This solicitation is for operation and maintenance services for the South Bay International Wastewater Treatment Plant. The International Boundary and Water Commission seeks a firm fixed price, non-personal services contract to provide full service O&M of the 25 million gallon per day wastewater treatment plant and associated facilities in San Diego County, California. Services required include day-to-day management, staffing, plant operations, maintenance, repairs, capital improvements, vehicles, supplies, chemicals, sampling, testing, reporting, and other services. The contract consists of a base year from October 1, 2020 to September 30, 2021 with four optional one-year extensions. The work is covered under NAICS code 221320 with a size standard of $20.5 million. Responses are due by dates specified in amendments to solicitation number 191BWC20R0002.
View the file
Other files for this federal contract opportunity
Show all 43
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE RATING
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
05/22/2020
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
IBWC_CODE
International Boundary and Water Commission
(IBWC)
USIBWC - ACQUISITIONS DIV
4191 NORTH MESA ST
EL PASO, TX 79902-1441
Philip Johnson
NAME
TEL.
johnsonpk@state.gov
6. ISSUED BY IBWC_CODE
International Boundary and Water Commission (IBWC)
USIBWC - ACQUISITIONS DIV
4191 NORTH MESA ST
EL PASO, TX 79902-1441
7. ADMINISTERED BY (If other than Item 6)
9A. AMENDMENT OF SOLICITATION NO.
191BWC20R0002
CONTACT DUNS
CODE FACILITY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, country, state and ZIP Code) (X)
X 9B. DATED (SEE ITEM 11)
04/28/2020
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X XThe above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended, Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning __1__copies of the amendment;(b)By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.__1__X
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this Amendment 004 is as follows.
a. Add answers to questions 32,34, and 47.
b. Add updated attachment 19.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Philip Johnson
(Signature of person authorized to sign)
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED
By (Signature of Contracting Officer)
16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
NSN 7540-01-152-8070
Previous edition unusable
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
191BWC20R0002
Section J- List of Attachments
Identifier Title Date Number of Pages
1 Att 1 SBIWTP OandM PWS.pdf - CHANGED 04/16/2020 33 2 Att 2 Revised Att2 QASP 2020 V2.pdf - CHANGED 05/05/2020 14 3 Att 3 Permit R9 2014 0009 Amended.pdf - CHANGED 04/16/2020 163 4 Att 4 Stormwater Permit wqo2014 0057 dwq rev mar2015.pdf - CHANGED 04/16/2020 208 5 Att 5 SBIWTP Site Latest Layout.pdf - CHANGED 04/16/2020 1 6 Att 6 FY19 PreMaint Unplanned Repairs.pdf - CHANGED 04/16/2020 54 7 Att 7 2019 Maintenance Tasks.pdf - CHANGED 04/16/2020 8 8 Att 8 2019 Maintenance Expenses.pdf - CHANGED 04/16/2020 12 9 Att 9 2019 Flows.pdf - CHANGED 04/16/2020 14 10 Att 10 2019 Chemicals Dosage.pdf - CHANGED 04/16/2020 4 11 Att 11 Chemicals Usage Summary.pdf - CHANGED 04/16/2020 2 12 Att 12 Form99 Canyon Inspections.pdf - CHANGED 04/16/2020 1 13 Att 13 Equipment Inventory.pdf - CHANGED 04/16/2020 69 14 Att 14 Section 508 Compliance Template.pdf - CHANGED 04/16/2020 1 15 Att 15 List of Permits.pdf - CHANGED 04/16/2020 1 16 Att 16 SBIWTP Capital Plan Report 2020 2024.pdf - CHANGED 04/16/2020 13 17 Att 17 SBIWTP SSP 042020.pdf - CHANGED 04/16/2020 116 18 Att 18 SBIWTP SOO V2 06192018.pdf - CHANGED 04/16/2020 70 19 Att 19 PLC Replacements Table.pdf - CHANGED 04/16/2020 18 20 WD 2015-5636 Rev 12 - CHANGED 05/04/2020 14 21 Sign In Sheets - CHANGED 05/12/2020
22 Q&A - CHANGED 05/12/2020 3
23 Att 23 - CHANGED 05/15/2020 35 24 att 24b and c - CHANGED 05/15/2020 148 25 Att 25 - CHANGED 05/15/2020 7 26 Att 26 - CHANGED 05/15/2020 1 27 Att 27 - CHANGED 05/15/2020 1 28 Att 28 - CHANGED 05/15/2020 16 29 Att 29 - ADDED 05/22/2020 1 30 Att 30 Attachment 19 Updated_.pdf - ADDED 05/22/2020 17
191BWC20R0002