Attachment D1 FY24 Drydock Repairs for NOAA Ship Ferdinand Hassler Specifications Rev1.pdf

PDF 8 MB Posted

Attached to
RFQ 1305M223QNMAN0111 FY24 Dry Dock Repairs NOAA Ship FERDINAND HASSLER
Solicitation number
1305M223QNMAN0111
Issued by

About this file

This document outlines specifications for dry dock repairs and maintenance work for the NOAA research vessel Ferdinand R. Hassler. Key work items include cleaning and gas-freeing tanks and enclosed spaces; removing and reinstalling composite buoyancy appendages; performing hull preservation work including blasting, cleaning, and recoating approximately 20% of the hull below the waterline; and conducting docking and undocking operations. The specifications provide requirements for surface preparation, coating systems, and quality assurance protocols to be followed for painting work. Additional requirements include cleaning seawater chests and piping, taking various clearance readings, and performing other inspections and certifications. The contractor must follow all applicable regulations and coordinate work with ABS and USCG to maintain necessary vessel classifications and certifications.

View the file

Other files

File Type Posted
Summit Appliance Use and Care Guide.pdf PDF
M286_-085_FA27_07 Outfit and Accomodation Arrangement Drawing.pdf PDF
Amendment A0004.pdf PDF
Amendment A0003.pdf PDF
Gauge Calibration List pdf.pdf PDF
Galley Frige Name Plate.jpg JPG image
Gauge Propeller Sample Report.pdf PDF
Gauge Example Report 2.pdf PDF
Galley Frige Tafco Plate.jpg JPG image
Pump Image ows process pump.jpg JPG image
Life Raft Certs.pdf PDF
Pump Image ows feed pump.jpg JPG image
Amendment A0002.pdf PDF
Attachment D7 Subcontracting Plan.doc DOC document
RFQ 1305M223QNMAN0111 FY24 Dry Dock Repairs NOAA Ship FERDINAND HASSLER Rev1.pdf PDF
Amendment A0001 FY24 Drydock Repairs for NOAA Ship Ferdinand Hassler.pdf PDF
Manuals Part 2-20230720T161458Z-001.zip ZIP file
Craft Bearing Installation Guide.pdf PDF
Manuals Part 3-20230720T161502Z-001.zip ZIP file
Quadrans_UserManualPack_October2021.zip ZIP file
Manuals Part 5-20230720T161511Z-001.zip ZIP file
TAFCO Pre-Fabricated Walkin Cooler and Freezer Manual Rev 2-22-02.pdf PDF
Carrier Transicold Chiller.pdf PDF
Global Davit Rescue Boat Davit.pdf PDF
Vestdavit Survey Boat Davit.pdf PDF
Manuals Part 4-20230720T161506Z-001.zip ZIP file
Part 3-20230719T185946Z-001.zip ZIP file
Part 2-20230719T185938Z-001.zip ZIP file
FH Drawings for Download-20230719T205605Z-001.zip ZIP file
3.10 Genset & Switchboard Drawings-20230718T205109Z-001.zip ZIP file
Part 2-20230719T185854Z-001.zip ZIP file
Manuals for Download - working-20230719T205609Z-001.zip ZIP file
Part 1-20230719T185822Z-001.zip ZIP file
NOAA Standard Specs-20230719T013456Z-001.zip ZIP file
FA12-20230718T201723Z-001.zip ZIP file
RFQ 1305M223QNMAN0111 FY24 Dry Dock Repairs NOAA Ship FERDINAND HASSLER (1) (1).pdf PDF
Gauge Calibration.xls XLS spreadsheet
AMC_634_1A Deck Coverings.pdf PDF
AMC-573-1C Weight Handling Gear Testing.pdf PDF
RO_s Installed FEB 2021-20230706T201749Z-001.zip ZIP file
Attachment D.4 US DOL POSTER.pdf PDF
AMC_505_1B _ Valve Overhaul and Test.pdf PDF
ATTACHMENT D2 Past Performance Information Form (1).docx DOCX document
Product Safety _SENR2995-04_.pdf PDF
MOC_510-1B_HVAC_Cleaning_.pdf PDF
3.17.2.6 FH Hose List.xlsx XLSX spreadsheet
AltiVAR VFD_s Ventilation-20230706T201805Z-001.zip ZIP file
3_17_2_6 FH Hose List.xlsx XLSX spreadsheet
AMC-581-1A Inspection and Preservation of Ground Tackle.pdf PDF
S2906 _ Arc Welding on Waterborne Vessels.pdf PDF
Show 40 more

Latest 50 of 86 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REVISION 1

JULY 2023

NOAA SHIP FERDINAND R. HASSLER (S-250)

FY24 DRY DOCK

SPECIFICATIONS

REV1

FY 2024 Dry Dock Repairs for NOAA Ship Ferdinand R. Hassler

TABLE OF CONTENTS

SCOPE

GENERAL

References

Requirements

Quality Assurance

Government Furnished Equipment

Notes

BASE ITEMS

Temporary Services and Support Equipment

Docking and Undocking

Clean & Gas Free Tanks, Voids, Cofferdams & Spaces

Hull Preservation

Buoyancy Appendage Removal and Reinstallation

ABS Drydocking Survey and Intermediate Hull Survey 3

ABS Tail Shaft Surveys, Rudder Inspection & Maintenance

Hull valve Overhauls

Anodes

Ship’s Re-Powering

Potable Water Tank Inspection, Cleaning, Preservation and Disinfection

Tank and Void Preservation

Annual Liferaft Inspection

Annual SOLAS Rescue Boat & Engine INSPECTION and Maintenance

Annual Fire Detection and Suppression System Inspection

Vestdavit & Survey Launch Maintenance Groom

Various Repairs, Maintenance and Upgrades

Deck Hatches & Door Seals

Oily Water Separator & Fuel Oil Purifier Annual Maintenance

AC & Refrigeration System Maintenance

Oil Replacement

Main Propulsion Diesel Engine Service – Top End Overhaul

Engine Uptake Clean and Inspect

Gauge Calibration

Air Receiver Inspection & Testing

Anchor, Windlass and Chain Maintenance

DOCK AND SEA TRIALS

ADDITIONAL WORK

INTENT

REFERENCES

GOVERNMENT FURNISHED MATERIAL

REQUIREMENTS

OPTION ITEMS

Mast Staging

Navigational Suite Upgrades

GMDSS Upgrade

Various Exterior Preservation end of item

Machinery Space Preservation

Crane Replacement

Chain Locker Cleaning and Preservation

Inclining Experiment

FH FY 24 Dry Dock Specifications

Revision History

Revision Date Change

- APR 19.2023 • Initial Issue

1 July 17th,

• Updates are shown in green text throughout this document

• 2.5.6: Modified verbiage

• 3.1.4.17: Added new

• 3.17.4.2.2: Updated generator maintenance requirements

• 3.17.4.2.5: Updated MER LED light requirements

• 3.17.4.4.8: Added new

• 3.17.4.4.9: Added new

• 3.18.4.2.1: Modified labor hours from 40 to 80.

• 3.21.2.3: Removed Iron Fist crane reference.

• 3.25.4: Administrative updates

• 5.2.4.3: Added new

• 5.2.4.4 Revised verbiage to clarify intent

• 5.2.4.4.1: Added New

• 5.2.6.7.2: Revised wording to clarify intent

• 5.6: Updated reference document number

• 5.6.2.3: Deleted reference. Moved to note 5.6.8.2.

• 5.6.4.1.2.2: Removed requirement to submit platform design & specified that platform is built IAW 5.6.2.3.

SCOPE

1.1.1 The National Oceanic and Atmospheric Administration (NOAA) operates a fleet of 15 research vessels that supports research and mapping for the National Marine Fisheries Service, National Ocean Service, Office of Atmospheric Research and the National Weather Service, as well as provides support to other Federal agencies. These research missions are time sensitive and therefore the data must be collected at specific times during the sailing season to be meaningful. At the end of each sailing season the vessels enter a repair period (drydock or dockside) to address repairs that have been previously identified, perform upgrades to mission systems or ship systems that either extend the life of the ship or provide new data collection capabilities or for safer operations of ships systems as well as address any emergent work that would adversely affect the ship’s ability to safely perform its mission on schedule, while meeting all regulatory body requirements (American Bureau of Shipping and United States Coast Guard) and all habitability requirements, including any that may be required as a result of contracts for personnel to augment ship staff.

1.1.2 The work items in the repair specification are identified well in advance of the performance period in order to meet the contracting lead times. Additional work items (emergent work) may arise during the period between the work package submittal, contract award, or even prior to the start of or during the contract performance period. In accordance with Commerce Acquisition Regulation (CAR) clause 1352.271-72, the Contracting Officer may order additional changes during the contract period of performance to address any additional work items identified as necessary to ensure the intent of the dockside repair contract is met; that is, that the vessel shall be able to safely perform its mission, that it will meet all habitability requirements and regulatory body requirements, and that such repairs will be timely performed to ensure to the maximum extent practicable that the ship’s schedule is not adversely impacted.

1.1.3 These Detail Specifications contain the requirements for dry dock repairs and modifications to NOAA Ship Ferdinand R. Hassler.

GENERAL

REFERENCES

2.1.1 NOAA Standard Specification No. AMC-000-1G, “General Requirements for Ship Repair Work on NOAA Ships.”

2.1.2 NOAA Standard Specification S1600, “Structural Access Cuts.”

2.1.3 NOAA Standard Specification, S2906, “Arc Welding on Waterborne Vessels.”

2.1.4 NOAA Standard Specification MOC-631-2D, “Coating Systems for Steel Surfaces.”

2.1.5 Drawing No. FA-01, NOAA Ship Ferdinand Hassler “Profiles”

2.1.6 Drawing No. FA-02, NOAA Ship Ferdinand Hassler “General Arrangement.”

2.1.7 Drawing No. FC-24, NOAA Ship Ferdinand Hassler Tank “Soundings Tables.”

2.1.8 NOAA Ship Ferdinand R. Hassler Drawing Index

2.1.9 NOAA Weight Report Form, Microsoft XL Format, “Weight Report.xls”

2.1.10 NOAA Standard Specification MOC-631-2D, “Coating Systems for Steel Surfaces.”

2.1.11 ABS: American Bureau of Shipping "Rules for Building and Classing Steel Vessels Under 90 Meters in Length”

2.1.12 ABS: American Bureau of Shipping “Rules for Survey After Construction”

2.1.13 CFR: U. S. Coast Guard "Subchapter F - Marine Engineering", 46 CFR 50 through 46 CFR 64

2.1.14 CFR: U. S. Coast Guard "Subchapter J - Electrical Engineering", 46 CFR 110 through 46 CFR 113

2.1.15 CFR: U.S. Coast Guard “Subchapter U – Survey Vessels”, 46 CFR Chapter 1

2.1.16 Oceanographic Research Vessel (ORV)- 46 CFR chapters 188-196

2.1.17 Standard: IEEE Std 45-2002, "IEEE Recommended Practice for Electric Installations on Shipboard"

2.1.18 NOAA Form 57-17-09 – NOAA Hot Work Permit

2.1.19 NOAA Standard Specification MOC-300-3 “General Requirements for Electrical/Electronic Systems

2.1.20 Hassler Dwg FC61 - Paint Schedule

REQUIREMENTS

2.2.1 Reference 2.1.1 forms a part of these Detail Specifications. All provisions and requirements contained therein are applicable to all work items, including all additional work items which are authorized by the Contracting Officer.

2.2.2 References 2.1.2 and 2.1.3 are amplifications of the requirements contained in reference 2.1.1 sections

4.17 and 4.21.

2.2.3 Some of the ship’s drawings and technical documentation have not been updated to reflect modifications to the ship throughout final delivery and post-delivery modifications. These drawings and reference documents are for planning purposes only. Actual shipboard configurations and conditions may be different from what is listed. Contractor shall be responsible for verifying all current configuration, construction, and arrangement changes, as necessary, to comply with and perform the work requirements of these specifications. Contractors are encouraged and expected to review ship’s drawings and attend the bidders inspection to inspect the locations and shipboard conditions where services are to be performed aboard the Ferdinand Hassler prior to submitting a bid proposal. This inspection should satisfy potential contractors regarding all general and local conditions, (including locations, interferences, tolerances and necessary “work-arounds”, etc.) that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the sites constitute grounds for a change order or claim after contract award.

2.2.4 Ship’s drawings and technical publications may be borrowed during the performance period. It would be preferable for the contractor to make copies of these drawing and technical publications if their intended use will be outside an office environment. All reference materials borrowed by the Contractor shall be signed for, and then returned to the COR after no further use of the reference materials is required.

2.2.5 Provide and maintain a status report of all American Bureau of Shipping (ABS) inspections and technical reviews required by ABS during the course of this contract, to ensure the ship’s ABS certification requirements are in compliance. Submit weekly ABS status reports to the COR, along with the preliminary progress reports.

2.2.6 Provide and maintain a status report of all United States Coast Guard (USCG) inspections and technical reviews required by USCG, during the course of this contract, to ensure the ship’s USCG certification requirements are in compliance. Submit weekly USCG status reports to the COR, along with the preliminary progress reports.

2.2.7 All visual examination, hydrostatic testing, and non-destructive testing shall be in accordance with CFR 46, Subchapter U or ABS Rules for Building and Classing Steel Vessels, Survey After Construction, Part 7 as appropriate. All contractors performing NDT and hull gauging shall be certified under the ABS external specialist program. The contractor shall provide Objective Quantifiable Evidence (OQE) of such upon request.

2.2.8 The contractor shall assign a Project Manager and Ship Superintendent (Project Coordinator) within 3 days following award of the contract. The Project Manager shall set up a meet-and-greet virtual meeting within 7 days of contract award with the COR, Port Engineer, Contracting Officer, Contracting Specialist and contractor personnel. Contractor shall set up biweekly meetings with the NOAA project team beginning at contract award and lasting until the ship arrives at the contractor’s facility. 3 meetings shall be held at the contractor’s facility, including 1 which shall occur within 21 days following contract award. On the first day of the contract performance period, provide the COR a detailed resource loaded production schedule.

Then, on a weekly basis (24 hours preceding the Weekly Progress Meeting) provide the COR a revised and updated production schedule reflecting actual work progress. Provide the COR with a project staffing plan (paper and electronically) by trade/craft and subcontractor showing how the project will be appropriately staffed to be completed by the end of the performance period. The plan should be “resource loaded” showing the planned labor needed and actual labor hours assigned Schedules shall have enough granularity to show the number of workers, by trade, for all given tasks. Once a Notice to Proceed (NTP) is issued, all additional work shall be added to and reflected in the resource loaded production schedule within 24 hours.

These deliverables shall be in Microsoft Project electronic format and 3 paper copies.

2.2.9 The contractor shall have daily production meetings (Plan of the Day, POD) with trade supervisors and the COR to discuss progress, milestones, labor staffing levels, material and other project issues. These production meetings shall be attended by both the project manager and project superintendent (trade superintendent or ship manager).

Provide an electronic copy of the POD to all stakeholders at least 2 hours prior to each meeting.

Provide paper copies of the POD each day for all attendees.

2.2.10 Contractor shall have a project manager and/or ship superintendent assigned exclusively to the Ferdinand Hassler for the duration of the project. Project Manager or COR approved alternate shall attend all shipboard safety meetings (normally at 0800 in the Garage) during the contract period for all days in which the contractor will be performing work on the ship.

2.2.11 Safety and housekeeping walkthrough inspections of the ship, pier, and other production areas shall be conducted on a regular basis (daily or more frequent) by the contractor.

Cleanliness and Ship’s Condition/ Preservation

2.2.11.1.1 The contractor shall film a walkthrough of the entire ship on the first day of the period of performance, prior to starting any work, to document the “as-found” condition of the ship. A digital copy of this video shall be provided to the COR.

2.2.11.1.2 Contractor shall clean up all production areas, sweep up messes, clear all trash and debris and roll back all lines and leads at the end of each shift.

2.2.11.1.2.1 All subcontractors and contractors shall clean areas to the condition they were in prior to the beginning of work. Any areas of concern shall be documented by the Contractor prior to commencing work

2.2.11.1.3 Any and all areas damaged by media blasting and/or paint overspray shall be sanded, primed and painted to match the surrounding area.

2.2.11.1.4 The contractor and subcontractors shall not use the shipboard restrooms/heads, sinks, electrical outlets or other shipboard services.

2.2.12 All new equipment and furnishings purchased by the Contractor for installation on the vessel shall be provided with factory or vendor supplied certificates, technical manuals, and data sheets, complete with parts listings. Faxed copies of this information are not acceptable. This documentation shall be turned over to the COR after installation is completed. Equipment technical manuals shall provide detailed information necessary to operate, maintain, troubleshoot, and repair the equipment. The manuals shall include detailed procedures for disassembly of equipment, parts lists, drawings, inspection criteria, troubleshooting, and test procedures. Provide four paper copies of each manual, plus one electronic copy in Abode Acrobat (PDF) format.

2.2.13 Submit all inspection, test, and quality reports to the COR in PDF or Microsoft Word electronic formats, in addition to providing hard paper copies.

2.2.14 Weigh all materials and items removed, installed, or relocated on the ship. Provide a summary report to the COR indicating the total weight in pounds of items and a breakdown of their locations by space, deck, frame, distance from centerline, and height above the deck, including associated work item number.

Reference 2.1.9 has been provided for the Contractor to identify, record, and document all weight changes for submitting the summary reports. Contractor may use their own weight report form for documenting weight changes. All the information required must be tracked and documented on any form provided.

2.2.15 Unless otherwise stated, the removal of all recyclable material from the ship (valves, steel, etc) shall be coordinated with COR for scrap recycling with the value credited to the Government

2.2.16 For individual work items, prepare and coat all new steel, all existing steel surfaces identified to be cleaned and painted, and all paint systems disturbed while accomplishing work items, in accordance with Reference 2.1.4. Finish coat colors and paint type shall match those of the surrounding, unmodified area.

2.2.17 Ship’s force will maintain a minimal presence during accomplishment of work to these specifications. Their availability to operate ship’s equipment will be limited. Crew availability is generally limited to the hours of 0600 and 1730 local time. Unless otherwise specified, provide a minimum of two working days’ prior notice for any equipment operations or system tag-outs.

2.2.18 All new and disturbed machinery and services shall be operated for a period sufficient to indicate satisfactory performance, but not less than one hour, after all adjustments and deficiency corrective actions have been made, without further adjustment.

All equipment that is to be disconnected, modified, maintained or otherwise disturbed shall be operationally tested prior to disturbance of the equipment. The contractor shall document any discrepancies with operational tests though a condition report; otherwise it will be assumed that the equipment was in good working order prior to disturbance.

2.2.19 Provide manufacturer’s technical representatives where required in the individual work items, to witness and to provide technical guidance during operational testing of equipment and systems. All tests and trials of equipment or systems shall be witnessed by the COR, ABS, and/or USCG as applicable, to ensure compliance with regulatory body requirements to maintain the ship’s ABS class certification, USCG Certificate of Inspection and to complete all requirements of these specifications.

2.2.20 The Contractor and COR shall designate a “on-load/off-load” area of the ship that shall be covered by the appropriate media (planks/tarps/etc) as to not damage the existing deck or surrounding structures.

Rails, handrails and gunnels shall have appropriate chaffing protecting as to protect the paint from any cables hanging over the side.

2.2.21 These Detailed Specifications are a combination of “performance specifications” and “design specifications.” Whenever possible, the Government has provided performance specifications, giving the Contractor the opportunity to accomplish the work requirements as best as he or she sees fit, while providing a fully functional repair and/or equipment/system installation in accordance with all work requirements. When specific details are required, the Government will provide design/detail specifications;

this will be more the exception, than the rule.

2.2.22 Frame numbers and space names are derived from ship’s drawings. All equipment changes and space modifications over the ship’s life span may not all be reflected in the referenced drawings.

Contractors are encouraged to review all referenced drawings and to perform a field inspection of the ship prior to submitting a bid. Copies of drawings and technical manuals not included herein may be made available for review during any scheduled pre-bid inspection and during the performance period.

Contractors may review available drawings and technical manuals on board ship.

2.2.23 During the last three weeks of the contract period, the contractor shall develop a requirements tractability matrix (Punchlist) of all outstanding items from the contract and have daily meetings to go through all remaining items. During the final 14 days, the meetings shall be conducted twice daily.

2.2.24 Maintenance of USCG and ABS Class and Certificates

All USCG and ABS rules required to maintain the ship’s Class and Certificates shall be adhered to by the contractor. This includes all rules for material, fabrication, quality control, inspection, and USCG or ABS on-site survey of work. Specifications may call out USCG/ABS surveyor inspection, but not all USCG/ABS inspections are necessarily identified in the specifications. The contractor shall consult with USCG/ABS on the entire work package and changes and assure USCG/ABS involvement where required to maintain Class and Certificates.

Contractor shall develop, in consultation with the USCG Marine Inspectors and ABS Surveyors, a written survey schedule that lists the items to be inspected and the scheduled dates and times of the inspections. Submit the survey schedule to the COR within 72 hours after the start of the contract performance period. The survey schedule shall list all initial inspections required by the USCG Inspector or ABS Surveyor. In addition, the Contractor shall schedule the services of an ABS Surveyor and USCG Inspector as required by the Authority for performing inspections of all new installations, machinery and hull repairs and modifications, tank inspections, gauging inspections, and load tests.

The contractor is responsible for initiating, scheduling and facilitating all USCG and ABS inspections and surveys due within the contract performance period and shall provide NOAA with copies of all correspondence with the regulating bodies. The costs of ABS ship surveys/inspections will be borne by NOAA unless otherwise stated.

2.2.24.3.1 The following is a list of ABS Surveys and Inspections due during the contract performance period, which shall be scheduled and facilitated by the Contractor, in coordination with the COR:

2.2.24.3.1.1 Drydocking Survey

2.2.24.3.1.2 Intermediate Hull Survey 3

2.2.24.3.1.3 Tailshaft Survey – Tail shaft, Port

2.2.24.3.1.4 Tailshaft Survey – Tail Shaft, Stbd.

2.2.24.3.1.5 Annual Automation Survey

2.2.24.3.1.6 Annual Hull Survey

2.2.24.3.1.7 Annual Machinery Survey

2.2.24.3.1.8 Annual Survey – NIBS 2

2.2.24.3.1.9 Annual Load Line Survey

2.2.24.3.1.10 Annual Safety Construction Survey 2

2.2.24.3.1.11 Intermediate Safety Construction Survey 3

2.2.24.3.1.12 Annual Survey – Cargo Gear 2

2.2.24.3.1.13 Buoyancy Appendage Inspection

2.2.25 Contractor shall empty, open, clean and certify (safe for entry) all shipboard ballast tanks, bilge tanks, CHT/black water tank, grey water tank, fuel oil tanks, potable water tanks, waste oil and oily water tanks, and voids as required to support work items.

The Ship’s crew will empty all tanks and void spaces to the lowest point possible using the ships systems. All remaining fluid in the tanks and voids that must be removed by the contractor to complete the tasks associated with these specifications will be the responsibility of the contractor at no additional cost to the Government.

2.2.26 In addition to the contractor’s requirements for hotwork and firewatches – Firewatches for hotwork shall be required as outlined in section 4.11.3 of Reference 2.1.1. Additionally, the contractor is required to fill out, maintain and comply with reference 2.1.9 (NOAA Hot Work Chit) for all hotwork completed on the ship unless otherwise accepted by ship’s command.

2.2.27 The contractor shall provide electronic copies all material certificates to COR and ABS within 24 hours of work being completed. Material certificates include, but are not limited to, pipe, valves, gauges, steel and equipment.

2.2.28 The contractor shall be responsible for all TWIC (Transpiration Worker Identification Card) requirements and escorts.

2.2.29 All opened and affected Cable Transits, cable penetrations and MCT’s shall be closed by the MCT and tested and accepted by ABS and USCG. Newly installed cables shall be banded to meet ABS requirements. Aluminum cable tags shall be installed on new cables at intervals of 10 feet and on either side of all penetrations.

QUALITY ASSURANCE

2.3.1 All welders shall be certified and only perform welding or brazing for processes and filler materials in which they are certified. A list of all welders and their respective certifications who will be performing work aboard the vessel during the period of performance, as well as applicable welding procedures (WPS) shall be provided to the COR within 3 days after the beginning of the period of performance.

2.3.2 Contractors shall ensure the ship remains water tight during the repair period. This includes rain water, hydrostatic testing, system drainage and water from high pressure water jetting.

2.3.3 The Contractor shall provide temporary heat and air conditioning, as required, to protect against freezing or overheating of sensitive electronics and ship’s systems. Note that ship’s power distribution will be offline for a portion of the period of performance, in order to execute work item 3.10.

2.3.4 The contractor shall repair all damaged paint, insulation, flashing and nonskid preservation as a result of work performed by these specifications. Paint shall match surrounding area. Non-skid shall be repaired with American Safety Technologies MS-7CZ Anti-Corrosive Low VOC Metal Primer (MIL-PRF-24667B) (5 mils DFT), and a full coat of American Safety Technologies AS-2500 epoxy anti-slip deck coating, 8 mils DFT, color: gray.

2.3.5 All paint preparations and application shall be completed in accordance with NACE, SSPC, IMO or QP1 Standards. Other paint certifications may be submitted for consideration. A paint inspector shall be onsite during all painting and painting preparation activities and continually inspect the process, product, preparation and application during the process.

2.3.6 All steel repairs shall conform to the standards of ABS and shall be inspected and approved by ABS.

2.3.7 Offers, and the successful Contractor, are herewith notified that Regulatory Body and NOAA inspections are independent of the Contractor’s function of Quality Assurance. The Contractor is not to rely upon NOAA or Regulatory Bodies or their agents to perform quality assurance inspections or tests.

Where possible, all tests and inspections shall be witnessed and inspected by the contractor prior to inspection or witness by the COR and Regulatory Bodies.

GOVERNMENT FURNISHED EQUIPMENT

2.4.1 Listed individually under each work item

2.4.2 The contractor shall take receipt of, secure and store Government furnished equipment up to 30 days before the beginning of the contract performance period. The Government will have up to 30 days following the start of the period of performance to deliver Government Furnished Equipment.

NOTES

2.5.1 Contractors are encouraged to review ship’s drawings and are expected to attend the Ferdinand R.

Hassler pre-bid inspection to inspect the locations and shipboard conditions of the work items in this package prior to submitting a bid proposal. This inspection should satisfy potential contractors regarding all general and local conditions, compatibility, locations, material sizes and types, components, and accessibility that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the sites during the pre-bid inspection constitute grounds for growth work, change order or claim after contract award.

2.5.2 The ship’s original paint may contain zinc chromate. Contractors may encounter this paint during the work aboard the vessel and should take this into account when preparing their bid as it relates to the necessary work required to accomplish the specific tasks.

2.5.3 The contractor and all subcontractors, regardless of tier, shall review other work items under this contact to determine their effect on each other.

2.5.4 Within 7 days following contract award, the contractor shall purchase all long lead material and provide a copy of the order/invoice and estimated delivery date to the COR.

The following list is not an all-inclusive list, but is a minimum list of equipment that shall be ordered under 2.5.4. Specific information on each item below can be found in the spec item.

1) Auto Pilot, Radars, ECDIS & associated components (if awarded) under 5.2

The contractor shall provide weekly status updates to the COR on the projected delivery dates for material ordered under 2.5.4.1 beginning 14 days after contract award.

The contractor Project Manager shall schedule, facilitate and conduct material status meetings daily with the COR for the first 7 days of the contract and then twice weekly after the first week until the COR is satisfied of the delivery dates of all required material.

2.5.5 The following descriptive data of the ship is provided for information:

NOAAS Ferdinand R. Hassler Ship Information

Length (LOA) 37.7 m (123.7 ft)

Breadth At Main Deck 16.4 m (53.8 ft)

Breadth At Pontoon, Max 18.5 m (60.7 ft)

Depth 7.0 m (23 ft)

Draft, Max 3.95m (12.96 ft)

Displacement, Max 744.4 tonnes (732.6 long tons)

Gross Tonnage (ITC) 809

Hull Welded Steel

2.5.6 The ship will be available for pre-bid inspection as outlined in the Solicitation. All potential contractors are strongly encouraged to attend this inspection. Arrangements for inspection shall be made with NOAA Port Engineer Alex Chartier, 228-281-3198, alex.chartier@noaa.gov.

BASE ITEMS

TEMPORARY SERVICES AND SUPPORT EQUIPMENT

3.1.1 Intent

Provide Services, equipment, protective coverings, training, security, parking, cleaning, and other services outlined below for the duration of the contract period.

3.1.2 References

NOAA Standard Specification No. AMC-000-1G, “General Requirements for Ship Repair Work on NOAA Ships.”

NOAA Standard Specification AMC-000-2C, “Temporary Services at the Contractor’s Facility”

3.1.3 Government-Furnished Material

None

3.1.4 Requirements

Provide all temporary services required in accordance with Reference 3.1.2.1, 3.1.2.2 and this work specification. In the event that conflicting requirements are discovered, the requirements set forth in this Statement of Work shall take precedence. The following additional information and requirements apply:

Electrical Power Requirements:

3.1.4.2.1 The Contractor shall provide a reliable, clean source of electrical power with a minimum capacity of 400 amps. This power shall be for ship’s use only; Contractor is responsible for furnishing separate power for Contractor activities unless prior arrangements are made with the COR. Shorepower substations shall be enclosed or designed to be weather-proof. Substation shall have a primary isolation switch.

Substation secondary shall be a three-phase ungrounded system and shall have 400-amp circuit breakers for each shore power connection. Line to line voltage at the ship’s service switchboard shall be maintained at 480V +/- 5%, 60 Hz +/- 3%. Line voltage imbalance shall not exceed 2%. Total Harmonic Distortion (THD) shall not exceed 6%.

3.1.4.2.1.1 One (1) 400 amp shore power cable with NATO (Joy type) plug is required to be furnished by the contractor, to connect the pier side substation secondary to the ship’s shore power connection. Cables shall be routed such that there is sufficient slack to allow for natural movement of the ship with tide and weather when not in dry dock, but length shall not be excessive such that the cables be allowed to fall into the water or become trapped between the ship’s hull and the pier. Subsequent to installation, but prior to energizing, resistance tests (500V, 1 megaohm minimum corrected to 70 degrees F) shall be performed between conductors, and between each conductor and ground for all cables. The cable shall be checked for proper phase rotation.

3.1.4.2.1.2 Ship and small boats shall be bonded to the pier whenever shore power connection is energized to ensure proper operation of ship’s ground detection equipment. Contractor shall be responsible to connect and disconnect upon ship’s arrival, in-yard shifts, dock and sea trial events, and for ship’s departure. Ship’s shore power connection box is located on the 01 Level aft bulkhead on centerline. Contractor shall perform walkthrough with the COR and the vessel’s Chief Marine Engineer upon arrival to lay out an approved shore power cable routing.

3.1.4.2.1.3 All ground fault deficiencies associated with the Contractor’s power supplied to the ship, shall be corrected at the Contractor’s expense. Such expense shall include housing allowance for ship’s crew, if the ship is still habitable at the time the deficiency is noted

3.1.4.2.2 Temporary lighting, power and ventilation: Provide temporary lighting, power and ventilation throughout the ship anytime that the ship’s lighting and power distribution systems are offline. Yard-provided 120VAC power shall be available for ship’s use in the following spaces, at a minimum: engineer’s workshop, garage, mess deck, wheelhouse, and survey lab.

Potable Water Requirements

3.1.4.3.1 Provide potable water at 60psig and approximately 100 GPM. Provide and install all required valves, adapters and hoses to connect to the ship’s shore potable water connection. All equipment and installations used shall meet United States Public Health Service or equivalent international public health service standards for drinking water intended for human consumption. It is strictly prohibited to connect anything other than potable water to the potable water manifold. The potable water connection shall be fully dedicated and direct connection to a potable water source. No split lines or additional headers allowed.

Sanitary & Sea Water Cooling

3.1.4.4.1 Provide sufficient salt water cooling water supply and return for air conditioning: 45 psig through a 1 ½” threaded connection located aft in the starboard side machinery space, 5-4-1. Provide and install all valves, fittings and hoses required to connect to the ship’s salt water cooling connection(s). Connect and disconnect salt water service lines upon ship’s arrival, at each in-yard shift, for tests and trials and for ship’s departure.

3.1.4.4.2 Provide required sea water cooling connections and supply to support testing of systems that require SW cooling while the ship is in dry-dock, or whenever ship’s cooling system is otherwise offline.

Sewage and Turbid Water Disposal Service:

3.1.4.5.1 Provide sewage and turbid water disposal. Yard shall supply ample hose and fittings to connect to the ship’s discharge: 3” camlok is located on the Main Deck weather deck, port frame 22 and starboard frame 32.

Storage Containers

3.1.4.6.1 Provide one enclosed, lockable storage containers for ship’s personnel use, with minimum nominal dimensions of eight feet high by eight feet wide by twenty feet deep. Container shall be available for the duration of the contract and up to 7 days before the period of performance begins. Provide COR three sets of keys to the lock for the storage container.

3.1.4.6.1.1 The container shall be lockable and air-conditioned, humidity controlled and be used to store shipboard mission equipment and other sensitive equipment and personal belongings.

3.1.4.6.1.1.1 Container box shall have exterior mounted humidity gauges and thermometer for conditions inside the container box. Temperature in container box shall be capable of maintaining temperatures between 60 and 70 degrees F. A fan shall circulate the air internally. Humidity shall be monitored and not reach greater than 50%. Provide electricity for storage container.

3.1.4.6.1.2 Container shall be moved to the dry dock or on the main deck of the ship during the first week of the availability in order to allow stowage of items and again during the last week of the availability for unloading.

3.1.4.6.1.3 The container shall be stored within 250 feet of the ship throughout the availability.

Stack Covers: Provide and install fitted temporary covers for each main engine and diesel generator exhaust stack. Covers shall be installed whilst the ship is in dry-dock and shall be removed by the contractor prior to any engine operations.

Security: Provide onboard Security Service from 1600 to 0800 on weekdays and 24 hour on-ship security on weekends, federal holidays and non-working days throughout the contract. In addition to Reference 3.1.2.1 requirements, increase the security round frequency from two-hour intervals to one-hour intervals. Performance standards for security members are as follows:

3.1.4.8.1 Training and vessel familiarization will be provided by the ship’s officers or designated crew members for the security watch supervisor and one initial group of security watch standers. Watch standers must be in uniform or a safety vest that identifies them as a security watch stander. Watch standers are for security and are not required to be armed. The company must have Security Guard Credentials, Certifications or Licenses; individual guards do not. Security watch standers will present themselves for their watch in sufficient time to be briefed on any changes to the routine or special instructions from the off going watch. Approximately 10-15 minutes may be required to exchange the watch and transfer information. Security watch standers will not depart the ship without being properly relieved following their watch.

3.1.4.8.2 The security watch standers shall provide hourly security rounds, inspecting all spaces of the ship, excluding staterooms. Specific stations shall be set up with Detex security stations or equal, which will be logged using a contractor provided Proxipen security wand. Provide six key stations to be placed at various locations in accordance with the COR. The security watch standers are required to contact the designated Officer of the Day (OOD), duty engineer or CO if any unusual events occur. Unusual events are defined as, but not limited to: bridge alarms, fire, flooding, unauthorized personnel boarding and spills affecting the marine environment. Security rounds and all unusual events shall be noted in the vessel’s watch stander log.

Security watches shall be attentive to the responsibilities of their position and should limit the use of their personal phones to emergencies and duties related to their security detail. The Contractor will be requested to investigate and manage perceived excessive use of phones during security watches.

High-Speed Internet Service: Provide high-speed, broadband internet connectivity via a local Internet Service Provider (ISP), or privately owned, internal internet connection. High-speed, broadband internet is defined as Digital Subscriber Service (DSL), Cable Network, or Fiber Optic Network services with minimum download speeds of 50 Mbps and upload speed of 10 Mbps. The service provided shall be a business- type account that supports Virtual Private Network (VPN) connections. Provide the proper number of connections necessary to satisfy the ship’s wet berth and drydock locations, as well as the ship and COR’s dockside office space(s). All necessary cabling, DSL or cable modem(s), or fiber translators shall be provided for an RJ-45 network connection to the ship and office(s) routers. Provide a minimum of one Internet Protocol (IP) address with Directory Name Server (DNS) service for each of the ship and dockside office(s) locations. The ship’s electronic technician (ET) will provide the necessary routers and switches needed. Wifi Internet shall also be provided in the office spaces.

Telephone lines: Connect one voice line from the ship to the shore office spaces. Provide for exterior calling capabilities on this line as well.

Office Spaces: Provide five secure locked office spaces (one office space for the COR, one for the assistant Port Engineer, and three for ship’s office space). Office spaces shall be no greater than 500 feet from the drydock and berthing area of the ship. Each office space shall be square or rectangular and a minimum of 100 square feet. Provide three sets of keys to each space to the COR.

COR’s and assistant PE office shall be made available five days prior to the ship’s arrival at the Contractor’s facility and shall remain so until five days after the ship has departed. Trash cans shall be provided in each office and emptied daily.

3.1.4.11.1 Dockside office for shipboard personnel shall be climate controlled and shall contain five desks along with six chairs. Provide high speed internet service as required in paragraph 3.3.4.2.3.

3.1.4.11.2 The COR, Assistant PE and one ship’s crew office spaces shall be climate controlled, contain one desk, one circular table and three chairs in each space. Provide one voice phone line in each office space (detailed above) capable of calling the line on the ship, as well as external calls. Provide high speed internet service as required in paragraph 3.3.4.2.3 above. Provide one (1) color printer and color copy machine capable of multiple copying, sorting, and paper size conversion (enlarging/reducing) of documents, in paper size ranges from letter (8.5 x 11 inches), legal (8.5 x 14 inches), and “D“ size drawings (11 x 17 inches).

Provide three (3) spare cartridges of black and each color ink for printer and copy machine. Provide twenty

(20) reams of 20 lb white 8 ½ x 11 inch paper. Provide four (4) 8 ½ by 11 ¾ inch legal pads and twelve (12) uni-ball Jetstream (or equivalent) roller ball black pens.

3.1.4.11.3 A climate-controlled restroom shall be located within 100 feet of office spaces. Sink shall have hot and cold running water and the restrooms shall be provided with both antibacterial and degreasing soap, and a means to dry hands. Restroom shall be cleaned and re-stocked at least every 24 hours, including trash removal.

3.1.4.11.4 Drinking water shall be provided aboard the ship in the mess deck, inside the COR and Ship’s dockside offices. Water dispensers for drinking water shall be capable of dispensing cold and hot water in each location. A minimum of 10 gallons of reserve drinking water shall be in each location at all times to prevent running out. Biodegradable disposable cups for hot and cold water shall be provided in both locations. Additionally, provide 50 cases of bottled water (minimum 16 oz bottles, 36 bottles per case).

Parking Spaces: Provide no less than ten (10) reserved vehicle parking spaces within 100 feet of the dockside office spaces. Identify additional parking spaces for twelve (12) vehicles, 250 yards away from the dockside offices, within or outside the shipyard, which may be available for parking by ship’s personnel and other NOAA representatives.

Protective Covering: In addition to the protective coverings specified in paragraph 4.5.1 of Reference 3.1.2.1, place a layer of heavy duty (minimum thickness of 4 mils) plastic sheeting between the deck and the protective covering of all habitable spaces where contractors will transit or work. This same covering shall also extend no less than 36 inches up joiner bulkheads, doors and other areas deemed likely for impacts or damages.

Temporary Heads: Two (2) “ship’s force only” toilets and 1 wash station with anti-bacterial soap and paper towels shall be located on the ship or within 100 feet of the ship – at the COR’s discretion, any time the ship’s sanitation system is down. The toilets and wash stations shall be cleaned and stocked daily. Toilets shall be appropriately marked “ship’s force only”. One toilet shall be marked “Women Only”. Provide and keep stocked hand-sanitization stations at the toilets and at the ship’s gangway.

Trash and rubbish disposal: Provide trash and rubbish disposal containers or dumpsters to be used by the ship’s crew during the period of performance and up to three days before and five days after. Containers shall be approved for normal trash disposal (general waste) and be located either on the ship or within 100 feet of ship gangway.

Fueling and Stores: The Ferdinand R. Hassler may take on fuel and lube oil (barge or semi-truck), scientific equipment and stores in the final days of the contract performance period.

The Government will order and pay for all fuel and stores directly. Contractor shall support and coordinate with the arrival of fuel, lube oil and stores.

Gangway: A primary gangway and secondary (emergency) means of egress shall be provided whilst the ship is in drydock. The secondary gangway shall be located off of the bow.

3.1.4.17.1 Contractor shall provide care and protection to the ship where an atypical gangway installation is in use. Repair damages and touch up paint upon removal of secondary gangway as required.

Provide 14 color copies of all pages of the contract specification turned over to the COR on the first day of the contract period of performance. Specification shall be full size on 8 ½ x 11 inch and be hard covered (front and back) - spiral bound book.

Support Materials: In the first 3 days of the period of performance, provide the following items to the COR:

3.1.4.19.1 Provide 200 pairs of disposable ear plugs. 32kb NRR or greater.

3.1.4.19.2 Provide 10 pairs of nitrile coated cotton gloves – size large. Provide 10 pairs of cotton heavyweight jersey gloves or equivalent – size large.

3.1.4.19.3 Provide one package (100 count) of disposable nitrile gloves – size large

3.1.4.19.4 Provide one package (100 count) of disposable nitrile gloves – size extra large (XL).

3.1.4.19.5 Provide twelve (12) pair of KLEENGUARD V30 Nemesis Safety Glasses, Indoor / Outdoor lens

3.1.4.19.6 Provide four (4) Nightstick XPP-5422GX Intrinsically Safe Flashlight or equal. Provide three (3) sets of batteries for each flashlight.

3.1.4.19.7 Provide two (2) pairs of noise reduction earmuffs with a Noise Reduction Rating of at least 30db

3.1.4.19.8 Provide two (2) – 32oz Hand Sanitizer bottles with hand pump dispenser

3.1.4.19.9 Provide five (5) disposable coveralls (Tyvek or similar) – size, large

3.1.4.19.10 Provide one (1) ANSI Z89.1 adjustable hard hats (color – white) – size: LARGE

3.1.4.19.11 Provide eight (8) sets of anti-scratch/anti-fog indoor/outdoor – ANSI Z87.1 compliant safety glasses.

3.1.4.19.12 Provide six (4) boxes of Purell Cottony Soft White Sanitizing cleaning wipes (120-count per box) or equivalent

3.1.4.19.13 Provide two (2) surge and noise suppressors, BPS-VCN-14.5-6-6 or equal.

3.1.5 Quality Assurance

In accordance with Reference 3.1.2.1 and 3.1.2.2

Provide potable Safe Drinking Water Act (SDWA) documentation.

3.1.6 Notes

Temporary services including electrical, potable water, cooling water, etc. may not be required for the entirety of the POP, as work item 3.10 will render the ship’s power distribution inoperable.

END OF ITEM

DOCKING AND UNDOCKING

3.2.1 Intent

This work item describes the requirement to dock and undock the ship.

3.2.2 References

Drawing M286-085-FA04, Docking Drawing

Drawing M286-097-C023, Trim & Stability Booklet

Drawing M286-085-FC05-001-02, Tank Capacity Curves

Drawing M286-085-FC24, Sounding Tables

Drawing M286-101-FH01, Shell Scantlings.

Drawing M286-243-FM01, Shaft Arrangement.

Drawing M286-562-FM02, Rudder & Fin Arrangement

Safety Certification Program for Dry-docking Facilities and Shipbuilding Ways for U.S.

Navy Ships, MIL-STD 1625-D

S0700-SWBS997 NOAA Docking Report

3.2.3 Government Furnished Equipment

None

3.2.4 Requirements

The Contractor shall schedule dry-docking of the vessel during the availability dates such that all dry dock work, plus an additional 25% of emergent dry dock necessary work can be accomplished, and the vessel will be undocked in a timely manner to allow the Ship’s force to light off and stabilize the machinery plant. This will enable the Dock Trials and Sea Trials to be conducted in accordance with Work Item 3.28 Dock & Sea Trials as outlined in this Work Item.

The ship shall be dry docked within 5 days of the beginning of the performance period.

The contractor shall conduct a formal docking conference and undocking conference at least 24 hours before docking and undocking. The COR and ship crew shall be invited to both meetings.

Arrangement/Outfitting

3.2.4.3.1 The Contractor shall provide a single section steel or concrete floating dock, marine railway or graving dock certified in accordance with Reference 3.2.2.8.

3.2.4.3.1.1 The dry dock must be certified to lift the vessel according to approved stability and docking calculations, as provided by the Contractor per the requirements of paragraph 3.2.4.

3.2.4.3.1.2 A copy of the Certificate must be submitted with the Proposal, as well as be available for inspection by the COR during the performance period.

3.2.4.3.1.3 The Certificate shall show Issuing Party, Docking facility name (i.e. Shipyard), specific name or number of the dock, issue date, expiration date, maximum lift capacity, maximum allowable keel line loading, and any restrictions or exceptions for operation of the dock.

3.2.4.3.1.4 If certificate is issued by a third party per Reference 2.8, the party shall be specifically identified, and the document shall be sealed and signed by a Professional Engineer representing the certifying third party.

3.2.4.3.2 Dock length overall is to be greater than the vessel’s LOA, regardless of type of dock used.

3.2.4.3.3 The Contractor shall provide all labor, material, equipment and services to dock/undock the vessel.

Provide the services of a Dockmaster for docking and undocking evolutions.

3.2.4.4.1 Provide a letter certifying that the Dockmaster is in charge of the docking and undocking evolutions and is professionally qualified, through training and experience, to conduct the evolutions in a safe and reliable manner.

Contractor shall erect, set and align blocks in Position No. 3 (Three) in accordance with Reference 3.2.2.1. Position blocking to ensure that propeller, rudder, and other equipment residing on the surface of or protruding from the hull will not be damaged and will be accessible for removal and repair.

3.2.4.5.1 Remove and/or shift blocks as required to accomplish work required by other work items and to permit examination of all tank’s drain plugs, transducers and other underwater hull appendages by the ABS Surveyor and COR.

3.2.4.5.1.1 Provide at least 60 inches of clearance between the vessel’s keel and the dry dock floor.

3.2.4.5.1.2 Provide at least 20 feet of clearance on each side of the vessel to allow performance of dry dock work.

3.2.4.5.1.2.1 Propeller shaft removal requires 10.2 m (33’6”) clearance aft of SRP.

3.2.4.5.1.2.2 Rudders require vertical removal clearance of 2.7 m (8’11”)

3.2.4.5.1.3 Exceptions to these clearance requirements will be considered on a case by case basis by the COR during the bid phase.

3.2.4.5.2 Blocking shall be constructed of hardwood or composite concrete/hardwood and softwood caps as specified in Reference 3.2.2.1 with at least two (2) inches of softwood cap thickness. All softwood caps shall be installed pre-shaped to fit the hull in accordance with Reference 3.2.2.1.

3.2.4.5.2.1 Crib and brace blocking as required by Reference 3.2.2.1. Blocking in excess of six (6) feet in height shall be cribbed and/or braced to the satisfaction of the COR.

3.2.4.5.2.2 Contractor proposals (or requests) to modify or deviate from the blocking arrangements specified by Reference 3.2.2.1 shall be submitted to the COR, in writing, sufficiently in advance of the docking to allow for full review and approval.

3.2.4.5.2.2.1 The proposal shall describe all intended modifications or deviations from Reference 3.2.2.1 and all technical data (i.e. proposed docking plan, table of offsets, block details, etc.) necessary to evaluate the results of the proposed modification.

3.2.4.5.3 All proposed modifications and deviations shall include supporting calculations which substantiate the block loading pressures are within the following maximum values:

3.2.4.5.3.1 Side blocks – 150 psi

3.2.4.5.3.2 Keel blocks – 130 psi

3.2.4.5.3.3 Knuckle block(s) with hardwood caps – 200 psi

3.2.4.5.3.4 NOTE: For narrow skegs or bar keels, or where knuckle load is in excess of 600psi, a minimum 40.8# plate steel cap shall be used.

3.2.4.5.3.5 All…