This notice solicits proposals for a Simplified Acquisition of Base Engineer Requirements (SABER) contract to provide maintenance, repair, and minor construction services at various U.S. Army installations in Japan, including Camp Zama, Sagamihara Family Housing Area, Sagami General Depot, and others. The contract has a minimum value of 500,000 Japanese yen and maximum aggregated value of 49,000,000 U.S. dollars over its five-year base period and one two-year option period. Prospective offerors must attend a pre-proposal conference on June 24, 2022 to ask questions. Past performance questionnaires are due from references by the proposal due date of July 15, 2022. The award will be a single-award IDIQ contract to one contractor to perform requirements on individual task orders. Registration on SAM.gov is required for offerors due to performance in Japan.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Range of Project Magnitude Estimated % **Estimated Value of Work Offeror’s Priced

Coefficient Total Price Including Coefficient

Standard Hours / Kanto Plain Kanto SH 26.80% ¥199,706,016 ¥0 None-Standard Hours / Kanto Plain Kanto NSH 0.60% ¥4,471,030 ¥0 Standard Hours / Hiroshima Area Hiroshima SH 6.60% ¥49,181,332 ¥0 None-Standard Hours / Hiroshima Area Hiroshima NSH 0.30% ¥2,235,515 ¥0 Standard Hours / Others Others SH 0.30% ¥2,235,515 ¥0 None-Standard Hours / Others Others NSH 0.10% ¥745,172 ¥0 Standard Hours / Kanto Plain Kanto SH 26.20% ¥195,234,985 ¥0 None-Standard Hours / Kanto Plain Kanto NSH 0.60% ¥4,471,030 ¥0 Standard Hours / Hiroshima Area Hiroshima SH 4.30% ¥32,042,383 ¥0 None-Standard Hours / Hiroshima Area Hiroshima NSH 0.30% ¥2,235,515 ¥0 Standard Hours / Others Others SH 0.40% ¥2,980,687 ¥0 None-Standard Hours / Others Others NSH 0.20% ¥1,490,343 ¥0 Standard Hours / Kanto Plain Kanto SH 24.70% ¥184,057,410 ¥0 None-Standard Hours / Kanto Plain Kanto NSH 0.60% ¥4,471,030 ¥0 Standard Hours / Hiroshima Area Hiroshima SH 6.90% ¥51,416,847 ¥0 None-Standard Hours / Hiroshima Area Hiroshima NSH 0.30% ¥2,235,515 ¥0 Standard Hours / Others Others SH 0.50% ¥3,725,859 ¥0 None-Standard Hours / Others Others NSH 0.30% ¥2,235,515 ¥0

100.00% ¥745,171,700 TEP ¥0

IMPORTANT:

Offeror shall provide and fill-in only "NAME OF OFFEROR" and "Offeror's Priced Coefficient".

Total Evaluated Price (TEP) will be used to determine low offer (Evaluation Purpose Only).

The above table illustrates anticipated total amount for each range of project magnitude broken down by the work locations and hours for an annual period.

The values and percent specified in this table are estimates only and are not purchased by this contract.

** Estimated value of work is applied to the offeror’s proposed coefficient to calculate TEP for evaluation purpose . Exchnage Rate: ¥106.4531

US.Dollar:Estimated Value /Year $7,000,000

LEVEL III

Y100,000,001 and above ¥100,000,001 above >¥100M

LEVEL II

Y30,000,001 to Y100,000,000

¥30,000,001 ¥100,000,000 >¥30M- ≤¥100M

LEVEL I

up to

Y30,000,000 ¥30,000,000 ≤¥30M