AMC_505_1B _ Valve Overhaul and Test.pdf

PDF 27 KB Posted

Attached to
RFQ 1305M223QNMAN0111 FY24 Dry Dock Repairs NOAA Ship FERDINAND HASSLER
Solicitation number
1305M223QNMAN0111
Issued by

About this file

This specification covers the overhaul and testing of valves for NOAA vessels. It requires the complete disassembly, cleaning, inspection, machining and lapping of parts to meet tight tolerances for contact between moving components, along with testing of valves under pressure. Valves must be removed from vessels for overhaul, except where welding prevents it, and be reinstalled after acceptance of tests witnessed by the Contracting Officer's Technical Representative. Tests involve applying 150% of system pressure to verify no leakage when open or closed. Checks and gate valves must seal fully across the contact surface, while plugs need 80% contact. Failures require rework until passing.

View the file

Other files

File Type Posted
Summit Appliance Use and Care Guide.pdf PDF
M286_-085_FA27_07 Outfit and Accomodation Arrangement Drawing.pdf PDF
Amendment A0004.pdf PDF
Amendment A0003.pdf PDF
Gauge Calibration List pdf.pdf PDF
Galley Frige Name Plate.jpg JPG image
Gauge Propeller Sample Report.pdf PDF
Gauge Example Report 2.pdf PDF
Galley Frige Tafco Plate.jpg JPG image
Pump Image ows process pump.jpg JPG image
Life Raft Certs.pdf PDF
Pump Image ows feed pump.jpg JPG image
Amendment A0002.pdf PDF
Attachment D7 Subcontracting Plan.doc DOC document
Attachment D1 FY24 Drydock Repairs for NOAA Ship Ferdinand Hassler Specifications Rev1.pdf PDF
RFQ 1305M223QNMAN0111 FY24 Dry Dock Repairs NOAA Ship FERDINAND HASSLER Rev1.pdf PDF
Amendment A0001 FY24 Drydock Repairs for NOAA Ship Ferdinand Hassler.pdf PDF
Manuals Part 2-20230720T161458Z-001.zip ZIP file
Craft Bearing Installation Guide.pdf PDF
Manuals Part 3-20230720T161502Z-001.zip ZIP file
Quadrans_UserManualPack_October2021.zip ZIP file
Manuals Part 5-20230720T161511Z-001.zip ZIP file
TAFCO Pre-Fabricated Walkin Cooler and Freezer Manual Rev 2-22-02.pdf PDF
Carrier Transicold Chiller.pdf PDF
Global Davit Rescue Boat Davit.pdf PDF
Vestdavit Survey Boat Davit.pdf PDF
Manuals Part 4-20230720T161506Z-001.zip ZIP file
Part 3-20230719T185946Z-001.zip ZIP file
Part 2-20230719T185938Z-001.zip ZIP file
FH Drawings for Download-20230719T205605Z-001.zip ZIP file
3.10 Genset & Switchboard Drawings-20230718T205109Z-001.zip ZIP file
Part 2-20230719T185854Z-001.zip ZIP file
Manuals for Download - working-20230719T205609Z-001.zip ZIP file
Part 1-20230719T185822Z-001.zip ZIP file
NOAA Standard Specs-20230719T013456Z-001.zip ZIP file
FA12-20230718T201723Z-001.zip ZIP file
RFQ 1305M223QNMAN0111 FY24 Dry Dock Repairs NOAA Ship FERDINAND HASSLER (1) (1).pdf PDF
Gauge Calibration.xls XLS spreadsheet
AMC_634_1A Deck Coverings.pdf PDF
AMC-573-1C Weight Handling Gear Testing.pdf PDF
RO_s Installed FEB 2021-20230706T201749Z-001.zip ZIP file
Attachment D.4 US DOL POSTER.pdf PDF
ATTACHMENT D2 Past Performance Information Form (1).docx DOCX document
Product Safety _SENR2995-04_.pdf PDF
MOC_510-1B_HVAC_Cleaning_.pdf PDF
3.17.2.6 FH Hose List.xlsx XLSX spreadsheet
AltiVAR VFD_s Ventilation-20230706T201805Z-001.zip ZIP file
3_17_2_6 FH Hose List.xlsx XLSX spreadsheet
AMC-581-1A Inspection and Preservation of Ground Tackle.pdf PDF
S2906 _ Arc Welding on Waterborne Vessels.pdf PDF
Show 40 more

Latest 50 of 86 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMC-505-1B

AUGUST 1995

SUPERSEDING

AMC-505-1A

SEPTEMBER 1990

NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION (NOAA)

ATLANTIC MARINE CENTER

STANDARD SPECIFICATION AMC-505-1B

VALVE OVERHAUL AND TEST

1. SCOPE. This specification contains the general requirements for overhaul and test of valves on and for NOAA ships and boats.

2. REFERENCES.

None

3. REQUIREMENTS.

3.1 Standard Overhaul. Overhaul all specified valves as

follows:

3.1.1 Except for valves which have welded ends preventing

removal without cutting the welds, or unless otherwise specified in the detail specification or other applicable procurement document, remove all specified valves from the ship or boat to a suitable machine shop for overhaul and tests. Specified valves which are not removed from the ship or boat shall be overhauled in place. See paragraph 3.2 for special requirements for sea valve removals.

3.1.2 Tag each valve prior to removing from the ship or

boat.

3.1.3 Completely disassemble each valve. Matchmark valve

parts. Thoroughly clean bonnets, stems, discs, gates, globes, seats, bodies, and other metal parts to bright metal.

3.1.4 Deleted.

3.1.5 Clean and chase all valve stem threads. Check stems

for straightness. Straighten stems to within 0.002 inch total indicator runout (TIR). Polish stems to a 32 Root-Mean-Square (RMS) finish in way of packing surface and remove all raised edges.

3.1.6 Visually inspect all parts, including all fasteners, for deterioration and other defects. Clean, dress, and true gasket mating surfaces.

3.1.7 Check the disc-to-seat, globe-to-seat, and plug-to-

bore contact fits using the bluing transfer method. Machine, grind, lap, spot-in, and recheck contact fits as necessary to obtain the following contacts:

a. Globe, globe angle, and globe stop-check valves shall have a 360-degree continuous globe-to-seat contact with a bluing transfer line not exceeding 1/16-inch width.

b. Gate valves shall have a 360-degree continuous gate-to-seat contact with a bluing transfer line which does not exceed 3/16-inch width. The transfer line shall appear within the lower 50-percent of the gate seating surface at the top and bottom of the gate.

c. Plug valves shall have a minimum 80-percent plug-to-bore surface contact, evenly distributed over 100-percent of the area.

d. Swing-check valves shall have a 360-degree continuous disc-to-seat contact.

3.1.8 If unable to obtain the above specified contact fits

by machining, grinding, and lapping, renew the globes, plugs, discs, gates, and renewable seats. Contractor may, at their option and at no additional cost to the Government, renew globes, plugs, discs, gates, and renewable seats after initial inspections and before machining, grinding, or lapping the existing parts to obtain the required contact fits.

3.1.9 (Modified and relocated to section 3.2)

3.1.10 Reassemble each valve. Insure that discs, gates, and plugs are in the half-open position during reassembly to avoid damaging seats or bending stems. Renew all gaskets, fasteners, rubber seals, and non-metallic seats. In butterfly valves, renew boots, o-rings, o-ring fasteners, and teflon bushings. Renew valve stem packing in feed water, condensate, and steam valves with packing conforming to MIL-P-24503 and DOD- P-24583. Renew valve stem packing in all other valves with packing conforming to MIL-P-24396, Type B.

3.1.11 Prior to disassembling and overhauling a valve, the

Contractor may, at their option and at no additional cost to the Government, renew the valve with an identical valve. If this option is exercised, the new valve must be tested and meet the same acceptance criteria as prescribed herein for overhauled valves. If a valve is determined after disassembly to be nonrepairable, the Government will negotiate an equitable cost adjustment, limited to the difference between the cost of the new valve and the costs which would have been incurred had the valve been overhauled. For valves of 3-inch IPS size and below, the cost adjustment will be limited to the costs incurred associated with disassembling the valves.

3.2 Additional Sea Valve Requirements.

3.2.1 Inspect all studs, bolts, and nuts in line and bonnet

flanges of non-ferrous sea valves to determine the material. If the fasteners are not nickel-copper (Monel), submit a Condition Report giving the actual material, condition, and recommendations.

3.2.2 Coat the interior of each steel valve, excluding

seating and polished surfaces, with the same epoxy primer used on the underwater body.

3.2.3 Remove all waster pieces and spool pieces installed

between the sea valves and the ship's hull. Thoroughly clean the waster and spool pieces, and inspect for deterioration or other defective conditions. Inspect all fasteners and submit a Condition Report same as specified above for sea valves.

3.2.4 Whenever a transducer sea chest valve is required to

be removed for overhaul, extreme care must be taken to prevent damaging the transducer assembly. Remove and reinstall the transducer assembly in accordance with the transducer manufacturer's technical manual, a copy of which will be provided by the COTR within 48 hours after requested.

3.3 Tests. After reassembling or renewing, conduct hydrostatic tests of each valve as follows:

3.3.1 All tests shall be performed using clean water as the

test medium. Unless otherwise specified, the test pressure shall be 150-percent of the maximum operating pressure of the system from which the valve was removed, but not less than 50 pounds-per-square-inch-gage (psig).

3.3.2 With the valve in the open position, test each valve

body for 10 minutes. No leakage is allowed.

3.3.3 Seat each plug and butterfly valve with hand force.

Seat all other valves using the torque values listed in the following table as the maximum allowable seating force applied to the handwheel.

Total Tangential Force Handwheel Diameter (pounds) on Rim of Handwheel

2 inches and below 90 3 inches 98 4 inches 106 5 inches 112 6 inches and greater 118 plus 3 pounds for each inch above 6, not to exceed 150 pounds.

3.3.4 Test each globe, angle globe, and globe stop-check

valve by applying test pressure in the direction tending to open the valve. Test each butterfly, gate, and plug valve by applying test pressure alternately on both sides of the disc, gate, or plug. Hold test pressure for a minimum of 3 minutes if there is no evidence of leakage. If there is evidence of leakage, hold the test pressure and measure the leakage rate.

3.3.5 Test each globe stop-check valve and swing-check

valve by applying test pressure in direction tending to close the valve (back pressure) for a minimum of 5 minutes. If leakage occurs, hold the test pressure and measure the leakage rate.

Globe stop-check valves shall be tested with stems in the open position. The test back pressure for valves having a pressure rating of 150 psig and below shall be 50 psig, and for valves having a pressure rating over 150 psig shall be 100 psig.

3.3.6 The seat leakage shall not exceed the following:

a. Check valve back pressure tests -- For valves up to and including 2 inches, the leakage rate shall not exceed 25 cc/hour/inch diameter. For valves 2-1/2 to 10 inches, the leakage rate shall not exceed 50 cc/hour/inch diameter. For valves over 10 inches, the leakage rate shall not exceed 100 cc/hour/inch diameter.

b. Soft-seated valves -- No leakage shall be permitted.

c. Metal-to-metal seated valves -- For valves less than 1 inch, the leakage rate shall not exceed 10 cc/hour. For larger valves, the leakage rate shall not exceed 10 cc/hour/inch of nominal pipe size.

3.3.7 Any valve which fails a seat leakage test shall be

renewed or overhauled and retested until an acceptable test is performed.

3.4 Reinstallation. After tests have been accepted by the COTR, reinstall each valve, using new flange gaskets.

4. QUALITY ASSURANCE.

4.1 Prior to requesting the COTR to witness the final bluing

contact inspection or the final acceptance hydrostatic tests of a valve, the Contractor shall perform preliminary inspections and tests which meet the acceptance criteria stated above.

4.2 After acceptable preliminary inspections and tests have been conducted, the Contractor shall notify the COTR and conduct final acceptance bluing contact inspection and final acceptance hydrostatic tests of each valve in the COTR's presence.

END OF SPECIFICATION