canyon Collector structures cleaning
C.3.2.b(7) random payment amount for each Canyon Collector structures if the structure is not fully cleaned of all debris and put back into service within forty-eight (48) hours of the end of a rainfall event
Acceptable Quality Levels
(AQL)
Method Of
Surveillance
Incentive
Canyon Collectors, off-site disposal of the debris (trash, garbage, sand, rocks, miscellaneous materials, etc.).
C.3.2.b(7) random
$15,000 shall be deducted payment amount for each canyon if off-site disposal is not completed within seven
(7) calendar days of each cleaning event.
Annual inventory
C.3.2.c(2) random payment amount if the Contractor did not submit the inventory results to the COR no later than ninety
(90) calendar days after receipt of the contract award or did not submit the annual inventory results by September 30th.
Chemicals
C.3.2.c(5) random payment amount if the Contractor did not report the current unit cost and total quantities used monthly for each chemical
Assessment and Five Year Capital Plan
C.3.2.c(9)
C.3.2g(10) random payment amount if the Contractor did not submit the initial assessment and Five Year Capital Plan to the COR by the contract due dates
Deferred Maintenance and Repairs Report
C.3.2.c(10)
C.3.2g(11)
Files review, payment amount if the Contractor did not submit the Deferred Maintenance and Repairs Report to the COR by the contract due
Acceptable Quality Levels
(AQL)
Method Of
Surveillance
Incentive
Maintain and repair of all equipment, machinery, instrumentation, structures, and plant furnishings to a fully operational condition.
C.3.2.d(1)
95% of all equipment are operational at all times.
random
$10,000/ month shall be deducted from the monthly progress payment amount if AQL not met.
Laboratory Management
C.3.2.e random
$3,000/month shall be deducted from the monthly progress payment amount if samples or test results are missing or incomplete.
Twenty-four hour reporting
C.3.2.g(4) random
$10,000/ event shall be deducted from the contract amount if the Contractor did not deliver report to the COR within Twenty-four
(24) hours.
Spill and Transboundary Wastewater Flow Events.
Paragraphs C.3.2.g(3)
C.3.2.g(4) random from the contract amount if the Contractor did not report spills and transboundary wastewater flows in accordance with Section VI.C.2.d of the NPDES Permit No.
CA018928, Order No. R9- 2014-0009, As Amended.
The Contractor did not report to COR within two
(2) hours Category 1 flow event specified in Section VI.C.2.d.i.a) of the NPDES Permit No. CA018928, Order No. R9-2014-0009, As Amended. The Contactor did not notify by telephone the County of San Diego Health Department and the City of Imperial Beach within two
(2) hours of discovery of Category 1 flow event.
Acceptable Quality Levels
(AQL)
Method Of
Surveillance
Incentive
Draft and final Monthly NPDES Monitoring Report (influent and effluent sampling)
C.3.2.g(6) random the Contractor did not deliver report to the COR by contract due dates
Annual Report for Storm Water Discharges
(SWPPP)
Paragraphs Paragraph C.3.1.c and C.3.2.g(7) random
$1,000 shall be deducted the Contractor did not deliver report to the USIBWC by contract due
Monthly Operations and Maintenance Report
Paragraphs C.3.2.d(1)
C.3.2.g(8) random the Contractor did not deliver report to the USIBWC by contract due
Markups/red-lines to the Plant as-builts
C.3.2.g(13) random
$3,000 shall be deducted the Contractor did not provide markups/red-lines to the Plant as-builts within 30 calendar days of completion of each modification to the Plant.
Daily Canyon Collector inspections
C.3.2.b (8) random the Contractor did not submit Form IBWC-99 by Wednesday of each week for the preceding week's inspections.
Acceptable Quality Levels
(AQL)
Method Of
Surveillance
Incentive
Receive favorable adjudication of background investigation and/or fingerprint check prior to physically working at the SBIWTP.
1) Contractor employees requiring a Moderate or High Risk investigation must receive a favorable adjudication of their background investigation prior to physically working at the SBIWTP and 2) Contractor employees requiring a Low Risk investigation must receive a favorable fingerprint check prior to physically working at the
SBIWTP.
C.4.14.j daily observations, periodic and/or from the contract amount for each new employee the Contractor allows to physically work at the SBIWTP prior to the favorable adjudication of their background investigation and/or fingerprint check.
Immediate removal of contractor employees that have not received a favorable adjudication of their background investigation prior to physically working at the
SBIWTP
C.4.14.j daily observations, periodic and/or from the contract amount for each day the employee is found on-site after the removal notification is received from USIBWC security office
File details come from the government source that posted it. Updated .