Annex 0100000 C General Information.pdf

PDF 43 KB Posted

Attached to
ISWM FOR NAVY AND MARINE CORPS INSTALLATIONS IN THE SAN DIEGO METRO AREA, CA
Solicitation number
N6247320R0075
Issued by

View the file

Other files

File Type Posted
ISWM_20R0075 NOTE TO CONTRACTORS 08132020.pdf PDF
Revised_ISWM combined synopsis 08112020_Amend 0005.pdf PDF
ISWM_20R0075 Amendment 0005.pdf PDF
Revised_ISWM combined synopsis 08112020_Amend 0005.pdf PDF
SCA Wage Determination_2015-5635 Rev 13.pdf PDF
Section G Contract Administration_Amendment_05.pdf PDF
Section H FedMall_ISWM_Amendment_05.pdf PDF
J 1503030 05 ISWM Inventory 08112020.xlsx XLSX spreadsheet
ISWM_20R0075 Amendment 0004.pdf PDF
J 1503030 05 ISWM Inventory 08062020.xlsx XLSX spreadsheet
J 1503030 ISWM Inventory 08052020.pdf PDF
J 1503030-05 ISWM Inventory 07292020.xlsx XLSX spreadsheet
FINAL_ISWM_20R0075 Amendment 0003.pdf PDF
Revised_ISWM combined synopsis 08052020_Amend 0003.pdf PDF
RFI Diversion Data_.xlsx XLSX spreadsheet
Exhibits A-G.pdf PDF
ISWM Pre-Proposal Conference Attendees_07202020.xlsx XLSX spreadsheet
ISWM_20R0075 Amendment 0002.pdf PDF
REVISED ISWM combined synopsis 07282020.pdf PDF
J 0200000-09 ISWM ELINs v2 07152020.xlsx XLSX spreadsheet
ISWM_20R0075 Amendment 01 FINAL.pdf PDF
J 1503030 02 ISWM Inventory.xlsx XLSX spreadsheet
EXHIBIT E Financial Questionnaire (2).docx DOCX document
EXHIBIT A OFFEROR EXPERIENCE PROJECT DATA SHEET.docx DOCX document
WD 2015-5635 San Diego County.pdf PDF
1503030 C ISWM.pdf PDF
MCRD MAP.pdf PDF
EXHIBIT F Small Business Subcontracting Plan (2).doc DOC document
0200000 J 05 (Contractor Incident Report System).pdf PDF
NBSD Wetside Dryside Index Map.pdf PDF
Mission Essential Contractor Services ISWM.pdf PDF
MCAS MIRAMAR MAINSIDE GD.pdf PDF
EXHIBIT C Safety Data and Narrative.docx DOCX document
20R0075 - ISWM combined synopsis.pdf PDF
NBPL BASE MAP.pptx PPTX presentation
1503030 F ISWM.pdf PDF
MCAS MIRAMAR EAST GD MAP July14.pdf PDF
1503030 J ISWM.pdf PDF
J 1503030 02 ISWM Inventory.xlsx XLSX spreadsheet
EXHIBIT B Management Approach.docx DOCX document
Request for Information _RFI Form.docx DOCX document
EXHIBIT D NAVFAC PPQ FORM.docx DOCX document
Annex 0200000 C Management and Administration.pdf PDF
Annex 0200000 F Management and Administration.pdf PDF
NBSD NMCSD Index Map.pdf PDF
Annex 0200000 J Management and Administration.pdf PDF
J 0200000-09 ISWM ELINs.xlsx XLSX spreadsheet
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0100000 – General Information Spec Item Title Description 1 General Information

1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work Statement (PWS) throughout the NAVFAC Southwest, Area of Responsibility (AOR), by means of a Firm Fixed Price and an Indefinite Delivery Indefinite Quantity type, performance-based contract that is comprised of both Recurring and Non-Recurring Work Items.

The PWS is organized into annexes. Annex 1 is "General Information."

Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements. The annex numbers are identified as 1 through 18 in the description column, but the full expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).

Annex 1 General Information - INCLUDED Annex 2 Management and Administration - INCLUDED Annex 3 Command and Staff Annex 4 Public Safety Annex 5 Air Operations Annex 6 Port Operations Annex 7 Ordnance Annex 8 Range Operations Annex 9 Health Care Support Annex 10 Supply Annex 11 Personnel Support Annex 12 Morale, Welfare and Recreation Support Annex 13 Galley Annex 14 Housing Annex 15 Facilities Support 1503030 Refuse Collection and Recycling- INCLUDED Annex 16 Utilities Annex 17 Base Support Vehicles and Equipment Annex 18 Environmental

1.2 Project Location Project locations include:

• Naval Base San Diego

• Admiral Baker Golf Course

• San Diego Naval Regional Medical Center

• Point Loma

• Miramar

• Marine Corps Recruit Depot

Also included are the following locations operated by Naval Base Coronado:

• U.S. Navy Remote Survival, Evasion, Resistance, and Escape (SERE), Warner Springs, CA

• Mountain Warfare Training Camp Michael Monsoor, Campo, CA

• Camp Morena, Campo, CA

See Attachment J-1503030-04 Maps and Locations for additional details.

1.3 Acquisition of

Additional Work

The Government reserves the right to acquire additional services at additional locations, within the scope of the annexes and areas included in Spec Item 1.1 Outline of Services, in addition to the services and locations identified in the requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the non-recurring work provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.

1.4 Background

Information

The intent of this solicitation is to obtain ISWM services. The contract is a performance based specification relying on the contractor’s experience and expertise determining the best method of service operations.

1.5 Verification of

Workload and Conditions

Throughout the PWS, the workload data is generally referred to as being located in Section J. Section J provides data such as inventories, maps, floor plans, and tables to represent the type, quantity and location of services to be provided. However, offerors are encouraged to visit the project site during the site visit for offerors and to visit the technical library during posted hours as part of its due diligence to assess the nature of work and conditions under which work is to be performed.

1.6 Climate Patterns Climate patterns vary from base to base in the NAVFAC SW AOR.

1.7 Related Information There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:

Informational Notes as used throughout this PWS provides additional information to offerors to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 is subject to this disclaimer. Offerors may not rely upon the "Informational Notes" as material representations of the Government. Information provided in "Informational Notes" does not create a contractual requirement on either party to this contract.

Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.

Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.

Requirement Information further describes client requirements associated with each Performance Objective.

1.8 Navy Approach to

Service Contracting The Department of Navy (DoN) spends over $1 billion in annual obligations to meet global requirements for facility operations and maintenance provided through Facility Support Contracts (FSC) and additional billions to provide other base operations support services (OBOS). The Head of the Contracting Activity (HCA) of the Naval Facilities Engineering Command (NAVFAC) has focused increased attention on re-engineering FSC contracts in response to customer and industry feedback, budget constraints, and the impact of a variety of contracting, program management and financial management regulations. The Navy also supports the following principles:

1.8.1 Partnering

Philosophy

The first principle is that the Navy views its contractors as partners and not just abstract service providers. The Navy wants its contractors to succeed because partners' success drives the Navy's successful mission completion.

Within the bounds of acquisition policy the Navy intends to work to find solutions that will be beneficial to both the Government and its partners.

1.8.2 Contractor's

Knowledge

The second principle is that the Navy will receive insightful management from its contractors. This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle.

Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.

1.8.3 Industry Best

Practices

The third principle is that the Navy will adopt industry best commercial practices and maintain state-of-the-art service delivery. It is the Navy's and contractor's responsibility as partners to reach this goal. To that end, the Navy's emphasis will be in evaluating performance objectives (end results).

1.9 Standard Template Key to implementing a programmatic approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs. This contract conforms to the standard template and has been tailored for this solicitation. NAVFAC intends to use this template-based approach for future service contracts. Offerors should develop an understanding of the template as part of performing due diligence in reaching an understanding of the Navy’s requirements and expectations.

The standard template contains 18 standard annexes. Annex 1 will always contain information that is relevant to the entire scope of the contract. Annex 2 contains on-site project management and administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 contain the technical information and requirements peculiar to that technical annex.

Within each technical annex, the organization of information and requirements are also standardized. Specification item 1 will always contain General Information. Specification item 2 will always contain the management and administrative requirements. Specification item 3 will always contain the Recurring Work requirements. Specification item 4 will always contain the Non-recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items. Specification Items 3.2 and 3.3 are not considered subordinate to 3.1. All costs associated with Annexes 1 and 2 and Specification items 1 and 2 must be priced and distributed within Specification Item 3 of Annexes 3 through 18.

1.10 Navy PBSA

Approach

The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.

1.11 Technical Proposal

Certification

The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.