12- 230800 sf - commissioning of hvac.pdf

PDF 18 KB Posted

Attached to
RECOVERYAkron, CO Repair building 1 HVAC system.
Solicitation number
AG-82HW-S-10-0005
Issued by

About this file

Attachment 12

View the file

Other files

File Type Posted
233600 sf - air terminal units.pdf PDF
233300 sf - air duct accessories.pdf PDF
Amendment 2 - Akron HVAC - ARRA.pdf.pdf PDF
232923 sf - variable frequency motor controllers.pdf PDF
233113 sf - metal ducts.pdf PDF
232123 sf - hydronic pumps.pdf PDF
233119 sf - hvac casings.pdf PDF
Amendment 1.pdf PDF
7- 230548 sf - vibration and seismic controls for hvac piping and equipment.pdf PDF
6- 230529 sf - hangers and supports for hvac piping and equipment.pdf PDF
24- DOL Wage Determiation for Akrion HVAC - ARRA.pdf PDF
14- 230993 sf - sequence of operations for hvac controls.pdf PDF
4- 230519 sf - meters and gages for hvac piping.pdf PDF
22- M601.pdf PDF
18- M101.pdf PDF
5- 230523 sf - general-duty valves for hvac piping.pdf PDF
16- E101.pdf PDF
2- 01350 Submittals.pdf PDF
21- M502.pdf PDF
23- MD101.pdf PDF
10- 230713 fl - duct insulation.pdf PDF
15- 232113 sf - hydronic piping.pdf PDF
3- 230513 sf - common motor requirements for hvac equipment.pdf PDF
11- 230719 fl - hvac piping insulation.pdf PDF
13- 230900 sf - instrumentation and control for hvac.pdf PDF
1- 01330 Coordination.pdf PDF
AG-82HW-S-10-0005 -B1 HVAC AKRON -ARRA -OPTIONS construction over 100K.pdf PDF
19- M401.pdf PDF
17- G101.pdf PDF
8- 230553 sf - identification for hvac piping and equipment.pdf PDF
9- 230593 sf - testing adjusting and balancing for hvac.pdf PDF
20- M501.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA / ARS

Repair Bldg 1 HVAC System Akron, CO

COMMISSIONING OF HVAC 230800 - Page 1 of 5

SECTION 230800 - COMMISSIONING OF HVAC

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes commissioning process requirements for HVAC&R systems, assemblies, and equipment.

1.2 DEFINITIONS

A. Commissioning Plan: A document that outlines the organization, schedule, allocation of resources, and documentation requirements of the commissioning process.

B. CxA: Commissioning Authority.

C. HVAC&R: Heating, Ventilating, Air Conditioning, and Refrigeration.

D. Systems, Subsystems, Equipment, and Components: Where these terms are used together or separately, they shall mean "as-built" systems, subsystems, equipment, and components.

1.3 UNIT PRICES

A. Commissioning testing allowance may be adjusted up or down by the "List of Unit Prices" Article in Division 01 Section "Unit Prices" when actual man-hours are computed at the end of commissioning testing.

1.4 CONTRACTOR'S RESPONSIBILITIES

A. Perform commissioning tests at the direction of the CxA.

B. Attend construction phase controls coordination meeting.

C. Attend testing, adjusting, and balancing review and coordination meeting.

D. Participate in HVAC&R systems, assemblies, equipment, and component maintenance orientation and inspection as directed by the CxA.

E. Provide information requested by the CxA for final commissioning documentation.

F. Provide measuring instruments and logging devices to record test data, and provide data acquisition equipment to record data for the complete range of testing for the required test period.

COMMISSIONING OF HVAC 230800 - Page 2 of 5

1.5 CxA'S RESPONSIBILITIES

A. Provide Project-specific construction checklists and commissioning process test procedures for actual HVAC&R systems, assemblies, equipment, and components to be furnished and installed as part of the construction contract.

B. Direct commissioning testing.

C. Verify testing, adjusting, and balancing of Work are complete.

D. Provide test data, inspection reports, and certificates in Systems Manual.

1.6 COMMISSIONING DOCUMENTATION

A. Provide the following information to the CxA for inclusion in the commissioning plan:

1. Plan for delivery and review of submittals, systems manuals, and other documents and reports.

2. Identification of installed systems, assemblies, equipment, and components including design changes that occurred during the construction phase.

3. Process and schedule for completing construction checklists and manufacturer's prestart and startup checklists for HVAC&R systems, assemblies, equipment, and components to be verified and tested.

4. Certificate of readiness, signed by the Contractor, certifying that HVAC&R systems, assemblies, equipment, components, and associated controls are ready for testing.

5. Certificate of completion certifying that installation, prestart checks, and startup procedures have been completed.

6. Certificate of readiness certifying that HVAC&R systems, subsystems, equipment, and associated controls are ready for testing.

7. Test and inspection reports and certificates.

8. Corrective action documents.

9. Verification of testing, adjusting, and balancing reports.

1.7 SUBMITTALS

A. Certificates of readiness.

B. Certificates of completion of installation, prestart, and startup activities.

COMMISSIONING OF HVAC 230800 - Page 3 of 5

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 TESTING PREPARATION

A. Certify that HVAC&R systems, subsystems, and equipment have been installed, calibrated, and started and are operating according to the Contract Documents.

B. Certify that HVAC&R instrumentation and control systems have been completed and calibrated, that they are operating according to the Contract Documents, and that pretest set points have been recorded.

C. Certify that testing, adjusting, and balancing procedures have been completed and that testing, adjusting, and balancing reports have been submitted, discrepancies corrected, and corrective work approved.

D. Set systems, subsystems, and equipment into operating mode to be tested (e.g., normal shutdown, normal auto position, normal manual position, unoccupied cycle, emergency power, and alarm conditions).

E. Inspect and verify the position of each device and interlock identified on checklists.

F. Check safety cutouts, alarms, and interlocks with smoke control and life-safety systems during each mode of operation.

G. Testing Instrumentation: Install measuring instruments and logging devices to record test data as directed by the CxA.

3.2 TESTING AND BALANCING VERIFICATION

A. Prior to performance of testing and balancing Work, provide copies of reports, sample forms, checklists, and certificates to the CxA.

B. Notify the CxA at least 10 days in advance of testing and balancing Work, and provide access for the CxA to witness testing and balancing Work.

C. Provide technicians, instrumentation, and tools to verify testing and balancing of HVAC&R systems at the direction of the CxA.

1. The CxA will notify testing and balancing Contractor 10 days in advance of the date of field verification. Notice will not include data points to be verified.

2. The testing and balancing Contractor shall use the same instruments (by model and serial number) that were used when original data were collected.

3. Failure of an item includes, other than sound, a deviation of more than 10 percent.

Failure of more than 10 percent of selected items shall result in rejection of final testing, COMMISSIONING OF HVAC 230800 - Page 4 of 5 adjusting, and balancing report. For sound pressure readings, a deviation of 3 dB shall result in rejection of final testing. Variations in background noise must be considered.

4. Remedy the deficiency and notify the CxA so verification of failed portions can be performed.

3.3 GENERAL TESTING REQUIREMENTS

A. Provide technicians, instrumentation, and tools to perform commissioning test at the direction of the CxA.

B. Scope of HVAC&R testing shall include entire HVAC&R installation, from central equipment for heat generation and refrigeration through distribution systems to each conditioned space.

Testing shall include measuring capacities and effectiveness of operational and control functions.

C. Test all operating modes, interlocks, control responses, and responses to abnormal or emergency conditions, and verify proper response of building automation system controllers and sensors.

D. The CxA along with the HVAC&R Contractor, testing and balancing Contractor, and HVAC&R Instrumentation and Control Contractor shall prepare detailed testing plans, procedures, and checklists for HVAC&R systems, subsystems, and equipment.

E. Tests will be performed using design conditions whenever possible.

F. Simulated conditions may need to be imposed using an artificial load when it is not practical to test under design conditions. Before simulating conditions, calibrate testing instruments.

Provide equipment to simulate loads. Set simulated conditions as directed by the CxA and document simulated conditions and methods of simulation. After tests, return settings to normal operating conditions.

G. The CxA may direct that set points be altered when simulating conditions is not practical.

H. The CxA may direct that sensor values be altered with a signal generator when design or simulating conditions and altering set points are not practical.

I. If tests cannot be completed because of a deficiency outside the scope of the HVAC&R system, document the deficiency and report it to the Owner. After deficiencies are resolved, reschedule tests.

J. If the testing plan indicates specific seasonal testing, complete appropriate initial performance tests and documentation and schedule seasonal tests.

3.4 HVAC&R SYSTEMS, SUBSYSTEMS, AND EQUIPMENT TESTING PROCEDURES

A. HVAC&R Instrumentation and Control System Testing: Field testing plans and testing requirements are specified in Division 23 Sections "Instrumentation and Control for HVAC"

COMMISSIONING OF HVAC 230800 - Page 5 of 5 and "Sequence of Operations for HVAC Controls." Assist the CxA with preparation of testing plans.

B. Pipe system cleaning, flushing, hydrostatic tests, and chemical treatment requirements are specified in Division 23 piping Sections. HVAC&R Contractor shall prepare a pipe system cleaning, flushing, and hydrostatic testing plan. Provide cleaning, flushing, testing, and treating plan and final reports to the CxA. Plan shall include the following:

1. Sequence of testing and testing procedures for each section of pipe to be tested, identified by pipe zone or sector identification marker. Markers shall be keyed to Drawings for each pipe sector, showing the physical location of each designated pipe test section.

Drawings keyed to pipe zones or sectors shall be formatted to allow each section of piping to be physically located and identified when referred to in pipe system cleaning, flushing, hydrostatic testing, and chemical treatment plan.

2. Description of equipment for flushing operations.

3. Minimum flushing water velocity.

4. Tracking checklist for managing and ensuring that all pipe sections have been cleaned, flushed, hydrostatically tested, and chemically treated.

END OF SECTION 230800